ML17158A848
| ML17158A848 | |
| Person / Time | |
|---|---|
| Site: | Susquehanna |
| Issue date: | 08/15/1995 |
| From: | NRC (Affiliation Not Assigned) |
| To: | |
| Shared Package | |
| ML17158A847 | List: |
| References | |
| NUDOCS 9508230391 | |
| Download: ML17158A848 (49) | |
Text
~
~~gR RE0(
"o Op 0O I
Yg
~O
+p*4W UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 S
EVALU ON BY TH OFFICE OF NU LEAR RE CTOR REGUL TION RELATED TO AMENDMEN NO. "5iTO FACILITY OPERATING LICENSE NO. NPF-14 AM NDMENT
- 0. 121 TO F CI TY OP TING IC NS 0.
NPF-22 NSYLVANI OWER GH COMP ALLEGHENY ELECTRIC COOPERATIVE INC.
SUS UEH NA STEAM CTRIC S
0 UNITS AND DOCKET NOS.
50-387 AND 388 I.O ~RIROOOO IO By letter dated November 21,
- 1994, (Reference 1) as supplemented by letters dated February 21,
- 1995, March 28, 1995, April 10,
- 1995, Hay 24,
- 1995, and June 23, 1995, the Pennsylvania Power and Light Company (the licensee) submitted a request for changes to the Susquehanna Steam Electric Station, Units 1 and 2, Technical Specifications (TS).
The requested changes would change the TS for the two units by deleting reference to the main steamline isolation valve (HSIV) leakage control system and its associated primary containment isolation valves, to reflect a design change and use of an alternate leakage pathway and increase the allowable leakage rate for any HSIV and the total maximum pathway leakage for all four main steam lines.
Specifically, the licensee requested that:
1.
The allowable leakage rate specified in TS 3.6. 1.2 be modified from the current 11.5 scfh for any one HSIV when tested at 22.5 psig to 100 scfh for any one HSIV with a total maximum pathway leakage of 300 scfh through all four main steam lines when tested at 22.5 psig; 2.
TS 3/4.6. 1.4 and its Bases, Tables 3.6.3-1 and 3.8.4.2, be amended to permit the deletion of the HSIV LCS from the TSs; 3.
A new requirement be added to TS 3.6. 1.2 related to the restoration of acceptable leak rates if any of the proposed limits are exceeded, such that if any HSIV exceeds 100 scfh, it will be repaired and retested to meet a leak rate limit of 11.5 scfh per valve; 4.
The Index, TS 3/4.6. 1.4, and Bases 3/4.6. 1.4 be administratively revised to reflect the above requested changes.
The licensee proposes these changes as an alternative to Regulatory Guide 1.96 (RG 1.96),
"Design of Hain Steam Isolation Valve Leakage Control Systems for Boiling Water Reactor (BWR) Nuclear Power'lants,"
by utilizing the main steam 95082303'Pl 9508'L5 PDR ADQCK 05000387' PDR
I ~
e
<<ga I
~
I4
lines and condenser, as an alternate method for NSIV leakage treatment.
The proposed changes are a result of extensive work performed by the Boiling Water Reactor Owners Group (BWROG) in support of the resolution of Generic Issue C-8, "HSIV Leakage and Leakage Failure."
In addition to the licensee's submittals, General Electric (GE) Report NEDC-31858P, Revision 2, "BWROG Report for Increasing Hain Steam Isolation Valve Leakage Rate Limits and Elimination of Leakage Control Systems,"
dated September 1993 (Reference 2),
also provided technical justification for the proposed changes.
The February 21,
- 1995, March 28, 1995, April 10,
- 1995, Hay 24,
- 1995, and June 23, 1995 letters provided clarifying information that did not change the initial proposed no significant hazards consideration determination.
2.0 BACKGROUND
The main steam lines (HSLs) contain dual quick-closing NSIVs.
These valves function to isolate the reactor system in the event of a break in a steam line outside the primary containment, a design basis loss of coolant accident (LOCA), or other events requiring containment isolation.
Although the NSIVs are designed to provide a leak-tight barrier, it is recognized that some leakage through the valves will occur, Operating experience at various BWR plants has indicated that degradation has occasionally occurred in the leak-tightness of HSIVs, and the specified low leakage has not always been maintained.
Because of recurring problems with excessive leakage of HSIVs, RG 1,96 recommended the installation of a supplemental LCS to ensure that the isolation function of the MSIVs complies with the specified limits, To meet this requirement, the licensee installed a safety-related NSIV LCS that is designed to eliminate the release of fission products.
This is accomplished by developing a negative pressure in the sections of the HSLs between the inboard and outboard
This negative pressure is developed by a series of blowers that discharge the leakage to an area where it is treated by the standby gas treatment system (SGTS).
Due to design limitations, the LCS would be unavailable if the HSIV leak rate was greatly in excess of the allowable value in the TSs.
- Hence, Generic Issue C-8 was initiated in 1983 to assess:
(1) the causes of HSIV failures, (2) the effectiveness of the LCS and alternative leakage
- paths, and (3) the need for regulatory action to limit public risk.
The resolution of C-8 (see NUREG-1372, Regulatory Analysis for the Resolution of Generic Issue C-8, "Main Steam Isolation Valve Leakage and LCS Failure," dated June
- 1990, concluded that no backfit requirements to reduce public risk were warranted and that no action should be taken.
- However, one of the alternative resolutions of C-8 showed that several non-seismic Category I paths gave off lower doses than the LCS and could handle larger NSIV leak rates.
In a parallel effort the BWROG formed an MSIV Leakage Committee in 1982 to identify and resolve the causes of high HSIV leakage rates.
The BWROG then
formed a follow-on HSIV Leakage Closure Committee to address alternate actions to resolve on-going but less severe HSIV leakage problems and to address the limited capability of the LCS.
The results of these committee activities were submitted to the NRC in several GE proprietary reports, the latest of which is NEDC-31858P, Revision 2, (Reference 2).
This report concludes that the proposed increase of the HSIV leakage limit will reduce radiation exposures to maintenance personnel, reduce outage durations, and extend the effective service life of the HSIVs.
The report also concludes that the proposed elimination of the LCS will similarly reduce exposures to maintenance personnel, reduce outage durations, and that the LCS can be replaced with an alternate method for HSIV leakage treatment using the MSLs and condenser.
The licensee referred to this report as a basis to delete the TS requirements for the HSIV LCS and requested a substantially higher (100 scfh per steam line and a total of 300 scfh for all four HSLs)
HSIV leak rate limit.
The proposed alternative treatment method recommended in the BWROG report, and as proposed by the licensee, takes advantage of the large volume in the main steam lines and main condenser to provide hold-up and plate-out of fission products that may leak from closed HSIVs.
This method uses the main steam drain lines to direct leakage to the main condenser.
In this approach, the main steam piping, the bypass/drain
- piping, and the main condenser are used to mitigate the consequences of an accident which could result in potential offsite exposures comparable to 10 CFR Part 100.
Therefore, as required by Appendix A to Part 100, the components and piping systems used in the alternative treatment path must be capable of performing their function during and following a safe shutdown earthquake (SSE).
The BWROG report and the licensee's submittals provide the technical justification for the seismic capability of the alternate treatment path and also provide the dose calculations to demonstrate the acceptability of the system.
3.0 EVALUATION This evaluation has been performed in several parts.
Section 3. 1 provides the radiological assessment; Section 3.2 provides the seismic evaluation; Section 3.3 provides the support evaluation; and Section 3.4 provides the plant systems evaluation.
- 3. 1 Radiolo ical Assessment 3.1.1
Background
In order to demonstrate the adequacy of the SSES Units 1 and 2 engineered safety features designed to mitigate the radiological consequences of the design basis accidents (DBAs) with a maximum HSIV leak rate of 300 scfh total from all four main steam lines and without the MSIV-LCS, the licensee assessed the offsite and control room radiological consequences which could result from the occurrence of a postulated loss of coolant accident (LOCA) and presented the results of that assessment in their submittal.
