ML17298B718

From kanterella
Jump to navigation Jump to search
Insp Repts 50-528/84-47,50-529/84-36 & 50-530/84-25 on 841015-1102.Violation Noted:Pipe Support Beam Attachment Welded to Lower Beam Flange on East & West Sides,Rather than North & South
ML17298B718
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 11/29/1984
From: Hollenbach D, Kellund G, Miller L, Narbut P, Sorensen R, Wagner W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17150A251 List:
References
RTR-NUREG-0578, RTR-NUREG-0660, RTR-NUREG-0737, RTR-NUREG-578, RTR-NUREG-660, RTR-NUREG-737, TASK-1.A.2.1, TASK-1.B.1.2, TASK-1.C.5, TASK-1.C.6, TASK-2.K.1, TASK-TM 50-528-84-47, 50-529-84-36, 50-530-84-25, IEB-79-06B, IEB-79-6B, NUDOCS 8412270397
Download: ML17298B718 (36)


See also: IR 05000528/1984047

Text

U.

S.

NUCLEAR REGULATORY COHHISSION

REGION V,

Report Nos.

50-528/84-47,

50-529/84-36

and 50-530/84-25

Docket Nos.

50-528,

50-529

and 50-530

Iicense Nos.

CPPR-141,

142 and

143

Licensee:

Arizona Public Service

Company

P.

O. Box 21666

Phoenix,

Arizona

85036

Facility Name:

Palo Verde Nuclear Generating Station - Units 1,

2 and

3

Inspection at:

Palo Verde Construction Site, Wintersburg, Arizona

Inspection conducted:

Octob

15 - November 2,

1984

Inspectors:

R.

C.

o

s n,

Rea tor Inspector

. J.

Wagner,

Reactor

nspect

Dat

Si ned

ad

Da

e

S gn

D. Holle bach,

eactor

Sp

P.

P. Narb

, Reactor Inspector

D

e

igned

li Z36

Date Signed

Approved by:

G.

e

und,

Reac or Inspector

T3PQ ~

L. F. Hiller, Jr., Chief

Reactor Projects

Section

2

Dat

S gned

li zg

Date Signed

~Summar

Ins ection on October

15 - November

2

1984

(Re ort Nos. 50-528/84-47,

50-529/84-36

and 50-530/84-25

R

of IE Circulars, 50.55(e) items, previously identified open items,

and

implementation of Three Hile Island Lessons

Learned actions in Unit 1, with

some examinations

carried over into Units

2 and 3.

The inspection involved

303 inspector-hours

onsite by five NRC inspectors.

Results:

One Severity Level IV violation of NRC requirements

was identified,

concerning

improper welding of pipe supports in the Auxiliary Feedwater

System

(paragraph 2.f).

8412270397

84i205

)

PDR

ADOCK 05000528

g

PDR

C

I'

DETAILS

1.

Persons

Contacted

a

~

Arizona Public Service

Com an

(APS)

"W

AL

""C.

"R

d T

'B

~T

J J

F.

P.

B.

J.

R.

J.

G.

R.

J.

S.

J.

Quinn, Licensing Manager

Souza, Assistant Corporate

QA/QC Manager

Russo,

Manager, Quality Audits 8 Monitoring

Hamilton, Quality Monitoring Supervisor

Green,

Supervisor of Training Support

Adney, Plant Superintendent,

Unit 2

Bloom, Licensing Engineer

Smith,

Compliance Engineer

Hicks, Training Manager

Wiley, Licensed Training Supervisor

Rudolph, Sr. Simulator Instructor

Allen, Operations

Manager

Bernier, Operations

Support Supervisor

Minnicks, DC Superintendent

Olson, Electrical Superintendent

Meyer, Fire Protection Supervisor

Stoudt, Mechanical Superintendent

Pennick,

QA/QC Engineer

Sherrin,

QA/QC Engineer

b.

Bechtel Power Cor oration (Bechtel)

-D. Hawkinson, Project

QA Manager

'"W. Stubblefield, Field Construction

Manager

"P. Huber, Project Quality Coordinator

"=A. Foster, Quality Control Manager

D. Freeland,

Engineering

Group'Supervisor'.

Guire,

QA Manager

>'Denotes

those persons

attending Exit Meeting, November 2,

1984.

The inspectors

also talked with other licensee

and contractor personnel

during the course of the inspection.

2.

Licensee Action on 10 CFR 50 '5(e) Construction Deficiencies

(DERs)

The following potential 50.55(e)

items were reviewed by the inspectors

for reportability and to determine

the thoroughness

of the licensee's

corrective action.

The items marked with an asterisk (-) were judged by

the licensee

to be reportable

under the

10 CFR 50.55(e) criteria; the

others

were considered

not reportable.

a

~

(Closed) Defects Discovered in Stainless

Steel Pi e

S ools (Licensee

DER No. 78-03

),

0

The licensee

informed the

NRC on September

27,

1978, that

deficiencies

might exist in certain stainless

steel pipe spools

delivered to the jobsite.

