ML17331B092
| ML17331B092 | |
| Person / Time | |
|---|---|
| Site: | Cook |
| Issue date: | 11/23/1993 |
| From: | Falevits Z, Gardner R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | |
| Shared Package | |
| ML17331B090 | List: |
| References | |
| 50-315-93-12, 50-316-93-12, NUDOCS 9312070133 | |
| Download: ML17331B092 (31) | |
See also: IR 05000315/1993012
Text
U. S.
NUCLEAR REGULATORY COMMISSION
REGION III
Reports
No. 50-315/93012(DRS);
No. 50-316/93012(DRS)
Docket Nos. 50-315;
50-316
Licenses
No. DPR-58;
No.
licensee:
Company
1 Riverside Plaza
Columbus,
OH
43216
Facility Name:
Donald
C.
Cook Nuclear .Power Plant
Units
1 and
2
Inspection At:
Bridgman,
MI
Inspection
Conducted:
August
17 through September
28,
1993
Inspection
Team:
Z.
D.
R.
E.
NRC Consultants:
C.
S.
Falevits,
Team Leader
Butler, Assistant
Team Leader
Mendez,
Reactor
Inspector
Schweibinz,
Senior Project Engineer
Crane,
Parameter,
Inc.
Godamunne,
Parameter,
Inc.
Approved By:
e
a ev>ts,
earn
ea er
Region III
ll-z3- g
ate
Approved By:
ona
.
ar ner,
C ie
Plant Systems
Section
Ins ection
Summar
li(~p(C10
ate
Ins ection
on Au ust
17 - Se tember
28
1993
Re orts
No. 50-315
93012
No. 50-316
93012
Areas
Ins ected:
Special
announced
systems
based
instrumentation
and control
inspection
(SBICI) in accordance
with Inspection
Procedure
93807.
Results:
The team determined that the design
and operation of the
instrumentation
and control
systems
examined
by the team were adequate.
The
team also concluded that instrumentation
and control
(IEC) engineering
and
technical
support
was generally good.
A summary of strengths
and weaknesses
in -18C system design
and engineering
support is provided in the Executive
Summary of this report.
The team identified two violations:
(1) design
control deficiencies
in ILC setpoint calculations
and design
drawings
(Section
3.6.1),
and (2) failure to perform
a
10 CFR 50.59 safety evaluation
(Section
4.2).
The team also identified one inspection
followup item with six examples
(Sections
3. 1, 3.2, 3.3
and 3.6)
and
one unresolved
item during this
inspection
(Section 4.3).
9312070133
931124
ADOCK. 0500031 S
8
'PDR
TABLE OF
CONTENTS
Pacae
EXECUTIVE SUMMARY...............................................
1 t 0
INTRODUCTION~ ~ ~
~
~
~
~
~ ~
~
~
~ ~
~
~ ~
~
~
~
~
~
~
~
~
~
~
~
~
~ ~
~
~
~
~ ~
~ ~
~ ~
~
~
~
~
~
1
2.0
ACTION ON PREVIOUSLY IDENTIFIED INSPECTION ITEMS..........
1
3.0
REVIEWS OF SELECTED
INSTRUMENT LOOPS.......... ...........
1
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
Setpoint Calculation Methodology...................
Hain Steam
Flow/Feedwater
Flow Mismatch............
Condensate
Storage
Tank (CST) Level Channels-
Function for Accident Mitigation.....'............
Essential
(ESW)
Pump Flow and
Discharge
Pressure
Channels - Function for
S
0 J
ystem Hon>toring.......................
~ ~ ~ ~
.
~ .
~
~
Main Turbine Control Oil Pressure
Switch - Function
for Turbine Control
and Reactor Protection.......
Refueling Water Storage
Tank
(RWST) Level Channels
Function for Accident Mitigation...............
Design Guides
and Criteria.........................
Measuring
and Test
Equipment
and Labeling of IKC
Components.......................................
Instrument Calibration
and Testing.
2
3
5
6
7
7
11
ll
12
4. 0
REVIEW OF
IKC MODIFICATIONS AND DESIGN CONTROL.............
12
5.0
ENGINEERING AND TECHNICAL SUPPORT..............
'
~
~
~
~
~
~
~
~
~
~
15
6.0
INSPECTION
FOLLOWUP ITEMS
16
7.0
UNRESOLVED ITEMS...........................
........ ......
16
8.0
EXIT MEETING.
Appendix
A - Personnel
Contacted
~
~
~ ~
~
~ I ~
~ ~
16
1
~
~
EXECUTIVE SUNHARY
During August
17 through September
28,
1993,
a U. S. Nuclear Regulatory
Commission
(NRC) inspection
team conducted
'a system
based
instrumentation
and
control inspection
(SBICI) at the
D.
C.
Cook Nuclear Power Plant,
Units I and
2.
The inspection
focused
on the design
and configuration of selected
safety
related
and important to safety instrumentation
and control
systems
and
components.
The main purpose of the inspection
was to: (I) determine if
selected
instrument setpoints
were properly derived such that automatic
actions would occur to prevent safety limits from being .exceeded;
(2)
determine if calculations,
supporting these setpoints,
considered all
appropriate
uncertainties;
(3) determine if setpoint calculation
methods
were
technically consistent
with accepted
standards;
and (4) evaluate
I&C related
activities, engineering
and technical
support,
and self assessment.
During the pre-inspection
preparation,
the team selected
specific
instrumentation
and control loops based
on probabilistic risk assessment
and
the importance of the equipment
in mitigating design basis
accidents.
The team considered
the design
and operation of the
I&C loops examined to be
adequate.
However,
the team identified the following weaknesses:
Some instrument setpoint calculations,
engineering control procedures
(ECPs)
and design
drawings contained
various omissions
and errors
and
lacked sufficient technical
supporting details.
o
AEP did not identify or assess
the impact of High Energy Line Break
(HELB) outside containment
on instrument channels
(including cables)
and
setpoints
examined
by the team.
I&C related
codes,
standards,
and industry guides applicable to D. C.
Cook were not properly identified.
Plant
I&C engineers
were not fully knowledgeable
on existing or old
plant instrumentation
design
and troubleshooting.
