ML17326B028

From kanterella
Jump to navigation Jump to search
Proposed Tech Specs Requesting Extension for Certain Surveillances That Must Be Performed During Shutdown & Before 860331 Including Reactor Trip Sys Instrumentation & ESFAS Instrumentation
ML17326B028
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 12/13/1985
From:
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To:
Shared Package
ML17326B027 List:
References
NUDOCS 8512200038
Download: ML17326B028 (18)


Text

ATTACHMENT 2 TO AEP:NRC:0967 PROPOSED CHANGES TO THE DONALD C.

COOK NUCLEAR PLANT UNIT NO.

2 TECHNICAL SPECIFICATIONS

( 8ggp200038 8512

'DR ADOCK 0 PDR P

3/4.0 APPLICABILITY SURVEILLANCE RE UIREMENTS b.

Surveillance intervals specified in Section XI of the ASME Boiler and Pressure Vessel Code and applicable Addenda for the inservice inspection and testing activities required by the ASME Boiler and Pressure Vessel Code and applicable Addenda shall be applicable as follows in these Technical Specifications:

ASME Boiler and Pressure Vessel Code and applicable Addenda terminology for inservice inspection and testin criteria Required frequencies for performing inservice in-spection and testing activities Weekly Monthly Quarterly or every 3 months Semiannually or every 6 months Yearly or annually At least once per 7 days At least once per 31 days At least once per 92 days At least once per 184 days At least once per 366 days c.

The provisions of Specification 4.0.2 are applicable to the above required frequencies for performing inservice inspection and testing activities.

d.

Performance of the above inservice inspection and testing activities shall be in addition to other specified Surveillance Requirements.

e.

Nothing in the ASME Boiler and Pressure Vessel Code shall be construed to supersede the requirements of any Technical Specification.

4.0.6 Those surveillances which must be performed on or before March 31, 1986 and are designated as 18-month surveillances (or required as outage-related surveillances under the provisions of Specification 4.0.5) may be delayed until the end of the refueling outage scheduled to begin on or before February 28, 1986.

The provisions of Specification 4.0.2.b are not applicable to any prior surveillances which have been performed under this provision of Specification 4.0.6. It should be noted that for surveillances performed under this section, previous surveillances required by Specification 4.0.2.b will never be considered again.

D. C.

COOK UNIT 2 3/4 0-3 Amendment No.

3/4.3 INSTRUMENTATION 3/4.3.1 REACTOR TRIP SYSTEM INSTRUMENTATION LIMITING CONDITION FOR OPERATION 3.3.1.1 As a minimum, the reactor trip system instrumentation channels and interlocks of Table 3.3-1 shall be OPERABLE with RESPONSE TIMES as shown in Table 3.3-2.

APPLICABILITY:

As shown in Table 3.3-1.

ACTION:

As shown in Table 3.3-1.

SURVEILLANCE RE UIREMENTS 4.3.1.1.1 Each reactor trip system instrumentation channel shall be demonstrated OPERABLE by the performance of the CHANNEL CHECK, CHANNEL CALIBRATION and CHANNEL FUNCTIONAL TEST operations for the MODES and at the frequencies shown in Table 4.3-1.*

4.3.1.1.2 The logic for the interlocks shall be demonstrated OPERABLE prior to each reactor startup unless performed during the preceding 92 days.

The total interlock function shall be demonstrated OPERABLE at least once per 18 months during CHANNEL CALIBRATION testing of each channel. affected by interlock operation.*

4.3.1.1.3 The REACTOR TRIP SYSTEM RESPONSE TIME of each reactor trip function shall be demonstrated to be within its limit at least once per 18 months.

Each test shall include at least one logic train such that both logic trains are tested at least once per 36 months and one channel per function such that all channels are tested at least once every N times 18 months where N is the total number of redundant channels in a specific reactor trip function as shown in the "Total No. of Channels" column of Table 3.3-1.*

The provisions of Specification 4.0.6 are applicable.

D. C.

COOK UNIT 2 3/4 3-1 Amendment No.

INSTRUMENTATION 3/4.3.2 ENGINEERED SAFETY FEATURE ACTUATION SYSTEM INSTRUMENTATION LIMITING CONDITION FOR OPERATION 3.3.2.1 The Engineered Safety Feature Actuation System (ESFAS) instrumentation channels and"interlocks shown in Table 3.3-3 shall be OPERABLE with their trip setpoints set consistent with the values shown in the Trip Setpoint column of Table 3.3-4 and with RESPONSE TIMES as shown in Table 3.3-5.

