ML17306A836

From kanterella
Jump to navigation Jump to search
Insp Repts 50-528/92-23,50-529/92-23 & 50-530/92-23 on 920615-19.Apparent Violation Noted.Major Areas Inspected: Circumstances Surrounding Unit 1 Containment Isolation Check Valve Found Improperly Assembled on 920318
ML17306A836
Person / Time
Site: Palo Verde  
Issue date: 06/26/1992
From: Wong H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17306A835 List:
References
50-528-92-23, 50-529-92-23, 50-530-92-23, NUDOCS 9207210133
Download: ML17306A836 (22)


See also: IR 05000528/1992023

Text

. S.

UC

EAR REGULATORY COMMISSION

QEGIOM V

59=52 /92-

, 59-52 / -2,

d

-5

/92-

3

~N

.

5 -52,

5 -529.

d 5 -53

N

.

IIPF-41. IIPF-51,

d

NPF-14'5

I'ct'o~o.92-119

~Lice see

Arizona Public Service

Company

P.

O. Box 53999, Station

9012

Phoenix,

AZ 85072-3999

9

PI

9

d

9

I

5

Igg<<d

Units 1, 2,

and

3

Ins ection

d

d

~es ector

June

15 through June

19,

1992

B. Olson, Project Inspector

ong,

ie

Reactor Projects

Section

2

Ins

ction Summar

Ins ection

on June

15 throu

h June

19

1992

Re ort Numbers

50-528 92-23

50-529 92-23

and 50-530 92-23

~ld:

Np

111

p

1.1

933

I

<<

5/g

51

1 containment isolation check valve found improperly assembled

on March 18;

1992.

This condition was documented

by Unit

1 Licensee

Event Report 92-005.

Inspection

Procedure

92700

was

used

as guidance during this inspection.

Results:

Genera

Conclusions

and

S ecific Findin s:

The inspector identified concerns with the level of detail of

instructions in a valve maintenance

work order

and in the test procedure

used to verify valve op'erability subsequent

to the maintenance

activities.

As

a result of using the work order

and the test procedure,

a containment isolation check valve was returned to service

even though

9207210133

920629

s

PDR

ADOCK 05000528

8

PDR

the valve internals

were installed backwards.

This condition existed

from August 1989 to March 1992.

Si n'ficant Safet

Matters:

The concerns

noted

above represent

a weakness

in the licensee's

control

of maintenance activities.

Summ r

of Violations:

One apparent violation was identified.

0

ersons

Contacted

ETAILS

The below listed technical

and supervisory

personnel

were

among those

contacted:

'na

ub

c Service

APS

B. Blackmore,

T. Bradish,

  • H. Friedlander,
  • A. Johnson,

B. Lehman,

H. McEwan

  • G. Over beck,

H. Radspinner,

  • R. Roehler,

System Engineer

Manager,

Compliance

Manager,

Component

and Specialty Engineering

Supervisor,

Compliance

Component

Engineer

System Engineer

Director, Site Technical

Support

(STS)

Supervisor,

Mechanical/Chemical

Engineering

Senior Engineer

Comb stion

n ineerin

CE

H. Crawford

J.

Isakson

uclear

Re ulator

Commission

D. Coe,

Senior Resident

Inspector

  • F. Ringwald,

Resident

Inspector

J. Sloan,

Resident

Inspector

Denotes

personnel

in attendance

at the Exit meeting held with the

NRC

inspector

on June

19,

1992.

n

The inspector also talked with other licensee

personnel

during the course

of the inspection.

2.

Co tainment Isolation Check Valve Ino erable

Due to Incorrect Maintenance

and

Inade uate Retest - Unit

1

On March 18,

1992, the'licensee

discovered that the valve bonnet

asse'mbly

for a Unit

1 containment isolation check valve was installed backwards.

The discovery

was

made during valve maintenance

while Unit

1 was in a

refueling outage.

The licensee

subsequently

determined that the valve

had

been improperly assembled

on August 22,

1989.

As

a result of the

improper assembly,

the licensee

declared that the valve had

been

inoperabl,e

and issued Unit

1 Licensee

Event Report

(LER)92-005.

The

LER

indicated

tPat

'the inoperabl,e',val.ve

was

a condition prohibited

by the

plant's Technical.Specific'ations'(TS).

r

Valve Back round

escri t'o

2)

3)

Unit

1 valve SIE-V133 was found to have its bonnet

assembly

installed approximately

160 degrees

from normal alignment.

The

valve was manufactured

by Borg-Warner

and is

a three inch swing

check,

model

77700.