During the SSES Units 1 and 2 licensing review, the staff previously assessed the offsite radiological consequences of a LOCA using 46 scfh HSIV total leak rate from four main steam lines with the HSIV-LCS.
The calculated results are shown in Table 15. 1 of NUREG-0776, "Safety Evaluation Report Related to the Operation of Susquehanna Steam Electric Station, Units 1 and 2" (OL-SER),
April 1981.
In this OL-SER, the staff considered the following sources and radioactivity transport paths to the environment following a postulated LOCA:
(1) containment leakage (2) main steam line isolation valve leakage (3) post-LOCA leakage from engineered safety features outside containment In this evaluation, the staff recalculated the radiological consequences associated with main steam isolation valve leakage path.
It is assumed that the radiological consequences associated with the other radioactivity transport paths would be negligibly affected by the proposed amendments, therefore, they were not recalculated.
The procedures used in the staff's calculation of the radiological consequences associated with HSIV valve leakage were based upon (1) the TID-14844 source term, consistent with the guidelines provided in the applicable sections of the Standard Review Plan (SRP, NUREG-0800) and Regulatory Guides and (2) assumptions and parameters used -in the SSES Units 1 and 2 OL-SER, except for the following two deviations.
The staff has accepted credit for radioactive iodine removal in the main steam lines, drain lines and main condenser by hold-up, decay and deposition.
The staff has also accepted the deletion of the TS requirements for the HSIV-LCS.
Dose contributions to the whole body from the increased HSIV leakage were recalculated based upon the ratio of the proposed leakage rate limit of 300 scfh to the current limit of 46 scfh.
No credit was given for holdup and decay of noble gases in the main steam lines and condenser.
The staff's recalculated offsite and control room operator doses resulting from a postulated LOCA and the parameters and assumptions used in the staff's recalculation are provided in Tables 1 and 2 of this safety evaluation, respectively.
The main steam lines in boiling water reactor plants, including SSES Units 1
and 2, contain dual quick-closing HSIVs.
These valves function to isolate the reactor system in the event of a break in a steam line outside the primary containment, a design basis LOCA, or other events requiring containment isolation.
Although the HSIVs are designed to provide a leak-tight barrier, it is recognized that-some leakage through the valves will occur.
The current SSES Units 1 and 2 technical specification limit for HSIV leakage is 11.5 scfh for any one HSIV.
Operating experience at various BWR plants has indicated that degradation has occasionally occurred in the leak-tightness of HSIVs, and the specified low leakage has not always been maintained.
Because of recurring problems with excessive leakage of HSIVs, Regulatory Guide 1.96, "Design of Hain Steam Isolation Valve Leakage Control Systems for Boiling Water Reactor Nuclear Power Plants,"
recommended the installation of a supplemental main steam leakage control system to ensure that the isolation function of the HSIVs complies with the specified limits:
In order to meet
~ ~
this requirement, the licensee installed a safety-related NSIV leakage Control System which is designed to eliminate the release of fission products through'he HSIVs that would bypass the reactor building and filtration by the Standby Gas Treatment System following a postulated LOCA.
In response to the MSIV leakage
- concerns, the BWR Owners Group (BWROG) in 1986 commissioned a program of studies to determine the causes of high leak rates and the means to eliminate them.
The results of these studies were submitted to the NRC in several revisions of a General Electric proprietary report, all
- titled,
" Increasing Main Steam Isolation Valve Leakage Rate Limits and Elimination of Leakage Control Systems'
(See Reference 2)
These reports conclude that the proposed increase of the NSIV leakage limit will reduce radiation exposures to maintenance personnel, reduce outage durations, and extend the effective service life of the NSIVs
~
The reports also conclude that the proposed elimination of the LCS will similarly reduce exposures to maintenance personnel and reduce outage durations and that the LCS can be replaced with an alternate method for NSIV leakage treatment utilizing the main steam lines and condenser.
The licensee referenced these ~
reports as a basis to delete the TS requirements for the HSIV Leakage Control System and to allow a substantially higher (100 scfh per valve)
HSIV leak limit.
The HSIVs generally have not provided a leak-tight containment pressure boundary to the extent intended in the plant design, Although substantial progress has been made in recent years to identify the causes of the leakage and to reduce the amount of leakage, the current typical BWR Technical Specification limit of 11.5 scfh per valve used at SSES Unit Nos.
1 and 2 is still difficult to achieve when the valve is rapidly closed against full flow conditions at reactor operating pressure and temperature.
The current assumption used by the staff for operating plants in calculating radiological consequences of potential DBAs is based upon a conservative assumption that the leakage limit allowed by the Technical Specification is released directly into the environment.
No credit is currently taken for the integrity and leaktightness of the main steam piping and condenser to provide holdup and plateout of fission products.
The proposal developed by the BWROG and adopted by the licensee would allow higher leakage limits (300 scfh total from four steam lines) and delete the TS requirements for the main steam LCS.
- 3. 1.2 Iodine Release Pathways following a LOCA, three potential release pathways exist for main steam leakage through the HSIVs:
(1) Main steam drain lines to the conden'ser with delayed release to the environment through the low pressure turbine seals.
E1 X'<
wl P
(2) Turbine bypass lines to the condenser with delayed release to the environment through the low pressure turbine seals.
(3) Hain steam lines through the turbine stop and control valves and through high pressure turbine seals to the environment bypassing the condenser.
The consequences of leakage from pathways 1 and 2 will be essentially the same because the condenser can be used to process HSIV leakage.
The condenser iodine removal efficiency will vary depending on the inlet location of the bypass or drainline piping, but in either case, iodine will be removed.
For pathway 3, HSIV leakage through the closed turbine stop and control valves will not be processed via the condenser.
For this case, the high-pressure turbine (having a large internal surface area associated with the turbine blades) will remove iodine.
The staff believes that as long as either the turbine bypass or drainline:
leakage pathway is available, HSIV leakage through the closed turbine stop and control valves (pathway 3) will be negligible.
Essentially all of the releases will be through the main condenser because there will be no differential pressure in the HSL downstream of the HSIVs following the 'closure of the valves'urthermore, MSIV leakage through pathway 3, if any, will have been subjected to the same iodine-removal processes in the HSLs (up to turbine stop valves) as the other pathways.
The leakage will be further subjected to iodine removal by deposition on the high-pressure turbine internal surfaces.
Removal by the main condenser is not applicable in pathway 3.
The licensee has selected to utilize pathway 1 using the main steam piping and its drain piping and the condenser to mitigate the radiological consequences of an accident which could result in potential offsite exposures comparable to the dose reference values specified in 10 CFR Part 100.
The staff has accepted the licensee's proposed pathway.
In the calculation of the contribution to the LOCA dose, the staff assumed that one of the inboard isolation HSIVs failed to close, thus allowing contaminated steam to travel to the outboard valve.
The leakage through this outboard valve and the valve pairs in the other three steamlines were assumed to have a total leak rate of 300 scfh.
- 3. 1.3 Iodine Transport Hodel Basic chemical and physical principles predict that gaseous iodine and airborne iodine particulate material will deposit on surfaces.
Several laboratory and in-plant studies have demonstrated that gaseous iodine deposits by chemical adsorption and that particulate iodine deposits through a
combination of sedimentation, molecular diffusion, turbulent diffusion, and impaction.
Gaseous iodine exists in nuclear power plants in several forms:
elemental (I<), hypoiodous acid (HOI), organic (CH~I), and particulate.
In accordance with RG 1.3, the staff assumed 91,percent of iodine is in the '
~ ~
II elemental form (includes hypoiodous acid),
5 percent in the particulate
- form, and 4 percent in the form of organic iodides.
Each of these forms deposits on surfaces at a different rate, described by a parameter known as the deposition velocity.
The elemental iodine form, being the most reactive, has the largest deposition velocity, and organic iodide has the smallest.
