Similar Documents at Fermi |
---|
Category:Letter type:NRC
MONTHYEARNRC-24-0007, Report of Changes to Quality Assurance Program for Radioactive Material Packages2024-01-12012 January 2024 Report of Changes to Quality Assurance Program for Radioactive Material Packages NRC-24-0002, Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122024-01-12012 January 2024 Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0079, Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 222023-12-14014 December 2023 Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 22 NRC-23-0077, Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan2023-12-0404 December 2023 Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan NRC-23-0073, Guarantee of Payment of Deferred Premiums2023-11-29029 November 2023 Guarantee of Payment of Deferred Premiums NRC-23-0071, Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-10-13013 October 2023 Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0062, Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-10-12012 October 2023 Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0068, Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-09-28028 September 2023 Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0064, Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-09-11011 September 2023 Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0057, Independent Spent Fuel Storage Installation Cask Registration2023-08-31031 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0054, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 20232023-08-31031 August 2023 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 2023 NRC-23-0056, Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval2023-08-31031 August 2023 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval NRC-23-0061, Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water..2023-08-30030 August 2023 Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water.. NRC-23-0059, Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0060, Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0053, Independent Spent Fuel Storage Installation Cask Registration2023-08-23023 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0050, Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-10010 August 2023 Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0048, Independent Spent Fuel Storage Installation Cask Registration2023-08-0101 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0049, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-07-24024 July 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0043, Independent Spent Fuel Storage Installation, Cask Registration2023-06-27027 June 2023 Independent Spent Fuel Storage Installation, Cask Registration NRC-23-0020, License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance2023-06-13013 June 2023 License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance NRC-23-0039, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-06-0606 June 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0030, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval2023-06-0505 June 2023 Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval NRC-23-0029, Snubber Program for the Fourth 10-Year Testing Interval2023-06-0505 June 2023 Snubber Program for the Fourth 10-Year Testing Interval NRC-23-0037, 56542-EN 56542 - Fermi2023-05-26026 May 2023 56542-EN 56542 - Fermi NRC-23-0031, Response to NRC Request from Audit of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources -Operating,' Emergency Diesel Generator Voltage and Frequency Surveillance Requirements2023-05-16016 May 2023 Response to NRC Request from Audit of License Amendment Request to Revise Technical Specification 3.8.1, AC Sources -Operating,' Emergency Diesel Generator Voltage and Frequency Surveillance Requirements NRC-23-0002, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-05-0505 May 2023 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0010, License Amendment Request to Correct Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage2023-05-0505 May 2023 License Amendment Request to Correct Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage NRC-23-0017, Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report2023-04-28028 April 2023 Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report NRC-23-0025, Submittal of 2022 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2023-04-28028 April 2023 Submittal of 2022 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-23-0018, Annual Non-Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Non-Radiological Environmental Operating Report NRC-23-0024, Levels and Sources of Property Insurance Coverage2023-04-0303 April 2023 Levels and Sources of Property Insurance Coverage NRC-23-0021, ISFSI, Decommissioning Funding Plan Update2023-03-30030 March 2023 ISFSI, Decommissioning Funding Plan Update NRC-23-0016, Decommissioning Funding Status Report2023-03-30030 March 2023 Decommissioning Funding Status Report NRC-23-0015, Decommissioning Funding Status Report for Fermi 12023-03-30030 March 2023 Decommissioning Funding Status Report for Fermi 1 NRC-23-0011, License Renewal Commitment 7c: Transmittal of Core Plate Hold-Down Bolt Analysis2023-03-0707 March 2023 License Renewal Commitment 7c: Transmittal of Core Plate Hold-Down Bolt Analysis NRC-22-0026, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements2022-12-16016 December 2022 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements NRC-22-0051, DTE Electric Company - Guarantee of Payment of Deferred Premiums2022-11-29029 November 2022 DTE Electric Company - Guarantee of Payment of Deferred Premiums NRC-22-0052, Replacement Files for Submittal of Revision 24 to the Fermi 2 Updated Final Safety Analysis Report (UFSAR) Through EIE on November 9, 20222022-11-17017 November 2022 Replacement Files for Submittal of Revision 24 to the Fermi 2 Updated Final Safety Analysis Report (UFSAR) Through EIE on November 9, 2022 NRC-22-0046, Submittal of Biennial Review of the Fermi 1 Safety Analysis Report2022-11-14014 November 2022 Submittal of Biennial Review of the Fermi 1 Safety Analysis Report NRC-22-0041, Evacuation Time Estimate Report2022-10-0505 October 2022 Evacuation Time Estimate Report NRC-22-0033, Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 20222022-08-29029 August 2022 Enrico Fermi Atomic Power Plant, Unit 1 - Annual Report for Period Ending June 30, 2022 NRC-22-0030, Inservice Inspection Summary Report2022-08-10010 August 2022 Inservice Inspection Summary Report NRC-22-0023, Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2022-08-0404 August 2022 Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements NRC-22-0022, Annual Non-Radiological Environmental Operating Report2022-04-29029 April 2022 Annual Non-Radiological Environmental Operating Report NRC-22-0021, Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report2022-04-29029 April 2022 Annual Radioactive Effluent Release Report and Radiological Environmental Operating Report NRC-22-0020, Enrico Fermi Atomic Power Plant, Unit No. 1 & Fermi 2 Power Plant - 10 CFR 20.2206 Report of Individual Monitoring2022-04-28028 April 2022 Enrico Fermi Atomic Power Plant, Unit No. 1 & Fermi 2 Power Plant - 10 CFR 20.2206 Report of Individual Monitoring NRC-22-0003, Submittal of 2021 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2022-04-26026 April 2022 Submittal of 2021 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-22-0019, Submittal of the National Pollutant Discharge Elimination System Permit Application for Reissuance2022-04-0404 April 2022 Submittal of the National Pollutant Discharge Elimination System Permit Application for Reissuance NRC-22-0011, Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report2022-03-31031 March 2022 Enrico Fermi Atomic Power Plant, Unit No. 1 - Decommissioning Funding Status Report 2024-01-12
