MONTHYEARML17241A5001999-10-21021 October 1999 Forwards Rev 3 to Emergency Response Data Sys (ERDS) Data Point Library for St Lucie Unit 1.Rev Provides Replacement Pages & Follows Format Recommended by NUREG 1394, ERDS Implementation, Rev 1,App C ML17309A9981999-10-19019 October 1999 Forwards Revised Epips,Including Rev 3 to EPIP-10 & Rev 25 to HP-202.EPIP-10 Added Onsite Monitoring Points,Made Administrative Changes & Incorporated New Attachments & HP-202 Added Red Team Survey Points ML20217F6171999-10-0808 October 1999 Forwards Insp Repts 50-335/99-11 & 50-389/99-11 on 990827 & 990907-09.No Violations Identified.Matl Encl Contained Safeguards Info as Defined by 10CFR73.21 & Disclosed to Unauthorized Individuals Prohibited by Section 147 of AEA ML17241A4811999-10-0101 October 1999 Reports Number of Tubes Plugged During Unit 1 Refueling Outage SL1-16,per TS 4.4.5.5.a ML20212M1601999-09-28028 September 1999 Refers to 990908 Engineering Meeting Conducted at NRC Region II to Discuss Engineering Issues at Lucie & Turkey Point Facilities.List of Attendees & Copy of Presentation Handout Encl ML17241A4701999-09-25025 September 1999 Forwards Info Requested by NRC Staff During 990916 Telcon to Complete Staff Review of Request for risk-informed Extension of Action Completion/Aot Specified for Inoperable Train of LPSI Sys at Plant ML17241A4721999-09-24024 September 1999 Forwards Rev 1 to Plant Change/Mod (PCM) 99016 to St Lucie Unit 1,Cycle 16 COLR, IAW TS 6.9.1.11.d.Refueling Overhaul Activities Are Currently in Progress & Reactor Operations for Cycle 16 Are Scheduled to Commence in Oct 1999 ML17241A4681999-09-22022 September 1999 Requests Restriction Be Added to Senior Operator License SOP-21093 for TE Bolander.Nrc Forms 369,encl.Encl Withheld Per 10CFR2.790(a)(6) ML17241A4671999-09-20020 September 1999 Forwards Completed NRC Form 536, Operator Licensing Exam Data, for St Lucie Units 1 & 2,as Requested in Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams. ML17241A4581999-09-13013 September 1999 Forwards Info Requested by NRC Staff During 990630 & 0816 Telcons,To Complete Review of Proposed License Amend for Fuel Reload Process Improvement Program ML17241A4531999-08-31031 August 1999 Informs That No Candidates from St Lucie Plant Will Be Participating in PWR Gfes Being Administered on 991006 ML17241A4521999-08-31031 August 1999 Withdraws Relief Request 16 & Suppl Relief Request 15 with Info Requested During 990526 Telephone Conference Re ISI Insp Plan,Third 10-yr Interval ML17241A4501999-08-26026 August 1999 Informs That FPL Has Reviewed Reactor Vessel Integrity Database,Called RVID2,re Closure of GL 92-01,rev 1,suppl 1. Requested Corrections & Marked Up Pages from Rvid 2 Database Summary Repts That Correspond to Comments,Attached ML17241A4371999-08-13013 August 1999 Forwards fitness-for-duty Program Performance Data for six- Month Period Ending 990630,per 10CFR26.71(d) ML17241A4461999-08-11011 August 1999 Requests That W Rept Entitled, Evaluation of Turbine Missile Ejection Probability Resulting from Extending Test Interval of Interceptor & Reheat Stop Valves at St Lucie Units 1 & 2, Be Withheld from Public Disclosure L-99-171, Forwards Rev 56 to Physical Security Plan.Summary of Changes & Marked Up Copy of Revised Pages Also Encl.Encls Withheld from Public Disclosure Per 10CFR2.790(a)(3)1999-07-29029 July 1999 Forwards Rev 56 to Physical Security Plan.Summary of Changes & Marked Up Copy of Revised Pages Also Encl.Encls Withheld from Public Disclosure Per 10CFR2.790(a)(3) ML17309A9911999-07-26026 July 1999 Forwards Revised EPIPs & Revised Procedures That Implement Emergency Plan as Listed.Procedures Provides Instruction for Operational Support Ctr (OSC) Chemistry Supervisor to Establish Remote Labs at Locations Specified ML17241A4471999-07-22022 July 1999 Requests That Rev 1 to WCAP-14732 & Rev 1,Add 1 to WCAP-14732 Be Withheld from Public Disclosure ML17241A4221999-07-22022 