- Further, studies of in-plant airborne iodine show that iodine (elemental and particulate) deposited on the surface undergoes both physical and chemical changes and can either be resuspended as an airborne gas or become permanently fixed to the surface.
The data also show that the iodine can change its form so that iodine deposited as one form (usually elemental) can be resuspended in the same or in another form (usually organic).
Conversion can be described in terms of resuspension rates that are different for each iodine species.
Chemical surface fixation can similarly be described in terms of a surface fixation rate constant.
The transport of gaseous iodine in elemental and particulate forms has been studied for many years and several groups proposed different models to describe the observed phenomena (References 12 through 16).
The staff used the model specifically developed by an NRC contractor (Reference
- 17) for iodine removal in BWR main steam lines and the main condenser following a LOCA.
The staff model treats the MSIV leakage pathway as a sequence of small segments for which instantaneous and homogeneous mixing is assumed, the mixing computed for each segment is passed along as input to the next segment.
The number of segments depends upon the parameters of the line and flow rate and can be as many as 100,000 for a long, large-diameter pipe and a low flow.
Each line segment is divided into five compartments that represent the concentrations of the three airborne iodine species, the surface that contains iodine available for resuspension, and surface iodine that has reacted and is fixed on the surface, The staff's model considers three iodine species:
elemental, particulate, and organic.
A fourth species, hypoiodous
- acid, was considered for the purpose of the staff's model to, be a form of elemental iodine.
All iodine in the segment undergoes'adioactive
- decay, The resulting concentration from each segment of the deposition'compartment serves as the input to the next segment.
The GE model, as wel:l,as the one developed and used by the staff, is based on time-dependent temperature adsorption phenomena with instantaneous and perfect mixing in a given volume.
Both models use the same MSIV leakage pathways.
- However, they differ in the treatment of buildup of iodine in the main steam lines and condenser.
GE assumed steady state iodine in equilibrium in a large volume while the staff model assumed transient buildup of iodine in a finite number of small volumes.
The staff does not consider these differences to be significant since the staff finds that the resulting iodine deposition and removal rates in the main steam lines and condenser are in good agreement.
'4 C%
-px
efl The staff's.transport model also assumed iodine transport through the condenser as a dilution flow rather than the plug flow as in the steam lines.
The staff assumed that the iodine input into the condenser mixes instantaneously with a volume of air in the condenser and that the diluted air exhausts at the same time and same rate as the input air (HSIV leakage) flows into the condenser.
The staff developed the equations for iodine deposition velocities, resuspension
- rates, and surface fixation rates as a function of temperature using published data found in the literature.
The equations and data are contained in the contractor's report (Reference 17).
The equation for the deposition velocity of elemental iodine is based on the least-squares fit to the available data.
Deposition velocity equations for HOI and organic iodine are based on the values at 30 'C; due to the lack of data at elevated temperatures, their temperature dependence is assumed to be similar to elemental iodine.
Resuspension and fixation equations as a function of temperature are based on measurements available in the literature at ambient temperature.
The staff assumed that resuspension and fixation rates will increase with increasing temperature.
The technical references and the GE and staff models indicate that particulate and elemental iodine would be expected to deposit on surfaces with rates of deposition varying with temperature,
- pressure, gas composition, surface
- material, and particulate size.
Therefore, the staff believes that an appropriate credit for the removal of iodine in the HSLs and main condensers should be provided in the radiological consequence assessment following a design-basis accident.
Consequently, the staff accepted the licensee's proposed elimination of the LCS and allowed a higher HSIV leakage providing an appropriate credit for the removal of iodine in the HSLs and condenser.
Sections III(c) and VI of Appendix A to 10.CFR Part 100 require that structures,
- systems, and components necessary to ensure the capability to mitigate the radiological consequences of accidents that could result in exposures comparable to the dose guidelines of Part 100 be designed to remain functional during and after a safe-shutdown earthquake (SSE).
- Thus, the HSL, portions of its associated
- piping, and the main condenser are required to remain functional if credit is taken for deposition of iodine and if the SSE occuls.
Consequently, the staff's past practice has been to classify these components as safety-related and seismic Category I.
In addition, Appendix A to 10 CFR Part 100 requires that the engineering method used to ensure that the safety functions are maintained during and after an SSE involve the use of either a
suitable dynamic analysis or a suitable qualification test.
For the purpose of providing a credit for iodine holdup and plateout, the staff's model requires that the main steam piping (including its associated piping to the condenser) and the condenser remain structurally intact following an
- SSE, so they can act as a holdup volume for fission products.
By the term "structurally intact," the staff assumes the steamline will retain sufficient structural integrity to transport the relatively low flow rate
~ ~
~ 'K c'
W. I
%r'
(g 2 ft /min) of NSIV bypass leakage throughout the steam lines and condenser.
The staff considers, in its radiological consequence assessment, that the condenser is open to the atmosphere via leakage through the low pressure turbine seals.
Thus, it is only necessary to ensure that gross structural failure of the condenser will not occur.
- 3. 1.4 Control Room Habitability The staff has previously evaluated the control room operator doses following a postulated LOCA in accordance with SRP Section 6.4 and found the calculated doses were within the guidelines of SRP Section 6.4 (OL-SER Section 6.4).
In this evaluation, the staff considered the fission product releases from the low pressure turbine seal due to the HSIV leakage (up to 300 scfh total) through the MSIV drain lines and the main condensers.
The staff assumed a
ground level release of airborne fission products from the turbine building as a fission product diffusion source and the control room emergency air intake as a single point receptor.
The staff's recalculated control room operator doses following a postulated LOCA are listed in Table 1 and the staff finds that the recalculated whole-body and equivalent organ doses (thyroid) are still within the guidelines of.
SRP Section 6.4, and therefore, the staff's conclusions stated in the OL-SER Section 6.4 are not affected and remain the same.
- 3. 1.5 Variations Between Staff and Licensee Calculated Doses The following table shows both the staff's and the licensee's calculated dose contributions to the thyroid (in Rem) from an HSIV leak rate of 300 scfh:
2-hour EAB 30-day LP2 30-day Control Room Licensee
- 0. 11 12.1 4.95 Staff 10.3 51.6 3.03 The staff's calculated 2-hour dose at the exclusion area boundary is significantly higher than that calculated by the licensee.
The main reason for this discrepancy is that the staff gave no credit for deposition and holdup in the main steam piping between the reactor vessel and the outboard HSIV.
Crediting that section of the main steam system would significantly increase radionuclide transport time to the low pressure tur bine seals.
The increased transport time would delay any releases from the low pressure turbine seals and, thus, significantly reduce the 2-hour dose at the EAB.
The increased radionuclide transport time from crediting the additional main steam piping will have little impact on the 30-day dose at the low population zone boundary by virtue of the long duration of 'assumed exposure.
- However, the atmospheric dispersion factors utilized by the staff for calculating the 30-day dose at the LP2 were more conservative than those used by the licensee.
Applying the licensee's atmospheric dispersion factors to the staff's
l~
tw calculated iodine releases would yield a 30-day dose at the LPZ of approximately 8 rem.
Therefore, good correlation can be shown between the staff's and the licensee's calculated iodine releases over 30 days.
The correlation is also supported by the control room operator doses which were calculated by the staff and the licensee utilizing the same atmospheric dispersion factors.
3.1.6 Findings Several technical references (Reference 12-16) including an NRC contractor's report (Reference
- 17) indicate that particulate and elemental iodine would be expected to deposit on surfaces with rates of deposition varying with temperature,
- pressure, gas composition, surface material, and particulate size.
The staff, therefore, concludes that an appropriate credit for the removal of iodine in the main steam lines and main condensers should be provided in the radiological consequence assessment following a DBA.
The staff has reviewed the licensee's analysis and has performed an independent reassessment of the radiological consequences resulting from the:.
MSIV leakage transport pathway described in this SER.
The calculated thyroid.
and whole-body dose are listed in the revised Table 1.