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARNRC-23-0068, Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-09-28028 September 2023 Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0055, NRR E-mail Capture - (External Sender) Fermi 2 Power Plant, Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 - Updated Clean Sheet for NRC-23-00552023-08-16016 August 2023 NRR E-mail Capture - (External_Sender) Fermi 2 Power Plant, Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 - Updated Clean Sheet for NRC-23-0055 ML23227A2212023-08-15015 August 2023 Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 NRC-23-0050, Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-10010 August 2023 Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0020, License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance2023-06-13013 June 2023 License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance NRC-23-0002, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-05-0505 May 2023 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0010, License Amendment Request to Correct Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage2023-05-0505 May 2023 License Amendment Request to Correct Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage NRC-22-0026, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements2022-12-16016 December 2022 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements NRC-22-0023, Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2022-08-0404 August 2022 Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements ML22101A0472022-04-0404 April 2022 Submittal of Application for the Renewal of National Pollutant Discharge Elimination System (NPDES) Permit NRC-21-0001, License Amendment Request to Revise Technical Specifications to Remove Obsolete Information, Make Minor Corrections, and Make Miscellaneous Editorial Changes2021-03-31031 March 2021 License Amendment Request to Revise Technical Specifications to Remove Obsolete Information, Make Minor Corrections, and Make Miscellaneous Editorial Changes NRC-20-0038, Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules2020-10-28028 October 2020 Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules NRC-20-0040, Response to NRC Request from Audit of License Amendment Request to Revise Technical Specifications to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2020-06-23023 June 2020 Response to NRC Request from Audit of License Amendment Request to Revise Technical Specifications to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle NRC-20-0032, Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2020-06-0505 June 2020 Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program NRC-19-0075, License Amendment Request - Proposed Revision to Technical Specifications for Secondary Containment Surveillance Requirements2019-12-0606 December 2019 License Amendment Request - Proposed Revision to Technical Specifications for Secondary Containment Surveillance Requirements NRC-19-0054, DTE Energy Company - License Amendment Request to Revise Technical Specifications to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2019-11-0808 November 2019 DTE Energy Company - License Amendment Request to Revise Technical Specifications to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle NRC-19-0028, License Amendment Request - Proposed Revision to Technical Specifications in Response to GE Energy - Nuclear 10 CFR Part 21 Safety Communication SC05-032019-09-0505 September 2019 License Amendment Request - Proposed Revision to Technical Specifications in Response to GE Energy - Nuclear 10 CFR Part 21 Safety Communication SC05-03 NRC-19-0001, License Amendment Request to Revise Technical Specification 3.3.5.3, Reactor Pressure Vessel (RPV) Water Inventory Control Instrumentation2019-02-27027 February 2019 License Amendment Request to Revise Technical Specification 3.3.5.3, Reactor Pressure Vessel (RPV) Water Inventory Control Instrumentation NRC-19-0002, Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR2019-02-0808 February 2019 Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR NRC-17-0063, License Amendment Request for Adoption of TSTF-484, Rev. 0, Use of TS 3.10.1 for Scram Time Testing Activities.2017-10-0909 October 2017 License Amendment Request for Adoption of TSTF-484, Rev. 0, Use of TS 3.10.1 for Scram Time Testing Activities. NRC-17-0067, Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control.2017-08-31031 August 2017 Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control. ML17237A1762017-08-24024 August 2017 License Amendment Request to Revise Technical Specifications to Eliminate Main Steam Line Radiation Monitor Reactor Trip and Primary Containment Isolation System Group 1 Isolation Functions NRC-17-0056, Supplemental Information Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-545, Revision 32017-08-15015 August 2017 Supplemental Information Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-545, Revision 3 NRC-17-0044, License Amendment Request to Revise Technical Specification 5.5.7, Ventilation Filter Testing Program, to Be Consistent with Standard Technical Specifications2017-08-14014 August 2017 License Amendment Request to Revise Technical Specification 5.5.7, Ventilation Filter Testing Program, to Be Consistent with Standard Technical Specifications NRC-17-0025, License Amendment Request to Revise Technical Specification Section 3.7.2 for Emergency Equipment Cooling Water / Emergency Equipment Service Water System and Ultimate Heat Sink2017-07-17017 July 2017 License Amendment Request to Revise Technical Specification Section 3.7.2 for Emergency Equipment Cooling Water / Emergency Equipment Service Water System and Ultimate Heat Sink NRC-17-0010, License Amendment Request to Revise Technical Specifications for Emergency Core Cooling System Instrumentation and Reactor Core Isolation Cooling System Instrumentation2017-02-23023 February 2017 License Amendment Request to Revise Technical Specifications for Emergency Core Cooling System Instrumentation and Reactor Core Isolation Cooling System Instrumentation NRC-16-0036, License Amendment Request to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, Using the Consolidated Line Item Improvement Pro2016-07-25025 July 2016 License Amendment Request to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, Using the Consolidated Line Item Improvement Proces NRC-16-0006, License