Also, guidance
and
training of corporate
I&C engineers
on the various specifications
and
criteria documents
was needed.
The team concluded that increased
management
attention is warranted
in the
area of I&C design control, specifically setpoint calculations.
The team identified the following strengths:
Highly experienced
engineering staff.
Instrument
Loop Setpoint Methodology Guide EG-IC-004 provided good
guidance to engineers
on setpoint methodology.
Also, newer setpoint
calculations
were more detailed
than the older ones.
~
~
Executive
Summary
h
The control of measuring
and test equipment
and the labeling of IEC
components
was considered
very good.
Calibration functional test
and response
time test surveillance
procedures
for loops selected
were considered
very good.
Procedure
revision program
and
I8C technician training were considered
positive initiatives.
l4
e
h
~
~
'
DETAILS
1.0
Introduction
Selected
instrumentation
and control setpoints
were examined in detail,
including the design basis requirements,
assumptions,
calculations,
and
component configuration.
In particular,
the uncertainties
(inaccuracies
or
errors)
associated
with the. instrumentation
loops were evaluated
to determine
if setpoints
were correct
and adequate
margin was achieved.
For this inspection,
the team reviewed the final updated safety analysis
report
(UFSAR), the licensee's
conclusions of the probabilistic risk
assessment
(PRA),
and the setpoint methodology program.
On the basis of the
predominant
accident scenarios,
the team selected
several
instrumentation
loops for inspection.
The areas
reviewed
and the concerns identified are described
in Sections 3.0,
4.0 and 5.0 of this report.
Personnel
contacted
and those
who attended
the
't meeting. on September
28,
1993,
are listed in Appendix A.
BX1
Action on Previousl
Identified Ins ection Findin
s
The team walked
down originally installed
and as-modified
I&C equipment for
configuration
and equipment
types
and reviewed
system
component qualification,
testing,
and calibration records.
The team also
assessed
the licensee's
E&TS
organization's
capability with respect to personnel
qualification and
staffing, timely and adequate
root cause
analyses
for failures
and recurring
problems,
and involvement in design modifications
and operations.
Closed
Unresolved
Item
315 316-90020-03
Inade uate Terminal Volta e at
Class
lE Inverter Terminals
The
NRC was concerned that voltage to components
supplied
by the Class
1E
inverters
would not be adequate if the input voltage to the inverters
was
210Vdc.
The licensee's
UFSAR and Technical Specifications
required that the
Class
1E inverter
remain operable for three
hour s" following a design basis
event.
According to the five year battery discharge test,
the battery voltage
was approximately
228Vdc.
The team determined that this voltage
was
sufficiently above the minimum equipment rating of 210Vdc.
This item is
considered
closed.
3.0
Reviews of Selected
Instrument
Loo s
In assessing
I&C capability, the team reviewed the plant's instrumentation
and
control
system design,
configuration
and operation.
The team reviewed the
setpoint
program, original
and contemporary
vendor
and licensee calculations,
installed
I&C equipment,
I&C testing
and procedures,
equipment qualification,
and compliance with regulations,
design engineering
standards
and accepted
engineering
practices.
The review was based
on the following information:
~
~
setpoint calculations
system descriptions
technical specifications
system design basis
documents
(PRA)
vendor documents
test,and
operating
procedures
control logic diagrams
elementary
and loop schematic
diagrams
The team conducted
ISC equipment
walkdowns to verify that the operational,
environmental
and seismic criteria had
been correctly applied.
For each
instrument loop selected
during the pre-inspection,
the team reviewed the
design of each loop .from the process
interface
sen'sing lines
and
instrumentation
to the setpoint bistable or control
room indicator.
The team
also performed
a walkdown inspection of the selected
instrument loops.
The inspection
focused
on review of the instrumentation
and control channels
listed below.
Refueling Water Storage
Tank
(RWST) Level Channels,
Units
1
& 2
Essential
Service
Water
(ESW) Flow and
Pump Discharge
Pressure
Channels,
Unit
1
3.1
Motor Driven Auxiliary Feedwater
Pump
(AFW) Flow and Discharge
Pressure
Channels,
Unit
1
Condensate
Storage
Tank
(CST) Level Channels,
Units
1
8. 2
Low Lube Oil Pressure
Switch
RPS Trip, Unit
1
Flow High/Feedwater
Flow Low Mismatch Reactor Trip;
ESF Steam
Line Isolation, Unit 2
Pressurizer
Pressure,
Unit
1
Pressurizer
Level, Unit
1
Level, Units
1
and
2
Set oint Calculation Methodolo
3.1. 1
Tri
Set oint Calculation
and Basis
The team determined that Westinghouse
Calculation
Revision
1,
"Setpoint Methodology for Protection
Systems - D.
C.
Cook, Unit 1," did not
require the licensee
to consider
environmental
allowances
(EA) (e.g.,
pressure,
temperature
and seismicity)in setpoint calculations for those
loops
that the licensee
considered
secondary
(backup).
Examples
included:
~
~
pressurizer
pressure
high reactor trip, low reactor trip and low safety
injection;
and
water level low, level low low and level high high.
The team concluded that
an engineering
evaluation
was needed
to confirm the
adequacy of the setpoint
bases.
This item is considered
an inspection
followup item pending further review and evaluation
by the Office of Nuclear
Reactor Regulation
316/93012-01A(DRS) ) .
3.1.2
Environmental
and Seismic
Performance
The licensee
did not provide the following information relative to PT-455,
LT-
461,
and LT-527 for the team's
review:
.
(a)
Seismic reports for component
supports (i.e., for transmitter,
piping
and tubing supports, etc.).
(b)
Environmental qualification report for the cable
from the transmitter to
the Control
Room.
Note:
Cable routing drawing No.
1-1437T-1 'shows that this cable runs through
a harsh
(419
F accident,
110'F normal) environment during
an accident.
This is considered
to be
an inspection followup item (315/93012-01B(DRS);
316/93012-018(DRS)).
Flow Feedwater
Flow Mismatch
The main steam flow and main feedwater flow instrumentation
and circuitry
provide protective signals to the reactor protection
system
(RPS)
and
engineered
safety features
actuation
system
(ESFAS).