July 1999 Forwards List of Proposed Licensing Actions for St Lucie Units 1 & 2,planned During Fys 2000 & 2001,in Response to Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates. ML17241A4151999-07-22022 July 1999 Forwards Revised Relief Request 25 for Second 10-yr ISI Interval for Unit 2 ML17241A4101999-07-16016 July 1999 Forwards FP&L Supplemental Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants ML17309A9881999-07-0707 July 1999 Forwards Rev 5 to EPIP-03, Emergency Response Organization Notification/Staff Augmentation. Rev 5 to EPIP-03 Was Revised to Transfer EP Responsibilities from Training Manager to Protection Svcs Manager ML20209F1541999-07-0606 July 1999 Informs That NRC in Process of Conducting Operational Safeguards Response Evaluations at Nuclear Power Reactors. Plant Chosen for Such Review Scheduled for Wk of 990823-26 ML17241A4011999-06-30030 June 1999 Forwards Info Copy of Florida Wastewater Permit (FL0002208) (Formerly NPDES Permit) Mod,Which Was Issued by Florida Dept of Environ Protection on 990604 ML17241A3971999-06-30030 June 1999 Forwards Suppl Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, as Requested in 990317 Ltr ML17355A3661999-06-30030 June 1999 Forwards Florida Power & Light Topical QA Rept, Dtd June 1999.Encl I Includes Summary of Changes Made to Topical QA Rept Since 1998 ML17241A3951999-06-29029 June 1999 Provides Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants.Gl 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants, Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl ML17241A3731999-06-17017 June 1999 Supplements Relief Requests 4,11 & 13 for Third ten-year ISI Interval with Info Requested During 990526 Telcon.Expedited Review Is Requested by 990730 to Avoid Negatively Impacting Upcoming St Lucie Unit 1 Refueling Outage (SL1-16) ML17241A3641999-06-14014 June 1999 Submits Supplement to Relief Request 24 with Info Requested by Nrc.In Addition Relief Request 24 Is Identical to St Lucie Unit 1 Relief Request 4 for Third ISI Interval Being Supplemented by FPL Ltr L-99-139 ML20195F3871999-06-11011 June 1999 Final Response to FOIA Request for Documents.App a Records Being Withheld in Entirety (Ref FOIA Exemption 5) IA-99-247, Final Response to FOIA Request for Documents.App a Records Being Withheld in Entirety (Ref FOIA Exemption 5)1999-06-11011 June 1999 Final Response to FOIA Request for Documents.App a Records Being Withheld in Entirety (Ref FOIA Exemption 5) L-99-129, Forwards Rev 55 to Physical Security Plan,Summary of Changes & Marked Up Copy of Revised Pages.With Directions for Incorporating Rev Into Plan & Copies of Replacement Pages.Rev Withheld,Per 10CFR2.790(a)(3)1999-06-0909 June 1999 Forwards Rev 55 to Physical Security Plan,Summary of Changes & Marked Up Copy of Revised Pages.With Directions for Incorporating Rev Into Plan & Copies of Replacement Pages.Rev Withheld,Per 10CFR2.790(a)(3) ML17241A3561999-06-0707 June 1999 Forwards Rept Containing Brief Description & Summary of SEs for Changes,Tests & Experiments Which Were Approved for Unit 3 During Period of 970526-981209 ML17241A3601999-06-0707 June 1999 Forwards Correction to Annual Radiological Environ Operating Rept for CY98.Util Has Identified Transcription Error on Last Page of Attachment C of Rept,Results from Interlaboratory Comparison Program 1998 ML20195F3941999-05-27027 May 1999 FOIA Request That Memo from J Calvo to Fl Lebdon Re TIA - St Lucie,Unit 1 Environ Qualification of Woodward Governor Controls Be Placed in PDR ML17241A3461999-05-24024 May 1999 Forwards Revised Relief Request 22 to Clarify Several Areas of Relief.Nrc Action Is Requested to Be Complete by Aug 1999 to Support Planning for Spring 2000 Unit 2 Refueling Outage ML17241A3391999-05-20020 May 1999 Forwards Notification of Change to Small Break LOCA ECCS Evaluation Model Used for St Lucie Unit 1.Anomaly Was Discovered & Corrected That Resulted in Reducing Calculated