Letter Sequence Other |
|---|
|
Results
Other: GO2-86-104, Forwards Addl Info Re Fire Protection Program,Per 861020 Request,Including Rev 2 to Emergency Procedure 5.3.6, Reactor Pressure Vessel Flooding (Contingency), GO2-86-310, Forwards Advance Copy of Update of App F Re Fire Protection Evaluation for Facility Fsar.Update Will Be Formally Submitted as Amend 37,currently Scheduled for Issue in June 1986, GO2-86-656, Responds to 860314 SER Implying That App R Analysis Requirements Performed for high-pressure-to-low-pressure Sys Interfaces Must Assume That Two Spurious Actuations Occur Simultaneously.Position Contrary to Generic Ltrs, GO2-87-019, Forwards Info Re Mods Proposed to Ensure Isolation of RHR-V-8 or RHR-V-9 Valve & Schedule for Completion of Mods, Per 870513 Request Re Generic Ltr 86-10 Interpretation of High/Low Pressure Interface Concerns, GO2-87-034, Forwards Fire Protection Program Description in Response to 870113-15 Fire Protection Insp to Facilitate Implementation of License Condition 2.C(14), GO2-87-179, Forwards Response to Unresolved Items Noted in Insp Rept 50-397/87-02.Corrective Actions:Independent Insp by Consultants Confirmed That Detection Sys Meets Requirements for safety-related Areas, GO2-87-232, Responds to Generic Ltr 86-10.Util Determined That Providing Transfer Switch on Remote Shutdown Panel for RHR-V-8 Valve Preferred Method for Ensuring Isolation of Either RHR-V-8 or V-9 in Event of Control Room Fire, GO2-88-008, Responds to Inconsistencies Noted in Introduction to SER Forwarded by Gw Knighton .Ser Addressed Fire Protection & Safe Shutdown Capability Per Amend 37 to FSAR, GO2-88-111, Informs That Rev to Plant Procedure 1.3.10, Fire Protection Program, Committed to in 870128 Response to Insp Rept 50-397/86-25,currently in Process to Incorporate Listed Addl Changes.Procedure Will Be Revised by 880513, GO2-88-136, Informs That Calculation Analyzing Structural Integrity of Specific Support Steel Configurations for Instrument Sensing Lines Rescheduled for Completion from 880515 to 880715 Due to Unavailability of Supporting Resources, GO2-88-155, Forwards Calculation Analyzing Structural Integrity of Specific Support Steel Configurations for Instrument Sensing Lines Re Fire Protection & Safe Shutdown Capability Response to SER, GO2-88-156, Provides Schedule for Completion of Fire Protection Issues from Insp Rept 50-397/88-16.Installation of Scuppers on South Doors Leading Outside Diesel Generator Bldg Will Be Completed by 880801, GO2-88-157, Forwards Completed Executive Summary of App R High Impedance Fault Analysis,Per NRC 880606 Request, GO2-88-168, Responds to NRC Re Violations Noted in Insp Rept 50-397/88-19.Corrective Actions:Instrument Rack Termination Procedure PPM 10.25.19 Will Be Revised by 890315 to Include Examples of Acceptable Crimp Configuration, GO2-88-209, Submits Revised Response to SER Question 25 Re Fire Protection & Safe Shutdown Capability.Analysis Performed to Identify high-to-low Pressure Interface Valve Motor Power Feeder Requiring Protection Against Fire Related Reconnects, GO2-88-214, Forwards Updated Schedule of Commitments for Completion of Fire Protection Issues,Per Concerns Noted in Insp Rept 50-397/88-16 & Open Items Noted During Fire Protection Audit on 880606-10, GO2-88-222, Submits Revised Response to Insp Rept 50-397/88-16 Re Fire Protection & Safe Shutdown Capability.Fire in Drywell Expansion Gap Has Very Low Probability of Starting, GO2-89-035, Provides Revised Schedule Dates for Commitments Made in Response to Violations Noted in Insp Repts 50-397/87-19 & 50-397/88-41.Plant Procedures 10.25.19 & 11.2.1.2 Will Be Issued by 890417, ML17278B122, ML17278B182, ML17279A257, ML17279A778