The team reviewed the t}ansmitters
and instrumentation
associated
with Unit ¹2
main steam flow high/main feedwater flow low mismatch
channels
flow 2-FT-523
[AEP No. 2-MFC-120]
and main feedwater flow 2-FT-521
[AEP No. 2-
FFC-221] ) .
3.2.1
Set oint Calculation
and Basis
(a)
The team
was concerned
that the Westinghouse
instrument loop setpoint
uncertainty calculations for the main steam flow high/feedwater flow low
mismatch trip channel
did not account for bias errors
due to harsh
accident
environments
and cable insulation resistance
degradation
effects.
Therefore,
portions of the instrument loop exposed
to a harsh
accident
environment could create additional
bias errors which,
when
added into the calculations,
could potentially exceed
setpoints
and
allowable margins.
"Setpoint Methodology for Protection
Systems,
D.
C.
Cook Unit ¹2," August
1993, contained
the instrument
loop
uncertainty calculations for the
and
ESFAS instrumentation
channels,
including. the main steam flow high/feedwater flow low mismatch trip
channel.
The main steam flow transmitters
(for the main steam
flow/feedwater flow mismatch channels)
are located inside containment
and would be exposed
to the adverse
environment created
by a steam line
break accident
inside containment.
(b)
The team determined that the D.
C.
Cook instrument loop error analysis
and setpoint
program is governed
by the procedures
and industry design
guidelines specified in Section 3.6.3 of this report.
setpoint methodology,
identified in WCAP-13801, required that
an
environmental
allowance bias error (due to accident
environment effects)
be applied to the instrument loop uncertainty calculation, if
applicable.
In response
to the team's
concern,
the licensee
stated that the
methodology considers
certain
and
ESFAS instrumentation
channels
to be diverse
(backup) to "primary" channels;
only the
"primary" channels
incorporate
environmental
allowances
(EA) into the
setpoint calculations to account for the effects of harsh
environments.
Diverse
(backup)
channels,
such
as the main steam flow high/feedwater
flow low mismatch trip, did not include
an
EA for bias errors
due to
adverse
environments.
The licensee
stated that this was consistent
with
the accident analysis,
and that this was not
a safety concern.
This
issue is considered
to be
an inspection followup item pending further
review and evaluation
by the Office of Nuclear Reactor Regulation
(NRR)
(315/93012-OIC(DRS);
316/93012-01C(DRS) ) .
The team
was concerned that the
use of containment
pressure
to detect
a
steam line break inside containment,
rather than steam line high flow,
did not conform to
IEEE 279-1968, "Criteria for Nuclear
Power Plant
Protection
Systems."
Section 4.8, which requires that, "to the extent
feasible
and practical, protection
system inputs shall
be derived from
signals
which are direct measures
of the desired variables."
Since
containment
pressure
is not
a direct variable for the steam line break
accident
inside containment
(high steam flow in
a single affected
steam
line is the direct variable),
the team determined that there
appeared
to
be
some
measure of feasibility and practicality for the licensee
to use
the direct variable to detect
steam line break.
The containment
pressure
channel
(whose transmitters
are located outside
containment)
was considered
the "primary" protection
channel for
detecting
secondary
steam piping breaks inside containment.
The main
steam flow high/feedwater
flow low mismatch
was considered
a diverse
channel
to the steam generator
(SG) low-low trip channel.
In addition,
the team determined that since the steam flow transmitters
were located inside containment,
they would sense
high steam flow
associated
with a steam line break inside containment,
and would be
exposed
to
a harsh
environment created
by the steam line break inside
containment,
However,
the team noted that
EA terms
due to harsh
environments
were not incorporated into the setpoint calculation.
~
~
3.3
Based
on the above considerations,
this issue is considered
to be
an
inspection followup item pending further review and evaluation
by the
Office of Nuclear Reactor Regulation
316/93012-01D(DRS)).
Condensate
Stora
e Tank
Level Channels - Function for
Accident Miti ation
The Condensate
Storage
Tank
(CST) is designed to provide
a water source for
large changes
in steam cycle inventory caused
by load transients,
system
draining or blowdown,
and startup
and shutdown activities during plant normal
operation.
During design basis accidents,
such
as loss of main feedwater,
steam line break'r loss of AC power to plant auxiliaries,
the
CST provides
the primary water source to the auxiliary feedwater
pumps.
The electronic
CST level channels
(1-2-CLI-113 and 1-2-CLI-114) are required
to meet the guidelines of Regulatory
Guide 1.97 for Type D, Category
1,
variables.
3.3.1
Set oint Calculation
and Basis
The team observed that setpoint calculation
E.C.P.
1-2-C1-01,
"Condensate
Storage
Tank Level," Revision 9,
used
Foxboro Model
N-E11GM-HSAA1 instead of
models
E13DM-HSAHl and
N-E13DM-HAH1-BHL for the determination of the sensor
uncertainty terms.
The licensee
stated that the correct performance
data
was
used in the setpoint calculation;
however,
the calculation listed the wrong
model
number
and failed to contain the actual transmitter
performance
documentation.
The licensee
issued
a condition report to track this
discrepancy
and committed to revise the E.C.P.
The team considered this to be
a calculation
weakness.
3.3.2
Instrument
Loo
Errors
Due to Seismic Effects not Addressed
The team found that setpoint calculation
E.C.P.
No. 1-2-C1-01,
"Condensate
Storage
Tank Level", dated August 1993, for the
CST electronic level channels
1, 2-CLI-113 and
1, 2-CLI-114 did not address
the bias errors
due to seismic
effects.
The team noted that the
UFSAR identifies
CST level as"a "type D"
variable (i.e.,
a variable that provides information to the operator to
indicate operation of safety systems
and for manual functions).
Regulatory
Guide 1.97,
" Instrumentation for Light Water Cooled Nuclear
Power Plants to
Assess
Plant
and Environs Conditions During and Following an Accident,"
Revision 3, identified
CST water level
as
a "type D" Category
1 variable which
require seismic qualification so that the instrumentation
continues to perform
within required
accuracy following a seismic event.
The team determined that the licensee
did not possess
supporting technical
evaluations
and
had not assessed
the impact of seismic events
on instrument
channels.
