Letter Sequence Meeting |
|---|
|
Results
Other: GO2-86-104, Forwards Addl Info Re Fire Protection Program,Per 861020 Request,Including Rev 2 to Emergency Procedure 5.3.6, Reactor Pressure Vessel Flooding (Contingency), GO2-86-310, Forwards Advance Copy of Update of App F Re Fire Protection Evaluation for Facility Fsar.Update Will Be Formally Submitted as Amend 37,currently Scheduled for Issue in June 1986, GO2-86-656, Responds to 860314 SER Implying That App R Analysis Requirements Performed for high-pressure-to-low-pressure Sys Interfaces Must Assume That Two Spurious Actuations Occur Simultaneously.Position Contrary to Generic Ltrs, GO2-87-019, Forwards Info Re Mods Proposed to Ensure Isolation of RHR-V-8 or RHR-V-9 Valve & Schedule for Completion of Mods, Per 870513 Request Re Generic Ltr 86-10 Interpretation of High/Low Pressure Interface Concerns, GO2-87-034, Forwards Fire Protection Program Description in Response to 870113-15 Fire Protection Insp to Facilitate Implementation of License Condition 2.C(14), GO2-87-179, Forwards Response to Unresolved Items Noted in Insp Rept 50-397/87-02.Corrective Actions:Independent Insp by Consultants Confirmed That Detection Sys Meets Requirements for safety-related Areas, GO2-87-232, Responds to Generic Ltr 86-10.Util Determined That Providing Transfer Switch on Remote Shutdown Panel for RHR-V-8 Valve Preferred Method for Ensuring Isolation of Either RHR-V-8 or V-9 in Event of Control Room Fire, GO2-88-008, Responds to Inconsistencies Noted in Introduction to SER Forwarded by Gw Knighton .Ser Addressed Fire Protection & Safe Shutdown Capability Per Amend 37 to FSAR, GO2-88-111, Informs That Rev to Plant Procedure 1.3.10, Fire Protection Program, Committed to in 870128 Response to Insp Rept 50-397/86-25,currently in Process to Incorporate Listed Addl Changes.Procedure Will Be Revised by 880513, GO2-88-136, Informs That Calculation Analyzing Structural Integrity of Specific Support Steel Configurations for Instrument Sensing Lines Rescheduled for Completion from 880515 to 880715 Due to Unavailability of Supporting Resources, GO2-88-155, Forwards Calculation Analyzing Structural Integrity of Specific Support Steel Configurations for Instrument Sensing Lines Re Fire Protection & Safe Shutdown Capability Response to SER, GO2-88-156, Provides Schedule for Completion of Fire Protection Issues from Insp Rept 50-397/88-16.Installation of Scuppers on South Doors Leading Outside Diesel Generator Bldg Will Be Completed by 880801, GO2-88-157, Forwards Completed Executive Summary of App R High Impedance Fault Analysis,Per NRC 880606 Request, GO2-88-168, Responds to NRC Re Violations Noted in Insp Rept 50-397/88-19.Corrective Actions:Instrument Rack Termination Procedure PPM 10.25.19 Will Be Revised by 890315 to Include Examples of Acceptable Crimp Configuration, GO2-88-209, Submits Revised Response to SER Question 25 Re Fire Protection & Safe Shutdown Capability.Analysis Performed to Identify high-to-low Pressure Interface Valve Motor Power Feeder Requiring Protection Against Fire Related Reconnects, GO2-88-214, Forwards Updated Schedule of Commitments for Completion of Fire Protection Issues,Per Concerns Noted in Insp Rept 50-397/88-16 & Open Items Noted During Fire Protection Audit on 880606-10, GO2-88-222, Submits Revised Response to Insp Rept 50-397/88-16 Re Fire Protection & Safe Shutdown Capability.Fire in Drywell Expansion Gap Has Very Low Probability of Starting, GO2-89-035, Provides Revised Schedule Dates for Commitments Made in Response to Violations Noted in Insp Repts 50-397/87-19 & 50-397/88-41.Plant Procedures 10.25.19 & 11.2.1.2 Will Be Issued by 890417, ML17278B122, ML17278B182, ML17279A257, ML17279A778
|