|
MONTHYEARGO2-86-310, Forwards Advance Copy of Update of App F Re Fire Protection Evaluation for Facility Fsar.Update Will Be Formally Submitted as Amend 37,currently Scheduled for Issue in June 19861986-04-0404 April 1986 Forwards Advance Copy of Update of App F Re Fire Protection Evaluation for Facility Fsar.Update Will Be Formally Submitted as Amend 37,currently Scheduled for Issue in June 1986 Project stage: Other GO2-86-656, Responds to 860314 SER Implying That App R Analysis Requirements Performed for high-pressure-to-low-pressure Sys Interfaces Must Assume That Two Spurious Actuations Occur Simultaneously.Position Contrary to Generic Ltrs1986-07-16016 July 1986 Responds to 860314 SER Implying That App R Analysis Requirements Performed for high-pressure-to-low-pressure Sys Interfaces Must Assume That Two Spurious Actuations Occur Simultaneously.Position Contrary to Generic Ltrs Project stage: Other ML17278B0471986-10-20020 October 1986 Forwards Request for Addl Info Re Current Condition of Unit 2 Compared to Regulations,License & Commitments to Fire Protection Program.Requests Response within 30 Days of Ltr Receipt Project stage: RAI ML17278B0461986-10-21021 October 1986 Discusses 861002 Meeting W/Ofc of General Counsel & Plant Sys Branch Re Plant Approved Fire Protection Program.Meeting Concluded That Program Includes Written Communications Docketed Prior to Issuing OL Project stage: Meeting ML17278B1221986-11-17017 November 1986 Rev 2 to Emergency Procedure 5.3.6, Reactor Pressure Vessel Flooding (Contingency) Project stage: Other GO2-86-104, Forwards Addl Info Re Fire Protection Program,Per 861020 Request,Including Rev 2 to Emergency Procedure 5.3.6, Reactor Pressure Vessel Flooding (Contingency)1986-12-0101 December 1986 Forwards Addl Info Re Fire Protection Program,Per 861020 Request,Including Rev 2 to Emergency Procedure 5.3.6, Reactor Pressure Vessel Flooding (Contingency) Project stage: Other GO2-87-034, Forwards Fire Protection Program Description in Response to 870113-15 Fire Protection Insp to Facilitate Implementation of License Condition 2.C(14)1987-01-29029 January 1987 Forwards Fire Protection Program Description in Response to 870113-15 Fire Protection Insp to Facilitate Implementation of License Condition 2.C(14) Project stage: Other ML17278B1821987-02-0505 February 1987 Informs That Attachment to Will Be Considered Approved Fire Protection Program.Approval of Program Contingent on Timely Submittal of License Amend Request Per Generic Ltr 86-10 Project stage: Other ML17279A2571987-05-13013 May 1987 Advises That Util Required to Implement Appropriate Mods to Isolation Valves RHR-V-8 & RHR-V-9 to Meet Objectives of App R to 10CFR50 Re Prevention of LOCAs at High/Low Pressure Interfaces.Submittal of Schedule Requested Project stage: Other GO2-87-179, Forwards Response to Unresolved Items Noted in Insp Rept 50-397/87-02.Corrective Actions:Independent Insp by Consultants Confirmed That Detection Sys Meets Requirements for safety-related Areas1987-05-27027 May 1987 Forwards Response to Unresolved Items Noted in Insp Rept 50-397/87-02.Corrective Actions:Independent Insp by Consultants Confirmed That Detection Sys Meets Requirements for safety-related Areas Project stage: Other GO2-87-019, Forwards Info Re Mods Proposed to Ensure Isolation of RHR-V-8 or RHR-V-9 Valve & Schedule for Completion of Mods, Per 870513 Request Re Generic Ltr 86-10 Interpretation of High/Low Pressure Interface Concerns1987-06-0303 June 1987 Forwards Info Re Mods Proposed to Ensure Isolation of RHR-V-8 or RHR-V-9 Valve & Schedule for