The pipe spools

were fabricated by

Pullman Power Products

from material supplied by Youngstown Welding

and Engineering

Company.

The corrective action called for a

100

percent ultrasonic examination to be performed

on all the Youngstown

material manufactured for the licensee.

These inspections

revealed

defective material that resulted in the rejection of 44 out of 103

pipe spools,

and

1 out of 4 pipe supports.

The inspector

reviewed documentation that revealed that these

examinations

were performed

on all Youngstown material,

under

observation

by Bechtel Quality Assurance

and Quality Control

personnel.

The inspector also verified accountability of all

Youngstown material received.

All the material had been identified,

located,

and all rejectable material shipped to Pullman for repair

or replacement.

The 45 rejectable

items were identified on Bechtel

Shipping Notice 3280 and 3519.

The corrective actions

taken by the licensee provide assurance

that

all items manufactured

by Pullman containing Youngstown material

conforms to ASME Code and specification requirements.

This item is

closed.

I

I

l

(Closed) Incorrectl

Installed

Han er Su

ort Assembl

(Iicensee

DER

No. 84-33

This it'em was initially reported to the

NRC by" the licensee

as

a

potential

10 CFR 50.55(e)

reportable deficiency but was subsequently

determined

by the licensee

to be not reportable.

The licensee

based

this conclusion

on engineering calculation analysis

13-MC-SI-503R

which provided justification that the nonconforming pipe support

would not degrade

the structural integrity of the pipe support if

left uncorrected.

Nonconformance

Report

(NCR) No. PA-8390 was

dispositioned

to "use-as-is".

Subsequently,

a new NCR No. PA-8630

was initiated and dispositioned to add the weld in order to preclude

any possible

concern regarding addition of possible future loads to

the support.

Both of these

NCR's are closed.

The inspector also

reviewed documentation indicating that training sessions

were

conducted to give Quality Control Engineers

specialized -training on

inspection techniques.

A weld between

a Hanger Support, Assembly and the base plate

was

accepted

by two different Quality Control Engineers

(QCEs)

even

though the weld was missing.

The inspector

asked the second

QCE who

inspected

the weld how he missed it.

The

QCE thinks this particular

weld was covered by a wood plank and scaffolding making it

inaccessible

at the time of his inspection.

The licensee

examined

a sample of both QCE's work.

For one

individual, no deficiencies

were identified.

For the second person,

a single undersized

weld was identified which was dispositioned

"Use-As-Is",

Based

on this reverification of past work the licensee

0

believes that the missing weld was an isolated instance of

inadequate quality control inspection.

This item was not reportable

under

10 CFR 50.55(e)

requirements

and

is closed.

(Closed)

DER 82-05

Unit 2 Reactor Coolant

Pum

Delivered With Sand

In Cooler Chamber Housin

Unit 2 Reactor Coolant

Pump

(RCP) lllO-B, supplied by Combustion

Engineering

(C-E), was delivered to the job site with foreign matter

in the cooler chamber housing.

The foreign matter was later

identified by C-E as sandblast

material saturated

with oil from the

50 hour5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> test.

The material

was found in the former overflow chamber

which was plugged

and seal welded.

The pump finished its 50 hour5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> test in March,

1981.

In May,

1981

insufficient thickness

and poor adhesion of paint was observed

on

the cooling chamber housing.

In September,

1981 the cooling chamber

housing

was stripped

and repainted.

C-E feels the blasting

sand

came from this stripping procedure.

C-E also feels this is an

isolated

case

because

this is the only pump with the converted

overflow design which was sandblasted

and repainted.

The inspector

examined the Nonconformance Report,

NCR NC-724,

documenting the sand found in the cooling chamber housing.

The sand

was found during the field cleanliness

inspection required prior to

pump assembly.

The NCR was dispositioned

remove the sand

and

continue assembly.

The

NCR was signed off as complete.

The pump is

assembled

and has

been tested.

This item was not reportable

under

10 CFR 50.55e

and is closed.

(Closed)

DER 84-29 " Plastic Coatin

on Diesel Generator

Heat

~Exchaa

era

While testing Train A of the Unit 2 Essential

Spray Pond the

licensee

discovered

an epoxy material in the temporary startup

strainer.

A Nonconformance

Report

(NCR SM-2935)

was written by the

licensee

to inspect the Unit 2 Diesel Generator

(D.G.) jacket water

cooler and lube oil cooler for plastic lining failure.

The

inspection revealed

extensive failure of plastic lining including

severe,

dense blistering and widespread

rusting.

NCRs and CIPs

(Construction Inspection Plans)

were written to examine,

document,

and correct the Diesel Generator

cooling system in Units

1 and 2.

The D.G. cooling system consists of:

the Lube Oil Cooler, the

Jacket

Water Cooler,

the Air After Cooler, the Governor Oil Cooler,

and the Fuel Oil Cooler.

The Lube Oil Cooler, Jacket

Water Cooler,

and Air-After Cooler all contained Plasite lining failures requiring

extensive repair.

The Governor Oil Cooler and Fuel Oil Cooler are

not Plasite lined.

However they contained

a significant buildup of

foreign material.