MONTHYEARGO2-86-310, Forwards Advance Copy of Update of App F Re Fire Protection Evaluation for Facility Fsar.Update Will Be Formally Submitted as Amend 37,currently Scheduled for Issue in June 19861986-04-0404 April 1986 Forwards Advance Copy of Update of App F Re Fire Protection Evaluation for Facility Fsar.Update Will Be Formally Submitted as Amend 37,currently Scheduled for Issue in June 1986 Project stage: Other GO2-86-656, Responds to 860314 SER Implying That App R Analysis Requirements Performed for high-pressure-to-low-pressure Sys Interfaces Must Assume That Two Spurious Actuations Occur Simultaneously.Position Contrary to Generic Ltrs1986-07-16016 July 1986 Responds to 860314 SER Implying That App R Analysis Requirements Performed for high-pressure-to-low-pressure Sys Interfaces Must Assume That Two Spurious Actuations Occur Simultaneously.Position Contrary to Generic Ltrs Project stage: Other ML17278B0471986-10-20020 October 1986 Forwards Request for Addl Info Re Current Condition of Unit 2 Compared to Regulations,License & Commitments to Fire Protection Program.Requests Response within 30 Days of Ltr Receipt Project stage: RAI ML17278B0461986-10-21021 October 1986 Discusses 861002 Meeting W/Ofc of General Counsel & Plant Sys Branch Re Plant Approved Fire Protection Program.Meeting Concluded That Program Includes Written Communications Docketed Prior to Issuing OL Project stage: Meeting ML17278B1221986-11-17017 November 1986 Rev 2 to Emergency Procedure 5.3.6, Reactor Pressure Vessel Flooding (Contingency) Project stage: Other GO2-86-104, Forwards Addl Info Re Fire Protection Program,Per 861020 Request,Including Rev 2 to Emergency Procedure 5.3.6, Reactor Pressure Vessel Flooding (Contingency)1986-12-0101 December 1986 Forwards Addl Info Re Fire Protection Program,Per 861020 Request,Including Rev 2 to Emergency Procedure 5.3.6, Reactor Pressure Vessel Flooding (Contingency) Project stage: Other GO2-87-034, Forwards Fire Protection Program Description in Response to 870113-15 Fire Protection Insp to Facilitate Implementation of License Condition 2.C(14)1987-01-29029 January 1987 Forwards Fire Protection Program Description in Response to 870113-15 Fire Protection Insp to Facilitate Implementation of License Condition 2.C(14) Project stage: Other ML17278B1821987-02-0505 February 1987 Informs That Attachment to Will Be Considered Approved Fire Protection Program.Approval of Program Contingent on Timely Submittal of License Amend Request Per Generic Ltr 86-10 Project stage: Other ML17279A2571987-05-13013 May 1987 Advises That Util Required to Implement Appropriate Mods to Isolation Valves RHR-V-8 & RHR-V-9 to Meet Objectives of App R to 10CFR50 Re Prevention of LOCAs at High/Low Pressure Interfaces.Submittal of Schedule Requested Project stage: Other GO2-87-179, Forwards Response to Unresolved Items Noted in Insp Rept 50-397/87-02.Corrective Actions:Independent Insp by Consultants Confirmed That Detection Sys Meets Requirements for safety-related Areas1987-05-27027 May 1987 Forwards Response to Unresolved Items Noted in Insp Rept 50-397/87-02.Corrective Actions:Independent Insp by Consultants Confirmed That Detection Sys Meets Requirements for safety-related Areas Project stage: Other GO2-87-019, Forwards Info Re Mods Proposed to Ensure Isolation of RHR-V-8 or RHR-V-9 Valve & Schedule for Completion of Mods, Per 870513 Request Re Generic Ltr 86-10 Interpretation of High/Low Pressure Interface Concerns1987-06-0303 June 1987 Forwards Info Re Mods Proposed to Ensure Isolation of RHR-V-8 or RHR-V-9 Valve & Schedule for Completion of Mods, Per 870513 Request Re Generic Ltr 86-10 Interpretation of High/Low Pressure Interface Concerns Project stage: Other GO2-87-232, Responds to Generic Ltr 86-10.Util Determined That Providing Transfer Switch on Remote Shutdown Panel for RHR-V-8 Valve Preferred Method for Ensuring Isolation of Either RHR-V-8 or V-9 in Event of Control Room Fire1987-08-20020 August 1987 Responds to Generic Ltr 86-10.Util Determined That Providing Transfer Switch on Remote Shutdown Panel for RHR-V-8 Valve Preferred