The bonnet

assembly

includes the attached

valve disc,

and the bonnet

assembly is secured to the valve

body with a bonnet retainer held by studs,

nuts,

and washers.

A silver plated seal

between the bonnet

and valve body provides

leakage protection.

The valve design allows the bonnet

assembly to be rotated in the valve body when the retainer

an'd

seal

are not present.

Attachment

1 depicts the valve assembly.

d

SIE-V133 is located in the high pressure

safety injection

(HPSI) system leading to reactor coolant system loop lA.

The

valve is located inside of containment,

within five feet of the

containment wall.

Upstream of the valve,'nd outside of

containment,

the two HPSI trains join to form one line.

A

motor operated

valve

(HOV) is located outside of containment

in

each of the

HPSI trains.

Downstream of SIE-V133, the low

pressure

safety injection (LPSI) system connects to the

injection piping.

Attachment

2 depicts the location of the

check valve in the safety injection system.

The valve remains

shut for normal plant operation.

Upon

initiation of HPSI, the valve would open to provide flow from

both

HPSI trai,ns.

e ulator

Basis

The two upstream

HOVs and check valve SIE-V133 are part of the

containment isolation system for containment piping penetration

number

15.

Section 6.2.4. 1.1 a) .of the Combustion

Engineering

Standard

Safety Analysis Report

(CESSAR) indicates that two

isolation valves

are provided at each containment penetration:

one inside the containment,

and

one outside the containment.

Section 6.2.4.2

and Figure 6.2.4-1A of the

CESSAR along with

Table 6.2.4-1 of the Palo Verde Updated Final Safety Analysis

Report

(UFSAR) indicate that this penetration

design satisfies

10 CFR Part 50, Appendix A, General

Design Criterion

(GDC) 55.

GDC 55 requires,

in part, that containment penetrations

have

an

automatic isolation valve located inside

and outside of

containment.

The check valve is considered

to be

an automatic

valve for the purpose of containment isolation.

SIE-V133 is listed in TS Table 3.6-1

as

a containment isolation

valve for penetration

15.

The applicable

TS Limiting Condition

II

t

t'I

1

for Operation, 3.6.3,

in'dicates that the valve is to be

operable in Modes 1, 2, 3,

and 4.

Following valve maintenance,

TS Surveillance

Requirement 4.6.3.1 indicates that the valve

shall

be demonstrated

to be operable prior to returning it to

service.

Although SIE-V133 forms part of the containment

isolation system,

TS Table 3.6-1 exempts

the valve from the

Type

C containment leak testing requirements of 10 CFR Part 50,

Appendix J.

SI -V133 Maintenance Activities

Work Order

(WO) 00356906

was prepared

in May 1989 to rework valve

SIE-V133 to fix a body-to-bonnet leak.

The valve was disassembled

on August 22,

1989, in the following procedure'sequence:

the studs,

nuts,

washers,

and bonnet

clamp were removed;

the bonnet retainer

.

was partially unscrewed,

and the bonnet

clamp was reinstalled;,a

scribe line was marked from the center line of 'one of the studs to

the valve body; the nuts were re-tightened to break the body-to-,

bonnet seal;

and the bonnet

was free to be lifted from the body.

The purpose of the scribe line was to provide alignment indication

for the bonnet

assembly

and the valve body.

Following inspection,

the valve seal

was replaced,

and the valve was assembled

on August

22,

1989.

The inspector reviewed SIE-V133

WOs issued

subsequent

to the

1989

seal

replacement

and noted that the valve was not disassembled

again

until March 18,

1992,

using

WO 00426283.

This

WO indicated the

valve was suspected

of leaking because

pressurizer

level dropped

approximately

one percent

every two minutes

when the "A" train of

shutdown cooling was in service with one of the

MOVs upstream of

'IE-V133

open.

In addition to reworking SIE-V133 to stop the

leakage

past the valve seat,

the

WO was to repair

a body-to-bonnet

leak.

During disassembly,

the licensee

found that the bonnet

assembly

was installed about

160 degrees

from normal alignment.

The

licensee

also observed

damage to the valve internals

as

a result of

installation in the reverse orientation.

The licensee initiated Condition Report/Disposition

Request

(CRDR)

1-2-0177 to investigate

the root cause of SIE-V133 being improperly

assembled.

The licensee

speculated,

but could not confirm, that the

improper assembly

was

due to incorrect scribe lines (possible

multiple scribe lines existed),

removal

and replacement

of a marked

stud in a different sequence,

or personnel difficulty associated

with working in a respirator during valve reassembly.

This event

was treated

as

an isolated occurrence.