The foreign material

was cleaned off returning

the coolers to the appropriate

cleanliness

class.

Tl

J

pl

The licensee

stated

the cause of the Plasite failure was the

improper application of the Plasite

by subcontractors

at the

factory.

Plasite

must be applied in thin coats,

less than

18 mils

thick, and allowed to cure for 4 to 6 days in air depending

on

weather conditions.

The licensee believes that the subcontractors

applied Plasite

coats in excess of 25 mils and sealed

the coolers

before the Plasite

was fully cured.

The inspector

examined

the system set up on site to correct. the D.G.

Cooler Plasite lining problems.

The inspector

examined

MPP/QCI

60.3, Plasite

Coating Application.

This procedure

establishes

instructions

and criteria for the field application

and inspection

of Plasite coatings.

All the Plasite manufacturers

specifications

are included in this procedure.

This procedure also

documents

and

requires

QC verification of the important factors which insure

proper application of the Plasite lining such as:

film thickness,

film integrity, and curing time.

The inspector also interviewed the Field Coating Engineer

responsible for correcting the plasite, lining problem.

He indicated

he has been using this material for over

6 years

and his supervisor

has over 20 years

experience

with. this material.

He also indicated

the craft personnel

responsible for recoating the coolers

have been

extensively trained in the precision

and care needed

when working

with Plasite.

The craft personnel

interviewed by the inspector

confirmed this.

The Plasite recoating of the Unit l. D.G. Coolers .'is finished.

The

plasite recoating of the Unit 2 D.G. Coolers is approximately 75/

complete

and all the necessary

documentation is in place to track it

thru to completion.

Any Plasite lining failures in Unit 3 will be

identified during its startup

inspections.'his

item is closed.

(Closed)

DER 84-46- Refuelin

Mater Tanks Penetration

Sleeves

Following completion of the final stress

calculation for the

Chemical

and Volume Control System

(CVCS) the licensee

learned that

no design calculation had been performed for the sleeve-to-pipe

cap

plate connection for two 20-inch diameter pipes penetrating

the

Refueling Water Tank

(RWT).

Calculations,

subsequently

performed,

revealed that the connection would be overstressed

during a seismic

event

due to loads resulting from seismic anchor movement.

To

prevent this movement,

the annular

space

between the sleeve

and the

pipe was filled with non-shrink grout.

Calculation No.

13-CC-C7-015

was performed to verify that this modification would prevent the

overstressed

condition.

DCPs

15C,

2CC,

3CC-ZY-134 have been issued

to correct this problem in Units 1, 2,

and

3 respectively.

The inspector verified these

DCPs have been issued.

The

DCP for

Unit 1 is signed off and stamped

by QC as being complete.

The

inspector

examined the Unit

1

RWT penetration

sleeves

and found them

filled with grout.

h

n

-This item is closed.

(0 en)

DER 84-38-

Im ro erl

Welded Flan

e

Pipe support

$/13-AF-005-H-007,

Rev.

1 was installed

and accepted in

Unit 2 by Field Engineering

and Quality Control.

During piping

rework,

two discrepancies

in the original installation were

discovered

and documented in NCR PC-8290:

The miscellaneous

steel

attached

to the pipe support

was at

a higher elevation than called

for and the beam attachment

was welded

on the East-Vest

sides

instead of the North-South sides of the lower beam'flange.

The

change in elevation of the miscellaneous

steel

causes

no additional

loading so the structural integrity of the pipe support is not

degraded.

However, incorrectly welding the beam attachment

to the

bottom flange causes

the flange to, improperly transfer

loads to the

structural

member.

The beam attachment

should be welded to the

I-Beam flange

so that the weld crosses

the web of the I-beam.

This

will transfer the loads

from the pipe support to the entire

beam

instead of just to the lower flange.

In this case,

transferring

loads to only the bottom flange results in 'exceeding

the structural

capacity of the bottom flange during

a DBE.

The inspector

examined

the proposed corrective action to repair the

improperly welded flange.

NCR PC-8290

was issued to add welds

on

the North-South sides of the beam attachment.

The'NCR was signed

off and stamped

by

QC as complete.

The inspector verified the

North-South sides of the beam attachment

were welded to the flange.

The licensee

feels this is an isolated

case

based

on a

1983

CAT

(Construction Assessment

Team) Inspection

and

a reverification

program of 2199 pipe supports

and pipe racks in Unit 1.

The inspector

examined

the

same pipe support in Unit 1 and found the

same deficiency.

A subsequent

inspection of this hanger in Unit 3

showed it is properly installed.

The inspector

then examined

35 pipe supports in Unit 1 against their

as built drawings.

Twenty-nine of the hangers

were part of the Unit

1 reverification program called for in WPP/QCI 543.0.

There were

2199 pipe supports

and pipe racks reinspected

in VPP/QCI 543.0.

All

problems identified by the inspector,

except Unit 1 pipe support

AF-005-H-007, were documented

on NCRs and FCRs.

This pipe support

was,

however,

documented in NCR PX-7902 for a missing Bracket Pin

North Retaining Ring.