Method for Ensuring Isolation of Either RHR-V-8 or V-9 in Event of Control Room Fire Project stage: Other ML17279A5771987-10-0202 October 1987 Recommends That Meeting Be Held to Ensure Completion of Mods to Preclude Spurious Opening of High Low Interface Valves in Event of Control Room Fire,Per NRC 870513 Request & Util 870820 Response Project stage: Meeting ML20236N1261987-11-11011 November 1987 Safety Evaluation Supporting Amend 37 to FSAR Re Fire Protection Program Project stage: Approval ML17279A7781987-12-23023 December 1987 Discusses 871002 Response to Re Util Preferred Course of Action for Precluding Spurious Opening of high-low Interface Valves RHR-V 8 & RHR-V-9 in Event of Control Room Fire.No Submittal on Subj Received to Date Project stage: Other GO2-88-008, Responds to Inconsistencies Noted in Introduction to SER Forwarded by Gw Knighton .Ser Addressed Fire Protection & Safe Shutdown Capability Per Amend 37 to FSAR1988-01-11011 January 1988 Responds to Inconsistencies Noted in Introduction to SER Forwarded by Gw Knighton .Ser Addressed Fire Protection & Safe Shutdown Capability Per Amend 37 to FSAR Project stage: Other ML17279A7751988-01-13013 January 1988 Notification of 880119 Meeting W/Util in Bethesda,Md to Discuss Fire Protection Plan & Util Responses to NRC Comments on Plan Project stage: Meeting ML17279A8881988-03-0909 March 1988 Summary of 880119 Meeting W/Util in Bethesda,Md Re Util Responses to 28 Fire Protection Questions Raised in NRC .Attendee List Encl Project stage: Meeting GO2-88-111, Informs That Rev to Plant Procedure 1.3.10, Fire Protection Program, Committed to in 870128 Response to Insp Rept 50-397/86-25,currently in Process to Incorporate Listed Addl Changes.Procedure Will Be Revised by 8805131988-05-0606 May 1988 Informs That Rev to Plant Procedure 1.3.10, Fire Protection Program, Committed to in 870128 Response to Insp Rept 50-397/86-25,currently in Process to Incorporate Listed Addl Changes.Procedure Will Be Revised by 880513 Project stage: Other GO2-88-136, Informs That Calculation Analyzing Structural Integrity of Specific Support Steel Configurations for Instrument Sensing Lines Rescheduled for Completion from 880515 to 880715 Due to Unavailability of Supporting Resources1988-06-0303 June 1988 Informs That Calculation Analyzing Structural Integrity of Specific Support Steel Configurations for Instrument Sensing Lines Rescheduled for Completion from 880515 to 880715 Due to Unavailability of Supporting Resources Project stage: Other GO2-88-155, Forwards Calculation Analyzing Structural Integrity of Specific Support Steel Configurations for Instrument Sensing Lines Re Fire Protection & Safe Shutdown Capability Response to SER1988-07-15015 July 1988 Forwards Calculation Analyzing Structural Integrity of Specific Support Steel Configurations for Instrument Sensing Lines Re Fire Protection & Safe Shutdown Capability Response to SER Project stage: Other GO2-88-157, Forwards Completed Executive Summary of App R High Impedance Fault Analysis,Per NRC 880606 Request1988-07-15015 July 1988 Forwards Completed Executive Summary of App R High Impedance Fault Analysis,Per NRC 880606 Request Project stage: Other GO2-88-156, Provides Schedule for Completion of Fire Protection Issues from Insp Rept 50-397/88-16.Installation of Scuppers on South Doors Leading Outside Diesel Generator Bldg Will Be Completed by 8808011988-07-15015 July 1988 Provides Schedule for Completion of Fire Protection Issues from Insp Rept 50-397/88-16.Installation of Scuppers on South Doors Leading Outside Diesel Generator Bldg Will Be Completed by 880801 Project stage: Other GO2-88-163, Submits Clarification of Approved Fire Protection Program Per 880610 Exit Meeting,Covering Plant Design,Door Openings, Fire Barriers,Fire Dampers & Doors & Safe Shutdown Capability1988-07-26026 July 1988 Submits Clarification of Approved Fire Protection Program