The inspector

reviewed the

WOs associated

with the disassembly

of

SIE-V133 and noted that there were

no specific instructions for

marking the line from a valve stud to the body.

The inspector noted

that this action

was critical as mismarking could allow the valve to

be reassembled

in the wrong orientation.

The licensee

indicated

that this action

had

been considered

to be. within the skill of the

H

~

t

craft.

The inspector also noted that the sequence

of WO steps

was.

. different than -specified

by the vendor manual.

The first step for

disassembly

in the Borg-Warner manual

was to mark the-body-to-bonnet

orientation.

The licensee,'s

WOs marked the valve orientation after

removal of the studs

and nuts, partially unscrewing the bonnet

retainer,

and reinstalling the studs

and nuts.

The inspector

questioned if some misalignment might occur while unscrewing the

bonnet retainer

and inadvertently rotating the bonnet

assembly prior

to match marking.

The licensee

indicated that while misalignment

was possible, it would be unlikely due to the force needed to break

the seal

between the bonnet

assembly

and the valve body.

The

licensee

added that the seal

in SIE-V133 did not show any markings

.

to indicate that it had rotated.

The inspector also noted that the

Borg-Marner manual

specified

measurement

of a seating

dimension for

the bonnet retainer,

and the

WOs did not specify making the

measurement.

ost Maintenance

ests

The licensee

conducted

a surveillance test for SIE-V133 following

the

1989 maintenance.

The test procedure,

73SR-IXI29, consisted of

operating the

HPSI

pumps

and measuring, the flow through the check

valve.

Since the test

was satisfactory,

even though the valve

internals

were reversed,

the valve was returned to service.

The

inspector reviewed the results

from tests

performed

on August 29,

1989,

and

on November 2,

1989,

and did not observe

any unusual

results

which may have indicated that SIE-V133 was improperly

assembled.

One stated objective of the licensee's

test procedure

was to satisfy

the requirements

of TS 4.0.5.

TS 4.0;5 indicates that inservice

testing of ASME Code Class

2 valves shall

be performed in accordance

with Section

XI of the

ASME Boiler and Pressure

Vessel

Code.

The

test procedure referred to Section XI, Subarticle

IWV-3520 of the

ASME Boiler and Pressure

Vessel

Code,

1980 Edition, Winter 1981

Addenda.

Subarticle

IWV-3520 indicated that check valves shall

be

exercised

'to the position required to fulfilltheir function,

and

the subarticle described test requirements

for normally, open

and

normally shut check valves.

The inspector

noted that the test

procedure

did not refer to Subarticle

IWV-3200 of ASME Section XI

which indicated that

a valve shall

be tested to demonstrate

that the

performance

parameters

which could

be affected

by maintenance

are

within acceptable limits.

Another stated objective of the test procedure

was to demonstrate

valve operability.

Testing to ensure

valve operability was required

by TS 4.6.3.1,

which indicated that containment isolation valves

shall

be demonstrated

operable prior to returning

a valve to service

after maintenance,

repair, or replacement

work is performed

on the

valve.

I

The inspector

noted that while the surveillance

procedure

would test

that valve SIE-V133 would pass flow, it would not test that the

valve, provided isolation capability.

The inspector discussed

the

function of SIE-V133 with various licensee

personnel

including

a

component engineer,

system engineers 'and

an engineer responsible for

the test procedure.

Licensee

personnel

indicated that the function'.

of the valve was to open after safety injection initiated.

These

personnel

did not indicate that the valve had

a design feature to

shut for the purpose. of containment isolation.

Other Occurrences

The licensee

had three other occurrences

where the bonnet

assembly

of similarly designed

valves

was misaligned.

Through discussions

with licensee

personnel

and review of documents,

the inspector learned of two previous

instances

where bonnet

assemblies

had

been improperly installed.

In 1986, during Unit 3

pre-operational

testing,

valves

SIE-V134 and SIE-V144 were found.to

have their bonnet

assemblies

installed approximately

30 degrees

from

normal.

Corrective action for these

two valves included repair of

minor defects

observed

during valve inspection.

The inspector did

not find any documentation

to indicate that corrective actions

were

taken to prevent future occurrences.

On April 30,

1992, Unit

1 valve SIA-V404, the HPSI "A" pump

discharge

check valve,

was disassembled

and the bonnet

assembly

was

found to be

180 degrees

out of normal alignment.

The licensee

had

been alerted to

a problem with the check valve when

a 300 to 1,000

psi pressure

drop across

the valve was observed

during flow testing

of the pumps's

discharge

HOV.

Additionally, the licensee

observed-

reduced safety injection flows during the testing.