Completion of Mods, Per 870513 Request Re Generic Ltr 86-10 Interpretation of High/Low Pressure Interface Concerns Project stage: Other GO2-87-232, Responds to Generic Ltr 86-10.Util Determined That Providing Transfer Switch on Remote Shutdown Panel for RHR-V-8 Valve Preferred Method for Ensuring Isolation of Either RHR-V-8 or V-9 in Event of Control Room Fire1987-08-20020 August 1987 Responds to Generic Ltr 86-10.Util Determined That Providing Transfer Switch on Remote Shutdown Panel for RHR-V-8 Valve Preferred Method for Ensuring Isolation of Either RHR-V-8 or V-9 in Event of Control Room Fire Project stage: Other ML17279A5771987-10-0202 October 1987 Recommends That Meeting Be Held to Ensure Completion of Mods to Preclude Spurious Opening of High Low Interface Valves in Event of Control Room Fire,Per NRC 870513 Request & Util 870820 Response Project stage: Meeting ML20236N1261987-11-11011 November 1987 Safety Evaluation Supporting Amend 37 to FSAR Re Fire Protection Program Project stage: Approval ML17279A7781987-12-23023 December 1987 Discusses 871002 Response to Re Util Preferred Course of Action for Precluding Spurious Opening of high-low Interface Valves RHR-V 8 & RHR-V-9 in Event of Control Room Fire.No Submittal on Subj Received to Date Project stage: Other GO2-88-008, Responds to Inconsistencies Noted in Introduction to SER Forwarded by Gw Knighton .Ser Addressed Fire Protection & Safe Shutdown Capability Per Amend 37 to FSAR1988-01-11011 January 1988 Responds to Inconsistencies Noted in Introduction to SER Forwarded by Gw Knighton .Ser Addressed Fire Protection & Safe Shutdown Capability Per Amend 37 to FSAR Project stage: Other ML17279A7751988-01-13013 January 1988 Notification of 880119 Meeting W/Util in Bethesda,Md to Discuss Fire Protection Plan & Util Responses to NRC Comments on Plan Project stage: Meeting ML17279A8881988-03-0909 March 1988 Summary of 880119 Meeting W/Util in Bethesda,Md Re Util Responses to 28 Fire Protection Questions Raised in NRC .Attendee List Encl Project stage: Meeting GO2-88-111, Informs That Rev to Plant Procedure 1.3.10, Fire Protection Program, Committed to in 870128 Response to Insp Rept 50-397/86-25,currently in Process to Incorporate Listed Addl Changes.Procedure Will Be Revised by 8805131988-05-0606 May 1988 Informs That Rev to Plant Procedure 1.3.10, Fire Protection Program, Committed to in 870128 Response to Insp Rept 50-397/86-25,currently in Process to Incorporate Listed Addl Changes.Procedure Will Be Revised by 880513 Project stage: Other GO2-88-136, Informs That Calculation Analyzing Structural Integrity of Specific Support Steel Configurations for Instrument Sensing Lines Rescheduled for Completion from 880515 to 880715 Due to Unavailability of Supporting Resources1988-06-0303 June 1988 Informs That Calculation Analyzing Structural Integrity of Specific Support Steel Configurations for Instrument Sensing Lines Rescheduled for Completion from 880515 to 880715 Due to Unavailability of Supporting Resources Project stage: Other GO2-88-155, Forwards Calculation Analyzing Structural Integrity of Specific Support Steel Configurations for Instrument Sensing Lines Re Fire Protection & Safe Shutdown Capability Response to SER1988-07-15015 July 1988 Forwards Calculation Analyzing Structural Integrity of Specific Support Steel Configurations for Instrument Sensing Lines Re Fire Protection & Safe Shutdown Capability Response to SER Project stage: Other GO2-88-157, Forwards Completed Executive Summary of App R High Impedance Fault Analysis,Per NRC 880606 Request1988-07-15015 July 1988 Forwards Completed Executive Summary of App R High Impedance