Amendment Request to Revise Integrated Leak Rate Test (Type a) and Type C Test Intervals2016-03-22022 March 2016 License Amendment Request to Revise Integrated Leak Rate Test (Type a) and Type C Test Intervals NRC-15-0081, License Renewal Application Update for the Boraflex Monitoring Program2015-09-24024 September 2015 License Renewal Application Update for the Boraflex Monitoring Program NRC-15-0090, License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process2015-09-24024 September 2015 License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process NRC-15-0067, Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 352015-06-18018 June 2015 Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 35 NRC-15-0062, Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 342015-06-0909 June 2015 Response to NRC Request for Additional Information for the Review of the License Renewal Application - Set 34 NRC-15-0044, Response to NRC Request for Additional Information for the Review of the License Renewal Application - Sets 27, 28, 29 and 312015-04-27027 April 2015 Response to NRC Request for Additional Information for the Review of the License Renewal Application - Sets 27, 28, 29 and 31 NRC-15-0030, Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 222015-03-19019 March 2015 Response to NRC Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 22 NRC-15-0028, Revision to Response to License Renewal Environmental RAI SSSH-12015-02-18018 February 2015 Revision to Response to License Renewal Environmental RAI SSSH-1 NRC-15-0021, License Renewal Application - Response to LR-ISG-2013-012015-02-0505 February 2015 License Renewal Application - Response to LR-ISG-2013-01 NRC-14-0055, License Amendment Request to Revise the Emergency Action Level Scheme for the Emergency Plan2014-10-21021 October 2014 License Amendment Request to Revise the Emergency Action Level Scheme for the Emergency Plan ML14121A5362014-04-24024 April 2014 Fermi 2, License Renewal Application, Page 3.3-2 Through Appendix C, Page C-13 ML14121A5352014-04-24024 April 2014 Fermi 2, License Renewal Application, Cover Through Page 3.3-1 ML14121A5382014-04-24024 April 2014 Fermi 2, License Renewal Application, Appendix D Through Appendix E, Page 3-169 ML14121A5392014-04-24024 April 2014 Fermi 2, License Renewal Application, Appendix E, Page 3-170 Through Page 9-23 NRC-14-0028, License Renewal Application, Appendix E, Page 10-1 Through End2014-04-24024 April 2014 License Renewal Application, Appendix E, Page 10-1 Through End NRC-13-0012, License Amendment Request to Revise Technical Specifications Regarding Control Room Envelope Habitability in Accordance with TSTF-448, Revision 3, Using the Consolidated Line Item Improvement Process2013-04-17017 April 2013 License Amendment Request to Revise Technical Specifications Regarding Control Room Envelope Habitability in Accordance with TSTF-448, Revision 3, Using the Consolidated Line Item Improvement Process NRC-13-0004, License Amendment Request for Measurement Uncertainty Recapture (Mur) Power Uprate2013-02-0707 February 2013 License Amendment Request for Measurement Uncertainty Recapture (Mur) Power Uprate NRC-13-0001, License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-423, Revision 1, Technical Specifications End States, NEDC-32988-A, Using the Consolidated Line Item Improvement Process2013-01-11011 January 2013 License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-423, Revision 1, Technical Specifications End States, NEDC-32988-A, Using the Consolidated Line Item Improvement Process NRC-13-0002, Proposed License Amendment to Revise the Fermi 2 Licensing Bases for Protection from Tornado-Generated Missiles2013-01-11011 January 2013 Proposed License Amendment to Revise the Fermi 2 Licensing Bases for Protection from Tornado-Generated Missiles NRC-12-0037, Proposed License Amendment to Relocate Pressure and Temperature Curves to a Pressure Temperature Limits Report2012-12-21021 December 2012 Proposed License Amendment to Relocate Pressure and Temperature Curves to a Pressure Temperature Limits Report NRC-12-0087, License Amendment Request to Change Name of Licensee from the Detroit Edison Company to DTE Electric Company2012-12-21021 December 2012 License Amendment Request to Change Name of Licensee from the Detroit Edison Company to DTE Electric Company NRC-12-0083, License Amendment Request to Change Licensee Name on the Operating License2012-12-21021 December 2012 License Amendment Request to Change Licensee Name on the Operating License NRC-12-0037, Fermi 2, Proposed License Amendment to Relocate Pressure and Temperature Curves to a Pressure Temperature Limits Report2012-12-21021 December 2012 Fermi 2, Proposed License Amendment to Relocate Pressure and Temperature Curves to a Pressure Temperature Limits Report 2023-09-28
[Table view] Category:Technical Specification
MONTHYEARNRC-23-0068, Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-09-28028 September 2023 Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0002, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-05-0505 May 2023 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0010, License Amendment Request to Correct Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage2023-05-0505 May 2023 License Amendment Request to Correct Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage NRC-22-0026, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements2022-12-16016 December 2022 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements NRC-22-0023, Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2022-08-0404 August 2022 Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements NRC-21-0001, License Amendment Request to Revise Technical Specifications to Remove Obsolete Information, Make Minor Corrections, and Make Miscellaneous Editorial Changes2021-03-31031 March 2021 License Amendment Request to Revise Technical Specifications to Remove Obsolete Information, Make Minor Corrections, and Make Miscellaneous Editorial Changes NRC-20-0038, Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules2020-10-28028 October 2020 Application to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules ML20282A2302020-10-13013 October 2020 Correction to Amendment No. 216 - Revision to Technical Specifications in Response to GE Energy-Nuclear's 10 CFR Part 21 Safety Communication SC05-03 NRC-20-0032, Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2020-06-0505 June 2020 Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program NRC-19-0054, DTE Energy Company - License Amendment Request to Revise Technical Specifications to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2019-11-0808 November 2019 DTE Energy Company - License Amendment Request to Revise Technical Specifications to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle NRC-19-0028, License Amendment Request - Proposed Revision to Technical Specifications in Response to GE Energy - Nuclear 10 CFR Part 21 Safety Communication SC05-032019-09-0505 September 2019 License Amendment Request - Proposed Revision to Technical Specifications in Response to GE Energy - Nuclear 10 CFR Part 21 Safety Communication SC05-03 