PCT for Limiting SBLOCA by More than 50 F ML17241A3371999-05-20020 May 1999 Forwards Util Suppl to GL 95-07 Response Re pressure-locking & Thermal Binding of safety-related power-operated Gate Valves,In Response to NRC Second RAI Dtd 990225 ML20207C7531999-05-17017 May 1999 Discusses Issue Identified by FPL in Feb 1998 Involving Potential for Fire to Cause Breach of Rc Sys High/Low Pressure Interface Boundary & NRC Decision for Exercise of Enforcement Discretion ML17241A3301999-05-17017 May 1999 Forwards LER 99-004-00 Re as Found Cycle 10 Psv Setpoints Outside TS Limits,Which Occurred on 990415.Root Cause Determination Not Yet Complete.Suppl to Include Root Cause & Corrective Actions Will Be Submitted ML17309A9821999-05-10010 May 1999 Forwards Rev 36 to St Lucie Emergency Plan, Per 10CFR50.54(q).Executive Summary & Summary of Changes Incorporated by Rev,Encl IR 05000335/19980141999-04-29029 April 1999 Provides Confirmation of NRC Staff Conclusions Re Cited & non-cited Violations in Insp Rept 50-335/98-14 & 50-389/98-14.Utils Position Re Consideration of Multiple Spurious Actuations in Event of Fire,Reiterated ML17241A3221999-04-29029 April 1999 Provides Confirmation of NRC Staff Conclusions Re Cited & non-cited Violations in Insp Rept 50-335/98-14 & 50-389/98-14.Utils Position Re Consideration of Multiple Spurious Actuations in Event of Fire,Reiterated ML17229B1071999-04-28028 April 1999 Forwards 1998 Annual Environ Operating Rept for St Lucie Unit 2. Rept Includes Discussions of 5-inch Barrier Net Maint & Taprogge Condenser Tube Cleaning Sys Ball Loss,As Agreed at First Biennial Sea Turtle Meeting Held on 980120 ML17229B1051999-04-22022 April 1999 Requests That Listed Individuals Be Placed on Official Serve List for Nuclear Matl Safety & Safeguards Info Notices ML17229B1061999-04-21021 April 1999 Notifies NRC of Change in Medical Status of Licensed Operator Pf Farnsworth (Docket 55-21285,license SOP-21094). NRC Form 3996, Medical Exam Certification, Encl.Encl Withheld Per 10CFR2.790(a)(6) ML17309A9851999-04-15015 April 1999 Requests That NRC Review Denial of Appeal from Assessment of Fees Assessed in 981101 Invoice RS0062-99 & Assessment of Fees in Invoice RS0182-99 Which Was Also Denied in 990305 Ltr.Both Invoices Are for Fees Re Inspector GG Warnick ML20205M0431999-04-13013 April 1999 Eighth Partial Response to FOIA Request for Records.App Q & R Records Encl & Being Made Available in PDR ML17229B0951999-04-0808 April 1999 Requests Approval of Encl Revised Relief Request 6,in Response to 990322 Telcon with NRC & 10CFR55.55a(a)(3). Request States That Visual VT-3 Exams Will Be Conducted IAW IWA-2213 & Repairs Will Be IAW Util ASME Section IX Program ML17229B0821999-04-0707 April 1999 Requests Approval of Interim Relief Request 26 Re Repair Requirements for Class 2 ECCS Piping,Per 10CFR50.55a(a)(3) & 50.55a(g)(iii).Alternative Actions Apply Guidance of GLs 91-18 & 90-05 & ASME Code Case N-513.Evaluation,encl 1999-09-28
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML17241A5001999-10-21021 October 1999 Forwards Rev 3 to Emergency Response Data Sys (ERDS) Data Point Library for St Lucie Unit 1.Rev Provides Replacement Pages & Follows Format Recommended by NUREG 1394, ERDS Implementation, Rev 1,App C ML17309A9981999-10-19019 October 1999 Forwards Revised Epips,Including Rev 3 to EPIP-10 & Rev 25 to HP-202.EPIP-10 Added Onsite Monitoring Points,Made Administrative Changes & Incorporated New Attachments & HP-202 Added Red Team Survey Points ML17241A4811999-10-0101 October 1999 Reports Number of Tubes Plugged During Unit 1 Refueling Outage SL1-16,per TS 4.4.5.5.a ML17241A4701999-09-25025 September 1999 Forwards Info Requested by NRC Staff During 990916 Telcon to Complete Staff Review of Request for risk-informed Extension of Action Completion/Aot Specified for Inoperable Train of LPSI Sys at Plant ML17241A4721999-09-24024 September 1999 Forwards Rev 1 to Plant