Based on the above evaluation and the calculated radiological consequences shown in Table 1, the staff concludes that the MSIV leak rate limit of 300 scfh total from four main steam lines and the proposed deletion of the TS requirements for the MSIV Leakage Control System are acceptable.
The staff further concludes that the existing distances to the exclusion area and to the low population zone boundaries of SSES, in conjunction with the remaining engineered safety features provided at the Susquehanna Steam Electric Station are still sufficient to provide reasonable assurance that the radiological consequences of a postulated LOCA will be within the dose reference values set forth in 10 CFR Part 100 and the control room operator dose limits specified in GDC-19 of Appendix A to 10 CFR Part 50.
~ ~
Table 1
Radiological Consequences of Loss-of-Coolant Accident (rem)
Containment Leakage*
00- 02 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> 00- 08 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> 08-24 hours 24-96 hours96-720 hours Thyroid Whole Body EAB LPZ 218 5.8 43.8 32.6 66.5 54.4 1.42 1.16 0.79 0.40 Thyroid Whole Body EAB LPZ Total containment leakage ECCS component leakage*
MSIV leakage Total 218 0.2 10.3 229 5.8
<0.1 3.9 9.8 197 0.16 51.6 249 3.77
<0.01 0.65
~Th roid Control Room Operator Doses (rem) 14.8
~Whole Bod 0.9
- From Table
- 15. 1 of NUREG-0776, Susquehanna OL-SER Table 2
Assumptions Used to Evaluate the Loss-of-Coolant Accident, MSIV Leakage Contribution Core Thermal Power (MWt):
Core Radionuclide Fractions Released to Drywell (X)
Noble Gases:
Forms of Iod'ine Species (X)
Elemental:
Organic:
Particulate:
3441 100 25 91 4
5 Iodine Dose Conversion Factors:
HSIV Total Leak Rate:
Containment Free Volume (ft ):
Control Room Free Volume (ft ):
Control Room Intake Flow (cfm):
Control Room Intake Filter Iodine Removal Efficiencies (X):
Elemental:
Organic:
Particulate:
ICRP-30 300 scfh 3.89 x 10 1.10 x 10 5810 99 99 99 Unfiltered Control Room Inleakage (cfm):
Control Room Geometry Factor:
Control Room Iodine Protection Factor:
Atmospheric Dispersion Factors (sec/m
)
0 -
2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, Exclusion Area Boundary:
0 - 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />, Low Population Zone:
8 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, Low Population Zone:
1 4 days, Low Population Zone:
4 - 30 days, Low Population Zone:
Effective Control Room Atmospheric Dispersion Factors (sec/m )
0 - 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />s:
8 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />s:
1 -
4 days:
4 - 30 days:
10 24 85 1.1 x 10 5.2 x 10 3.6 x 10 1.6 x 10
'.3 x 10 3.32 x 10 1.96 x 10 7.64 x 10 2.19 x 10
S la~
W l'
I 3.2 Seismic Mechanical Evaluation 3.2. 1 Background As discussed
- above, PPKL proposed to use the main steam piping, drain lines, and main condenser as an alternate means for MSIV leakage treatment.
Because the original design basis of certain main steam piping and components is not Seismic Category I, PPKL has performed evaluations and seismic verification walkdowns to demonstrate that the main steam system piping and components which comprise the alternate leakage treatment (ALT) system are seismically rugged and are able to perform the safety function of an MSIV leakage treatment system.
The licensee also performed a design evaluation of the seismic adequacy of the turbine building (TB) which houses the ALT system, The structural integrity of the TB is important to the issue of MSIV leakage because a non-seismically designed TB should be capable of withstanding the earthquake and not degrade the capability of the ALT system,
~4 The BWROG report, NEDC-31858P, Revision 2, has not been approved by the staff;.
- However, based on a preliminary review to date, the staff has found the BWROG:
approach of utilizing the earthquake experience-based methodology, supplemented by plant-specific seismic adequacy evaluation, an acceptable basi's to demonstrate the seismic ruggedness of non-seismically analyzed main steam system piping and condensers.
The staff, therefore, has relied upon portions of the earthquake experience
- data, in the BWROG Report, for piping and main condenser in support of this safety evaluation.
It should be noted that there are no provisions in the Susquehanna Final Safety Analysis Report (FSAR) and the staff's safety evaluation associated with the facility operating license that would permit the use of experience data as a means of seismic qualification for piping systems and components.
However, requiring the non-seismically analyzed portions of the main steam system piping and components to meet Seismic Category I requirements would not be practical because modifications required to upgrade the system to Seismic Category I requirements can not be justified from the cost-benefit standpoint.
The BWROG has retained Earthquake Engineering, Inc.
(EgE) as a consultant to conduct a review of the earthquake experience data on the performance of facility piping and condensers.
The study summarized the data on the performance of main steam system piping and condensers in primarily non-nuclear facilities which experienced strong motion earthquakes.
In addition, it compared these piping systems and condensers with the piping systems and condensers typically used in GE boiling water reactors (BWRs) in the United
- States, The result of the comparison appears to support the BWROG contention that main steam piping and condensers employed in GE BWRs would maintain pressure boundary integrity during a Design Basis Earthquake (DBE).
According to EgE, based on past earthquake experiences, welded steel piping and condensers designed and constructed to normal industrial practices (e.g.,
ANSI B31. 1 and Heat Exchange Institute (HEI) Standard, respectively) have been
~ ~
l
/
I
found to be seismically rugged and not susceptible to a primary collapse mode of failure as a result of the seismic vibratory motions experienced at sites examined in the earthquake database.
The earthquake experience is derived from a database that includes the seismic performance of power plant units and industrial facilities in actual earthquakes.
The above BWROG Report notes that a relatively small number of seismically-induced piping failures have occurred due to excessive relative support movements or seismic interactions.
The primary components to be relied upon for the proposed ALT system are the main turbine condenser and the primary drain pathway piping which consists of the drain lines that originate in the steam tunnel just downstream of the outboard HSIVs and terminate at the High Pressure (HP) Condenser.
Other potential drain pathways, which are not credited in the radiological dose calculation, are those originating from the main steam lines in the turbine building just upstream of the Hain Stop Valves (MSVs) and discharging into the HP Condenser.
The condenser forms the ultimate boundary of the ALT system.
Boundaries upstream of the condenser were established by utilizing existing
- valves, and were used to limit the extent of the seismic verification walkdown.
These valves were selected using the criteria outlined in the BWROG Report and documented in PP&L Engineering Studies,
- Analyses, and Evaluations
-'SEA),
SEA-HE-423, "HSIV Leakage Seismic Verification Boundary Determination'tudy, SSES Unit 1" and SEA-NE-424, "HSIV Leakage Seismic Verification Boundary Determination
- Study, SSES Unit 2."
3.2.2 Reliability of Boundary Valves In Reference 6,
PP&L identified that there are two motor-operated valves associated with the primary drain line pathway of which one is normally open and the other is designed to fail safe upon loss of offsite power.
The F020 valve is the safety-related normally open valve that is designed to fail safe, while the F021 valve is normally closed and is required to be open to establish the primary flow path to the condenser.
The F021 valve will be powered from a bus that is supplied from two independent offsite power
- sources, and a reliable diesel generator.
The F021 valve will also be included in the IST program and stroke tested (open) once per cycle.
The F021 valve operator has been evaluated to function under postulated accident conditions.
In Reference 11, PP&L identified that, in addition to the F020 and F021 valves, there are three normally open motor-operated boundary valves that will need to be closed when the condenser pathway is used to treat the MSIV leakage.
These are HV-10107 to Steam jet Air Ejector, HV-10109 to Steam Seal Evaporator, and HV-10111 to Reactor Feed Pump Turbines.
PP&L stated that these latter valves are also boundary valves and their reliability is established based on the same factors addressed for valve F021 (i.e.,
independent power sources, inclusion in the IST program, and evaluation of the operators to function under accident conditions).