APPLICABILITY:

As shown in Table 3.3-3.

ACTION:

a.

With an ESFAS instrumentation channel trip setpoint less conservative than the value shown in the Allowable Values column of Table 3.3-4, declare the channel inoperable and apply the applicable ACTION requirement of Table 3.3-3 until the channel is restored to OPERABLE status with the trip setpoint adjusted consistent with the Trip Setpoint value.

b.

With an ESFAS instrumentation channel inoperable, take the ACTION shown in Table 3.3-3.

SURVEILLANCE RE UIREMENTS'.3.2.1.1 Each ESFAS instrumentation channel shall be demonstrated OPERABLE by the performance of the CHANNEL CHECK, CHANNEL CALZBRATION and CHANNEL FUNCTIONAL TEST operations for the MODES and at the frequencies shown in Table 4.3-2.*

I 4.3.2.1.2 The logic for the interlocks shall be demonstrated OPERABLE during the automatic actuation logic test.

The total interlock function shall be demonstrated OPERABLE at least once per 18 months during CHANNEL CALIBRATION testing of each channel affected by interlock operation.*

4.3.2.1.3-The ENGINEERED SAFETY FEATURES

RESPONSE

TIME of each ESFAS function shall be demonstrated to be within the limit at least once per 18 months.

Each test shall include at least one logic train such that both logic trains are tested at least once per 36 months and one channel per function such that all channels are tested at least once per N times 18 months where N is the total number of redundant channels in a specific ESFAS function as shown in the*

"Total No. of Channels" Column of Table 3.3-3.*

The provisions of Specification 4.0.6 are applicable.

D. C.

COOK UNIT 2 3/4 3-14 Amendment No.

TABLE 4.3-10 POST-ACCIDENT MONITORING INSTRUMENTATION SURVEIILANCE RE UIREMENTS CRH INSTRUMENT 1.

Containment Pressure 2.

Reactor Coolant Outlet Temperature - T (Wide Range) 3.

Reactor Coolant Inlet Temperature T

(Wide Range)

CHANNEL CHECK CHANNEL CALIBRATION 4.

Reactor Coolant Pressure Wide Range S.

Pressurizer Water Level 6.

Steam Line Pressure 7.

Steam Generator Water Level Narrow Range 8.

RWST Water Level 9.

Boric Acid Tank Solution Level

10. Auxiliary Feedwater Flow Rate ll. Reactor Coolant System Subcooling Margin Monitor 12.

PORV Position Indicator Limit Switches 13.

PORV Block Valve Position Indicator - Limit Switches*

14. Safety Valve Position Indicator Acoustic Monitor fh80 0
  • The provisions of Specification 4.0.6 are applicable.

REACTOR COOLANT SYSTEM 3/4.4.6 REACTOR COOLANT SYSTEM LEAKAGE LEAKAGE DETECTION SYSTEMS LIMITING CONDITION FOR OPERATION 3.4.6.1 The following Reactor Coolant System leakage detection systems shall be OPERABLE:

a.

One of the containment atmosphere particulate radioactivity monitoring channels (ERS-2301 or ERS-2401),

b.

The containment sump level and flow monitoring system, and c.

Either the containment humidity monitor or one of the containment atmosphere gaseous radioactivity monitoring channels (ERS-2305 or ERS-2405).

APPLICABILITY:

MODES 1, 2, 3 and 4.

ACTION:

With only two of the above required leakage detection systems

OPERABLE, operation may continue for up to 30 days provided grab samples of the containment atmosphere are obtained and analyzed at least once per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> when the required gaseous and/or particulate radioactivity monitoring channels are inoperable; otherwise, be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

SURVEILLANCE RE UIREMENTS 4.4.6.1 The leakage detection systems shall be demonstrated OPERABLE by:

a ~

Containment atmosphere particulate and gaseous (if being used) monitoring system-performance of CHANNEL CHECK, CHANNEL CALIBRATION and CHANNEL FUNCTIONAL TEST at the frequencies specified in Table 4.3-3, b.

Containment sump level and flow monitoring system - performance of CHANNEL CALIBRATION at least once per 18 months,*

I c ~

Containment humidity monitor (if being used) - performance of CHANNEL CALIBRATION at least once per 18 months.