SIA-V404 had

been previously disassembled

during the refueling outage,

and the

valve internals

had

been reversed

only during

a time period when the

HPSI train was inoperable.

Corrective Actions

Unit

1

LER 92-005 indicated that mechanical

maintenance

personnel

would be briefed

on the misassmbly of SIE-V133.

The

LER also

indicated that since starting

a check valve inspection

program in

February

1990,

no other check valve alignment problems

had

been

identified,

and SIE-V133 was

an isolated occurrence.

The

LER stated

that before SIE-V133, there

had

been

no previous similar events

reported

pursuant to 10 CFR Part 50.73.

Following the discovery of SIA-V404 misassembly,

the licensee

initiated

CRDR 1-2-0310 to identify the root cause

and evaluate

additional corrective actions

since the valve was the second

one

found to be misassembled

during the Unit

1 refueling outage.

The

licensee

took the additional action of assessing

the need

for'urther

testing of check valves at all units.

This assessment

resulted in the identification of 208 bonnet

hung swing check valves

for all three units.

Most of these

valves were judged not to be

suspect

due to being reverse flow tested or due to the bonnet

, bolting directly to the valve body (versus the silver seal

valve

design which allows bonnet rotation after positioning the

internals'nside

the valve body).

The licensee

determined that

10 valves per

.unit required verification.

The licensee

chose to use

an ultrasonic

(UT) technique to identify the orientation of a groove cut into the

underside of the bonnet.

The location of the groove verified the

orientation of the hanging disc.

The

10 valves in each unit were

inspected

and were found to be satisfactory.

In addition to the

CRDRs issued for the two Unit

1 valves found

misassembled,

the licensee initiated Engineering Evaluation

Request

(EER) 91-SI-032 to evaluate

the safety function and determine if

reverse

flow testing is required for HPSI

pump discharge

check

valves

and the LPSI and

HPSI containment isolation check valves that

are not required to be leak tested.

Safet

S

n f ca

ce

During the period when Unit

1 operated

at power with SIE-V133

improperly assembled,

three reactor trips occurred

and two shutdowns

were performed.

The licensee did not report

any abnormal

operation

of the safety injection system during these

events.

At the time of

completion of this inspection,

the licensee

indicated that

an

assessment

of the effects of design

bases

accidents

coupled with

valve misassembly

would be performed.

The safety significance of the misassembly of SIE-V133 is based

primarily on the generic implication of not. performing acceptable

post maintenance

tests

on safety related

check valves prior to their

return to service.

Many of these

check valves are

opened

and

inspected

in accordance

with the licensee's

check valve preventive

maintenance

program,

and therefore,

continue to be vulnerable to

misassembly

and inadequate

testing.

As discussed

above,

two

instances

arose in which safety related

check valves in the

same

system

were similarly misassembled.

One,

SIA-V404, was identified

prior to returning the valve to service,

and the other,

SIE-V133,

was not.

As a result of SIE-V133 misassembly,

GDC requirements

for

containment isolation were not met for an entire fuel cycle.

Adherence to,the General

Design Criteria is still required to

maintain the "defense

in depth" posture

inherent in the

10

CFR

requirements.

The Palo Verde

UFSAR did not appear to credit SIE-V133 with an

isolation function since it was always

assumed

to be open for safety

injection flow throughout

any analyzed

accident.

Even if one train

of HPSI sustained total failure (single failure criteria),

system

design

would continue to provide opposite train flow through the

penetration.

The inspector

noted that the

CESSAR stated that check

valve failures were not considered

credible

and therefore,

analysis

did not consider

such

a failure.

Other containment isolation check

valves are credited with design functions related to different

system failure modes.

For example,

CESSAR 6.3.2.5.4,

"Capacity to

Maintain Cooling Following a Single Failure,"

and Table 6.3.2.-2,

"Safety Injection System Failure Nodes

and Effects Analysis," (Item

No. 6) credits the

LPSI penetration

containment isolation check

valves with preventing recirculation

mode backflow from HPSI

pumps

if the

NOV containment isolation valve for LPSI fails open.

The

inspector thus noted,'t

was fortunate that

a more significant valve

did not suffer degradation.

g.

Conclusions

Based

on the discussion

above,

the inspector

concluded

the

following:

1)

The licensee initially limited the scope of corrective actions

because

SIE-V133 was considered

to be

an isolated event.

The

licensee

did not take into account

two previous

instances

where

similarly designed

valves were found to be misassembled.

Additional corrective actions

were initiated as

a result .of

finding SIA-V404 misassembled.

Unit

1

LER 92-005 did not

address

the previous occurrences.