Based on the above, the staff believes the licensee has provided sufficient basis to ensure that the valves and the pathway will function as required to establish the primary NSIV leakage pathway to the condenser.
3.2.3 Seismic Verification Walkdowns The ALT system consists of the main steam piping (beyond the outboard HSIVs),
the steam drain lines, the condenser, and interconnected piping.
The ALT
- system, in general, is not seismically analyzed as this analysis was not required in the original licensing basis of either unit at Susquehanna.
In order to confirm the functional capability of the ALT system, the licensee has performed seismic verification walkdowns for Susquehanna Units 1
& 2.
The purpose of the walkdowns was to ensure that the ALT system falls within the bounds of the design characteristics of the seismic experience database as discussed in Section 6.7 of the BWROG Report.
Specifically, the walkdowns were performed to
( 1) verify that Susquehanna plant features have attributes similar to those in the earthquake experience database that have demonstrated good seismic performance, (2) verify general conformance of pipe support spans to the requirements of ANSI 831. 1, and (3) examine the ALT system from the outboard HSIVs to the condenser to identify potential seismic vulnerabilities considering those structural details and causal factors that resulted in component damage at database plants.
The walkdowns focused on piping systems which were not seismically analyzed;
- however, those systems which are seismically analyzed, were also examined to identify any anomalies that may have gone undetected during the original construction.
The potential vulnerabilities which were identified as "outliers" include categories such as support failure, failure of non-seismically designed plant features (II/I), proximity and impact, and differential seismic anchor motion on piping systems.
PP&L's Harch 28, 1995 (Reference
- 3) submittal presents a complete list of the outliers identified during the walkdowns and their resolution and modification status.
These outliers have been either evaluated or analyzed by PP&L to demonstrate acceptability as-is, or to implement plant modifications to resolve the concerns.
Where analysis was used to resolve the outliers, the evaluation for seismic loads was based on 5X of critical damping floor response spectral curves that were extrapolated from the existing 0.5N and 1.0% of critical damping spectra curves derived from the SSES DBE, anchored at 0. lg peak ground acceleration.
In addition to the resolution of the outliers, seismic margin assessment of a representative sample of pipe supports on the main drain line has also been conducted, as part of the bounding seismic analysis performed by the licensee for. a representative main steam drain piping in the ALT system.
As a result of the walkdowns and the subsequent evaluations (Reference 3),
PP&L identified the need for the following modifications:
Unit 1
(1) Hain Steam from HSIV to Stop Valve:
install restraints as necessary for the hoists above HSIV A to 0;
~ j IB gag (2) Main Steam Drip Leg Drains:
add a new dead load support; (3) Stop Valve Seat Drains to Condenser:
modify Springs SP-MSV-IOO-Hl, H2, H3,
& H4; and (4)
HPCI Steam Drain to Main Steam Drain Header:
modify Supports SP-EBD-114-H24
& H25.
Unit 2 (1) Main Steam Drain to Condenser:
modify Supports H17
& H19 (2) Main Steam Bypass to Condenser:
modify platform; (3) Main Stearp Drip Leg Drains:
modify insulation on 4" GBD and 10" HBD Line; (4) Main Steam Drip Leg Level Instrumentation:
modify insulation on 1" DBB &,
16" HFD & 14" HBD Line; (5) Main Steam Averaging Manifold to Pressure Transducer Panel:
modify Supports SP-DCD-212-H2603
& H2604; and The licensee has committed to complete the above modifications prior to the restart of each unit of the plant from its respective upcoming refueling outages.
In addition, the licensee also indicated that further walkdowns will be performed on Main Steam Pressure Sensing
- Lines, and that duct supports will be installed prior to startup, if none exist.
3.2.4 Validation of Earthquake Experience Database The staff reviewed the earthquake data to assure that the vibratory ground motion, experienced at each of the facilities with piping and equipment being used as a surrogate for that at
The ideal case for the estimation of ground motions would be to have actual recordings of the earthquake ground motion made at each of the facilities.
PP&L has indicated (Reference
- 4) that only about 25 percent of the ground motion estimates in the database in the BWROG Report are from actual instrument recordings at (or near) a facility site.
For the other facility-earthquake pairs in the database, the ground motion estimates were extrapolated from instruments located at some distance from the facilities or were made by speculation based on nearby damage or other arguments (Reference 4).
The ground motion from an earthquake at a particular site is a function of the earthquake source characteristics such as the magnitude, focal mechanism, radiation pattern, stress drop, location of asperities and fault rupture
- history, and depth and orientation of the fault.
It is also a function of the distance of the facility to the fault and the propagation properties of the rocks between them.
The geology immediately under the facility site can-also have a large effect on the amplitude and frequency content of the ground
~ 1 I
motion.
Two of the more appropriate methods of estimating earthquake ground motion, where there are no nearby recordings are:
by calibrated numerical modeling of the fault rupture and the wave propagation
- process, and by the use of empirical attenuation relationships obtained from the statistical analysis of large sets of earthquake data.
It has been observed from numerous earthquakes that the variation of peak ground motion values within short distances can be substantial.
Consequently, applicability of inferred ground motion parameters needs to be carefully evaluated.
PP8L has stated that the SSES condenser design is typical of those at the Hoss Landing Steam Plant, which experienced the Lorna Prieta 1989 earthquake, and the Ormond Beach Generating
- Station, which experienced the Point Hugu 1973 earthquakes They also stated that the SSES main drain and its associated piping as well as the interconnected piping systems are similar to the commercial piping at the Hoss Landing Steam Plant, which experienced the Lorna Prieta 1989'arthquake, the Ormond Beach Generating
- Station, which experienced the Point Mugu 1973 earthquake, the El Centro Steam Plant, which experienced the Imperial Valley 1979 earthquake, the Valley Steam Plant, which experienced the San Fernando 1971 earthquake, and the PALCO Co-generation Plant which experienced the Cape Mendocino earthquakes of 1992.
In order to allow the NRC staff to evaluate the adequacy of the ground motion estimates made for each of the above facilities, the staff requested additional information from PP&L (Reference 5).
The following information was requested for each of the facilities in the earthquake experience database used to demonstrate the seismic adequacy of the Susquehanna ALT system.
1.
The name, location, and foundation geology (i.e. rock, deep soil, shallow soil) of the facility.
2.
The name,
- date, time, epicenter, magnitude and distance to the facility of the earthquake.
3.
The five percent of critical damping response spectra of the ground motion estimated for the facility due to the earthquake.
4.
The method used to estimate the ground motion at the facility. If the ground motion is based on actual ground motion recordings, provide the location and foundation geology of the recording station and its distance from the facility and its distance to the closest part of the fault rupture.
If the estimation is based on a method other than an actual recording of the earthquake ground motion or if the recording station is not collocated with the facility, describe the method used to estimate the ground motion in detail and provide any ground motion attenuation equations which may have been used to obtain the estimate.
The PP8L's response (Reference
- 6) to the above RAI provided some of the information requested.
A subsequent telephone conference with PP8L resulted in a letter from PP8L (Reference
- 4) supplementing the response.
This allowed
\\ ~
F~
k, ci)gr the staff to make independent analyses of the suitability of the ground motion for the earthquake-facility pairs which PP&L has indicated it relied on to demonstrate the seismic adequacy of the Susquehanna ALT system.
The
- E0E, Inc. ground motion estimate at the El Centro Steam Plant from the Imperial Valley 1979 earthquake was based on a recording made at a U.S.
Geological Survey (USGS) strong ground motion station about 1 kilometer from the facility.
Because of the density of seismic recordings in that area and the distribution of the ground motion, the staff concluded that the estimated ground motion for the site is significantly larger than the SSES OBE and is, therefore, appropriate for use in establishing the seismic capacity of the SSES piping and equipment similar to that in the El Centro Steam Plant.