The provisions of Specification 4.0.6 are applicable.

D. C.

COOK UNIT 2 3/4 4-14 Amendment No.

REACTOR COOLANT SYSTEM RELIEF VALVES OPERATING L1MITING CONDITION FOR OPERATION 3.4.11 Three power operator relief 'valves (PORVs) and their associated block valves shall be OPERABLE.

APPLICABILITY:

MODES 1, 2, and 3.

ACTION:

a.

With one or more PORV(s) inoperable, within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> either restore the PORV(s) to OPERABLE status or close the associated block valve(s) and remove power from the block valve(s); otherwise, be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

b.

With one or more block valve(s) inoperable within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> either (1) restore the block valve(s) to OPERABLE status, or (2) close the block valve(s) and remove power from the block valve(s), or (3) close the associated PORV(s) and remove power from the associated solenoid valve(s); otherwise, be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.*

c.

The provisions of Specification 3.0.4 are not applicable.

SURVEILLANCE RE UIREMENTS 4.4.11. 1 Each of the three PORVs shall be demonstrated OPERABLE:

a.

At least once per 31 days by performance of a CHANNEL FUNCTIONAL TEST, excluding valve operation, and b.

At least once per 18 months by performance of a CHANNEL CALIBRATION.**

When ACTION 3.4.1l.b(3) is applied, no report pursuant to Specification 6.9.1.9 is required for the PORV.

    • The provisions of Specification 4.0.6 are applicable.

D. C.

COOK UNIT 2 3/4 4-32 Amendment No.

EMERGENCY CORE COOLING SYSTEMS SURVEILLANCE RE UIREMENTS 4.5.2 Each ECCS subsystem shall be demonstrated OPERABLE:*

a.

At least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> by verifying that the following valves are in the indicated positions with power to the valve operators removed:

Valve Number Valve Function Valve Position c.

IMO-325 d.

e.f.

go h.

IMO-262**

IMO-263**

IMO-261**

ICM-305**

ICM-306**

a.

IMO-390 b.

IMO-315 a.

RWST to RHR b.

Low head SI to Hot Leg c.

Low head SI to Hot Leg d.

Mini flow line e.

Mini flow line f.

SI Suction g.

Sump line h.

Sump line c.

Closed d.

e.f.

gi h.

Open Open Open Closed Closed a.

Open b.

Closed b.

At least once per 31 days by verifying that each valve (manual, power operated or automatic) in the flow path that is not locked, sealed, or otherwise secured in position, is in its correct position.

c.

By a visual inspection which verifies that no loose debris (rags, trash, clothing, etc.) is present in the containment which could be transported to the containment sump and cause restriction of the pump suctions during LOCA conditions.

This visual inspection shall be performed:

1.

For all accessible areas of the containment prior to establishing CONTAINMENT INTEGRITY, and 2.

Of the areas affected within containment at the completion of each containment entry when CONTAINMENT INTEGRITY is established.

The provisions of Specification 4.0.6 are applicable.

    • These valves must change position during the switchover from injection to recirculation flow following LOCA.

D. C.

COOK UNIT 2 3/4 5-4 Amendment No.

EMERGENCY CORE COOLiNG SYSTEMS SURVEILLANCE RE UIREMENTS 4.5.3.1 The ECCS subsystem shall be demonstrated OPERABLE per the applicable Surveillance Requirements of 4.5.2.*

4.5.3.2 All charging pumps and safety injection pumps, except the above required OPERABLE charging pump, shall be demonstrated inoperable, by verifying that the motor circuit breakers have been removed from their electrical power supply circuits, at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> whenever the temperature of one or more of the RCS cold legs is less'han or equal to 152 F as determined at least 0

0 0

once per hour when any RCS cold leg temperature is between 152 F and 200 F.

The provisions of Specification 4.0.6 are applicable.

D. C.

COOK - UNIT 2 3/4 5-8 Amendment No.

CONTAINMENT SYSTEMS DIVIDER BARRIER SEAL LIMITINGCONDITION FOR OPERATION 3.6.5.9 The divider barrier seal shall be OPERABLE.

APPLICABILITY:

MODES 1, 2, 3 and 4.

ACTION:

With the divider barrier seal inoperable, restore the seal to OPERABLE status prior to increasing the Reactor Coolant System temperature above 200 F.

