Forwards IE Bulletin 80-20, Failures of Westinghouse Type W-2 Spring Return to Neutral Control Switches. Requests Info Re Estimate of Manpower Associated W/Corrective Actions Needed After Identifying Problem
ML17296A911
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 07/31/1980
From: Engelken R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
References
NUDOCS 8008140496
Download: ML17296A911 (10)


Text

~

J

~R RECT~

~

0 0

++**+

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION V 1990 N. CALIFORNIABOULEVARD SUITE 202, WALNUTCREEK PLAZA WALNUTCREEK, CALIFORNIA94596

~ A

~

July 31, 1980 Docket Nos.

50-528, 50-529 50-'530 Arizona Public Servi ce Company P.

0.

Box 21666

Phoenix, Arizona 85036 Attention:

Hr.

E.

E.

I/an Brunt, Jr.

Vice President, NuclearProjects Gentlemen:

Enclosed is IE Bulletin No. 80-20 which requires action by you with regard to your nuclear power facility(ies) with operating, license or construction permit.

In order to assist the NRC in evaluating the value/impact of each Bulletin on licensees, it would be helpful if you would provide an estimate of the manpower expended in conduct of the review and preparation of the report(s) required by the Bulletin.

Please estimate separately the manpower associated with correc-tive actions necessary following identification of problems through the Bulletin.

Should you have any questions regarding this bulletin or the actions required by you, please contact this office.

Sincerely, R.

H. Engelken Director

Enclosures:

l.

IE Bulletin No. 80-20 2.

List of Recently Issued IE Bulletins cc w/enclosures:

F.

W. Hartley, APS 80081 40+(0

'l t

UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.

20555 July 31.

1980 SSINS No.:

6820 Accession No.:

8006190023 IE Bulletin No. 80-20 FAILURES OF WESTINGHOUSE TYPE W-2 SPRING RETURN TO NEUTRAL CONTROL SWITCHES By letter dated June 18,. 1980, Commonwealth Edison Company submitted Licensee Event Report No.

LER 50-295/80-24 to the NRC describing a malfunction of a Westinghouse Type W-2 control switch at the Zion Generating Station, Unit 1.

The malfunctioning switch is a three position spring return to neutral switch.

Although the switch was in its proper neutral position when it malfunctioned, its neutral contacts failed to close properly thereby preventing the automatic start of 1A Service Water Pump.

Subsequent tests conducted on the malfunctioning switch revealed that contact closure was intermittent with the switch in the neutral (or "Auto Start" )

position.

Other tests conducted on identical switches from spares and from Unit 2 equipment disclosed two additional switches with a tendency for inter-mittent contact closure.

A review of this matter by Westinghouse

'led to the issuance of NSD Technical Bulletin No. NSD-TB-80-9 to the utility owners of all Westinghouse operating

.plants.

The recommendations contained in the Westinghouse technical bulletin include: (i) testing the neutral position contacts of the subject W-2 switches for continuity, and (ii) rewiring of the indicating light circuit to permit the early detection of a neutral contact failure as shown in Figure l.

Depending on how the indicating light circuit is wired, loss of continui ty thru the neutral position contact of a W-2 switch could remain undetected until the equipment associated with the switch were called upon to operate.

Since such a failure would be equivalent to by-passing the system associated with the switch, consideration should be given to rewiring the switches used in safety-related applications as shown in Figure 1.

Such rewiring would provide an acceptable means for detecting contact failure, provided the indicating light is in the control room and readily visible by the operator.

If the indicating light is not so located, consideration should be given to annunciating the neutral position contact failures at the control room to alert the operator of the inoperable status of a safety-related system.

In addition, consideration should be given to. adding redundant contacts to the W-2 switches or to replacing the W-2 switches with others having a more posi-tive contact wiping action.

ACTIONS TO BE TAKEN BY LICENSEES AND HOLDERS OF CONSTRUCTION PERMITS:

1.