Errors associated
with the seismic events
have not been
analyzed
in
the setpoint calculations.
The licensee
agreed
to strengthen
the design guide in the discussion
of
seismic effects
and to define what specific plant conditions
and instrument
loop functions should
be considered for inclusion into the calculations.
Per
NRC request,
the licensee
performed
a preliminary assessment
which indicated
that after the event transmitters
are restored to normal
accuracy,
with
extreme errors of +0.28X/-0.21K of span,
based
on seismic testing.
Although
the calculation would need to be revised to accommodate
the seismic error,
sufficient margin remained
between the actual
setpoints
and the required
setpoints.
Additionally, Westinghouse
has also stated that the Reactor
Protection
System
(RPS)
and Engineered
Safeguard
Feature Actuation System
(ESFAS) equipment typically experiences
an error, but returns to normal
accuracy
based
on seismic testing experience.
This issue is considered
an inspection followup item pending further review
and evaluation
by the Office of NRR (315/93012-01E(DRS);
316/93012-01E(DRS)).
3.4
Essential
Pum
Flow and Dischar
e Pressure
Channels
Function for S stem Monitorin
The Essential
Service'Water
(ESW) System provides the cooling water under all
operating
modes
and accident conditions for the component cooling water
(CCW)
heat exchangers,
the emergency diesel
generator
coolers,
the containment
spray
heat exchangers
and the control
room air conditioning condensers.
It also
provides
an emergency
supply of water to the auxiliary feedwater
pumps in the
event the condensate
storage
tanks are emptied or unavailable.
All four
pumps receive
a Safety Injection (SI) start signal during
a
DBA and are shared
by both units.
The team reviewed the
ESW east
pump flow channel
(1-WFA-701)
and the discharge
pressure
channel
(1-WPA-701).
This instrumentation
was classified
as
BOP by
the licensee.
0
3.4. 1
Set oint Calculation
and Basis
The team identified the following discrepancies
in E.C.P. setpoint
calculations
No. 1-2-W7-04, "Essential
Service Water Instrument Sensitivity
Review," Revision
1,
and
No. 1-2-W7-02, "Essential
Service
Water Flow Mismatch
Alarm Setpoints,"
Revision 2:
(1)
E.C.P.
No. 1-2-W7-02 indicated that the alarm setpoint for
lE
flow mismatch
(1-WFA-701) was changed
from 10X to
25%%d (less
conservative).
However,
a detailed
basis for the flow alarm
and the
basis for the setpoint
change
had not been provided in the calculation.
(2)
The team determined that calculations
No.
1-2-W7-02
and
No.
1-2-W7-04
were unauditable
because
the calculations
did not contain supporting
documentation (i.e., the calculations
did not have vendor data sheets
and Westinghouse
data).
Also, the setpoint calculations did not account
for sensor
and rack measurement
and test equipment uncertainty
terms
(SMTE and
RMTE).
(3}
E.C.P.
No.
1-2-W7-04 did not account for uncertainties
with respect
to
head
and line loss
between
the pressure
transmitter
and its
process
tap connection.
Also, the setpoint for the
ESW pump discharge
pressure
alarm was chosen
based
on engineering
judgement.
In addition,
the
team was concerned
as to why the
ESW flow mismatch
alarm
(WFA-?01
and
WFA-703) had
been recently defeated.
The licensee's
(PRA) Report indicated that loss of
ESW is
an
6
analyzed
event
and restoration of flow to one
one hour.
Also,'he
UFSAR (page 9.8-27) stated that the
ESW system
was
equipped with flow alarms and/or indicators which signify losses
from the
supply headers.
Although indication in the control
room would be available,
the team was concerned
that potentially valuable information to the operators
has
been lost with the removal of the control
room annunciators.
Therefore,
the team questioned
the basis for the setpoint
change
and the subsequent
disconnection of the mismatch alarm.
In response
to the above concerns,
the licensee
stated that the
instrumentation
and alarm functions were considered
nonsafety related, that
the
ESW flow and
pump discharge
pressure
instrumentation
was not critical to
the operation of the plant during normal or DBA conditions,
and that the
flow and pressure
alarms
and indication were not identified in the plant
Emergency Operating
P'rocedures
(EOPs).
In addition, the team was informed
that the
ESW flow mismatch
alarm was defeated
by Plant Nodification PH-676 due
to nuisance
alarms in low flow conditions
and obsolete electronic equipment
causing
increased
maintenance
and decreased reliability of the alarm.
The
licensee
had concluded that the E.C.P. calculation did not need to be
comprehensive
with respect
to setpoint uncertainties.
The team was concerned
over the apparent
loss of necessary
information to the
operator.
The team could not identify specific requirements
with respect to
the basis for classifying the
ESW instrumentation
loops
as nonsafety related.
However, the team informed the licensee that omissions,
errors,
and lack of
supporting documentation
were additional
examples of calculation weaknesses.
Hain Turbine Control Oil Pressure
Switch
Function for Turbine
Control
and Reactor Protection
The team reviewed the Unit 81 main turbine control oil pressure
switch
instrumentation
(I-LPS-90).
This pressure
switch senses
low EHC control oil
pressure
and provides
a signal to the reactor trip system.
3.5.1
Set oint Calculation
and Basis
The team noted that pressure
switch I-LPS-90 did not have
a setpoint
calculation or analysis to substantiate
the setting,
The licensee
informed
the team that the setpoint
was based
on the vendor's
recommendation.
This was
acceptable
to the team.
3.6
Refuelin
Water Stora
e Tank
Level Channels
Function for
Accident Hiti ation
The Refueling Water Storage
Tank
(RWST) provides
a means of storage
and
transfer of water for refueling operations
and
a source of water for the
Emergency
Core Cooling System
(ECCS).
During design basis
accidents,
the
supplies
low concentration,
borated water to the safety injection system,
residual
heat
removal
system,
centrifugal charging
system,
and containment
spray system.
The
RWST for each unit has
two level instrumentation
channels
(ILS-950 and
ILS-951) which provide recording
and indication, level alarms
(high, minimum,
low, and low-low) and
a low-low level trip of the
RHR pumps.