Change/Mod (PCM) 99016 to St Lucie Unit 1,Cycle 16 COLR, IAW TS 6.9.1.11.d.Refueling Overhaul Activities Are Currently in Progress & Reactor Operations for Cycle 16 Are Scheduled to Commence in Oct 1999 ML17241A4681999-09-22022 September 1999 Requests Restriction Be Added to Senior Operator License SOP-21093 for TE Bolander.Nrc Forms 369,encl.Encl Withheld Per 10CFR2.790(a)(6) ML17241A4671999-09-20020 September 1999 Forwards Completed NRC Form 536, Operator Licensing Exam Data, for St Lucie Units 1 & 2,as Requested in Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams. ML17241A4581999-09-13013 September 1999 Forwards Info Requested by NRC Staff During 990630 & 0816 Telcons,To Complete Review of Proposed License Amend for Fuel Reload Process Improvement Program ML17241A4531999-08-31031 August 1999 Informs That No Candidates from St Lucie Plant Will Be Participating in PWR Gfes Being Administered on 991006 ML17241A4521999-08-31031 August 1999 Withdraws Relief Request 16 & Suppl Relief Request 15 with Info Requested During 990526 Telephone Conference Re ISI Insp Plan,Third 10-yr Interval ML17241A4501999-08-26026 August 1999 Informs That FPL Has Reviewed Reactor Vessel Integrity Database,Called RVID2,re Closure of GL 92-01,rev 1,suppl 1. Requested Corrections & Marked Up Pages from Rvid 2 Database Summary Repts That Correspond to Comments,Attached ML17241A4371999-08-13013 August 1999 Forwards fitness-for-duty Program Performance Data for six- Month Period Ending 990630,per 10CFR26.71(d) ML17241A4461999-08-11011 August 1999 Requests That W Rept Entitled, Evaluation of Turbine Missile Ejection Probability Resulting from Extending Test Interval of Interceptor & Reheat Stop Valves at St Lucie Units 1 & 2, Be Withheld from Public Disclosure L-99-171, Forwards Rev 56 to Physical Security Plan.Summary of Changes & Marked Up Copy of Revised Pages Also Encl.Encls Withheld from Public Disclosure Per 10CFR2.790(a)(3)1999-07-29029 July 1999 Forwards Rev 56 to Physical Security Plan.Summary of Changes & Marked Up Copy of Revised Pages Also Encl.Encls Withheld from Public Disclosure Per 10CFR2.790(a)(3) ML17309A9911999-07-26026 July 1999 Forwards Revised EPIPs & Revised Procedures That Implement Emergency Plan as Listed.Procedures Provides Instruction for Operational Support Ctr (OSC) Chemistry Supervisor to Establish Remote Labs at Locations Specified ML17241A4221999-07-22022 July 1999 Forwards List of Proposed Licensing Actions for St Lucie Units 1 & 2,planned During Fys 2000 & 2001,in Response to Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates. ML17241A4471999-07-22022 July 1999 Requests That Rev 1 to WCAP-14732 & Rev 1,Add 1 to WCAP-14732 Be Withheld from Public Disclosure ML17241A4151999-07-22022 July 1999 Forwards Revised Relief Request 25 for Second 10-yr ISI Interval for Unit 2 ML17241A4101999-07-16016 July 1999 Forwards FP&L Supplemental Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants ML17309A9881999-07-0707 July 1999 Forwards Rev 5 to EPIP-03, Emergency Response Organization Notification/Staff Augmentation. Rev 5 to EPIP-03 Was Revised to Transfer EP Responsibilities from Training Manager to Protection Svcs Manager ML17241A4011999-06-30030 June 1999 Forwards Info Copy of Florida Wastewater Permit (FL0002208) (Formerly NPDES Permit) Mod,Which Was Issued by Florida Dept of Environ Protection on 990604 ML17241A3971999-06-30030 June 1999 Forwards Suppl Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, as Requested in 990317 Ltr ML17355A3661999-06-30030 June 1999 Forwards Florida Power & Light Topical QA Rept, Dtd June 1999.Encl I Includes Summary of Changes Made to Topical QA Rept Since 1998 ML17241A3951999-06-29029 June 1999 Provides Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants.Gl 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants, Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl ML17241A3731999-06-17017 June 1999 Supplements Relief