VPP/QCI 543.0 identified problems with beam attachments

being welded

on the wrong sides.

All these

problems

were dispositioned

"Use As

Is".

The difference between these

hangers

and the

one identified in

DER 84-38 is hanger configuration.

The hanger identified in DER

84-38 is the only one which involves

a combination of a heavily

loaded hanger improperly welded to a light gauge

I-beam.

The inspector

found Pipe Hanger No. 13-AF-005-H-007, located in Unit

1, welded

on the East

and West sides to the lower I-Beam flange.

Pipe Support Assembly Drawing No. 13-AF-005-H-007, Revision 2, dated

0

A'

July 26,

1984, details the pipe support be welded to the lower

I-beam flange on its North and South sides.

This is the

same

problem with the

same

hanger in Unit, 2 identified in DER 84-38.

This DER states

the hanger in Unit 2 would fail during

a seismic

event.

This appears

to be

a violation of 10 CFR 50, Appendix B,

Criterion V, Instructions,

Procedures

and Drawings; which states in

part, "Activities affecting quality shall be prescribed

by

documented instructions,

procedures

or drawings of a type

appropriate

to the circumstances

and shall be accomplished in

accordance

with these instructions,

procedures

or drawings."

(Violation 50-528/84-47-01)

3.

Licensee Action on Previousl

Identified Items

a

~

(Closed) Follow-U

Item (50-528/84-20-01)

Receivin

Ins ections of

Materials Procured

from Vendors

b

C-E.

Previous

Ins ection

During a previous inspection,

the inspector

reviewed six

documentation

packages

of material procured by C-E (Combustion

Engineering)

from vendors.

The inspector

was unable to determine if

the proper quality documentation,

such

as specifications

and

purchase

orders,

was

on site.

The inspector

determined that the licensee

had reviewed all the Unit

1 C-E Purchase

Orders

(P.O.s)

and Field Material Requisitions for

completeness

of required documentation.

During this review the

licensee

discovered that

some material procured by C-E was shipped

without a procurement inspection.

This was documented in Nonconformance

Report

(NCR) NX-1491.

The

NCR

lists all P.O.s which did not have

a procurement inspection.

The

licensee

rereviewed all the P.O.s

and verified all the required

documentation

was present

and conformed to specifications.

The

licensee

also retrained

the receiving inspectors

to recognize

C-E

procured material requiring

a procurement inspection.

The inspector

randomly chose five purchase

orders for review.

Each

purchase

order package

and all required quality documentation,

and

the appropriate specifications,

were referenced

and available

onsite.

Based

on this sample, this item is closed.

b.

(0 en) Unresolved Item:

50-530/82-09/02 Flare Bevel Weld Re uirement

NRC Inspection Report No. 50-530/82-09

documents

the concerns

raised

by the inspector regarding

gC inspection of flare bevel weld joints.

The inspector questioned

whether

a

(}C inspector could actually

measure

and verify a flare bevel weld size

as called out on the pipe

support drawing,

and whether the effective throat of the weld was

y

achieved

using the criteria stated in Bechtel Drawing No.

13-S-ZAS-519.

Bechtel issued

Drawing Change Notice

(DCN) No.

5 to Drawing No.

13-S-ZAS-519 to provide further clarification for gC inspection of

flare bevel weld joints.

This action resolved the question

regarding the acceptance

criteria used by gC inspectors

during

verification of flare bevel weld size.

The question regarding effective throat requirements

has not been

addressed

by the licensee.

The licensee is committed to the 1972-73

edition of AWS Dl.l Structural Welding Code,

which does not address

flare bevel weld joints.

The

1975 "and subsequent

code editions,

however, did include flare bevel weld joints as being prequalified

provided certain conditions were met.

These conditions included

taking random sections of production welds to verify that the

effective throat is consistently obtained.

Since the licensee is

not committed to these later requirements,

the inspector

questioned

whether the effective throat was being achieved.

Bechtel

Interoffice Hemorandum

No. HB-104-03 of 10-12-84,

stated that tests

were conducted to determine

the minimum effective throat for flare

bevel weld joints,

and that the tes't results

were recorded in PgR

830.

However, the test results

were not representative

of the

structural materials of concern.

Therefore,

during the exit meeting

of 10-26-84,

the licensee

committed to provide the inspector with

objective evidence

demonstrating reconciliation of design

requirements for effective throat with that actually achieved in the

field.

This item will remain open.

(0 en) Deviation 50-528/84-25-03:

A Audits of the Subcontractor

Installin

S ra

On Pire roofin

Had Not Been Performed

The inspector

examined

the licensee's

response

to the deviation,

I,etter ANPP-30484-EVB/WEl dated

September

12,

1984.

Back round

The deviation was given because

the

APS commitment, given in the Fire

Protection Evaluation Report,Section IV Part

C indicates fire

protection work would be performed under the auspices

of a equality

Assurance

program.

The deviation addressed

the specific activity of spray-on-

fireproofing since it appeared

that no comprehensive

(}uality

Assurance

audits

had been conducted of the Spray-on-fireproofing

contractor's

work.