ML17305A0382017-10-16016 October 2017 Enclosures 1-6: 10CFR50.59 Evaluation Summary Report, Commitment Management Report, Revisions to Technical Requirements Manual and Technical Specifications Bases NRC-17-0063, License Amendment Request for Adoption of TSTF-484, Rev. 0, Use of TS 3.10.1 for Scram Time Testing Activities.2017-10-0909 October 2017 License Amendment Request for Adoption of TSTF-484, Rev. 0, Use of TS 3.10.1 for Scram Time Testing Activities. NRC-16-0036, License Amendment Request to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, Using the Consolidated Line Item Improvement Pro2016-07-25025 July 2016 License Amendment Request to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing, Using the Consolidated Line Item Improvement Proces NRC-15-0091, License Amendment Request to Revise Technical Specification Section 3.5.1, ECCS - Operating.2015-09-24024 September 2015 License Amendment Request to Revise Technical Specification Section 3.5.1, ECCS - Operating. NRC-15-0090, License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process2015-09-24024 September 2015 License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process NRC-14-0055, License Amendment Request to Revise the Emergency Action Level Scheme for the Emergency Plan2014-10-21021 October 2014 License Amendment Request to Revise the Emergency Action Level Scheme for the Emergency Plan NRC-14-0010, License Amendment Request to Revise Technical Specification Surveillance Requirements for Direct Current Batteries2014-04-23023 April 2014 License Amendment Request to Revise Technical Specification Surveillance Requirements for Direct Current Batteries NRC-13-0004, License Amendment Request for Measurement Uncertainty Recapture (Mur) Power Uprate2013-02-0707 February 2013 License Amendment Request for Measurement Uncertainty Recapture (Mur) Power Uprate NRC-12-0067, Fermi 2, Submittal of Revision 18 to the Updated Final Safety Analysis Report, 10 CFR 50.59 Evaluation Summary Report, Commitment Management Report and Revision to the Technical Requirements Manual and the Technical Specifications Bases2012-11-0505 November 2012 Fermi 2, Submittal of Revision 18 to the Updated Final Safety Analysis Report, 10 CFR 50.59 Evaluation Summary Report, Commitment Management Report and Revision to the Technical Requirements Manual and the Technical Specifications Bases NRC-11-0049, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration.2011-12-20020 December 2011 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration. NRC-11-0013, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-514, Revision 3, Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation.2011-04-0808 April 2011 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-514, Revision 3, Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation. NRC-10-0047, Proposed Emergency License Amendment for a Onetime Extension of the Completion Time in Technical Specification 3.7.3, Control Room Emergency Filtration (CREF) System, Condition B2010-05-14014 May 2010 Proposed Emergency License Amendment for a Onetime Extension of the Completion Time in Technical Specification 3.7.3, Control Room Emergency Filtration (CREF) System, Condition B ML0735506002007-12-18018 December 2007 Tech Spec Pages for Amendment 177 Technical Specification (TS) Change (TSTF-477) to Add an Action Statement for Two Inoperable Control Center Air Conditioning Subsystems to TS 3.7.4 NRC-07-0047, Transmittal of Revised Technical Specifications (TS) Pages for Use with the Application to Add an Action Statement for Two Inoperable Control Center Air Conditioning Subsystems in TS 3.7.42007-09-11011 September 2007 Transmittal of Revised Technical Specifications (TS) Pages for Use with the Application to Add an Action Statement for Two Inoperable Control Center Air Conditioning Subsystems in TS 3.7.4 NRC-07-0036, Proposed License Amendment to Delete the Note Associated with the Performance of Channel Calibration for Primary Containment High Range Radiation Monitor in Technical Specification 3.3.3.1 Surveillance Requirement2007-07-12012 July 2007 Proposed License Amendment to Delete the Note Associated with the Performance of Channel Calibration for Primary Containment High Range Radiation Monitor in Technical Specification 3.3.3.1 Surveillance Requirement NRC-07-0030, Application for Technical Specification Change (TSTF-477) to Add an Action Statement for Two Inoperable Control Center Air Conditioning Subsystems to Technical Specification 3.7.4 Using the Consolidated Line Item Improvement Process2007-06-12012 June 2007 Application for Technical Specification Change (TSTF-477) to Add an Action Statement for Two Inoperable Control Center Air Conditioning Subsystems to Technical Specification 3.7.4 Using the Consolidated Line Item Improvement Process NRC-06-0063, Application for Technical Specification Change TSTF-374, Revision to TS 5.5.13 and Associated TS Bases for the Diesel Fuel Oil Testing Programs Using the Consolidated Line Item Improvement Process2006-11-27027 November 2006 Application for Technical Specification Change TSTF-374, Revision to TS 5.5.13 and Associated TS Bases for the Diesel Fuel Oil Testing Programs Using the Consolidated Line Item Improvement Process NRC-06-0010, Emergency License Amendment Request for One-Time Extension of Allowed Outage Time for the Plant Emergency Diesel Generator 122006-02-0505 February 2006 Emergency License Amendment Request for One-Time Extension of Allowed Outage Time for the Plant Emergency Diesel Generator 12 ML0529900182005-10-25025 October 2005 Technical Specification Page Control Rod Scram Time Testing Frequency ML0433800092004-12-0707 December 2004 Correction to Amendment No. 163 Technical Specification Change Regarding Increased Flexibility in Mode Changes ML0433502482004-11-29029 November 2004 Technical Specifications, Technical Specification Change Regarding Increased Flexibility in Mode Changes NRC-04-0074, Proposed License Amendment Request to Revise Technical Specification 2.1, Safety Limit Minimum Critical Power Ratio2004-10-0707 October 2004 Proposed License Amendment Request to Revise Technical Specification 2.1, Safety Limit Minimum Critical Power Ratio ML0412503642004-04-23023 April 2004 Licensing Document Transmittal Firm 2 Technical Requirements Manual - Vol I, Revision 67, 04/23/2004. NRC-04-0006, Proposed License Amendment to Revise Technical Specification 3.3.6.1, Primary Containment Isolation Instrumentation.2004-03-19019 March 2004 Proposed License Amendment to Revise Technical Specification 3.3.6.1, Primary Containment Isolation Instrumentation. ML0407808262004-03-15015 March 2004 Technical Specification Pages for Amendment 159 NRC-04-0004, Proposed Amendment to Revise Technical Specification 3.3.6.2, Secondary Containment Isolation Instrumentation.2004-01-30030 January 2004 Proposed Amendment to Revise Technical Specification 3.3.6.2, Secondary Containment Isolation Instrumentation. ML0402207862004-01-16016 January 2004 Technical Specification Pages for Fermi 2, Amendment No. 158 ML0330903572003-10-30030 October 2003 Tech Spec Pages for License Amendment 157, Revised Action for SCRAM Discharge Volume Vent and Drain Valves NRC-03-0009, Proposed License Amendment for Revision of TS Section 5.5.10, TS Bases Control Program to Be Consistent with Revised 10 CFR 50.592003-02-13013 February 2003 Proposed License Amendment for Revision of TS Section 5.5.10, TS Bases Control Program to Be Consistent with Revised 10 CFR 50.59 2023-09-28