The differential
pressure
transmitters
used with these
level channels
are located in the
'ipe
tunnel.
The
RWST level channels
are required to meet the guidelines of
Regulatory
Guide 1.97 for Type A, Category
1, variables.
3.6. I
Set oint Calculation
and Basis
The team identified the following discrepancies,
errors
and omissions
in
E.C.P. Calculation
No. 1-2-I9-03,
"RWST Level/RHR Pumps Interlock," Revision
10,
and its associated
design drawings
and technical
data:
(1)
The uncertainty.
values for the
RWST level transmitters
(ILS-950 and ILS-
951)
wer e based
on vendor performance
data sheets for Foxboro "N-E13"
series transmitters rather than the installed Foxboro model
transmitters.
Justification for use of "N-E13" series transmitter
performance
data
was not provided in the calculation.
In response
to
the team's
concern,
the licensee
performed
an equivalency evaluation
which demonstrated
that the N-E13 and
E-13 series transmitters
were
functionally identical.
The licensee
informed the team that E.C.P.
No.
1-2-I9-03 will be revised to resolve this issue
and incorporate
the
appropriate
evaluation.
(2)
(3)
Calculation
E.C.P.
No. 1-2-I9-03 determined
the uncertainty for process
measurement
effects,
due to water height
and density values,
using
licensee
selected
worst case transmitter elevation of 599'" (i.e., the
lowest elevation of Units ¹1
and ¹2 transmitters
or the largest
span).
When questioned
by the team,
the engineer
could not provide
justification for selecting elevation 599'".
The team observed that
instrument piping drawing 1-5568C-2, and installation drawing 1-2-19-03,
Revision
10,
showed the transmitters
installed at different elevations
below 599'3".
In response
to the team's
concern,
the licensee
walked
down the installation
and determined that Unit ¹1 transmitters
were
installed at elevation
599'
1/2" (1-ILS-950)
and 599'
1/2" (1-ILS-
951),
and Unit ¹2 transmitters
were installed at elevation 599'" (2-
ILS-950 and 2-ILS-951).
Consequently,
instrument loop uncertainty
calculation
E.C.P.
No 1-2-I9-03 used incorrect data in the determination
of the process
measurement
effect error.
The licensee
generated
a
Condition Report to document
the elevation discrepancies
and revise the
installation drawings
and E.C.P.
No. 1-2-I9-03.
The team noted that the
RWST level transmitters,
ILS-950 and ILS-951,
use
an impulse line with connection directly off the 24" diameter safety
injection suction pipe.
The team determined that
RWST level instrument
loop setpoint calculation E.C.P.
No. 1-2-I9-03 did not account for the
error effects of the velocity head of the
pump flow (safety
injection and residual
heat
removal
pumps) during design basis
accidents'
In response
to the team's
concern,
the licensee
generated
a condition
report to document this issue.
The licensee
also prepared
a preliminary
assessment
which showed that although the calculation will change,
sufficient margin remains
between
the actual setpoints
and the required .
setpoints.
The team determined that the findings noted
above did not have
a significant
impact
on safety;
however,
the team examined only a small
sample of the
instrument loops at D.
C.
Cook and
was concerned
with the number of problems
in the small
sample.
noted
~
~
3.6.2
Sensin
Line Slo es
and
Bend Radii
(4)
The team identified that flow diagram OP-1-5144-13,
System Unit O'I," incorrectly showed
RWST level transmitter
ILS-950 as
having
a minimum level alarm at elevation 638'l".
However, the team
determined that the correct setpoint value was 637'".
It
In addition, Installation drawing 1-2-I9-03, Revision
10,
showed
a 36"
required separation
between
the
RWST level transmitters,
ILS-950 and
ILS-951.
Instrument piping drawing 1-5568C-2
shows only 28" separation.
The licensee
performed
a walkdown of the transmitters
and determined
that the transmitters
were separated
by greater than 36".
The licensee
generated
a Condition Report to document
and resolve the setpoint
and
as-built discrepancy
on the drawings.
The design control errors discussed
in items
(1) through
(4) above,
are
considered
to be examples of a violation of 10 CFR 50, Appendix B, Criterion
III (315/93012-02(DRS);
316/93012-02(DRS)).
The team identified that the instrument
impulse lines routed
from the tap
connection to the
RWST level transmitters
(ILS-950 and ILS-951) were not
sloped
downward to the transmitter
and instrument piping drawing 1-5568C-2 did
not specify requirements
for sloping impulse lines.
The licensee
performed
a walkdown and confirmed that the lines were not
sloped.
The licensee
stated that lack of line slope will not adversely affect
the ability of these transmitters
to sense
level
as long as the lines are
filled and vented.
The team verified that the licensee's
calibration
procedure
required filling and venting the lines prior to placing the
transmitters
back into service.
The team also noted that sensing line slopes
and
bend radii were not depicted
in the sensing line routing drawings
reviewed
by the team.
Consequently,
gases
trapped
in wrongly sloped pressure
measuring
sensing lines could cause
response
times to increase
and incorrect
bend radii
may result in sensing line
failures.
The team informed the licensee that the lack of instrument line slope
requirements
was not consistent
with industry installation good practices.
3.6.3
Instrument
Loo
Errors
Due to Accident Environments
not Addressed
The team found that the setpoint calculation for RWST level channels
ILS-950
and
ILS-951
(No. 1-2-I9-03) did not address
the impact of the
HELB environment
and the resultant
bias errors associated
with the instrument cable insulation
resistance
degradation effects.
In fact, the team noted that E.C.P.
No. 1-2-
I9-03 incorrectly stated that the
RWST instrument
loops are located in a
"mild" environment.
The team determined that the instrumentation
cables for
transmitters
ILS-950 and ILS-951,
shown
on Conduit and Cable
Plan Drawing 1-
1437A-55,
were routed through
(HELB) environment
area.
The
HELB environment,
defined
as
a harsh
environment
by the
environmental qualification (Eg) program, is caused
by a postulated
steam
generator
blowdown accident at the 633'levation of the auxiliary building.