0 SURVEILLANCE RE UIREMENTS 4.6.5.9 The divider barrier seal shall be determined OPERABLE at least once per 18 months during shutdown by:*

a ~

Removing two divider barrier seal test coupons and verifying that the physical properties of the test, coupons are within the acceptable range of values shown in Table 3.6-2.

b.

Visually inspecting at least 95 percent of the seal's entire length and:

1.

Verifying that the seal and seal mounting bolts are properly installed, and 2.

Verifying that the seal material shows no visual evidence of deterioration due to holes, ruptures, chemical attack,

abrasion, radiation damage, or changes in physical appearances.

The provisions of Specification 4.0.6 are applicable.

D. C.

COOK - UNIT 2 V

3/4 6-47 Amendment No.

PLANT SYSTEMS 3/4.7.7 SNUBBERS LIMITINGCONDITION FOR OPERATION 3.7.7.1 All snubbers listed in Table 3.7-9 shall be OPERABLE.

APPLICABILITY:

MODES 1, 2, 3 and 4.

(MODES 5 and 6 for snubbers located on systems required OPERABLE in those MODES).

ACTION:

With one or more snubbers inoperable, within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> replace or restore the inoperable snubber(s) to OPERABLE status and perform an engineering evaluation per Specification 4.7.7.1c on the supported component or declare the supported system inoperable and follow the appropriate ACTION statement for that system.

SURVEILLANCE RE UIREMENTS 4.7.7.1 Each snubber shall be demonstrated OPERABLE by performance of the following augmented inservice inspection program and the requirements of Specification 4.0.5.*

a.

Visual Inspections The first inservice visual inspection of snubbers shall be performed after four months but within 10 months of commencing POWER OPERATION and shall include all snubbers listed in Table 3.7-9. If less than two (2) snubbers are found inoperable during the first inservice visual inspection, the second inservice visual inspection shall be performed 12 months

+ 25'rom the date of the first inspection.

Otherwise, subsequent visual inspections shall be performed in accordance with the following schedule:

No. Inoperable Snubbers er Ins ection Period 0

1 2

3, 4

5, 6, 7

8 or more Subsequent Visual >

Ins ection Period 18 months

+

25%

12 months

+ 25%

6 months

+

25%

124 days

+

25%

62 days

+

25%

31 days

+

25%

The snubbers may be categorized into two groups:

Those accessible and those inaccessible during reactor operation.

Each group may be inspected independently in accordance with the above schedule.

The provisions of Specification 4.0.6 are applicable.

The inspection interval shall be lengthened more than one step at a time.

5 The provisions of Specification 4.0.2 are not applicable.

D. C.

COOK UNIT 2 3/4 7-20 Amendment No.

PLANT SYSTEMS SURVEILLANCE RE UIREMENTS (Continued) b.

At least once per 18 months:*

1.

By performing a system functional test which includes simulated automatic actuation of the system, and:

a)

Verifying that the automatic valves in the flow path actuate to their correct positions on a test signal and b)

Cycling each valve in the flow path that is not testable during plant operation through at least one complete cycle of full travel.

2.

By inspection of deluge and preaction system spray headers'o verify their integrity.

3.

By inspection of each open head deluge nozzle to verify no blockage.

c.

At least once per 3 years by performing an air flow test through each open head deluge header and verifying each open head deluge nozzle is unobstructed.

The provisions of Specification 4.0.6 are applicable.

D. C.

COOK UNIT 2 3/4 7-40 Amendment No.

ELECTRICAL POWER SYSTEMS ACTION (Continued) c.

With two of the above required offsite A.C. circuits inoperable, demonstrate the OPERABILITY of two diesel generators by performing Surveillance Requirement 4.8.1.1.2.a.4 within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter, unless the diesel generators are already operating; restore at least one of the inoperable offsite sources to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

With only one offsite source restored, restore at least two offsite circuits to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from time of initial loss or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

d.

With two of the above required diesel generators inoperable, demonstrate the OPERABILITY of two offsite A.C. circuits by performing Surveillance Requirement 4.8.1.1.1.a within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; restore at least one of the inoperable diesel generators to OPERABLE status within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

Restore at least two diesel generators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from time of initial loss or be in least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

SURVEILLANCE RE UIREMENTS 4.8.1.1.1 Each of the above required independent circuits between the offsite transmission network and the onsite Class 1E distribution system shall be:*

a.