Requests 4,11 & 13 for Third ten-year ISI Interval with Info Requested During 990526 Telcon.Expedited Review Is Requested by 990730 to Avoid Negatively Impacting Upcoming St Lucie Unit 1 Refueling Outage (SL1-16) ML17241A3641999-06-14014 June 1999 Submits Supplement to Relief Request 24 with Info Requested by Nrc.In Addition Relief Request 24 Is Identical to St Lucie Unit 1 Relief Request 4 for Third ISI Interval Being Supplemented by FPL Ltr L-99-139 L-99-129, Forwards Rev 55 to Physical Security Plan,Summary of Changes & Marked Up Copy of Revised Pages.With Directions for Incorporating Rev Into Plan & Copies of Replacement Pages.Rev Withheld,Per 10CFR2.790(a)(3)1999-06-0909 June 1999 Forwards Rev 55 to Physical Security Plan,Summary of Changes & Marked Up Copy of Revised Pages.With Directions for Incorporating Rev Into Plan & Copies of Replacement Pages.Rev Withheld,Per 10CFR2.790(a)(3) ML17241A3601999-06-0707 June 1999 Forwards Correction to Annual Radiological Environ Operating Rept for CY98.Util Has Identified Transcription Error on Last Page of Attachment C of Rept,Results from Interlaboratory Comparison Program 1998 ML17241A3561999-06-0707 June 1999 Forwards Rept Containing Brief Description & Summary of SEs for Changes,Tests & Experiments Which Were Approved for Unit 3 During Period of 970526-981209 ML20195F3941999-05-27027 May 1999 FOIA Request That Memo from J Calvo to Fl Lebdon Re TIA - St Lucie,Unit 1 Environ Qualification of Woodward Governor Controls Be Placed in PDR ML17241A3461999-05-24024 May 1999 Forwards Revised Relief Request 22 to Clarify Several Areas of Relief.Nrc Action Is Requested to Be Complete by Aug 1999 to Support Planning for Spring 2000 Unit 2 Refueling Outage ML17241A3371999-05-20020 May 1999 Forwards Util Suppl to GL 95-07 Response Re pressure-locking & Thermal Binding of safety-related power-operated Gate Valves,In Response to NRC Second RAI Dtd 990225 ML17241A3391999-05-20020 May 1999 Forwards Notification of Change to Small Break LOCA ECCS Evaluation Model Used for St Lucie Unit 1.Anomaly Was Discovered & Corrected That Resulted in Reducing Calculated PCT for Limiting SBLOCA by More than 50 F ML17241A3301999-05-17017 May 1999 Forwards LER 99-004-00 Re as Found Cycle 10 Psv Setpoints Outside TS Limits,Which Occurred on 990415.Root Cause Determination Not Yet Complete.Suppl to Include Root Cause & Corrective Actions Will Be Submitted ML17309A9821999-05-10010 May 1999 Forwards Rev 36 to St Lucie Emergency Plan, Per 10CFR50.54(q).Executive Summary & Summary of Changes Incorporated by Rev,Encl ML17241A3221999-04-29029 April 1999 Provides Confirmation of NRC Staff Conclusions Re Cited & non-cited Violations in Insp Rept 50-335/98-14 & 50-389/98-14.Utils Position Re Consideration of Multiple Spurious Actuations in Event of Fire,Reiterated IR 05000335/19980141999-04-29029 April 1999 Provides Confirmation of NRC Staff Conclusions Re Cited & non-cited Violations in Insp Rept 50-335/98-14 & 50-389/98-14.Utils Position Re Consideration of Multiple Spurious Actuations in Event of Fire,Reiterated ML17229B1071999-04-28028 April 1999 Forwards 1998 Annual Environ Operating Rept for St Lucie Unit 2. Rept Includes Discussions of 5-inch Barrier Net Maint & Taprogge Condenser Tube Cleaning Sys Ball Loss,As Agreed at First Biennial Sea Turtle Meeting Held on 980120 ML17229B1051999-04-22022 April 1999 Requests That Listed Individuals Be Placed on Official Serve List for Nuclear Matl Safety & Safeguards Info Notices ML17229B1061999-04-21021 April 1999 Notifies NRC of Change in Medical Status of Licensed Operator Pf Farnsworth (Docket 55-21285,license SOP-21094). NRC Form 3996, Medical Exam Certification, Encl.Encl Withheld Per 10CFR2.790(a)(6) ML17309A9851999-04-15015 April 1999 Requests That NRC Review Denial of Appeal from Assessment of Fees Assessed in 981101 Invoice RS0062-99 & Assessment of Fees in Invoice RS0182-99 Which Was Also Denied in 990305 