EPID:L-2017-LLA-0227, Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specifications 3.2.a and 3.2.f.8 (Approved, Closed) |
|
MONTHYEARA11010, 30441R00030, Revision a, Mo-99 Target Cooling System Eismic Analysis Design Calculation Report2017-01-11011 January 2017 30441R00030, Revision a, Mo-99 Target Cooling System Eismic Analysis Design Calculation Report Project stage: Other ML17128A3942017-05-0303 May 2017 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specifications 3.2.a and 3.2.f.8 Project stage: Request ML17172A1952017-06-19019 June 2017 University of Missouri-Columbia Research Reactor - Supplemental Information in Support of the Request to Amend the Technical Specifications, Which Are Appended to Renewed Facility Operating License No. R-103 Project stage: Request ML17292A0522017-10-17017 October 2017 University of Missouri-Columbia Research Reactor - Supplemental Information in Support of May 3, 2017 Request to Amend Technical Specifications Project stage: Request ML17285B1862017-10-19019 October 2017 University of Missouri-Columbia-Request for Extension to Respond to the Request for Additional Information License Amendment Request to Implement Selective Gas Extraction Target Experimental Facility at the University of Missouri Research R Project stage: RAI ML17335A0342017-11-29029 November 2017 University of Missouri - Columbia, Request for a 45-day Extension to Respond to the for Additional Information License Amendment Request to Implement Selective Gas Extraction Target Experimental Project stage: Request ML17338A9342017-12-0505 December 2017 University of Missouri-Columbia - Request for Extension to Respond to the Request for Additional Information License Amendment Request to Implement Selective Gas Extraction Target Experimental Facility at the University of Missouri Research Project stage: RAI ML18022A2592018-01-16016 January 2018 University of Missouri at Columbia - Response to Request for Additional Information Re License Amendment Request to Implement Selective Gas Extraction Target Experimental Facility at the University of Missouri Research Reactor Project stage: Response to RAI ML18047A1382018-02-14014 February 2018 Request for a Closed Meeting Session During the February 26, 2018 Public Meeting on Meeting to Discuss Part 2 of an Experimental Facility at the University of Missouri Columbia Research Reactor to Produce Molybdenmp-99, (ML18038B494) Project stage: Request ML18045A3462018-02-16016 February 2018 University of Missouri Research Reactor - Request for Withholding Information from Public Disclosure Revision to License Amendment Request to Implement Selective Gas Extraction Target Experimental Facility at the University of Missouri Rese Project stage: Withholding Request Acceptance ML18052B0632018-03-0707 March 2018 University of Missouri at Columbia -Request for Withholding Information from Public Disclosure Public Meeting Closed Session Ti Discuss Proprietary Information on the Selective Gas Extraction Target Experimental Facility at the Univ of Miss Project stage: Withholding Request Acceptance ML18059A4902018-03-0707 March 2018 February 26, 2018, Summary of Public Meeting to Discuss the Proposed Molybdenum-99 Production Facility at the University of Missouri Research Reactor Project stage: Meeting ML18099A0652018-04-0505 April 2018 University of Missouri-Columbia Research Reactor, Withdrawal of 05/03/2017 Request to Amend Renewed Facility Operating License No. R-103 in Support of Selective Gas Extraction (Sge) Mo-99 Project Project stage: Request ML18102A4502018-04-17017 April 2018 University of Missouri Columbia-Acknowledgement of Withdraw of License Amendment Request in Support of License Amendment Request in Support of the University of Missouri Research Reactor (CAC A11010/05000186/L-2017-LLA-0227) Project stage: Other ML20245E5672020-09-0303 September 2020 University of California, Davis - Review of the Emergency Plan in Support of the Renewal for Facility Operating License No. R 130 Project stage: Approval 2017-06-19
[Table View] |
Text
December 5, 2017 Mr. Matt Sanford Interim Reactor Facility Director University of Missouri-Columbia Research Reactor Center 1513 Research Park Drive Columbia, MO 65211
SUBJECT:
UNIVERSITY OF MISSOURI-COLUMBIA - REQUEST FOR EXTENSION TO RESPOND TO THE REQUEST FOR ADDITIONAL INFORMATION RE: LICENSE AMENDMENT REQUEST TO IMPLEMENT SELECTIVE GAS EXTRACTION TARGET EXPERIMENTAL FACILITY AT THE UNIVERSITY OF MISSOURI RESEARCH REACTOR (CAC A11010/05000186/L-2017-LLA-0227)
Dear Mr. Sanford:
By letter dated May 3, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession Package No. ML17132A252), the University of Missouri-Columbia Research Reactor (MURR) submitted a license amendment request (LAR) to produce molybdenum-99 using the General Atomics, Selective Gas Extraction process. By letter dated November 1, 2017 (ADAMS Accession No. ML17284A043), the NRC staff submitted a request for additional information (RAI) to support its continued review of the LAR. By letter dated November 29, 2017 (ADAMS Accession No. ML17335A034), MURR staff requested a 45-day extension, to January 15, 2018, to complete the RAI responses.
The NRC staff accepts the 45-day extension request.
If you have any questions regarding this review, please contact me at (301) 415-0893, or by electronic mail at Geoffrey.Wertz@nrc.gov.
Sincerely,
/RA Michael Balazik for/
Geoffrey A. Wertz, Project Manager Research and Test Reactors Licensing Branch Division of Licensing Projects Office of Nuclear Reactor Regulation Docket No. 50-186 License No. R-103 Enclosure As stated cc: See next page
University of Missouri-Columbia Docket No. 50-186 cc:
Les Foyto, Associate Director Reactor and Facilities Operations University of Missouri - Columbia Research Reactor Center 1513 Research Park Drive Columbia, MO 65211 Homeland Security Coordinator Missouri Office of Homeland Security P.O. Box 749 Jefferson City, MO 65102 Planner, Dept of Health and Senior Services Section for Environmental Public Health P.O. Box 570 Jefferson City, MO 65102-0570 Deputy Director for Policy Department of Natural Resources 1101 Riverside Drive Fourth Floor East Jefferson City, MO 65101 A-95 Coordinator Division of Planning Office of Administration P.O. Box 809, State Capitol Building Jefferson City, MO 65101 Test, Research and Training Reactor Newsletter P.O. Box 118300 University of Florida Gainesville, FL 32611
ML17338A934 *concurrence via e-mail NRR-106 OFFICE NRR/PRLB/PM*
NRR/PRLB/LA* NRR/PRLB/BC NRR/PRLB/PM NAME GWertz NParker AAdams (MBalazik for)
GWertz (MBalazik for)
DATE 12/5/17 12/5/17 12/5/17 12/5/17