This Ins ection

The inspector

examined

the

gA audit addressed

by the

APS response

and concluded

the audit encompassed

only a very limited look at

spray-on coating thickness

(three probes for thickness)

and

a

confirmation that the specified spray-on material is included in the

U.L. Directory.

Ten specific equality Assurance .criteria are committed .to in the Fire

Protection Evaluation Report.

This represents

a gA program of

reduced

scope

from that used for safety related

systems

(10 CFR 50

Appendix B) but is

a

QA program that fulfills the requirements

of

the

NRC guidelines set forth in BTP A'PCSB 9.5-1 for fire protection

systems.

The deviation was cited against the tenth

QA criterion committed to

in the Fire Protection Evaluation Report, that is, "Audits" because

this criterion would typically encompass

the other nine criteria.

The "Audit" criterion states:

"Audits should be-conducted

and

documented to verify compliance with the fire protection program

including design

and procurement"'documents,

instructions,

procedures

and drawings,

and inspection

and test activities."

The licensee's

limited gA audit review of the spray-on coating

contractor's

work does not appear to meet the commitment to perform

rocedures

ins ection and test activities.

The licensee's

response

also states

that the applied coating

thickness

was also monitored by contract coordinators

and that the

presence

of coatings in the 'required places

was walked

down by

engineering personnel.

C'owever,

the response

did not provide rationale for whether adequate

control of spray proofing design, material procurement,

application

procedures,

and other applicable inspection or test attributes

(other than thickness)

has been exercised.

In discussions

with licensee

management

the inspector

concluded

that, if controls

have not been exercised

on certain aspects,

a

rationale for why these certain aspects

are not of technical

significance should be provided.

Additionally, in discussing

the original deviation and the

APS

response

with site management

personnel

during the week of October

15,

1984, it became

apparent that the issue involved was larger than

indicated by the original deviation, that is, applicable to more

than the spray-on-fireproofing contractor.

Specifically, the licensee

had earlier identified a lack of QA

involvement in several of the fire protection system contractors,

including the sprinkler piping installations

and

some of the Bechtel

controlled fire protection system installations.

As a result

a fire

protection audit was performed

(C83-10) which had

some significant

findings including improper seismic design criteria used for Bechtel

installed fire protection piping and indications of a lack of

control over the subcontractor for sprinkler installation.

Independent

NRC inspections of a limited scope, in the area of fire

protection conducted after the single

APS gA audit have identified

additional problem areas

(e.g.

improper seismic design by a fire

LII

protection subcontractor

and seismic design criteria not in

accordance

with FSAR commitments

(reference

report 50-528/84-25)).

These additional

NRC findings apparently indicate that the single

APS gA audit was not sufficiently comprehensive

to assure

that the

QA attributes

committed to in the Pire Protection Evaluation Report

were adequately

implemented.

During the week of October 15,

1984 licensee

management

indicated

that other independent verifications had been performed in various

areas

which could provide the assurances

required.

At the exit interview on October 26,

1984

a licensee

representative

committed to provide

a comprehensive

study of the fire protection

system work done by the contractor

and subcontractors

which will

demonstrate

the adequacy of controls

on design,

procurement,

procedures

inspection

and testing,

or alternately,

define the

actions that need to be taken to demonstrate

that adequacy.

This deviation,

expanded in scope,

remains

open pending receipt

and

evaluation of the licensee's

study of the adequacy of controls in

the construction of fire protection systems.

4.

Review of IE Circulars

(Closed) Circular 80-01

Service Advice for General Electric Induction

Bechtel letter B/ANPP-E-57954

MOC 112581 of April 22,

1980 provided the

results of examination of relays

from all suppliers

except Metalclad

Switchgear.

Evidently General Electric could not confirm whether

defective type relays

were shipped in Metalclad Switchgears.

Therefore,

Bechtel committed to examine all Metalclad Switchgear

and issue

a

Nonconformance

Report if defective relays

are found.

Design

Change

Package

(DCP) No.

10E-PB-017 for Unit

1 was issued to inspect

and repair

as required the =GE supplied 4.16

KV Class

1E switchgear

as described

by

Circular 80-01.

The work under this

DCP is completed for Unit 1.

Identical

DCPs have been initiated for Units 2 and 3.

This Circular is closed.

5.

Im lementation of Three Mile Island Lessons

Learned

The inspector

reviewed the below listed items which represent

a portion

of a comprehensive

and integrated plan to improve safety following the

events at Three Mile Island, Unit. 2 in March,

1979.

(The item numbers

are from Enclosure

2 of NUREG-0737).

I.B.1.2 Inde endent Safet

En ineerin

Grou

(ISEG) (0 en)

V

r

10

This item involves establishment

of an independent

group located

onsite to feedback operating experience

to plant personnel

and

monitor plant operations

to improve safety.

One concern raised in Inspection Report 84-43

was

a deviation from

the commitment

made in the Palo Verde Lessons

Learned Implementation

Report.