[Table view] Category:Bases Change
MONTHYEARNRC-22-0026, License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements2022-12-16016 December 2022 License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements NRC-22-0023, Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2022-08-0404 August 2022 Application to Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements NRC-21-0001, License Amendment Request to Revise Technical Specifications to Remove Obsolete Information, Make Minor Corrections, and Make Miscellaneous Editorial Changes2021-03-31031 March 2021 License Amendment Request to Revise Technical Specifications to Remove Obsolete Information, Make Minor Corrections, and Make Miscellaneous Editorial Changes ML17305A0382017-10-16016 October 2017 Enclosures 1-6: 10CFR50.59 Evaluation Summary Report, Commitment Management Report, Revisions to Technical Requirements Manual and Technical Specifications Bases NRC-17-0063, License Amendment Request for Adoption of TSTF-484, Rev. 0, Use of TS 3.10.1 for Scram Time Testing Activities.2017-10-0909 October 2017 License Amendment Request for Adoption of TSTF-484, Rev. 0, Use of TS 3.10.1 for Scram Time Testing Activities. NRC-15-0090, License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process2015-09-24024 September 2015 License Amendment Request to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process NRC-14-0055, License Amendment Request to Revise the Emergency Action Level Scheme for the Emergency Plan2014-10-21021 October 2014 License Amendment Request to Revise the Emergency Action Level Scheme for the Emergency Plan NRC-13-0004, License Amendment Request for Measurement Uncertainty Recapture (Mur) Power Uprate2013-02-0707 February 2013 License Amendment Request for Measurement Uncertainty Recapture (Mur) Power Uprate NRC-12-0067, Fermi 2, Submittal of Revision 18 to the Updated Final Safety Analysis Report, 10 CFR 50.59 Evaluation Summary Report, Commitment Management Report and Revision to the Technical Requirements Manual and the Technical Specifications Bases2012-11-0505 November 2012 Fermi 2, Submittal of Revision 18 to the Updated Final Safety Analysis Report, 10 CFR 50.59 Evaluation Summary Report, Commitment Management Report and Revision to the Technical Requirements Manual and the Technical Specifications Bases NRC-11-0049, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration.2011-12-20020 December 2011 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration. NRC-11-0013, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-514, Revision 3, Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation.2011-04-0808 April 2011 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-514, Revision 3, Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation. NRC-07-0047, Transmittal of Revised Technical Specifications (TS) Pages for Use with the Application to Add an Action Statement for Two Inoperable Control Center Air Conditioning Subsystems in TS 3.7.42007-09-11011 September 2007 Transmittal of Revised Technical Specifications (TS) Pages for Use with the Application to Add an Action Statement for Two Inoperable Control Center Air Conditioning Subsystems in TS 3.7.4 NRC-07-0030, Application for Technical Specification Change (TSTF-477) to Add an Action Statement for Two Inoperable Control Center Air Conditioning Subsystems to Technical Specification 3.7.4 Using the Consolidated Line Item Improvement Process2007-06-12012 June 2007 Application for Technical Specification Change (TSTF-477) to Add an Action Statement for Two Inoperable Control Center Air Conditioning Subsystems to Technical Specification 3.7.4 Using the Consolidated Line Item Improvement Process NRC-06-0063, Application for Technical Specification Change TSTF-374, Revision to TS 5.5.13 and Associated TS Bases for the Diesel Fuel Oil Testing Programs Using the Consolidated Line Item Improvement Process2006-11-27027 November 2006 Application for Technical Specification Change TSTF-374, Revision to TS 5.5.13 and Associated TS Bases for the Diesel Fuel Oil Testing Programs Using the Consolidated Line Item Improvement Process ML0433800092004-12-0707 December 2004 Correction to Amendment No. 163 Technical Specification Change Regarding Increased Flexibility in Mode Changes NRC-03-0009, Proposed License Amendment for Revision of TS Section 5.5.10, TS Bases Control Program to Be Consistent with Revised 10 CFR 50.592003-02-13013 February 2003 Proposed License Amendment for Revision of TS Section 5.5.10, TS Bases Control Program to Be Consistent with Revised 10 CFR 50.59 2022-08-04
[Table view] |
Text
Keith J. Polson Senior Vice President and CNO DTE Energy Company 6400 N. Dixie Highway, Newport, MI 48166 Tel: 734.586.6515 Fax: 734.586.4172 Email: keith.polson@dteenergy.com October 9, 2017 10 CFR 50.90 NRC-17-0063 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001
References:
- 1) Fermi 2 NRC Docket No. 50-341 NRC License No. NPF-43
Subject:
License Amendment Request for Adoption of TSTF-484, Rev. 0, Use of TS 3.10.1 for Scram Time Testing Activities In accordance with the provisions of Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR 50.90), DTE Electric Company (DTE) is submitting a request for an amendment to technical specifications (TS) for Fermi Unit 2 (i.e. Appendix A, Technical Specifications of Renewed Facility Operating License NPF-43).
The proposed amendment would revise LCO 3.10.1, and the associated Bases, to expand its scope to include provisions for temperature excursions greater than 200°F as a consequence of inservice leak and hydrostatic testing, and as a consequence of scram time testing initiated in conjunction with an inservice leak or hydrostatic test, while considering operational conditions to be in Mode 4. This change is consistent with NRC approved Revision 0 to Technical Specification Task Force (TSTF) Improved Standard Technical Specification Change Traveler, TSTF-484, Use of TS 3.10.1 for Scram Time Testing Activities. The availability of the TS 3.10.1 revision was announced in the Federal Register on October 27, 2006 (71 FR 63050) as part of the consolidated line item improvement process (CLIIP). provides an evaluation of the proposed change. Enclosure 2 provides the existing TS pages marked up to show the proposed change. Enclosure 3 provides the proposed TS changes in final typed format (i.e. clean TS pages). Enclosure 4 provides the existing TS Bases pages marked up to show the proposed change. Enclosure 4 is provided for information only.
DTE requests approval of the proposed license amendment by August 31, 2018, to support the next refueling outage, with the amendment being implemented within 60 days.
USNRC NRC-17-0063 Page 2 In accordance with 10 CFR 50.91, a copy of this application, with enclosures, is being provided to the designated Michigan State Official.