The
UFSAR stated that during
a
SG blowdown, the steam
blowdown cools the
reactor
coolant
and the high pressure
delivery of RWST borated water
by the
centrifugal
charging
pumps reestablishes
adequate
Procedure
NESP 19.04,
"Engineering Control Procedures,"
required instrument
loop error analyses
to be in accordance
with Engineering
Guide EG-IC-004,
"Instrument Setpoint/Uncertainty."
Engineering
Guide EG-IC-004 required that
the error effects associated
with accident
environments (i.e., high
temperature
steam,
pressure
and radiation)
be accounted for in the loop
uncertainty calculation, if applicable.
Similarly, Westinghouse
setpoint
methodology presented
in WCAP-13801,
"Setpoint Methodology for Protection
Systems,
Donald
C.
Cook, Unit 2," dated August 1993, required that
an
environmental
allowance bias error
(due to accident
environment effects)
be
applied to the instrument loop uncertainty calculation, if applicable.
In
addition, ANSI/ISA-S67.04-1988,
"Setpoints for Nuclear Safety-Related
Instrumentation" delineates
consideration
of accident
environmental effects.
Regulatory
Guide
1. 105,
"Instrument Setpoints for Safety Related
Systems,"
Revision 2, endorses
ISA S67.04.
Finally, Regulatory Guide 1.97,
"Instrumentation for Light Water Cooled Nuclear
Power Plants to Assess
Plant
, and Environs Conditions During and Following an Accident," Revision 3, states
that instrumentation for Category
1
and
2 variables require environmental
qualification
and instrumentation for Category
1 require seismic
qualifications
so that the instrumentation
continues
to perform within
required accuracy following a design basis accident.
The licensee
contended that cable degradation
errors would not be present
under conditions for which the alarms or interlocks associated
with the
level channel
are required.
Further,
the licensee
stated that the safety
analysis
and licensing basis require
assessment
of environmental
errors which
are
a direct result of design basis
events for safety system setpoints
associated
with reactor trip and safeguards
actuation.
The
D.
C.
Cook
setpoint methodology for protection
systems
incorporates
environmental
allowances for all functions that are credited in the plant safety analysis
for design basis
events,
where cables
and transmitters
could
be potentially
exposed to harsh
environments,
inside or outside containment.
For post-
accident monitoring (as
opposed
to protection functions), in conjunction with
the Westinghouse
Owner's
Group
(WOG) Emergency
Response
Guidelines
(ERGs),
provisions
were
made to accommodate
environmental
allowances for cable
and
transmitters
associated
with harsh
environments
inside containment only.
The
10
0
- team determined. that there
was
no provision in the
ERGs to account for the
effect on instrument readings
due to line breaks
outside containment.
The
licensee
stated that this methodology
was
used
because
there are
many diverse
instruments,
not exposed to the accident
environment,
which would function
under line break conditions outside containment;
that harsh
environmental
conditions
due to accidents
are generally of short duration;
and the resulting
errors associated
with harsh
environments
outside containment
are often small
and insignificant.
Although the team agreed that for the setpoint in question
the errors would generally
.be small,
we were concerned that these
issues
had
not been
addressed
by the licensee prior to the team's inquiry.
The team concluded that the assessment
of environmental
effects should
have
been
accounted for in the setpoint calculations.
This issue is considered
an
inspection followup item pending further review and evaluation
by the office
316/93012-01F(DRS) ) .
3.7
Desi
n Guides
and Criteria
The team noted that the licensee
lacked
adequate
design standards,
design
criteria and design specifications for instrument
component installations.
For example:
There were
no drawings which show the installation or routing of
instrument
sensing lines.
There
was
no specification for minimum dew point requirements
of
instrument air which supplied
pneumatic
instruments.
Although there
was
no safety related
pneumatic
instruments,
a number of instruments
were
used
by the licensee
to satisfy Regulatory
Guide 1.97 requirements.
There
was
no design specification for determination of instrument
sensing line piping ovality.
Also, the team noted that corporate
engineers
were not always
aware of which
specifications,
industry codes,
standards,
guides, etc., to use during
preparation
and review of I&C calculations
and modifications.
Inadequate
identification of applicable
codes,
standards,
industry guides etc.
was
evident in engineering
design
documents
that were reviewed
by the team.
In
response
to the team's
concern,
the l,icensee
stated that efforts were underway
to improve access
to pertinent information.
The licensee
also stated that
a
Design Basis Reconstitution
Program
was underway.
3.8
Measurin
and Test
E ui ment
and Labelin
of I&C Com onents
The inspectors
noted that the licensee's
control of measuring
and test
equipment
(M&TE) was very good.
The team found that
M&TE issue control,
accuracy,
storage
and the intervals for calibration were adequate
and within
vendor recommendations
and
damaged
or out of tolerance
M&TE instruments
were
adequately
controlled.
Also, labeling of I&C components
was excellent.
11
3.9
Instrument Calibration
and Testin
The team reviewed the calibration
and functional tests,
surveillance tests,
and response
time tests
associated
with the instrument loops reviewed.
The
test procedures
were user friendly and incorporated
clear
acceptance criteria.
The procedures
incorporated
the correct Technical Specification
(TS) setpoint
values,
and the instrument channel/system
response
times fulfilled TS
requirements
and were equal to or conservative
to the values
assumed
in the
accident analysis.
The team concluded the instrument testing program
was
good.
4.0
Review of I&C Modifications and Desi
n Control
Based
on 'the review of 10
I&C modifications, the team concluded that the D. C.
Cook program for controlling plant modifications associated
with I&C was
generally good;
however,
several
weaknesses
were identified during review of
I&C modifications.
4.1
Modifications MM-003 and
MM-210
(a)
MM-003:
Installation of Permanent
Test
Gau
es
The team noted that both units'ast
and west containment
spray
pump inservice
test
(IST) suction
gauge isolation valves were signed off as being closed,
but
were not independently verified closed.
The pressure
were not
seismically qualified which made the isolation valve the pressure
boundary.
~
~
~
In response,
the licensee
added
an independent verification step to the
affected
IST procedures.
This was acceptable
to the team.
(b)
MM-210:
S ent Fuel Pit Hi
h
Low Level Alarm
0
Annunciator Procedure
12-OHP 4024. 134,
Drop 2, initiating device
RLA-500
(63-1
SFPL)
was changed
to RLA-501
(63X SFPL) instead of adding
RLA-501
to the device list.