The licensee

had stated in the ILIR that Shift Technical

Advisors

(STAs) and

ISEG would be

a single group, i.e.,

STAs will

perform the functions of the

ISEG when not on duty or assisting

the

shift supervisor.

However, the arrangem'ent

implemented by the

licensee

involves the

STAs and

ISEG being two separate,

independent

groups.

NRC has

reviewed this arrangement

and found it acceptable

as

documented in the upcoming Supplement

6 to the Palo Verde

SER.

The inspector

reviewed the experience qualifications of,each

new

member of ISEG by .interviewing each individually. It was confirmed

that the

6 individual ISEG members

and the supervisor

possess

experience

and college

degrees

consistent with the Technical

Specifications,

Paragraph

6.2.3.2.

The inspector also reviewed

a draft ANPP policy procedure that

governs the functioning of ISEG, 7N405.02.00,

Rev.

1.

No

deficiencies

were identified, however,,this

item will remain open

until an approved version is available for review.

In addition, the

inspector will review the ISEG staff's familiarity with this

procedure

and other implementing procedures

to ensure that

ISEG is

a

functioning body, with an understanding

of their role in pl'ant

safety.

I.C.5 Feedback of 0 eratin

Ex erience

(0 en)

Review of operating experience

and dissemination

to plant personnel,

is

a function of ISEG.

The inspection of this TMI Action Plan Item was first documented in

Inspection Report 84-23.

At the time, responsibility for this

function was assigned

to the

STA group.

At that time, the inspector

had

comments

concerning procedure

79AC-9ZZ03, Operating Experience

Review, which the licensee

had agreed to incorporate.

Subsequently,

responsibility for review o'f operating experience

was transferred

to

ISEG.

ANPP policy procedures

are

now used to govern this function

of ISEG vice Station Manual procedures,

therefore,

procedure

79AC-9ZZ03 has been superseded

by procedure

7I405.02.01,

lSEG

Operating Experience

Review.

The inspector

reviewed the draft

version of 7I405.02.01

and identified two aspects

of the TMI Action

Plan item that are inadequately

addressed:

(1) Identifying the

recipients of various categories

of operating information and (2)

Assuring plant personnel

do not routinely receive

extraneous

or

unimportant information that would obscure priority information and

detract from overall job performance.

The

ISEG staff agreed

to incorporate

these

comments into procedure

7I405.02.01.

This item will remain open pending procedure

approval

p, '

and subsequent

NRC verification of the incorporation of these

comments.

I.C.6 Procedures

for Verif in

the Correct Performance

of 0 eratin

Activities

Closed

This TMI Action Plan Item involves independent verification of

operator activities

as

a means of reducing

human, error.

The inspector interviewed cognizant licensee

personnel

and reviewed

samples of the following procedures:

(1), Sire protection

surveillance tests,

(2) ISC surveillance 'tests

and preventive

maintenance

tests,

(3) electrical surveillance tests

and preventive

maintenance

tests,

(4) mechanical surveillance tests

and preventive

maintenance

tests,

(5) operational surveillance tests

and operating

procedures,

(6) work order facsimiles.

Although some operational

surveillance test procedures

and ISC surveillance test procedures

have yet to be completed

and approved,

the inspector verified that

an independent verification program, is in place at Palo Verde.

Applicable licensee

procedure writers and supervisors

are aware of

the requirement

and have incorporated

independent verification

criteria into the applicable procedures

that the inspector

reviewed.

The applicable

ISC and operations

procedure writers committed to the

'nspector

to continue to write procedures

in light of independent

verification criteria.

Additionally, training will be given within the next

2 weeks for all

Senior Reactor Operators in the conduct of all aspects

of

independent verification.

The inspector verified that open aspects

from Inspection Report 84-43 have been satisfactorily resolved by

the licensee.

However,

one additional deficiency was identified.

Procedure

73AC-9ZZ04, Surveillance Testing,

does not include provisions for

independent verification.

The licensee

representative

committed to

including guidance in 73AC-9ZZ04 for independent verification.

This

procedure revision will be completed prior to licensing

and followed

up as part of routine inspection.

This item is closed.

New Items

I.A.2.1 Immediate

U

radin

and

RO and

SRO Trainin

and

qualifications

0 en

NRC Position

References:

a)

NUREG 0737

b)

Denton Letter of March 28,

1980

c)

NUREG 0694

f'

IJ

8

Applicants for SRO license shall have

4 years of responsible

power

plant experience,

of which at least

2 years shall be nuclear power

plant experience

(including 6 months at the specific plant) and no

more than

2 years shall be academic or related technical training.

Certifications

that= operator license applicants

have learned to

operate

the controls shall be signed by the highest level of

corporate

management for plant operation.

Revise training programs to include training in heat transfer, fluid

flow, thermodynamics,

and plant transients.

Licensee

Commitment

Reference:

PVNGS TMI-2 Lessons

Learned Implementation Report

ln summary,

the licensee's

commitment generally follows the

applicable guidelines of NUREG 0694 and the Denton letter of March

28,

1980.