Should you have any questions or require additional information, please contact Mr. ScottA. Maglio, Manager - Nuclear Licensing at (734) 586-5076.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on October 9, 2017 Keith J. Polson Senior Vice President and CNO
Enclosures:
- 1. Evaluation of Proposed Change
- 2. Proposed Technical Specification Change (Mark-Up)
- 3. Proposed Technical Specification Change (Re-Typed)
- 4. Proposed Technical Specification Bases Change (Mark-up) cc: NRC Project Manager NRC Resident Office Reactor Projects Chief, Branch 5, Region III Regional Administrator, Region III Michigan Public Service Commission Regulated Energy Division (kindschl@michigan.gov)
Enclosure 1 to NRC-17-0063 Fermi 2 NRC Docket No. 50-341 Operating License No. NPF-43 License Amendment Request for Adoption of TSTF-484, Rev. 0, Use of TS 3.10.1 for Scram Time Testing Activities Evaluation of Proposed Change to NRC-17-0063 Page 1 Contents 1.0 Description 2.0 Proposed Change 3.0 Background 4.0 Technical Analysis 5.0 Regulatory Safety Analysis 5.1 No Significant Hazards Determination 5.2 Applicable Regulatory Requirements / Criteria 6.0 Environmental Consideration 7.0 References to NRC-17-0063 Page 2
1.0 DESCRIPTION
The proposed amendment would revise LCO 3.10.1, and the associated Bases, to expand its scope to include provisions for temperature excursions greater than 200°F as a consequence of inservice leak and hydrostatic testing, and as a consequence of scram time testing initiated in conjunction with an inservice leak or hydrostatic test, while considering operational conditions to be in Mode 4. This change is consistent with NRC approved Revision 0 to Technical Specification Task Force (TSTF) Improved Standard Technical Specification Change Traveler, TSTF-484, Use of TS 3.10.1 for Scram Time Testing Activities. The availability of the TS 3.10.1 revision was announced in the Federal Register on October 27, 2006 (71 FR 63050) as part of the consolidated line item improvement process (CLIIP).
2.0 PROPOSED CHANGE
Consistent with the NRC approved Revision 0 of TSTF-484, the proposed TS changes include a revised TS 3.10.1, Inservice Leak and Hydrostatic Testing Operation. Proposed revisions to the TS Bases are also included in this application. Adoption of the TS Bases associated with TSTF-484, Revision 0 is an integral part of implementing this TS amendment. The changes to the affected TS Bases pages will be incorporated in accordance with the TS Bases Control Program.
This application is being made in accordance with the CLIIP. DTE Electric Company (DTE) is not proposing variations or deviations from the TS changes described in TSTF-484, Revision 0, or the NRC staffs model safety evaluation (SE) published on October 27, 2006 (71 FR 63050) as part of the CLIIP Notice of Availability.
3.0 BACKGROUND
The background for this application is adequately addressed by the NRC Notice of Availability published on October 27, 2006 (71 FR 63050).
4.0 TECHNICAL ANALYSIS
DTE has reviewed the safety evaluation (SE) published on October 27, 2006 (71 FR 63050) as part of the CLIIP Notice of Availability. DTE has concluded that the technical justifications presented in the SE prepared by the NRC staff are applicable to Fermi Unit 2 and therefore justify this amendment for the incorporation of the proposed changes to the Fermi Unit 2 TS.
The technical justification presented in the SE prepared by the NRC staff discusses the TS requirement for two low-pressure Emergency Core Cooling System (ECCS) injection / spray subsystems to be operable in Mode 4. This requirement is consistent with the current Fermi 2 TS 3.5.2. Note that DTE has submitted a license amendment request to adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, which modifies the number of subsystems required to to NRC-17-0063 Page 3 be operable in Mode 4 for TS 3.5.2. This pending change, which is technically justified in TSTF-542, does not impact the conclusions of the SE dated October 27, 2006.
5.0 REGULATORY ANALYSIS
5.1 No Significant Hazards Determination DTE Electric Company (DTE) has reviewed the no significant hazards determination published on August 21, 2006 (71 FR 48561) as part of the CLIIP Notice for Comment. The no significant hazards determination was made available on October 27, 2006 (71 FR 63050) as part of the CLIIP Notice of Availability. DTE has concluded that the determination presented in the notice is applicable to Fermi Unit 2 and the determination is hereby incorporated by reference to satisfy the requirements of 10 CFR 50.91(a).
5.2 Applicable Regulatory Requirements / Criteria A description of the proposed TS change and its relationship to applicable regulatory requirements was provided in the NRC Notice of Availability published on October 27, 2006 (71 FR 63050).
6.0 ENVIRONMENTAL CONSIDERATION
DTE has reviewed the environmental evaluation included in the safety evaluation (SE) published on October 27, 2006 (71 FR 63050) as part of the CLIIP Notice of Availability. DTE has concluded that the staffs findings presented in that evaluation are applicable to Fermi Unit 2 and the evaluation is hereby incorporated by reference for this application.
7.0 REFERENCES
- 1. Federal Register Notice, Notice of Availability published on October 27, 2006 (71 FR 63050).
- 2. Federal Register Notice, Notice for Comment published on August 21, 2006 (71 FR 48561)
- 3. TSTF-484 Revision 0, Use of TS 3.10.1 for Scram Times Testing Activities
Enclosure 2 to NRC-17-0063 Fermi 2 NRC Docket No. 50-341 Operating License No. NPF-43 License Amendment Request for Adoption of TSTF-484, Rev. 0, Use of TS 3.10.1 for Scram Time Testing Activities Proposed Technical Specification Change (Mark-Up)
Inservice Leak and Hydrostatic Testing Operation 3.10.1 3.10 SPECIAL OPERATIONS 3.10.1 Inservice Leak and Hydrostatic Testing Operation LCO 3.10.1 The average reactor coolant temperature specified in Table 1.1-1 for MODE 4 may be changed to "NA," and operation considered not to be in MODE 3; and the requirements of LCO 3.4.9, "Residual Heat Removal (RHR) Shutdown Cooling System Cold Shutdown," may be suspended to allow reactor coolant temperature > 200°F,:
For to allow performance of an inservice leak or hydrostatic test, As a consequence of maintaining adequate pressure for an inservice leak or hydrostatic test, or As a consequence of maintaining adequate pressure for control rod scram time testing initiated in conjunction with an inservice leak or hydrostatic test, provided the following MODE 3 LCOs are met:
- a. LCO 3.3.6.2, "Secondary Containment Isolation Instrumentation," Functions 1, 3, and 4 of Table 3.3.6.2-1;
- b. LCO 3.6.4.1, "Secondary Containment";
- c. LCO 3.6.4.2, "Secondary Containment Isolation Valves (SCIVs)"; and
- d. LCO 3.6.4.3, "Standby Gas Treatment (SGT) System."