The
- EgE, Inc, ground motion estimate at the Valley Steam Plant from the San Fernando 1971 earthquake was based on an extrapolation of data from a relatively distant location (8
km from the plant).
In 1988, the USGS performed studies to estimate the ground motion at selected sites from the San Fernando 1971 earthquake in support of the NRC's resolution of the USI A-46 program (Reference 7),
Figure 1 is a plot of the SSES DBE response spectrum,:
and the E(E, Inc.
and USGS estimates of the Valley Steam Plant ground motion response spectrum from San Fernando 1971 earthquake.
The USGS spectrum, whil'e lower than the E(E, Inc. spectrum, is significantly higher than the SSES OBE spectrum.
As in the resolution of A-46 ground motion issue, the staff considered the USGS estimate to be the characterization of the ground motion at the Valley Steam Plant from the San Fernando 1971 earthquake and is, therefore, the appropriate ground motion estimate for use in establishing the seismic capacity of the SSES piping and equipment similar to that in the Valley Steam Plant.
The
- EgE, Inc. ground motion estimate at the Moss Landing Steam Plant from the Lorna Prieta 1989 earthquake is based on a study performed by Pacific Gas and Electric Company (PG&E) (Reference 8), the owner of the Hoss Landing Steam Plant.
PG&E provided a copy of the report for the NRC staff's use.
The analysis performed by PG&E was found to be technically sound and comprehensive.
The staff, therefore, concluded that its estimate of the ground motion is appropriate for use in establishing the seismic capacity of the SSES piping and equipment similar to that in the Hoss Landing Steam Plant.
The ground motion estimate at the PALCO Co-generation Plant from the Cape Mendocino magnitude 7 earthquake of 1992 is based on a recording at a
California Department of Mines and Geology station in Rio Dell at some distance from the facility.
The NRC staff, using two ground motion estimation formulas which are based on the statistical analyses of large sets of empirical data, made its ow'n estimate of the ground motion at PALCO Co-generation Plant from the Cape Mendocino 1992 earthquake.
Figure 2 contains a
- spectrum, the
- EgE, Inc.
and the two NRC estimates of the PALCO Co-generation Plant response spectrum from the Cape Mendocino 1992 earthquake, The NRC spectra, while lower than the EOE, Inc.
The staff considered the lower bound envelope of the NRC estimates to be the appropriate characterization of the ground motion at the PALCO Co-generation Plant from the Cape Mendocino 1992 earthquake for use in establishing the seismic capacity of the SSES piping and equipment similar to that in the PALCO Co-generation Plant.
In Reference 4,
PP&L stated "The E(E ground motion estimate at the Ormond Beach Generating Station from the Point Mugu 1973 earthquake is based on typical California attenuation relationships and independently based on observation and measurement of pipe displacements.
The data provided establishes that the documented peak ground accelerations for the Ormond Beach Generating Station are substantially less than the other plants included in this evaluation."
Figure 6 of Reference 1 shows PP&L's comparison of the SSES ground response spectrum to PP&L's characterization of the database spectra.
PP&L's spectrum for the Ormond Beach Generating Station is a straight line between the frequencies of 25 and 30 Hertz at an acceleration level of 0. 15 g, which is higher than the SSES design ground motion of 0, 1 g, The NRC staff, using two ground motion estimation formulas which are based on the statistical analyses of large sets of empirical data, made its own estimate of the ground motion at the Ormond Beach Generating Station from the Point Mugu 1973 earthquake.
Figure 3 contains a plot of the SSES DBE response
- spectrum, the PP&L and the two NRC estimates of the ground motion at the Ormond Beach Generating Station from the Point Mugu 1973 earthquake.
The staff considered'he lower bound envelope of the NRC estimates to be the appropriate characterization of the ground motion at the Ormond Beach Generating Station from the Point Mugu 1973 earthquake for use in establishing the seismic capacity of the SSES piping and equipment similar to that in the Ormond Beach Generating Station.
The NRC estimate is lower than the SSES DBE spectrum at frequencies less than
- 1. 1 Hertz.
Therefore, the Ormond Beach Generating Station can only be used as an analog for SSES for structures,
- systems, or components that do not have vibrational modes with resonances below l. 1 Hertz.
Based on the independent analysis of the earthquake experience
- database, the staff concluded that SSES DBE demand is well below the seismic ground motion which was experienced at the facilities discussed above except as noted for the estimated ground motion at the Ormond Beach Generating Station from the 1973 Point Mugu earthquake.
Consequently, the use of the database with the exceptions noted is acceptable for this SSES license amendment request.
3.2.5 Comparison of SSES and Experience Data The staff reviewed the information provided in the licensee's November 21, 1994 submittal (Reference 1),
and found that additional information related to piping and pipe supports would be required from the licensee in order for the staff to complete its review.
During the January 24,
- 1995, meeting with PP&L, the staff discussed the extent of the additional information that would be required.
The staff also requested the licensee to perform a bounding dynamic analysis of a representative drain line to address compliance to Appendix A of 10 CFR Part 100.
The staff's RAIs were subsequently sent to the licensee on
a ~
el g4 4
+\\.
f w
4 l~
February 3 (Reference 9),
and March 3, 1995 (Reference 3).
The licensee, in turn, provided its responses to the above staff requests in the letters of February 21 (Reference 11),
March 28 (Reference 3),
and April 10, 1995 (Reference 6).
In Reference 3, the licensee provided a database for main steam and process piping at the above mentioned plants, i.e., Valley Steam Plant, Ormond Beach Power Plant, El Centro Steam Plant, and Hoss Landing Power Plant.
Data provided included pipe diameter,
- schedule, wall thickness and pipe diameter-to-thickness (D/t) ratio.
The licensee also provided a data comparison between the SSES ALT system piping and the piping of the above selected database facilities.
The SSES data were presented on a system-by-system breakdown, through the ALT path, that included both seismically and non-seismically analyzed systems.
The data were presented categorically for pipe
- diameter, schedule, wall thickness and pipe diameter-to-thickness ratio.
The staff found the above database of the facilities'rocess piping to be an adequate upgrade of the original database provided in the BWROG Report (Reference 2).
The staff also found that the Susquehanna ALT piping data are mostly enveloped by the experience database discussed in Reference 3.
For the.
cases where the D/t ratios of the Susquehanna ALT piping are not enveloped bye'he database piping, the Susquehanna D/t ratios are favorably smaller than the respective values of the database piping.
For the 1/2" diameter main steam drain line at Susquehanna, no counterpart seismic experience data is available.
- However, the associated D/t ratio was found to be favorably smaller than those of the other database pipe sizes.
The staff determined that the upgraded database provided by the licensee is adequate for comparison with the corresponding Susquehanna ALT piping and is acceptable.
As indicated in Reference 6, the licensee has compared the structural characteristics of the SSES main condenser to those of similar database condensers which have experienced significant earthquakes as addressed in the BWROG Report.
The SSES condenser is made up of three shells:
high pressure, intermediate
- pressure, and low pressure units.
Each condenser shell is specifically compared to the database condensers from Moss Landing, Units 6 and 7, and Ormond Beach, Units 1
and 2.
The licensee stated that these condensers have physical arrangements and construction details similar to the SSES condenser and would function similarly in their responses to seismic excitations.
The licensee also provided the overall dimensions and weights for each of the three condenser
- shells, By comparison to the database condensers, the licensee stated that most of the physical features of the SSES condenser structure are either enveloped by, or less critical than, the database condensers, with one possible exception.
The SSES condenser is generally higher than the database condensers.
The laYger ratio of height to base width is likely to cause larger overturning moments
- and, hence, larger stresses in the shell.
The licensee did not consider the effects of this greater height to be critically significant, based on (1) the operating weight of each Susquehanna condenser shell in comparison to the shell side area is comparable to that of the database condensers,
- and, as a result, the shear stress in the shell plate would not be significantly greater than that of the database condensers under the same
s1
$A seismic load, and (2) the anchors for the SSES condenser assembly have been determined to have more than enough capacity to prevent overturning caused by the combined DBE seismic forces and operating loads.