Ltr.Both Invoices Are for Fees Re Inspector GG Warnick ML17229B0951999-04-0808 April 1999 Requests Approval of Encl Revised Relief Request 6,in Response to 990322 Telcon with NRC & 10CFR55.55a(a)(3). Request States That Visual VT-3 Exams Will Be Conducted IAW IWA-2213 & Repairs Will Be IAW Util ASME Section IX Program ML17229B0821999-04-0707 April 1999 Requests Approval of Interim Relief Request 26 Re Repair Requirements for Class 2 ECCS Piping,Per 10CFR50.55a(a)(3) & 50.55a(g)(iii).Alternative Actions Apply Guidance of GLs 91-18 & 90-05 & ASME Code Case N-513.Evaluation,encl ML17229B0851999-04-0505 April 1999 Requests Approval of Encl Relief Request 25 Which Proposes to Use Alternative Requirements of ASME Code Case N-613 in Lieu of Requirements of ASME Section XI Figures IWB-2500-7(a) & IWB-2500-7(b).Action Requested by Aug 1999 ML17309A9791999-03-31031 March 1999 Forwards Revised EPIPs Including Rev 2 to EPIP-00,rev 2 to EPIP-09,rev 2 to EPIP-10 & Rev 10 to HP-207.Summary of Revs Listed ML17309A9761999-03-23023 March 1999 Forwards Revised Epips,Including Rev 4 to EPIP-03, Er Organization Notification/Staff Augmentation, Rev 3 to EPIP-05, Activation & Operation of OSC & Rev 14 to HP-200, HP Emergency Organization. Changes to Epips,Discussed ML17229B0691999-03-19019 March 1999 Transmits TS Pages Requested by NRC for Use in Issuance of Proposed License Amend Re SFP Storage Capacity,Per Soluble Boron Credit ML17229B0721999-03-16016 March 1999 Requests Approval of Enclosed Relief Requests 23 & 24 Re ISI Plan for Second ten-year Interval.Nrc Action Is Requested to Be Complete by Aug 1999 to Support Planning for Spring 2000 Unit 2 Refueling Outage ML17355A2631999-03-12012 March 1999 Forwards FPL Decommissioning Fund Status Repts for St Lucie, Units 1 & 2 & Turkey Point,Units 3 & 4.Rept for St Lucie, Unit 2 Provides Status of Decommissioning Funds for All Three Owners of That Unit ML17229B0481999-03-10010 March 1999 Informs That Util Delivered Matls Requested in Encl 1 of NRC Ltr by Hand on 990308,as Requested by NRC Ltr Dtd 990218 1999-09-25
[Table view] |
Text
CATEGORY 1 REGULATOR.E INFORMATION
~
DISTRIBUTION SYSTEM (RIDS)
ACCESSION NBR:9806090141 DOC.DATE: 98/06/03 NOTARIZED: NO DOCKET FACIL:50-335 St; Lucie Plant, Unit 1, Florida Power &, Light Co. 05000335 AUTH.NAME, < 'UTHOR AFFILIATION STALL,J.A. Florida Power 5: Light Co.
RECIP.NAME RECIPIENT AFFILIATION COLLINS,S.J.
SUBJECT:
Informs that licensee will comply w/listed commitment re Thermo-Lag 330-1 fire barrier, in response to JA Zwolinski' 980501 ltr.Signed consent to confirmatory order, modifying license on Thermo-Lag commitments, encl.
DISTRIBUTION CODE: A029D COPIES RECEIVED:LTR, ENCL SIZE:
TITLE: Generic Letter 92-008 Thermo-Lag 330 Fire Barrier E
NOTES:
RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL 0 PD2-3 LA 1 0 PD2-3 PD 1 1 GLEAVES,W 1 1 INTERNAL: %Xjg~C@NXEEE. 01 1 1 NRR/DE/EELB 1 1 Y NRR/DRPW/PD3-1 1 1 NRR/DSSA/SPLB 1 1 NRR/KUGLER,A 1 1 RGN2 FILE 1 1 EXTERNAL: NOAC 1 1 NRC PDR D
U E
N NOTE TO ALL "RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD) ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 11 ENCL 10
Florida Power 5 Light Company, 6351 S. Ocean Drive, Jensen Beach, FL 34957 June 3, 1998 L-98-134 10 CFR 50.4 Mr. Samuel J. Collins, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 RE: St. Lucie Unit 1 Docket No. 50-335 Consent to Confirmatory Order Mh
Dear Mr. Collins:
In response to J. A. Zwolinski's letter dated May 1, 1998, Florida Power & Light Company (FPL) will comply with the following commitment with respect to St. Lucie Unit 1 (reproduced in the attachment):
FPL shall complete final implementation of the Thermo-Lag 330-1 fire barrier corrective actions at St. Lucie Unit 1, as described in FPL letters L-97-19 dated March 17, 1997, and I 98-134 dated June 3, 1998, by December 31, 1998. There are three exceptions to this commitment as discussed in FPL letter L-98-134.