2)

The maintenance

procedure

did not provide sufficient detail for

marking the orientation of the valve during disassembly.

The

procedure relied

on the skill of the craft to ensure that this

action

was successfully

accomplished.

In addition, the

maintenance activities did not accomplish the intended

goal of

proper valve reassembly.

3)

The function of the valve to provide containment isolation was

not fully considered

when developing the post maintenance test

procedure to demonstrate

operability.

Isolation capability was

not tested.

4)

As

a result of the improper maintenance

and the lack of testing

to demonstrate

isolation capability, the valve was

inappropriately placed into service.

The unit was operated

in

Nodes

1, 2, 3,

and

4 with the valve inoperable,

and the

TS 3.6.3 action requirements

were not met.

This is an apparent

violation of NRC requirements

(Violation 528/92-23-01).

5)

The actual safety significance of plant operation with SIE-V133

inoperable

appeared

to be low in that the check valve was not

called

upon to perform a containment isolation function during

the period of improper assembly.

In addition, it appeared

that

the Palo Verde

UFSAR accident

analyses

did not credit the

ability of the valve to close (safety function is to open for a

safety injection).

h.

Licensee

Commitments

The conclusions of the inspector

were presented

to licensee

management

at the exit meeting.

Licensee

management

made the

following commitments:

1)

To evaluate

the need for a supplement to LER 92-05 or a new LER

'o assess

the

TS surveillance

and

ASME Section XI requirements

and

any needed corrective action (clarifying the position that

there were

no requirements

to test

SIE-V133 for reverse flow),

and to modify the statement that SIE-V133 was

an isolated

occurrence.

2)

To review the guidance

promulgated in Generic Letter 89-04 for

adequacy.

This generic letter addressed

reverse

flow testing

of check valves.

3)

To review guality Assurance

(gA) program involvement

and the

need for program modifications, if necessary.

4)

To review the mechanical

technician valve maintenance

training

program for needed modifications.

5)

To develop

a Model Work Order for disassembly

of silver seal

bonnet valves.

6)

To evaluate

the safety significance of SIE-V133 being

misassembled

when coupled with design basis accidents.

7)

To perform an inspection or test to confirm isolation

capabilities of the

HPSI

pump discharge

check valves

and the

HPSI

and LPSI'containment isolation check valves that are not

, tested for leakage.

The'inspection

or test would be performed

after any maintenance activity that is completed prior to the

licensee

completing their evaluation of the need for reverse

flow testing of the valves.

One apparent violation of NRC requirements

was identified.

3.

Exit Meetin

30702

An exit meeting

was held

on June

19,

1992, with licensee

management

and

the inspector during which the observations

and conclusions

in this

report were generally discussed.

( gq)i.

,y$Q8'~9 '-

/,~y-~

(28!~ Q

0

jir>:;.I

i j(it(

fbi'!

I

(n~ ia.

Sf'Dlui

/7'8'll'f'g

ion~

.eg~

8

l9 Q I

/Z igi

4 ECOQ

C

pa~o~r~ cwO.

.f

l2

l5

.77f

lB

4Z

2'bkD's.Oaa

'I5.940

'.rr

rin~i A A

SI S.HV609

I

OUTSIDE

CONTAINIAENT

SID Hvss1

INtlDE

CONTAIN1ltNT

HOT LTG

LOOP I

DIII(

VI

Z

.D

~m

t4

LI7

HP$ 1 tVMP '2

$10102

LPSI PUMP 2

SI SP01

M

Vl

O

54

SISAIV699

$104IV201

I

T

M

M

SISVV515

ISIS.VV616

SIA UV51$

5 I04lvdI5

SIS UV625

SIA UV611

M

I

SlbVV6$6

g) p

M

SIA UV6$1

I

SIS.VV644

1

QT

QS.X 0IA

SIT

QS X01~

SIT

SIT XOIC

SIT

SIT XOIO

SISAIVSIA

SISUV61<

COLO LSG )2

COLO LSG f2

LOOP 20

COLO I.SG

LOOP IA

N0z

RCOr

n m

Ib P

O

O

Im

LPSI

tUMI'

SIAP01

HPSI PUMP I

SIA t01

SIA HV595

SIA UV611

SIAVV64$

SIA HVSOI

SIC.HVSTI

SIA.UV I~

$1'S.UV515

SAFETY INJECTION SYSTEM

INJECTION MODE

SIA UV644

M

COHTAINMTHT

SVMPS

SIAVVbll

OM

COLD LSG

LOOP 10

HOT LTG

LOOt 2

O

0m

Til

nZ

0Z

Cll

C

Trl

111

O

crln

O

Oz