Based on the above, the staff determined that the SSES HSIV ALT system components are generally enveloped by the database components, and that they possess sufficient capability to withstand the combined DBE seismic forces and operating loads.
3.2.6 Analyses for Alternate Leakage Treatment Pathway As indicated in Reference 1, the main steam lines from containment isolation valves to the turbine stop valves, the bypass piping from the main steam lines to the main condenser, the main steam drain line header from containment isolation valves to in-line pipe anchors, and portions of main steam branch connection lines to in-line pipe anchors were seismically analyzed.
These piping systems at SSES were designed in accordance with the requirements of ASNE Code Section III, Class 2,
1971 Edition including Winter 1972 Addenda, and ANSI B31. 1, 1973 Edition.
These piping systems were designed using reactor building and turbine building response spectra inputs of Operating Basis Earthquake (OBE) and DBE, in combination with other applicable design loads.
The analysis results satisfy the allowable limits specified for Class 2 pipes in the ASME Section III Code.
The licensee stated that the remaining portion of main steam drain and associated piping were analyzed for dead weight and thermal loads using a
combination of piping analysis and spacing criteria, without consideration of seismic loads.
These non-safety related pipes are generally composed of welded steel piping and standard support components, and are similar to piping found in the seismic experience database.
The system is predominantly supported for dead weight utilizing rod hangers, constructed from standard support catalog parts typically consisting of clamps, threaded rods, weldless eye nuts, turnbuckles, welding legs and are attached to either concrete or structure steel.
The objective of the assessment of the non-seismic main steam drain piping is to demonstrate that piping position retention will be maintained during a seismic event and hence provide assurance that the pipe supports will behave in a ductile manner and that all lines are free of known seismic hazards.
Ultimately, it will ensure that these SSES piping systems will perform in a manner similar to piping and supports that have been observed to demonstrate good seismic performance.
As stated by. PPLL in the above discussion, the non-seismically analyzed main steam drain and associated piping are generally bounded in diameter and diameter-to-thickness ratio by those installed in'he earthquake experience database facilities, as evidenced in the BWROG Report and the supplemental updated earthquake performance data discussed above.
PPKL has stated that upon completion of all necessary modifications, piping position retention and pressure boundary integrity will be maintained by the deadweight supports under normal and earthquake loadings.
sl I
l 4
I,
,p T
~,lh Iq Based on the above, the staff determined that the SSES non-seismically analyzed main steam system piping and condenser that will be used for the ALT system compared well with the earthquake experience
- database, and that the seismic verification walkdowns of the system and subsequent evaluations have addressed characteristics associated with the limited component damage situations observed at the database facilities.
The staff also determined that PPKL has taken proper measures to ensure resolution for all of the identified outliers.
3.2.7 Bounding Seismic Analysis During the January 24, 1995, meeting, and subsequently in the Harch 3,
- 1995, RAI (Reference 5), the staff requested that a bounding seismic analysis be performed for a representative main steam drain piping in the ALT system which had not been seismically analyzed.
This analysis is necessary in order to supplement the BWROG's earthquake experience methodology and to further demonstrate analytically that the proposed ALT piping system will maintain its functionality under the Susquehanna DBE.
The piping selected consists of the main steam, reactor core isolation cooling (RCIC),
and high pressure coolant injection (HPCI) turbine steam line drains from valves
- F019, F026, and F029, respectively, to the HP condensers.
The Unit 1 model envelopes approximately 283 feet of 4-inch schedule 120 piping which is supported by 23 hangers.
These hangers include anchor,
- spring, structural
- members, hanger rod and strut.
Four pipe supports were selected from each unit for the seismic margin evaluation.
The selection was based on an overview of the support configurations and the original design qualification.
The selected population, included both vertical and lateral restraint type supports.
Dead weight and operating mechanical
- loads, in addition to the seismic DBE
- loads, are accounted for in the dynamic analysis.
The actual piping stress and pipe support loads due to these loading combinations are calculated by performing HE-101 computer analysis.
The methodology utilized to demonstrate the seismic adequacy of the non-seismically-designed main steam drain lines is called Conservative Deterministic'ailure Hargin (CDFH),
as described in the EPRI report, EPRI NP-
- 6041, dated August 1991.
Although this methodology has not been approved by the NRR staff for licensing reviews involving Seismic Category I systems, the staff determined that, in consideration of the available safety margins demonstrated by PP&L, its employment to demonstrate the functional operability of the ALT system to be adequate, During the original design of the plant, seismic floor response spectra were generated, for 0.5%
and 1.0% of critical damping, to determine seismic anchor forces and displacements for the piping systems that are attached to the turbine building.
For the bounding analysis, 5% of critical damping floor response spectra were recommended by the above EPRI report.
These were obtained by extrapolation from the existing floor response spectra of 0.5% and
I
~%
\\
1.0X values.
The results of the bounding analysis were provided by PPKL in Reference 10.
It indicated that the pipe stresses are within the allowable limits for sustained
- loads, occasional loads as well as thermal expansion, with safety margins of 3.34, 2.47 and 3.95, respectively.
- Supports, which include steel support
- members, anchor plates,
- welds, and anchor bolts, were also evaluated and found to be within the allowable limits.
The staff found these seismic analysis results acceptable for providing confirmation to the seismic adequacy of the ALT system that was established on the basis of the earthquake database.
3.2 '
Seismic Dynamic Analysis of Turbine Building The SSES turbine building (TB) is entirely supported on competent rock with reinforced concrete retaining walls extending up to grade level (Reference 1).
As stated in the SSES FSAR section 3.7b.2.4 and in the staff's April 1981 safety evaluation report (SER (NUREG-0776)),
the seismic dynamic analysis of the TB was done assuming a fixed base.
The superstructure is framed with structural steel and reinforced concrete (RC), with exterior walls made of pre-cast RC panels except for the upper 30 feet (ft) which is metal siding.
Each of the two turbine generator units housed in the TB is supported on a
free standing RC pedestal extending down to the bedrock.
The DBE peak ground" acceleration at SSES is O.lg, and the OBE peak ground acceleration is 0.05g.
For the analysis, the ground motion was applied at the foundation level of the TB.
As stated in Reference 6,
PP8L did not perform a seismic re-analysis of the TB in connection with this license amendment request.
- Instead, PPKL utilized the results of the original seismic analysis of the plant.
The dynamic analysis of the TB was performed by the response spectrum method.
Separate analyses were made for the vertical and two horizontal directions to calculate
- shears, moments, and deflections.
Time history analyses were performed utilizing the two horizontal and one vertical models in order to calculate the floor response spectra (FRS).
During the original design of SSES, FRS curves were generated for O.SX and 1X of critical damping.
The FRS curves were broadened by +/-20 percent to account for the parametric variations associated with the structure. frequency, structure damping and the soil moduli.
For the purpose of the MSIV lice'nse
.amendment
- request, PPKL extrapolated the existing 0.5X and 1/ of critical damping FRS curves to generate the 5X of critical FRS curves by mainly using ghat is cal.led the power method.
This method enables the extrapolation, of the spectral acceleration
- values, frequency by frequency, using the spectral values from both the 0.5/
and the 1X of critical damping curves to determine the spectral values for the 5X FRS curves.
For the few locations where only one set of FRS curves (either for 0.5% or 1/ of critical damping) was available, PPKL used the square root method to generate the 5X curves.
The staff considered the licensee's procedures to generate the 5X of critical damping FRS curves for piping and equipment using the existing FRS curves reasonable and adequate for this MSIV license amendment.
Reference 6 states that the structural acceptance criterion for the building did not permit the material to reach its yield limit under the loading combination including the DBE.
The use of dynamic analyses in conjunction
oa
~ "c
C ~
-" ~ ~ M 1
with the no-yielding criterion ensures that the turbine building will remain elastic during a
DBE.