Fault Analysis,Per NRC 880606 Request Project stage: Other GO2-88-156, Provides Schedule for Completion of Fire Protection Issues from Insp Rept 50-397/88-16.Installation of Scuppers on South Doors Leading Outside Diesel Generator Bldg Will Be Completed by 8808011988-07-15015 July 1988 Provides Schedule for Completion of Fire Protection Issues from Insp Rept 50-397/88-16.Installation of Scuppers on South Doors Leading Outside Diesel Generator Bldg Will Be Completed by 880801 Project stage: Other GO2-88-163, Submits Clarification of Approved Fire Protection Program Per 880610 Exit Meeting,Covering Plant Design,Door Openings, Fire Barriers,Fire Dampers & Doors & Safe Shutdown Capability1988-07-26026 July 1988 Submits Clarification of Approved Fire Protection Program Per 880610 Exit Meeting,Covering Plant Design,Door Openings, Fire Barriers,Fire Dampers & Doors & Safe Shutdown Capability Project stage: Meeting GO2-88-168, Responds to NRC Re Violations Noted in Insp Rept 50-397/88-19.Corrective Actions:Instrument Rack Termination Procedure PPM 10.25.19 Will Be Revised by 890315 to Include Examples of Acceptable Crimp Configuration1988-07-29029 July 1988 Responds to NRC Re Violations Noted in Insp Rept 50-397/88-19.Corrective Actions:Instrument Rack Termination Procedure PPM 10.25.19 Will Be Revised by 890315 to Include Examples of Acceptable Crimp Configuration Project stage: Other GO2-88-209, Submits Revised Response to SER Question 25 Re Fire Protection & Safe Shutdown Capability.Analysis Performed to Identify high-to-low Pressure Interface Valve Motor Power Feeder Requiring Protection Against Fire Related Reconnects1988-09-30030 September 1988 Submits Revised Response to SER Question 25 Re Fire Protection & Safe Shutdown Capability.Analysis Performed to Identify high-to-low Pressure Interface Valve Motor Power Feeder Requiring Protection Against Fire Related Reconnects Project stage: Other GO2-88-214, Forwards Updated Schedule of Commitments for Completion of Fire Protection Issues,Per Concerns Noted in Insp Rept 50-397/88-16 & Open Items Noted During Fire Protection Audit on 880606-101988-10-0707 October 1988 Forwards Updated Schedule of Commitments for Completion of Fire Protection Issues,Per Concerns Noted in Insp Rept 50-397/88-16 & Open Items Noted During Fire Protection Audit on 880606-10 Project stage: Other GO2-88-222, Submits Revised Response to Insp Rept 50-397/88-16 Re Fire Protection & Safe Shutdown Capability.Fire in Drywell Expansion Gap Has Very Low Probability of Starting1988-10-28028 October 1988 Submits Revised Response to Insp Rept 50-397/88-16 Re Fire Protection & Safe Shutdown Capability.Fire in Drywell Expansion Gap Has Very Low Probability of Starting Project stage: Other GO2-88-250, Clarifies Min Staffing Needed for Safe Shutdown Re Insp Rept 50-397/88-16 Dtd 880725.Util Understands That Any Combination of Personnel Meeting 10CFR50,App R Requirements Acceptable1988-11-28028 November 1988 Clarifies Min Staffing Needed for Safe Shutdown Re Insp Rept 50-397/88-16 Dtd 880725.Util Understands That Any Combination of Personnel Meeting 10CFR50,App R Requirements Acceptable Project stage: Meeting GO2-89-035, Provides Revised Schedule Dates for Commitments Made in Response to Violations Noted in Insp Repts 50-397/87-19 & 50-397/88-41.Plant Procedures 10.25.19 & 11.2.1.2 Will Be Issued by 8904171989-03-0606 March 1989 Provides Revised Schedule Dates for Commitments Made in Response to Violations Noted in Insp Repts 50-397/87-19 & 50-397/88-41.Plant Procedures 10.25.19 & 11.2.1.2 Will Be Issued by 890417 Project stage: Other 1987-06-03
[Table View] |
Text
Docket No. 50-397 G.