Determined OPERABLE at least once per 7 days by verifying correct breaker alignments, indicated power availability, and b.

Demonstrated OPERABLE at least once per 18 months by transferring the unit power source automatically from the normal auxiliary source to the preferred reserve source and by transferring manually to the alternate reserve source.

4.8.1.1.2 Each diesel generator shall be demonstrated OPERABLE:*

a.

In accordance with the frequency specified in Table 4.8-1 on a STAGGERED TEST BASIS by:

1.

Verifying the fuel level in the day fuel tank.

2.

Verifying the fuel level in the fuel storage tank.

The provisions of Specification 4.0.6 are applicable.

D. C.

COOK UNIT 2 3/4 8-2 Amendment No.

ELECTRICAL POWER SYSTEMS SHUTDOWN LIMITING CONDITION FOR OPERATION 3.8.1.2 As a minimum, the following A.C. electrical power sources shall be OPERABLE:

a.

One circuit between the offsite transmission network and the onsite Class lE distribution system, and b.

One diesel generator with:

1.

A day fuel tank containing a minimum volume of 70 gallons of fuel, 2.

A fuel storage system containing a minimum volume of 42,000 gallons of fuel, and 3.

A fuel transfer pump.

APPLICABILITY:

MODES 5 and 6.

ACTION:

With less than the above minimum required A.C. electrical power sources OPERABLE, suspend all operations involving CORE ALTERATIONS or positive reactivity changes.

SURVEILLANCE RE UIREMENTS 4.8.1.2 The above required A.C. electrical power sources shall be demonstrated OPERABLE by the performance of each of the Surveillance Requirements of 4.8.1.1.1 and 4.8.1.1.2 except for Requirement 4.8.1.1.2.a.5.*

The provisions of Specification 4.0.6 are applicable.

D. C.

COOK UNIT 2 3/4 8-5 Amendment No.

ELECTRICAL POWER SYSTEMS D.C. DISTRIBUTION OPERATING LIMITING CONDITION FOR OPERATION 3.8.2.3 The following D.C. bus trains shall be energized and OPERABLE with tie breakers between bus trains open:

TRAIN AB consisting of 250-volt D.C. bus AB, 250-volt D.C. battery bank No.

2 AB, and a full capacity charger.

TRAIN CD consisting of 250-volt D.C. bus CD, 250-volt D.C. battery bank No.

2 CD, and a full capacity charger.

APPLICABILITY:

MODES 1, 2, 3 and 4.

ACTION:

a.

With one 250-volt D.C. bus inoperable, restore the inoperable bus to OPERABLE status within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

b.

With one 250-volt D.C. battery and/or its charger inoperable, restore the inoperable battery and/or charger to OPERABLE status within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

SURVEILLANCE RE UIREMENTS 4.8.2.3.1 Each D.C. bus train shall be determined OPERABLE and energized with the breakers open at least once per 7 days by verifying correct breaker alignment and indicated power availability.

4.'8.2.3.2 Each 250-volt battery bank and charger shall be demonstrated OPERABLE:*

a.

At least once per 7 days by verifying that:

1.

The electrolyte level of each pilot cell is between the minimum and maximum level indication marks, The provisions of Specification 4.0.6 are applicable.

r D. C.

COOK UNIT 2 3/4 8-8 Amendment No.

4

ELECTRICAL POWER SYSTEMS D.C. DISTRIBUTION SHUTDOWN, LIMITINGCONDITION FOR OPERATION 3.8.2.4 As a minimum, the following D.C. electrical equipment and bus shall be energized and OPERABLE:

1 250 volt D.C. bus, and 1

250 volt battery bank and charger associated with the above D.C. bus.

APPLICABILITY:

MODES 5 and 6.

ACTION:

With less than the above complement of D.C. equipment and bus

OPERABLE,

-establish CONTAINMENT INTEGRITY within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.

SURVEILLANCE RE UIREMENTS 4.8.2.4.1 The above required 250 volt D.C. bus shall be determined OPERABLE and energized at least once per 7 days by verifying correct. breaker alignment and indicated power availability.

4.8.2.4.2 The above required 250 volt battery bank and charger shall be demonstrated OPERABLE per Surveillance Requirement 4.8.2.3.2.*

The provisions of Specification 4.0.6 are applicable.

D. C.

COOK UNIT 3/4 8-11 Amendment No.

s'g

~

~

j 1