0
Annunciator Procedure
1-OHP 4024. 105,
Drop 27,
had
an incorrect
initiating device.
c
Drawing OP-12-98315-6
contained deficient labeling for Annunciator-Drop
27 and the relay table for 63-SFPL.
In response,
the licensee
corrected
the annunciator
procedures
and issued
a
condition report to track the drawing revision.
The team verified the wiring
'onfiguration
was correct in the field and concluded
the annunciator
procedures
setpoint value,
window description
and operator actions
were
unaffected
by the identified discrepancies.
12
4.2
Review of Tem orar
Modification to Hain Feedwater
Pum
I
The team identified that the licensee failed to perform
evaluation.
In addition, the team was concerned
with the licensee's
design
implementation of nonsafety related
temporary modification 2-93-015.
Due to
previous
problems with the Unit 2 automatic
mode control, the licensee
initiated
a temporary modification to install two I/I (current to current)
converters
in the east
and west main feed
pump speed control circuits.
The
I/I converters
were installed
between the main feed
pump pressure
setters
and
the auto/manual
control stations.
The modification would correct the problem
with the automatic
mode
and provide ground fault isolation between
the
pressure
setters
and the hand(auto stations.
Mork under job order
(JO)
A0041043
was started
on August 6,
1993,
and completed
on August 10.
On
August 27,
1993,
one of the two I/I converters failed which produced
a minimum
speed
signal to the east
main feed
pump.
The reduction in feedwater flow
caused
a low-low steam generator
level which resulted in the Unit 2 reactor
trip.
The team evaluated
the circumstances
associated
with the failure of the I/I
converter.
The team concluded that measures
were not established
to assure
adequate
design
implementation
and review of temporary modification 2-93-015.
The team identified the following:
.
The D. C.
Cook Onsite Safety Review Committee does not evaluate
nonsafety related
temporary modifications which have the potential for
causing
a reactor trip or challenging
a safety system.
During the temporary modification design process,
the
IKC engineer
failed to refer to the Foxboro I/I converter vendor manual.
The
engineer
instead referred to another
D. C.
Cook instrumentation
drawing
which had
no relation to the terminal connections of the I/I converters.
Consequently,
the engineer specified the wrong input and output terminal
connections
on the design drawings.
The engineer failed to specify the required
100
ohm voltage drop
resistor
across
the input for the I/I connector.
The nameplate
on the
I/I converter specifically stated that for correct resistor size,
the
vendor manual
must
be reviewed (the licensee's
original installation
drawing did not specify any resistor).
The
I8C supervisor
performed
two separate
independent
reviews
and signed
off on the drawings
and the modification package,
even
though the
installation drawings
and the temporary modification package
contained
the above design errors.
The incorrect input and output connections
to the I/I converters
were
subsequently
identified during calibration;
however,
the engineer still
did not refer to the vendor manual
to verify the input and output
connections.
13
Unable to calibrate
the I/I converter,
licensee
personnel finally
discovered that the
100
ohm resistor
was missing.
The licensee failed to document
on
a job order or condition report that.
the above deficiencies
were encountered.
The
IEC engineer that provided the design input for the temporary
modification was not trained in Foxboro instrumentation.
There was
no training on troubleshooting of vendor supplied
components
such
as the pressure
setter in the speed control. circuitry.
The licensee
lacked adequate
interconnection
design drawings which
depicted
the circuitry of the pressure
setter.
The licensee's
failure to perform
a 50.59 evaluation
was due to the plant
engineers'verly
restricted interpretation of the main feed
pump speed
control
system which was described
in the
The team noted that all five
sections of the safety evaluation
screening checklist were marked
"no"
including the section which asks whether the modification is
a change to the
plant
as described
in the
Section
10.5. 1. 1 of the
D.
C.
Cook
stated that the variable
speed turbine driven main feedwater
pumps were
designed to provide the required
feedwater to the steam generators.
10 CFR 50.59 states
that the licensee
must include
a safety evaluation
providing the bases
for determining that the change did not involve an
unreviewed safety question.
The licensee
stated that the failure of the I/I converter
was determined to
have the
same effect as the failure of the hand/auto station already in the
circuit.
Although this statement
was basically correct,
the team determined
that the licensee failed to perform
a safety evaluation
and include
a written
evaluation
which provided the bases for the determination that the change did
not involve an unreviewed safety question.
The licensee
stated that failure of the east
main feed
pump speed control
circuit was directly related to failure of the I/I converter.
Consequently,
failure of the I/I converter,
which had not previously been part of the speed
control circuit, resulted
in a significant plant transient.
On September
10,
1993, the licensee
removed the I/I converter
from the speed control circuit.
By failing to recognize that the
speed control
system
was described
in the
UFSAR, the licensee
concluded that
was not applicable,
therefore,
no safety evaluation
was performed.
The licensee's
failure to perform
a
safety evaluation is considered
to be
a violation of 10 CFR 50.59 (315/93012-
4.3
Field Walkdown Ins ection
The team observed
during field walkdown inspection,
that instrument
sensing
line 2-FFS-257,
associated
with the auxiliary feedwater
system,
was not
supported
over
a span of about
10 feet.
The licensee's
hanger specification
14
,
required that the line be supported
over
a span not to exceed six feet.
The
licensee
wa's in the process of performing
a calculation to determine
whether
the sensing line installation
was adequate.
Pending review of the
calculation, this item is considered
unresolved
(315/93012-04(DRS);
316/93012-.
04(DRS)).
5.0
En ineerin
and Technical
Su
ort
The team evaluated
D.
C. Cook's
I8C engineering
and technical
support
capability.
The team reviewed the licensee's
programs for temporary
modifications, plant modifications
(PHs), request for change
(RFC),
and minor
modifications
(HHs}, engineering interfaces,
document
and drawing control,
discrepancy
management,
safety evaluations
(10 CFR 50.59), test development
and control,
and maintenance.
In addition, the team
reviewed root cause
analyses
and training programs for engineers
and
interviewed corporate
and plant
I8C engineers.
Overall, the team concluded that the extent
and quality of engineering
and
technical
support
was good.