Ins ector Findin s

References:

a)

b)

c)

Procedure

82TR-9ZZ03 Requalification Procedure for Iicensed

Operator Retraining

Procedure

82TR-9ZZ01 Cold License Training

Procedure

82TR-9ZZ02 Hot License Training

The inspector

examined lesson plans,

course

manuals

and training

records to ensure

the licensee's

compliance with this TMI Action

Plan Item.

In addition, training procedures

were reviewed

and other

applicable documentation

as necessary.

The inspector

was satisfied that the licensed operator training and

retraining program is adequate

and follows NRC guidelines, with the

exception of 3 identified deficiencies:

1.

The requalification training program does not include

Mitigating Core

Damage

as part of the curriculum,

as required

by the Denton letter.

The licensee

representative

committed to revi'se procedure

82TR-9ZZ03 to make inclusion of this material mandatory

and to

create

lesson plans for inclusion of Mitigating Core

Damage in

the requalification program.

2.

All operator control manipulations

required

as part of

'equalification

training in Enclosure

4 of the Denton letter

are included in 82TR-9ZZ03.

However, the checksheet

used to

track the training the operators

receive in these manipulations

is missing

one control manipulation from the Denton letter,

"Loss of Protective

System Channel".

The licensee identified

4

I

lh

C

13

this previously and is in the process

of revising the checklist

to include the missing manipulation.

3.

Due to the omission of the radiation monitoring portion of

Mitigating Core Damage, all operators

must receive this missed

training prior to fuel load..

This item will remain open until these corrective actions

can be

verified by the inspector.

II.X.1.5 Review of ESF Valves

(o en)

NRC Position

References:

a)

IEB 79-068

b)

NUREG 0660

J

Review all safety-related

valve positions, positioning requirements

and positive controls to assure

that valves, remain positioned

(open

or closed) in a manner to ensure

the proper operation of engineered

safety features.

Also review related procedures,

such

as those for

maintenance,

testing, plant and system startup,

and supervisory

periodic (e.g., daily/shift checks),

surveillance to ensure that

such valves are returned to their correct positions following

necessary

manipulations

and are maintained in their proper positions

during all operational

modes.

Licensee

Commitment

Reference:

PVNGS TMI-2 Lessons

Learned Implementation Report

Refer to CESSAR Appendix B, Item II.K.1.5.

In addition,

PVNGS will

have tagout procedures

and surveillance test procedures

that will

control safety system status.

They will provide appropriate

logs

and checklists to ensure control of plant systems.

Additionally,

reviews will be conducted

to verify that procedures

for

safety-related

systems

return those

systems

to service after having

been tagged out for repair or surveillance testing.

Refer to item

I.C.2 for a discussion of procedures

for shift relief and turnovers

to ensure current plant conditions

and system status is conveyed to

the oncoming shift.

Periodic audits will also be conducted

to verify that tagouts

are

removed

and systems

returned to normal when the repair/testing

has

been completed.

Ins ector Findin s

References:

a)

40AC-9ZZ02, Conduct of Shift Operations

l

i j"

tt

a

t

4

14

b)

c)

d)

e)

Operating Department Instruction No.

17

40AC-9ZZ16, Shift Turnover

73AC-9ZZ04, Surveillance Testing

40AC-OZZ05, Station Tagging and Clearance

The inspector

reviewed the above procedures

in addition to samples

of various surveillance test procedures

a'nd preventative

maintenance

procedures.

Interviews with plant personnel

were also conducted.

The inspector

determined that the provisions of this TMI Action Plan

Item have been satisfactorily addressed

by the licensee.

Procedures

are in place to independently verify restoration of safety systems

and control safety system status.

The Shift Turnover procedure will

ensure that the oncoming shift is made

aware of safety system status

and overall plant conditions.

However,

one deficiency was identified.

The periodic audit referred

to in the licensee

commitment is not being conducted,

nor have plans

been

made to begin conducting this audit., The licensee

has opted to

pursue

an LLIR revision to delete this commitment to a periodic

audit.

Per discussion with the

NRR Project Manager

on November 2,

1984,

this item may be closed contingent

upon the licensee

issuing the

ILIR revision.

Any NRC comments

would be directed

from NRR to the

licensee.

This item will remain open pending issuance

of the LLIR revision.

II.K.1.10 - 0 erabilit

Status of Safet -Related

S stems

(Closed)

NRC Position

References:

a)

NUREG 0660

b)

IEB 79-06B

Review and modify as necessary

your maintenance

and test procedures

to ensure that they require:

a.

Verification, by test or inspection,

of the operability of

redundant safety-related

systems prior to the removal of any

safety-related

system from service.

b.

Verification of the operability of all safety-related

systems

when they are returned to service following maintenance

or

testing.

c.

Explicit notification of involved reactor operational personnel

whenever

a safety-related

system is removed from and returned

to service.

Licensee

Committment

V

Reference:

PVNGS TMI-2 Lessons

Learned Implementation Report

The licensee states:

The

PVNGS evaluation of item I.C.6 adequately

addresses

the concerns

of this item.