C. Sorensen, Manager Regulatory Programs Washington Public Power Supply System P.O.
Box 968 3000 George Washington Way Richland, Washington 99352
Dear Mr. Sorensen:
DISTRIBUTION NRC/L PDR DMCrutchfield GMHolahan RSamworth/JLee OCG-Bethesda EJordan/JPartlow ACRS (10)
JRidgely Thadani Wermiel Craig
Subject:
COMPLIANCE WITH RE(UIREMENTS OF APPENDIX R TO 10 CFR PART 50 RELATING TO PREVENTION OF LOCAS AT HIGH/LOW PRESSURE INTERFACES.
(TAC 863528)
We are writing to reinform you of the NRC staff position and required action on the issue of spurious opening of high/low pressure interface valves during fires to meet the objective of Appendix R.
Your attention is directed specifically to the valves identified as RHR-V-8 and RHR-V-9 on the RHR suction line.
We are advising you that we require WPPSS to implement appropriate modifications to these isolation valves aC soon as practical to meet the objectives of Appendix R to 10 CFR Part 50.
We would hope that this can be done prior to restart following the current 1987 refueling outage.
By this letter we request that you advise us of modifications which WPPSS will make to ensure isolation and provide us with a schedule for completion of those modifications.
n 0Q t5%
XO Ql
>m VO aw OlQ
%CJOY Olg OO acn "00~
C5MG)
In correspondence to you dated October 20, 1986, NRC asked that WPPSS "document your committment to remove the power from the RHR-V-8 valve during non-shutdown operating condition" and that you "provide a schedule and a
justification for the schedule" for doing so.
Your response, dated December 1, 1986, to that letter instead referenced the position set forth in your letter of July 16, 1986 (that "the Supply System feels that the design should remain as is").
Appendix R to 10 CFR Part 50, Section III.L.1, concerning postfire alternate shutdown, specifically states that "during the postfire shutdown... there shall be no fuel cladding
- damage, rupture of any primary coolant boundary, or rupture of the containment boundary."
One specific area of concern regarding protection of the primary coolant boundary is the high/low pressure interface.
The high/low pressure interface is the junction of piping at isolation valves which separate piping designed for full reactor pressure on one side from piping designed for low pressure service on the other side.
The concern with the high/low pressure interface is that because the low pressure side of the valves is not designed for operation at the normal operating pressure of the reactor, if the valves were to open (such as could result
H H l II e'
'H 1
~
~
H lfl >>
D t
J, I
b 4
H) f III
~ r tl H
J I
S f'
'I II t')
'I t
lf I
I J )It 4
fl fib
~ f If i I>>
(
i
~
)
'li'<<
g, l)IL j, I
f H
)
H'll '."
. Jf)"I d
b tfb r )l
..)i i
(
H b
g
.Jf I' f,l H)
)
I r,
JI ll
)
S H
I I <<.'.t '
t'iJ
')f b
Jl t )
'I ri <<)>>
)')
J '
'I') H. )",
lilt<<e ~
~
Q)ff) I'>>r P H)'ili')
II f tt
) I
, 1
) )(,
H M>>s)
]lift,...J b )
) ",) 'b'1) lr
'H
'f t
~
H C
SH 'll t
J.bff I'l g)
)b(
,lt 1
f 1st f,)
) )
flt
~ 'tf)
III H I, ~
If<< f th sl r
- r. ).J').i
)
'. t I
t I.)
)'IH'
>>)
f ) b H.,
II
)I ',l.Ilff)fl H
H t'
)f)f>~1)t i )f
)Ifb., '). Ilf' i,
sfl(
..)
~HI,
)fl) I>>>><< i..tS')
I,)
t-)rfk <<:I<<)1"S f
)C~
'r
~ <<,'l J't
~ 0 G.