APPLICABILITY: MODE 4 with average reactor coolant temperature > 200F.
FERMI - UNIT 2 3.10-1 Amendment No. 134
Enclosure 3 to NRC-17-0063 Fermi 2 NRC Docket No. 50-341 Operating License No. NPF-43 License Amendment Request for Adoption of TSTF-484, Rev. 0, Use of TS 3.10.1 for Scram Time Testing Activities Proposed Technical Specification Change (Re-Typed)
Inservice Leak and Hydrostatic Testing Operation 3.10.1 3.10 SPECIAL OPERATIONS 3.10.1 Inservice Leak and Hydrostatic Testing Operation LCO 3.10.1 The average reactor coolant temperature specified in Table 1.1-1 for MODE 4 may be changed to "NA," and operation considered not to be in MODE 3; and the requirements of LCO 3.4.9, "Residual Heat Removal (RHR) Shutdown Cooling System Cold Shutdown," may be suspended to allow reactor coolant temperature > 200°F:
For performance of an inservice leak or hydrostatic test, As a consequence of maintaining adequate pressure for an inservice leak or hydrostatic test, or As a consequence of maintaining adequate pressure for control rod scram time testing initiated in conjunction with an inservice leak or hydrostatic test, provided the following MODE 3 LCOs are met:
- a. LCO 3.3.6.2, "Secondary Containment Isolation Instrumentation," Functions 1, 3, and 4 of Table 3.3.6.2-1;
- b. LCO 3.6.4.1, "Secondary Containment";
- c. LCO 3.6.4.2, "Secondary Containment Isolation Valves (SCIVs)"; and
- d. LCO 3.6.4.3, "Standby Gas Treatment (SGT) System."
APPLICABILITY: MODE 4 with average reactor coolant temperature > 200F.
FERMI - UNIT 2 3.10-1 Amendment No. 134
Enclosure 4 to NRC-17-0063 Fermi 2 NRC Docket No. 50-341 Operating License No. NPF-43 License Amendment Request for Adoption of TSTF-484, Rev. 0, Use of TS 3.10.1 for Scram Time Testing Activities Proposed Technical Specification Bases Change (Mark-Up)
Inservice Leak and Hydrostatic Testing Operation B 3.10.1 B 3.10 SPECIAL OPERATIONS B 3.10.1 Inservice Leak and Hydrostatic Testing Operation BASES BACKGROUND The purpose of this Special Operations LCO is to allow certain reactor coolant pressure tests to be performed in MODE 4 when the metallurgical characteristics of the reactor pressure vessel (RPV) require the pressure testing at temperatures > 200F (normally corresponding to MODE 3) or to allow completing these reactor coolant pressure tests when the initial conditions do not require temperatures
> 200°F. Furthermore, the purpose is to allow continued performance of control rod scram time testing required by SR 3.1.4.1 or SR 3.1.4.4 if reactor coolant temperatures exceed 200°F when the control rod scram time testing is initiated in conjunction with an inservice leak or hydrostatic test. These control rod scram time tests would be performed in accordance with LCO 3.10.4, "Single Control Rod WithdrawalCold Shutdown," during MODE 4 operation.
Inservice hydrostatic testing and system leakage pressure tests required by Section XI of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (Ref. 1) are performed prior to the reactor going critical after a refueling outage. Recirculation pump operation and a water solid RPV (except for an air bubble for pressure control) are used to achieve the necessary temperatures and pressures required for these tests. The minimum temperatures (at the required pressures) allowed for these tests are determined from the RPV pressure and temperature (P/T) limits required by LCO 3.4.10, "Reactor Coolant System (RCS) Pressure and Temperature (P/T) Limits." These limits are conservatively based on the fracture toughness of the reactor vessel, taking into account anticipated vessel neutron fluence.
With increased reactor vessel fluence over time, the minimum allowable vessel temperature increases at a given pressure.
Periodic updates to the RPV P/T limit curves are performed as necessary, based upon the results of analyses of representative irradiated surveillance specimens as part of the BWR Vessel and Internals Project (BWRVIP) Integrated Surveillance Program (Ref. 3). Hydrostatic and leak testing may eventually be desired required with minimum reactor coolant temperatures > 200F. However, even with required minimum reactor coolant temperatures 200°F, maintaining RCS temperatures within a small band during the test can FERMI - UNIT 2 B 3.10.1-1 Revision 17
Inservice Leak and Hydrostatic Testing Operation B 3.10.1 BASES BACKGROUND (continued) be impractical. Removal of heat addition from recirculation pump operation and reactor core decay heat is coarsely controlled by control rod drive hydraulic system flow and reactor water cleanup system non-regenerative heat exchanger operation. Test conditions are focused on maintaining a steady state pressure, and tightly limited temperature control poses an unnecessary burden on the operator and may not be achievable in certain instances.
The Inservice hydrostatic and RCS system leakage pressure tests require increasing pressure to greater than normal reactor operating pressure without exceeding the Safety Limit of 1375 psig approximately 1050 psig. Scram time testing required by SR 3.1.4.1 and SR 3.1.4.4 requires reactor pressures 800 psig.
Other testing may be performed in conjunction with the allowances for inservice leak or hydrostatic tests and control rod scram time tests.
APPLICABLE Allowing the reactor to be considered in MODE 4 during SAFETY ANALYSES hydrostatic or leak testing, when the reactor coolant temperature is > 200F, during, or as a consequence of, hydrostatic or leak testing, or as a consequence of control rod scram time testing initiated in conjunction with an inservice leak or hydrostatic test, effectively provides an exception to MODE 3 requirements, including exceptions to OPERABILITY of primary containment and the full complement of redundant Emergency Core Cooling Systems. Since the hydrostatic or leak tests are performed nearly water solid, at low decay heat values, and near MODE 4 conditions, the stored energy in the reactor core will be very low. Under these conditions, the potential for failed fuel and a subsequent increase in coolant activity above the LCO 3.4.7, "RCS Specific Activity," limits are minimized. In addition, the secondary containment will be OPERABLE, in accordance with this Special Operations LCO, and will be capable of handling any airborne radioactivity or steam leaks that could occur during the performance of hydrostatic or leak testing. The required pressure testing conditions provide adequate assurance that the consequences of a steam leak will be conservatively bounded by the consequences of the postulated main steam line break outside of primary containment described in Reference 2. Therefore, these requirements will conservatively limit radiation releases to the environment.