- 1. The proposed corrective action for the Thermo-Lag wall separating the St. Lucie Unit 1 cable spreading room and 'B'witchgear room will not be completed by December 31, 1998. As discussed in L-98-134, FPL will complete the implementation of this proposed corrective action by the completion of the St. Lucie Unit 1 1999 refueling outage (SL1-16).
)/
- 2. Thermo-Lag ampacity derating methodology issues, which are still under NRC review, will likely not be resolved by December 31, 1998. Schedules for any corrective actions related to ampacity derating will be determined separately and are not part of this order.
- 3. The resolution of any new Thermo-Lag corrective actions resulting from the pilot fire protection functional inspection (FPFI) conducted at St. Lucie during March 1998 are not con'sidered part of this confirming order since FPL has neither received nor responded to the inspection report. Such issues and any corrective actions will be scheduled and resolved as part of that inspection.
9806090i4i 'F80608 g PDR ADQCK 05000835 f OR+
an FPL Group company
~~
t
St. Lucie Unit 1 Docket No..50-335 L-98-134 Page 2 The above properly reflects FPL's commitments to implement Thermo-Lag 330-1 fire barrier corrective actions at St. Lucie Unit 1. These differ from the commitment proposed in Mr. Zwolinski's May 1, 1998 letter because a number of the submittals referenced in his letter do not reflect the St. Lucie Unit 1 final commitment as discussed below.
FPL letter L-94-104 dated April 29, 1994, proposed a performance-based approach for resolving Thermo-Lag fire barrier issues. NRC notified FPL that the staff would not review the FPL proposed approach by letter dated August 11, 1994. FPL letter L-94-104 did not, therefore, contain any Thermo-Lag 330-1 fire barrier corrective action commitments.
FPL letter L-96-28 dated February 12, 1996, responded to a NRC request for additional information (RAI) concerning Thermo-Lag fire barrier ampacity derating issues. The FPL ampacity derating methodology is still under NRC review. FPL is also currently in the process of responding to an additional NRC RAI concerning Thermo-Lag fire barrier ampacity derating dated April 23, 1998. Therefore, any order confirming commitments for the Thermo-Lag ampacity derating corrective actions would be premature at this time.
FPL letters L-93-96 dated April 16, 1993, L-94-33 dated February 11, 1994, L-94-275 dated November 4, 1994, L-95-101 dated March 28, 1995, L-95-286 dated October 27, 1995, and L-96-211 dated August 27, 1996, submitted in response to Generic Letter 92-08 and NRC RAIs described the FPL program to resolve Thermo-Lag 330-1 issues at St. Lucie Units 1 and 2. These commitments have been superseded by FPL letter L-97-19 dated March 17, 1997, and this letter, L-98-134.
As a result of NRC issues raised during the pilot fire protection functional inspection (FPFI) conducted at St. Lucie during March 1998, FPL has reevaluated the planned corrective action for the Thermo-Lag wall separating the St. Lucie Unit 1 cable spreading room and 'B'witchgear room. FPL had originally intended to upgrade this wall utilizing Thermo-Lag fire barrier material. However, concerns over the fire rating of the proposed Thermo-Lag wall upgrade raised during the FPFI have caused FPL to revise its planned corrective action. FPL now intends to replace the existing Thermo-Lag wall separating the St. Lucie Unit 1 cable spreading room and
'B'witchgear room with a non-Thermo-Lag 3-hour rated fire barrier. The proposed wall replacement creates interferences with existing plant structures and protected circuits required for alternate shutdown. FPL has determined that circuit rerouting combined with the wall replacement is the preferred option. However, the circuit modifications will require a unit outage for implementation. FPL intends to complete the implementation of the proposed wall replacement by the end of the St. Lucie Unit 1 1999 refueling outage (SL1-16) This is consistent
~
with the continge'ncy specified in FPL letter L-97-19 dated March 17, 1997.