C. Sorensen from fire-induced spurious signal) when the reactor is at pressure, the low pressure piping could rupture.
Further, fire damage may also result in an inability to close the isolation valves resulting in an unisolatable LOCA outside of containment.
For the Appendix R review, it is postulated that a fire in the control room could result in spurious opening of valves RHR-V-8 and RHR-V-9 which would create an unisolatable LOCA outside the containment, thus violating two of the three aforementioned 10 CFR Part 50 Appendix R req'uirements.
- The, consequence of this accident would be significant and could adversely affect the health and safety of the public.
Furthermore, we are not aware of any plant that has not removed power from one of the RHR suction line isolation valves or has not provided other modification outside of the control room fire area to preclude the valve from opening.
Amendment 37 to the WNP-2 FSAR, which you submitted to the NRC on September 22, 1986, states that "during normal plant operation, power is removed from valve RHR-V-8... to assure that inadvertent opening will not occur."
The staff finds that this approach constitutes adequate compliance with the Appendix R requirement.
We recognize that alternative modifications could also achieve compliance.
We are informing you of our requirement on this item in advance of our completion of our review of Amendment 37 because of the importance of the fire protection issues and because the current outage may provide an opportune time for taking the corrective actions described in this portion of Amendment 37. If other alternatives are to be used an amendment to the FSAR describing the change must be provided on the docket.
We are prepared to discuss this as necessary to expedite action within the current refueling outage.
Sincerely, 7
Original slgt'.Gti 4 J:
.Gt.orge N. Kai1 htOn George W. Knighton, Director Project Directorate V
Division of Reactor Projects - III/IV/V 5 Special Projects cc:
See next page
D:PD5 RSamworth:cd G
nighton 5/11/87 5/ g /87 OFFICIAL RECORD COPY
>I JJ
,lt
.1 r
li
> )fP II~I )~) I'>)'tJLI!
")f; I l
>l))~) '>')l'<)
J>(>>
I
> tt>>
t IIt >>v/vit))
t
>II J
)
y)>
<<'1 I
v I
11.>
')
lllI >>'
ll I t>
I,
)N>I, ti I
~
1 1
I II I'l, >
- J~f 1Lj'll
'",y
>tip ) ) 'yI f >.)>>If it', rt>LI
) y r ) g,t )> v Dt's>
>>3 It I
tl>
t l
v >
N tt'
'")
p1
')
'L) 3 I'
I N
It
)
i tt
>I li t
~
',4,V
'll Ct> '
> ).r 1
I Ilt>
t C')X
~
~
~
"> I rs
'vt
.'>L, y>) I >I'Lr >'1 I3
>t L)'>,)
t y
)
ti t
Lt I II
>1t I
r
't w
v L
"t
)
> ) t
>u) S
,>II ll lt F
t
> t"'
1 I
f') r t,
1: >9 I y fI
)
'I'> ~ >
">I
> <<:II a
II I
)tv I
>1 tt
>J t
gt
'>'I'
)
~
>pl>i t
t> 1" t;~~
V tt>,"II"l
>'t),"'
't>
v
>" v
> I'
> ~Jg,v.r>L)
II t
,I,i y lt t )ti
).t/
'V.)
>'>I i~>J1
'l'I ~
I) V
>I!
II
~
~
~ 0 G. C. Sorensen 2
from fire-induced spurious signal) when the reactor is at pressure, the low pressure piping could rupture.
Further, fire damage may also result in an inability to close the isolation valves resulting in an unisolatable LOCA outside of containment'.
For the Appendix R review, it is postulated that a fire in the control room could result in spurious opening of valves RHR-V-8 and RHR-V-9 which would create an unisolatable LOCA outside the containment, thus violating two of'he three aforementioned 10 CFR Part 50 Appendix R requirements.
The consequence of this accident would be significant and could adversely affect the health and safety of the public.
Furthermore, we are not aware of any plant that has not removed power from one o'f the RHR suction line isolation valves or has not provided other modification outside of the control room fire area to preclude the valve from opening.