Per 880610 Exit Meeting,Covering Plant Design,Door Openings, Fire Barriers,Fire Dampers & Doors & Safe Shutdown Capability Project stage: Meeting GO2-88-168, Responds to NRC Re Violations Noted in Insp Rept 50-397/88-19.Corrective Actions:Instrument Rack Termination Procedure PPM 10.25.19 Will Be Revised by 890315 to Include Examples of Acceptable Crimp Configuration1988-07-29029 July 1988 Responds to NRC Re Violations Noted in Insp Rept 50-397/88-19.Corrective Actions:Instrument Rack Termination Procedure PPM 10.25.19 Will Be Revised by 890315 to Include Examples of Acceptable Crimp Configuration Project stage: Other GO2-88-209, Submits Revised Response to SER Question 25 Re Fire Protection & Safe Shutdown Capability.Analysis Performed to Identify high-to-low Pressure Interface Valve Motor Power Feeder Requiring Protection Against Fire Related Reconnects1988-09-30030 September 1988 Submits Revised Response to SER Question 25 Re Fire Protection & Safe Shutdown Capability.Analysis Performed to Identify high-to-low Pressure Interface Valve Motor Power Feeder Requiring Protection Against Fire Related Reconnects Project stage: Other GO2-88-214, Forwards Updated Schedule of Commitments for Completion of Fire Protection Issues,Per Concerns Noted in Insp Rept 50-397/88-16 & Open Items Noted During Fire Protection Audit on 880606-101988-10-0707 October 1988 Forwards Updated Schedule of Commitments for Completion of Fire Protection Issues,Per Concerns Noted in Insp Rept 50-397/88-16 & Open Items Noted During Fire Protection Audit on 880606-10 Project stage: Other GO2-88-222, Submits Revised Response to Insp Rept 50-397/88-16 Re Fire Protection & Safe Shutdown Capability.Fire in Drywell Expansion Gap Has Very Low Probability of Starting1988-10-28028 October 1988 Submits Revised Response to Insp Rept 50-397/88-16 Re Fire Protection & Safe Shutdown Capability.Fire in Drywell Expansion Gap Has Very Low Probability of Starting Project stage: Other GO2-88-250, Clarifies Min Staffing Needed for Safe Shutdown Re Insp Rept 50-397/88-16 Dtd 880725.Util Understands That Any Combination of Personnel Meeting 10CFR50,App R Requirements Acceptable1988-11-28028 November 1988 Clarifies Min Staffing Needed for Safe Shutdown Re Insp Rept 50-397/88-16 Dtd 880725.Util Understands That Any Combination of Personnel Meeting 10CFR50,App R Requirements Acceptable Project stage: Meeting GO2-89-035, Provides Revised Schedule Dates for Commitments Made in Response to Violations Noted in Insp Repts 50-397/87-19 & 50-397/88-41.Plant Procedures 10.25.19 & 11.2.1.2 Will Be Issued by 8904171989-03-0606 March 1989 Provides Revised Schedule Dates for Commitments Made in Response to Violations Noted in Insp Repts 50-397/87-19 & 50-397/88-41.Plant Procedures 10.25.19 & 11.2.1.2 Will Be Issued by 890417 Project stage: Other 1987-06-03
[Table View] |
Text
8710080456 87i002 PDR ADQCH, 0500035'7 F
+DR Docket No.:
50-397 GOT p ~gy Mr. G. C. Sorensen, Manager Regulatory Programs Washington Public Power Supply System P.O.
Box 968 3000 George Washington Way Richland, Washington 99352
Dear Mr. Sorensen:
DISTRIBUTION NRC 8
L PDRs PD85 Plant File GHolahan JLee RSamworth OGC-Bethesda EJordan JPartlow ACRS (10)
JCraig JRidgely
/Docket Fi'le"
SUBJECT:
WNP-2 PROPOSED RESOLUTION OF SPURIOUS OPENING OF RHR-V-8 AND RHR-V-9 IN THE EVENT OF A CONTROL ROOM FIRE On May 13, 1987 I wrote to you asking that you advise NRC of modifications which WPPSS will make to preclude spurious opening of high low interface valves RHR-V-8 and RHR-V-9 in the event of a control room fire.
Your response of August 20, 1987 (G02-87-232) declared that your preferred action is to provide a transfer switch on the remote shutdown panel and to have control of RHR-V-8 transferred to the remote panel during normal operation.
Your response identified several items which WPPSS must resolve before your preferred action can be implemented.