The engineering staff was generally competent
and
very experienced.
Permanent
modifications reviewed generally contained
good
design control, well documented
safety evaluations
and adequate
post
modification testing.
However, the team
was concerned
with the design control
and implementation of temporary modification 2-93-015
as discussed
in Section
4.2 of this report.
Communication
between
engineering
and other groups
appeared
to be effective.
However,
some of the engineers
that interfaced with
the team were not aware of I&C plant design
requirements
and could not explain
the technical
content in their response
to team concerns.
Also, there
appeared
to be
a lack of coordination
between
the
Eg engineering
group
and the
I&C engineers
that perform setpoint calculations.
5.1
En ineerin
Staff Trainin
The team was informed that there were
23 engineers
in AEP's Nuclear
Engineering Electrical
Instrumentation
(NEEI) Department in Columbus,
Ohio.
Their primary involvement for several
years
has
been associated
with the
reactor protection
system
(RPS/ESFAS)
Foxboro H-Line instrumentation
upgrade
program for the D.C.
Cook nuclear
power plant.
The
I8C engineers
who were
interviewed
had substantial
engineering
experience
and appeared
to have
positive attitudes.
In addition, the
I8C corporate
engineers
appeared
to be
involved with the detailed instrumentation
and control design activities at
the plant.
The team reviewed selected
I&C engineer's
training program, training records
and work .experience.
In addition, the team conducted
interviews
and technical
discussions
with selected
I8C engineers.
The team determined that
I&C plant
system
and component
engineers
were not trained
on existing or old plant
instrumentation,
design
and troubleshooting.
This fact may have contributed
to the poor design effort and implementation of temporary I/I converter
modification 2-93-015.
In addition,
the
team determined that there
appeared
to be
a need for guidance
and training of corporate
I&C engineers
in the use
of the various specifications,
industry codes
and standards
such
as sloping
requirements,
impulse line support criteria, accident
analyses,
etc.
15
5.2
Safet
Evaluation Screenin
Process
The team noted that procedure
No.
PHP 1040.SES.OOI,
Revision 0, "Safety
Evaluation Screening,"
did not stress
that the second
reviewer perform an
independent
evaluation.
The screening
preparer identifies during the
screening
process
the applicable references/justification.
A safety
evaluation
was not required if all of the questions
were answered
"no".
In response,
the licensee
provided the initial and continuing training lesson
plans
used to teach the safety evaluation
screening
process.
The lesson
plans
contained instructions that both the original screening
preparer
and the
reviewer are to perform independent
screening
evaluations.
In addition, the
licensee
indicated they would revise procedure
No.
PHP 1040.SES.OOI
to stress
that both reviewers
must perform an independent
evaluation.
This was
acceptable
to the team.
5.3
Review of Licensee Self Assessment
Pro
ram in the
I&C Area
The team reviewed
ILC related audits
and surveillances
performed in the last
two years.
The team noted that in preparation for the SBICI, the licensee
had
hired
a contractor to evaluate
and assess
the various
I&C areas.
The audit
and surveillance
performed in Hay-June
1993, identified some similar findings
to the ones identified by the team.
The team considered
the self-initiated
SBICI a positive management initiative.
However,
the team noted that except
for the SBICI preparation
audit, very little similar audit activity was
performed in the
I&C area relative to the setpoint
program.
The licensee
informed the team that this audit activity has
been recently
added to the
audit schedule.
6.0
Ins ection Followu
Items
Inspection followup items are matters
which have
been discussed
with the
licensee,
which will be reviewed further by the team,
and which involve some
action
on the part of NRC or licensee
or both.
Followup items disclosed
during the inspection
are discussed
in Sections
3. 1, 3.2, 3.3
and 3.6 of this
report.
7.0
Unresolved
Items
Unresolved
items are matters
about which more information is required
in order
to ascertain
whether they are acceptable
items, violations or deviations.
Unresolved
items disclosed
during this inspection
are discussed
in Section 4.3
of this report.
8.0
Exit Meetin
The team conducted
an exit meeting
on September
28,
1993, at the
D. C. Cook
Nuclear
Power Plant, to discuss
the major areas
reviewed during the
inspection,
the strengths
and weaknesses
observed
and the inspection results.
licensee
representatives
and
NRC personnel
in attendance
at this exit meeting
are documented
in Appendix A.
The team also discussed
the inspection report's
likely informational content with regard to documents
reviewed 'by the team
J
during the inspection.
The licensee identified the proprietary documents
and
the team agreed to handle this information accordingly.
The licensee
considered
EG Instrument
Loop Setpoint Hethodology Guide EG-IC-004;
WCAP-13055, Revision
1, "Setpoint Hethodology for Protection
Systems - D.
C.
Cook, Unit 1," and Westinghouse
"Setpoint
Hethodology for Protection
Systems - D.
C.
Cook Unit 2," August 1993, to be
proprietary.
No proprietary information from that guide is contained
in this
report.
17
i ~ g
0
APPENDIX A
PERSONNEL
CONTACTED
American Electric Power Service
Cor oration
AEPSC
M. Ackerman,
Engineer,
Nuclear Licensing
S. Brewer,
Manager,
Nuclear Safety
and Licensing
S. Farlow, Assistant
Manager',
Nuclear Engineering
Department
B. Kalinowski, gA/gC Engineer
P. McCardy,
gA Senior Engineer
C. Savitscus,
Nuclear Licensing
Indiana Michi an
Power
D. C.
Cook Nuclear
Power Plant
K. Baker, Assistant
Plant Manager,
Production
A. Blind, Plant Manager
J. Kovari k, Systems
Engineer/PLE
S. Hacey,
I8C System
Engineer/PLE
S. Richardson,
Operations
Superintendent
J.
Rotkowski, Assistant
Plant Manager,
Technical
R. Russell,
Project Engineering
T. Walsh,
Procedures
Supervisor,
Maintenance
G. Weber,
Superintendent/PLE
J.
Wiebe, Superintendent,
Surveillance
and Audits
U.
S. Nuclear
Re ulator
Commission
~
~
R. Gardner,
Chief, Plant Systems
Section
D. Hartland,
Resident
Inspector
~ g