Amendment 37 to the WNP-2 FSAR, which you submitted to the NRC on September 22, 1986, states that "during normal plant operation, power is removed from valve RHR-V-8... to assure that inadvertent opening will not occur."
The staff finds that this approach constitutes adequate compliance with the Appendix R requirement.
We recognize that alternative'modifications could also achieve compliance.
1, I am informing you of our requirement on this item in advance of our completion of our review of Amendment 37"because of the importance of the fire protection issues and because the current outage may provide an opportune time for taking the corrective actions described in this portion of Amendment 37.
We are prepared to discuss this as necessary to expedite action within the current refueli'ng outage.
Sincerely, George W. Knighton, Director Project Directorate V
Division of Reactor Projects - III/IV/V 5 Special Projects cc:
See next page ESP/PD5 DRSP/D: PD5 D
P/QB RSamworth:cd GWKnighton G
lahan 5/ // /87 5/
/87
/
87 OFFICIAL RECORD COPY
1 lb' ll>><<>>
1 H
)Jl(tr
)
i t<<>>I fj
",') Ji t.>>"Jtl Pll
)it, l t )fil~ HI ))
III I
t, r) HV I
II (
>.)fr)
II f
'i)
If('v I
H I
W T
H i
i I
i if
)
II I)
< f V)'< ".i)
..I ') t>>l
"'li.)))>'>V
<<I)
Vii)lv VP I
H)CJ ill k l j i
~ H) tt
>>'j t>>)
)
't I
(IV I'g (f
JF f )I, l it f)CI()'flf)$
i
.I" H))
<< 'ii) I,.
)')f )1 f H))
1
<<1 I )(V" i
i(V i) 8 I I
))
I J>>l r
I i>>
Tl li,
) ~ )
H f
. JH>>
J t'
)
"-I f
) I ft tg(','I i
>>fl',I ) 4 "'-)
. f~9
'l
) i>>'f )
ll H
I )H)
I <<>VI',f<<j.
lt
.'IH H
er<<J'I "iI
il '/
I",
V II l l'i>>') '
V
".)V V
hl.i" >>
11<< (
I'l )
II t(
$ ~
'I',) )
il<<) ',
>>V
~
)
Il Hi
'I 1
I V(I'I
'Vl V>>. Hgi ')
1 t) )I'"
HF )H<
H f')
i, 'I('I) I) )
V t
II
')
ll i <<)"
'I) i it H
') lft
'IH H
HT H
tl 1
(
Ii( <<
II
\\
Nr. G: C. Soreni, Nanager Washington Public Power Supply System KPPSS ttuclear Project tto.
2 (eP-2) cc: Nicholas S. Reynolds, Esq.
Bishop, Lfberman,
- Cook, Purcell 5 Reynolds Seventeenth
- Street, N.W.
Washington, D.C.
20036 Nr. G. E. Doupe, Esquire Mashington Public Power Supply System P. 0.
Box 968 3000 George Mashington May Richland, Mashfngton 99532 Nr, Curtis Eschels, Chairman Energy Facility Site Evaluation Councfl
'ail Stop PY-ll Olympia, Washington 98504 L. Powell, Licensing Nanager Washington Public Power Supply System P. 0. Box 968, ND 9568 Richland, Washington 99352 Hr. M. G. Conn Burns and Roe, Incorporated c/o Mashington Public Power Supply System P. 0. Box 968, HD 994E Rfchland, Washington 99352 R. B. G'lasscock, Director Licensing and Assurance Mashington Public Power Supply System P. 0. Box 968, ND 280 Richland, Mashington 99352 Nr. C. N. Powers MNP-2 Plant Nanager Washington Public Power Supply System P. 0. Box ND 927M Richland, Mashington 99352 Regional Administrator, Region V
U.S. Nuclear Regulatory Coamission 1450 Naria Lane, Suite 210 1200 Walnut Creek, Calf fornfa 94596
~