Ins ector Pindin

s

References:

a)

b)

c)

d)

Procedure

73AC-9ZZ04, Surveillance Testing

Procedure

70AC-9ZZ02, Conduct of Shift Operations

Operating Department Instruction No.

17

Procedure

40AC-OZZ05, Station Tagging and Clearance

The inspector

reviewed

a sample of surveillance

and preventative

maintenance

procedures,

and interviewed several licensee

personnel.

It was noted that specific guidance is given in this area,

in the

Procedure for Surveillance Testing,

73AC-9ZZ04. If an individual

surveillance procedure

removes

a redundant train or channel

from

service,

the shift supervisor or his assistant

signs in the

prerequisite

section to verify operability of the remaining train or

channel.

The inspector

reviewed

a sample of surveillance procedures

to ensure

this policy is implemented

and identified no deficiencies.

Provisions

are

made in the Conduct of Shift Operations

procedure,

40AC-9ZZ02 and in the Station Tagging and Clearance

procedure,

40AC-OZZ05 to ensure that the shift supervisor authorizes

removal

and return to service of safety systems.

In addition,

40AC-9ZZ02

adequately

addresses

properly return'ing safety systems

to service.

Finally, the inspector interviewed

an

SRO to ensure

operator

knowledge of this requirement.

In summary,

no deficiencies

were identified concerning ths

TMI

Action Plan Item,

and therefore, this item is considered

closed.

I.C.l.l Guidance for the Evaluation

and Develo ment of Procedures

for Transients

and Accidents - Small Break Loss of Coolant Accident

SBLOCA

0 en

NRC Position

References:

NUREG 0737

NUREG 0578

Analyses,

procedures,

and training addressing

the following are

required:

i

1.

Small break loss-of-coolant accidents;

2.

Inadequate

core cooling;

and

3.

Transients

and accidents.

Some analysis

requirements for small breaks

have already been

specified by the Bulletins and Orders

Task Force.

These

should be

completed.

In addition, pretest calculations of some of the Loss of

Fluid Test

(IOFT) small break tests

(scheduled

to start in September

1979) shall be performed

as

means to verify the analyses

performed

in support of the small break emergency procedures

and in support of

an eventual long term verification of compliance with Appendix K of

10 CFR Part 50.

Licensee

Commitment

Reference:

PVNGS THI-2 Lessons

Learned Implementation Report

PVNGS intends to submit

a Procedures

Generation

Package,

in

accordance

with Section 6.0 of Draft NUREG-0899, to the

NRC for

staff review following NRC approval of C-E Owner's

Group emergency

procedure

guidelines.

A target submission

date of August 1,

1982

has been established

for this package.

Emergency operating

procedures will be developed

and implemented in accordance

with this

package

and will be ready for NRC onsite review 60 days prior to

fuel load.

Ins ector Findin s

References:

a)

b)

c)

41R0-1ZZ08,

Small Ioss of Coolant Accident

CEN-152,

Rev.

01, Combustion Engineering

Emergency Procedure

Guidelines

Palo Verde Emergency Procedure

Generation

Package

The licensee

uses

the Emergency Procedure

Guidelines to develop the

Emergency Procedure

Generation

Package.

The Procedure

Generation

Package is then used to generate

the Emergency Operations

Procedure,

41EP-lZZ01,

and the

10 recovery operations

procedures,

which

includes the

SBLOCA procedure,

The inspector

reviewed the Small Break

LOCA procedure

(41RO-1ZZ08)

to compare

the procedure with the Generic Guidelines

and the

Procedure

Generation

Package.

The inspector questioned

a deviation of the procedure

from the

Generic Guidelines which was identified by APS in the Procedure

Generation

Package.

The

SBLOCA procedure

uses different criteria for determining the

mode of Iong Term Cooling (LTC) than called for in the Generic

Guidelines.

The Generic guidelines dictate

use of pressurizer level

and subcooling margin to determine if the Shutdown Cooling System

can support plant cooldown.

The licensee

uses pressurizer

pressure

e,

1

~ 7

of 538 psi, which is recommended

by the

CESSAR, or RVLMS (Reactor

Vessel Level Measurement

System) level of 73/,'o

make this

determination.

lI

Per discussion with NRR on November 6,

1984 as to the technical

acceptability of this deviation, it was determined that the

licensee's

approach is acceptable.

However,

NRR still has

comments

concerning

the

SBLOCA procedure

which the licensee is resolving, but the 'inspector identified no

additional deficiencies

or deviations of hi;s own.

Finally, the inspector

observed

a training session for recovery

operations

procedures.

Two or three procedures

are covered in

classroom training and then practiced by the operators. on the

simulator.

Thus, the aspects

of analysis,

procedure preparation

and training

have been adequately

addressed

by the licensee,

as far as the

SBLOCA

procedure is concerned.

This item remains

open pending assurance

that the

SBLOCA procedure is actually in place in the Control Room,

with the latest revision incorporated,

and approved.

6.

Exit Interview

The inspectors

met with the licensee

management

representatives

denoted

in paragraph

1 on November 2,

1984.

The scope of the inspections

and the

inspector's

findings as noted in this report were discussed.

~

.

0