St. Lucie Unit 1 Docket Na. 50-335 L-98-134 Page 3 FPL agrees to the incorporation of the above commitment in a confirmatory order modifying the St. Lucie Unit 1 Operating License DPR-67 (St. Lucie Unit 1 Order) that will be effective immediately upon issuance. FPL also recognizes that by signing below, FPL consents to the issuance of an immediately effective St. Lucie Unit 1 Order incorporating the above commitment for St. Lucie Unit 1 and, by doing so, pursuant to 10 CFR f 2.202(a)(3), FPL will not have a right to request a hearing on all or any part of the St. Lucie Unit 1 Order. However, it is FPL's position that this waiver of a right to a hearing is limited to the issuance of the specific St, Lucie Unit 1 Order and does not extend to any future right to a hearing or to any other legal process that FPL might have concerning any other order, issuance or determination by the NRC, including, for example, any NRC determination that good cause has not been shown for the relaxation or rescission of the St. Lucie Unit 1 Order. Moreover, it is FPL's position that, in the event FPL requests a hearing on the NRC's denial of a showing of good cause, the effectiveness of the above commitment will be suspended until the completion of the hearing.
Additionally, consistent with the confirmatory order issued to Washington Public Power Supply System concerning Nuclear Project No. 2 dated March 25, 1998, as well as confirmatory orders issued to other licensees, FPL's acceptance is based on the premise that the St. Lucie Unit 1 Order will expressly provide that "The Director, Office of Nuclear Reactor Regulation, may relax or rescind, in writing, any provisions of this Confirmatory Order upon a showing by the Licensee of good cause." By way of example, and not by way of limitation, FPL considers a showing of good cause to include delays or disruptions which directly affect FPL's ability to satisfy the St. Lucie Unit 1 Order and which result from unforeseeable conditions beyond the control of FPL, including, but not limited to, acts of God, labor difficulty, unavailability of materials, embargoes, or acts of governmental authorities, including changes in laws, regulations, licenses, or orders.
Further, FPL believes that a showing of good cause would include such matters as the need to revise the completion date of the above commitment in order to perform other work because FPL determines that the safety significance of such work takes precedence over the above-described Thermo-Lag 330-1 modifications. In that case, FPL recognizes that the showing of good cause should also demonstrate that the new work cannot be performed at the same time as the Thermo-Lag 330-1 modifications due to budget, resource, or space constraints.
St. Lucie Unit 1 Docket Nq. 50-335 L-98-134 Page 4 In a phone call on May 11, 1998, the NRC Project Manager for St. Lucie, W. C. Gleaves, extended the due date for the response to Mr. Zwolinski's May 1, 1998, letter to 15 business days after FPL received the letter. FPL received Mr. Zwolinski's letter on May 13, 1998, making the response due by June 3, 1998.
Please contact us if there are any questions about this consent letter.
Very truly yours, J. A. Stall Vice President St, Lucie Plant Attachment JAS/GRM CC: Document Control Desk, Washington, D. C.
Regional Administrator, Region II, USNRC Senior Resident Inspector, USNRC, St. Lucie Plant
St. Lucie Unit 1 Docket No. 50-335 L-98-134 Attachment I, Mr. J. A. Stall, Site Vice President, St. Lucie Nuclear Plant, Florida Power & Light Company, hereby agree on behalf of Florida Power & Light Company that Florida Power & Light Company will comply with the following commitment for St. Lucie Unit 1:
FPL shall complete final implementation of the Thermo-Lag 330-1 fire barrier corrective actions at St. Lucie Unit 1, as described in FPL letters L-97-19 dated March 17, 1997, and L-98-134 dated June 3, 1998, by December 31, 1998. There are three exceptions to this commitment as discussed in FPL letter L-98-134.
- 1. The proposed corrective action for the Thermo-Lag wall separating the St. Lucie Unit 1 cable spreading room and 'B'witchgear room will not be completed by December 31, 1998, As discussed in L-98-134, FPL will complete the implementation of this proposed corrective action by the completion of the St. Lucie Unit 1 1999 refueling outage (SL1-16).
- 2. Thermo-Lag ampacity derating methodology issues, which are still under NRC review, will likely not be resolved by December 31, 1998.
Schedules for any corrective actions related to ampacity derating will be determined separately and are not part of this order.
- 3. The resolution of any new Thermo-Lag corrective actions resulting from the pilot fire protection functional inspection (FPFI) conducted at St. Lucie during March 1998 are not considered part of this confirming order since FPL has neither received nor responded to the inspection report. Such issues and any corrective actions will be scheduled and resolved as part of that inspection.
Florida Power & Light Company also agrees to incorporating this commitment into a Confirmatory Order Modifying License (Order) that will be effective immediately upon issuance.
I recognize that by signing below, Florida Power & Light Company consents to the issuance of an immediately effective Order incorporating the above commitment and, by doing so, pursuant to 10 CFR 2.202(a)(3), Florida Power & Light Company will not have a right to request a hearing on all or any part of this Order.
J. A. Stall, Site Vice President Date St, Lucie Nuclear Power Plant Florida Power & Light Company