Since your letter reflects some uncertainty as to licensing procedures and NRC staff positions pertainent to your preferred action I believe that a meeting with your engineering staff may serve to ensure completion of your modifications in accordance with the schedule which you proposed.
We are open to discussing the points which you raised in your August 20th letter and thus are not taking a position on your preferred action at this time.
However, I am making some preliminary comments, again in the spirit of expediting the completion of this very important matter.
You stated that as you are proposing the action, with control of RHR-V-8 transfer red to the remote shutdown panel, the RHR permissive interlock (reactor pressure high) would be bypassed.
You are correct that this would constitute an unreviewed safety question requiring prior NRC approval.
Our initial reaction is that modifications should not be made which would permit operation of the valves with the interlocks bypassed.
)
1
't
,(
V.~
J
oe Your letter also inquired about technical specification changes needed to reflect the modifications to the controls.
You asked us to identify other licensed facilities which have amended their technical specifications because of similar design or operating changes.
We are not aware of any facility which has taken the type of corrective action for which you have indicated a
preference.
Shoreham has a pressure interlock outside of the control room for
'ach of its RHR suction lines.
Thus a control room fire could not result in spurious opening of the high/low pressure interface.
Nine Nile Point Unit Two elected to lock power out to one of the Rl{R suction line valves during power operation.
I Because of these site specific differ'ences in achieving isolability, we can not provide a directly applicable example technical.specification.
However the changes do not appear to be particularly complicated.
Technical Specification 3.6.3 (Page 3/4 3-10), has the objective of ensuring isolability of the containment.
Valves RHR'-V-'
and RHR-V-9, however, are normally in the containment isolation position.
What you are trying to achieve with the proposed transfer switch is to avoid'spurious opening.
Thus there is no real conflict between the proposed action and the containment isolation objective.
When control of'RHR-V-8 is transferred back to the control room so that the Residual Heat Removal System can be placed into service, spurious opening will no longer be'f concern and the valve will be operable in the event that an isolation signal occurs.
Therefore, it would appear that the objective of Technical Specification 3.6.3 will be 'met.
A footnote might be added to Table 3.6.3-1 to document the normal situation regarding RHR suction line isolation control.
It appears that your concern over Table 3.3.'2-1 is tied to your proposal that the interlocks might be bypassed.
Otherwise, the clarification to Table 3.6.3-1 would appear to suffice.
We expect that you will submit FSAR and Technical Specification amendments in a timely manner to permit our review 'and then your implementation of the action before the end of the next refueling outage.
We would recommend an
'early meeting to discuss these matters if necessary to ensure that objective is met.
Sincerely, Original sfgn<3 by:
George K Koighton George W. Knighton, Director Project Directorate No.
V Division of Reactor Projects - III, IV, V and Special Projects Office of Nuclear Reactor Regulation c :~
e next page DRSP/PDV DR RSamworth:rs G
i 10/~87 10/&/87
~ ~
~ ~
l i
t f
d in gi tj I
Mr. G. C. Sorensen, Hanager Washington Public Power Supply System WPPSS Nuclear Project No.
2 (WNP-2)
CC Nicholas S. Reynolds, Esq.
Bishop, Cook, Purcell 5 Reynolds 1200 Seventeenth
- Street, N.W.
Washington, D.C.
20036 Mr. G. E. Doupe, Esquire Washington Public Power Supply System P. 0.
Box 968 3000 George Washington Way Richland, Washington 99532 Mr. Curtis Eschels, Chairman Energy Facility Site Evaluation Council Mail Stop PY-ll Olympia, Washington 98504 P. L. Powell, Licensing Manager
~
Washington Public Pow'er Supply System P. 0.
Box 968, MD 956B
- Richland, Washington 99352 Mr. A. Lee Oxsen Assistant Managing Director for Operations Washington Public Power Supply System P. 0.
Box 968, MD 1023
- Richland, WA 99352 R.
B. Glasscock, Director Licensing and Assurance Washington Public Power Supply System P. 0.
Box 968, MD 280 Richland, Washington 99352 Mr. C.
M. Powers WNP-2 Plant Manager Washington Public Power Supply System P. 0.
Bok MD 927M Richland, Washington 99352 Regional Administrator, Region V
U.S. Nuclear Regulatory Commission 1450 Maria Lane, Suite 210 Walnut Creek, California 94596 Chairman Benton County Board of Comnissioners
- Prosser, Washington 99350