FERMI - UNIT 2 B 3.10.1-2 Revision 72
Inservice Leak and Hydrostatic Testing Operation B 3.10.1 BASES APPLICABLE SAFETY ANALYSES (continued)
In the event of a large primary system leak, the reactor vessel would rapidly depressurize, allowing the low pressure core cooling systems to operate. The capability of the low pressure coolant injection and core spray subsystems, as required in MODE 4 by LCO 3.5.2, "ECCS Shutdown," would be more than adequate to keep the core flooded under this low decay heat load condition. Small system leaks would be detected by leakage inspections before significant inventory loss occurred.
For the purposes of this test, the protection provided by normally required MODE 4 applicable LCOs, in addition to the secondary containment requirements required to be met by this Special Operations LCO, will ensure acceptable consequences during normal hydrostatic test conditions and during postulated accident conditions.
As described in LCO 3.0.7, compliance with Special Operations LCOs is optional, and therefore, no criteria of 10 CFR 50.36(c)(2)(ii) apply. Special Operations LCOs provide flexibility to perform certain operations by appropriately modifying requirements of other LCOs. A discussion of the criteria satisfied for the other LCOs is provided in their respective Bases.
LCO As described in LCO 3.0.7, compliance with this Special Operations LCO is optional. Operation at reactor coolant temperatures > 200F can be in accordance with Table 1.1-1 for MODE 3 operation without meeting this Special Operations LCO or its ACTIONS. This option may be required due to P/T limits, however, which require testing at temperatures
> 200F, while the ASME inservice test itself requires the safety/relief valves to be gagged, preventing their OPERABILITY. Additionally, even with required minimum reactor coolant temperatures 200°F, RCS temperatures may drift above 200°F during the performance of inservice leak and hydrostatic testing or during subsequent control rod scram time testing, which is typically performed in conjunction with inservice leak or hydrostatic testing.
While this Special Operations LCO is provided for inservice leak and hydrostatic testing, and for scram time testing initiated in conjunction with an inservice leak or hydrostatic test, parallel performance of other tests and inspections is not precluded.
FERMI - UNIT 2 B 3.10.1-3 Revision 26
Inservice Leak and Hydrostatic Testing Operation B 3.10.1 BASES LCO (continued)
If it is desired to perform these tests while complying with this Special Operations LCO, then the MODE 4 applicable LCOs and specified MODE 3 LCOs must be met. Additionally, all control rods will remain fully inserted when >200F, while using this Special Operations LCO. This Special Operations LCO allows changing Table 1.1-1 temperature limits for MODE 4 to "NA" and suspending the requirements of LCO 3.4.9, "Residual Heat Removal (RHR) Shutdown Cooling System Cold Shutdown." The additional requirements for secondary containment LCOs to be met will provide sufficient protection for operations at reactor coolant temperatures
> 200F for the purpose of performing either an inservice leak or hydrostatic test, and for control rod scram time testing initiated in conjunction with an inservice leak or hydrostatic test.
This LCO allows primary containment to be open for frequent unobstructed access to perform inspections, and for outage activities on various systems to continue consistent with the MODE 4 applicable requirements that are in effect immediately prior to and immediately after this operation.
APPLICABILITY The MODE 4 requirements may only be modified for the performance of, or as a consequence of, inservice leak or hydrostatic tests, or as a consequence of control rod scram time testing initiated in conjunction with an inservice leak or hydrostatic test, so that these operations can be considered as in MODE 4, even though the reactor coolant temperature is > 200F. The additional requirement for secondary containment OPERABILITY according to the imposed MODE 3 requirements provides conservatism in the response of the unit to any event that may occur. Operations in all other MODES are unaffected by this LCO.
ACTIONS A Note has been provided to modify the ACTIONS related to inservice leak and hydrostatic testing operation.
Section 1.3, Completion Times, specifies that once a Condition has been entered, subsequent divisions, subsystems, components, or variables expressed in the Condition discovered to be inoperable or not within limits, will not result in separate entry into the Condition.
Section 1.3 also specifies that Required Actions of the Condition continue to apply for each additional failure, with Completion Times based on initial entry into the Condition. However, the Required Actions for each requirement of the LCO not met provide appropriate FERMI - UNIT 2 B 3.10.1-4 Revision 0
Inservice Leak and Hydrostatic Testing Operation B 3.10.1 BASES ACTIONS (continued) compensatory measures for separate requirements that are not met. As such, a Note has been provided that allows separate Condition entry for each requirement of the LCO.
A.1 If an LCO specified in LCO 3.10.1 is not met, the ACTIONS applicable to the stated requirements are entered immediately and complied with. Required Action A.1 has been modified by a Note that clarifies the intent of another LCO's Required Action to be in MODE 4 includes reducing the average reactor coolant temperature to 200F.
A.2.1 and A.2.2 Required Action A.2.1 and Required Action A.2.2 are alternate Required Actions that can be taken instead of Required Action A.1 to restore compliance with the normal MODE 4 requirements, and thereby exit this Special Operation LCO's Applicability. Activities that could further increase reactor coolant temperature or pressure are suspended immediately, in accordance with Required Action A.2.1, and the reactor coolant temperature is reduced to establish normal MODE 4 requirements. The allowed Completion Time of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> for Required Action A.2.2 is based on engineering judgment and provides sufficient time to reduce the average reactor coolant temperature from the highest expected value to 200F with normal cooldown procedures. The Completion Time is also consistent with the time provided in LCO 3.0.3 to reach MODE 4 from MODE 3.
SURVEILLANCE SR 3.10.1.1 REQUIREMENTS The LCOs made applicable are required to have their Surveillances met to establish that this LCO is being met.
A discussion of the applicable SRs is provided in their respective Bases.
REFERENCES 1. American Society of Mechanical Engineers, Boiler and Pressure Vessel Code,Section XI.
- 2. UFSAR, Section 15.6.4.
- 3. BWRVIP-86-A, October 2002 FERMI - UNIT 2 B 3.10.1-5 Revision 17