Determine whether Westinghouse Type W-2 control switches with spring return to neutral position are used in safety-related applications at your facility. If so, identify the safety-related systems using these

IE Bulletin No. 80-20 July 31, 1980 Page 2 of 2 switches and the total number of switches so used.

If no such switches are used in your facility, you should indicate that this is the case and ignore the remaining questions.

2.

Licensees of operating plants using Type W-2 spring return to neutral control switches in safety-related applications shall perform continui ty tests on all such switches.

These tests shall be performed with the switch operator in the neutral position and completed within ten (10) days of the date of this bulletin.

In addition, this continuity test shall be repeated at least every thirty-one (31) days after the initial test and after each manipulation of the switch from its neutral position.

These continuity tests may be discontinued subsequent to implementing the longer term corrective measures described below.

3.

Licensees of operating plants and holders of construction permits shall describe the longer term corrective measures planned and the date by which such measures will be implemented by actual installation or by design

change, as appropriate.

As a minimum, the longer term corrective measures should include rewiring the indicating light as shown in Figure 1 provided the light is readily visible to the control room operator.

If not, failures of the neutral position contacts should be annunicated in the control room.

A report addressing the above matters, including the number of failures detected during the first series of tests and the safety-related systems involved, shall be submitted to the director of the appropriate i<RC regional office within forty-five (45) days of the date of this bulletin.

A copy of the report shall be forwarded to the Director, Division of Reactor Operations Inspection, Office of Inspection and Enforcement, lluclear Regulatory Commission, Washington, D.

C. 20555.

Approved by GAO, B180225 (R0072); clearance expires 7/31/80.

Approval was given under a blanket clearance specifically for identified generic problems.

Enclosure:

Figure 1

IE Bulletin No. 80-20 July 31, 1980 RECENTLY ISSUED IE BULLETINS Enclosure Bulletin No.

80-19 80-18 Supplement 2

to 80-17 Supplement 1

to 80-17 80-17 Subject Failures of t)ercury-Wetted i~1atrix Relays in Reactor Protective Systems of Operating Nuclear Power Plants Designed by Combus-tion Engineering Maintenance of Adequate Minimum Flow Thru Centrifugal Charging Pumps Following Secondary Side High Energy Line Rupture Failures Revealed by Testing Subsequent to Failure of Control Rods to Insert During a

Scram at a

BWR Failure of Control Rods to Insert During a Scram at a BMR Failure of Control Rods to Insert During a Scram at a

BMR Date Issued 7/31/80 7/24/80 7/22/80 7/18/80 7/3/80 Issued To All nuclear power facilities having either an OL or a

CP All PMR power reactor facilities holding OLs and to those PMRs nearing licensing All BMR power reactor facil ities holding OLs All BWR power reactor facilities holding OLs All BMR power reactor facilities holding OLs 80-16 80-15 80-14 80-13 80-12 Possible Loss Of Hotline With Loss Of Off-Site Power Degradation of Scram Discharge Yolume Capability Cracking In Core Spray Spargers 6/18/80 6/12/80 5/12/80 Decay Heat Removal System 5/9/80 Operabi 1 ity Potential ftisapplication of 6/27/80 Rosemount Inc., models 1151 and 1152 Pressure Transmitters with Either "A" or "D" Output Codes All Power Reactor Facilities with an OL or a

CP All nuclear facilities holding OLs All BMR's with an OL All BWR's with an OL Each PWR with an OL

t

[

I

EXIST NC INDICATING LIGHT CIRCUIT (TYPXCAL)

NEUTRAL SMITCH CONTACT.

INDICATING LIGHT SAFETY SIGNAL PROPOS=D REVXRXNG OF INDXCATING LIGHT CIRCUXT (T",PICAL)

NEUTRAL SWITCH CONTACT INDICATING LIGHT SAFETY SIGNAL FIGURE 1

REWIRING OF INDICATING LIGHT CIRCUIT Of M-2 S'HITCHES AS RECON')ENDED SY 'WESTINGHOUSE TECHNXCAL BULLETIN NSD-T8"80-9

/