The staff concluded that the turbine building will withstand a
OBE and is adequate for this license amendment request.
3.2.9 Anchorage for piping As part of the previously stated bounding seismic analysis, PPKL performed piping anchorage evaluation for the selected eight representative supports.
PPEL stated in Reference 6 that pipe support loads resulting from the loading combination of dead weight, thermal expansion, and OBE were calculated and then compared with the anchorage capacity which was evaluated using Appendix C
to Generic Implementation Procedure (GIP) criteria established by the Seismic Qualification Utility Group (SQUG).
The comparison results indicated that the anchorage capacities were greater than the seismic demand.
The licensee also stated that no concrete cracking around ancho} bolts was found during recent walkdowns.
For the evaluation of the adequacy of equipment anchorage at older operating plants, the staff has accepted the GIP criteria for anchorage.
Based on this, the staff concluded that the anchorage for the ALT piping at Susquehanna is adequate.
3.2.10 Anchorage for Condenser As stated previously, the condenser is made up of three shells:
high pressure, intermediate
- pressure, and low pressure shells.
Each shell is independently supported on the concrete base slab of the turbine pedestal by six embedded plate assemblies.
Positive attachment is provided by anchor bolts and welds to the embedded plate assemblies.
Forces in the anchoring systems of these condenser shells were calculated for the DBE loading.
Capacities of the anchoring systems were also calculated.
The results indicated that the tension capacities of bolts in the three condenser shells are about two times the values of the demand capacities due to the
- OBE, and that the shear capacities of bolts are about four times the demand capacities.
Based on the
- above, the licensee determined that the overall anchor system of the SSES condenser was capable of withstanding the calculated OBE loads, in combination with operating loads.
Based on its review of the licensee's information, the staff concluded that the condenser anchorage is adequate.
3.2. 11 Findings Based on the above evaluation, the staff concludes that upon completion of the plant modifications necessary for the identified outliers, there is reasonable assurance that the Susquehanna main steam lines, main steam drain lines, condenser, and associated interconnected piping and supports will be seismically adequate for the proposed HSIV ALT system.
The staff's conclusion is based on (1) the staff's independent analysis of the earthquake experience database confirmed that the DBE demand at SSES is well below the seismic ground motion that was experienced at the facilities i.n the earthquake experience database except for the estimated ground motion at the Ormond Beach Generating Station from the 1973 Point Nugu earthquake at frequencies below
- 1. 1 Hertz, (2) the Susquehanna main condenser is generally enveloped by the condensers in the earthquake experience
- database, and that the condenser assembly has suffi'cient anchorage
- capacity, (3) the majority of the main steam system piping was seismically analyzed as part of the initial design of the
- plant, (4) the non-seismically analyzed ALT pipes are represented by those in the earthquake experience database that demonstrated good seismic performance, (5) the bounding seismic analysis performed for the non-seismic portion of main steam drain lines indicated adequate safety margins for piping stresses and support loads, and (6) the turbine building has adequate capability to withstand the DBE loads.
The staff, therefore, concludes that the licensee's proposed ALT system complies with Appendix A of 10 CFR Part 100 and is acceptable.
It should be noted that the staff's acceptance of the experience-based methodology as presented by the BWROG and PPSL is restricted to its application for ensuring the pressure boundary integrity and functionality of the HSIV alternate leakage treatment system.
The staff's acceptance of the methodology for this application is not an endorsement for the use of the experience-based methodology for other applications at Susquehanna.
3.4 Plant S stems Evaluation The proposed HSIV leakage alternate (alternate to the existing HSIV-LCS and alternate to RG 1.96) drain pathway is considered the primary success (credited) pathway for "treating" HSIV leakage following a LOCA and employs a
HSL drain line downstream of the NSIVs.
There are two motor operated valves (HOVs) in series in this line between the HSLs and the main condenser.
Both valves must be open to establish the required drain path.
The first (upstream)
HOV, F020, is normally open and will fail "as-is" on a loss of power.
The second (downstream)
NOV, F021, is normally closed (with a small bypass orifice around the valve to allow drainage during normal operation) and is required to be opened following the design basis LOCA to establish a drain path to support the radiological analysis.
Both valves are powered from Class IE sources.
The staff requested the licensee to address the single failure of this downstream valve to open on demand, due to a valve or power supply failure.
In its Hay 24, 1995 submittal, the licensee stated that the downstream valve is powered from a bus which is supplied from two independent offsite sources and a diesel generator providing a highly reliable power source to the valve.
To increase the reliability of the MOV itself, the valve will be included in the Susquehanna inservice test (IST) program.
The valve will be stroke tested (open) once per cycle in accordance with the program.
Engineering evaluations of the F021 valve operator have also been performed to verify the valve's capability to function under the postulated accident conditions.
However, given that the valve may be highly reliable, the licensee; nonetheless, evaluated the effects of a failure of the valve to open and demonstrated that other adequate (secondary) flow paths would still be available, The licensee verified there are a number of different orificed pathways that are included in the boundary of the NSIV leakage alternate drain pathway that would be available to convey HSIV leakage to the isolated condenser if the downstream valve (F021) fails to open.
None of these secondary drain paths require the opening of any valves.
These "backup" or secondary drain paths provide orificed flow pathways, which ensure that even with the failure of a valve in the primary flow path, flow will be directed to the main condenser at the same or lower elevation as that assumed in the radiological dose calculation.
The radiological analysis did not take credit for these open pathways.
Therefore, these backup pathways will ensure sufficient flow to the main condenser and will act to reduce the radiological impact to within the regulatory limits.
Thus the backup paths will convey essentially all of the MSIV leakage to the main condenser.
Consequently, the radiological dose assessment for these backup pathways should be equivalent to the dose assessment for the primary path.
Additionally, the licensee has committed to update the Operating and/or Emergency Operating Procedures as necessary to address the alternate and backup leakage treatment methods.
Based on the above, the staff concludes that the proposed design provides a
reliable leakage treatment method which, overall, satisfies the single failure criterion of GDC 41, "Containment Atmosphere Cleanup."
The staff; therefore, concludes the proposed design is acceptable and the TSs associated with the LCS can be deleted from the plant TSs.
The licensee further proposed new requirements in TS Section 3.6. 1.2 related to restoration of acceptable leak rates if any of the proposed limits are exceeded.
The new requirements basically require that if any single MSIV leakage rate exceeds 100 scfh, it will be repaired and retested to meet a leak rate limit of 11.5 scfh per valve (the current criterion for leakage) and that the maximum total leak rate will be restored to less than or equal to 300 scfh whenever the 300 scfh limit is exceeded.
The staff concludes that this new requirement will restore the leakage rates to values that are consistent with the revised radiological analysis and is; therefore, acceptable.
3.0 STATE CONSULTATION
In accordance with the Commission's regulations, the Pennsylvania State official was notified of the proposed issuance of the amendments.
The State official had no comments.
4.0 ENVIRONMENTAL CONSIDERATION
The amendments-change a requirement with respect to installation or use of a facility.component lo'cated within the restricted area as defined in 10 CFR Part 20.~,.The NRC staff has determined that the amendments involve no significant in'crease in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure.
The Commission has previously issued a proposed finding that the amendments involve no significant hazards consideration, and there has been no public comment on such finding (60 FR 503),
Accordingly, the amendments meet eligibility criteria for categorical exclusion set forth in 10 CFR
~
cw 4.4 51.22(c)(9).
Pursuant to 10 CFR 51.22(b) no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendments.
- 5. 0 CONCLUSION The Commission has concluded, based on the considerations and findings discussed above, that:
(1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed
- manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendments will not be inimical to the common defense and security or to the health and safety of the public.
Principal Contributors:
A.
Lee R.
Rothman J.
Ha R.
Pichumani S.
Boynton W.
LeFave CD Poslusny Date:
August 15, i995 REFERENCES 2.
3.
5.
6.
7.
8.
9.
Letter for R.
G.
- Byram, PP8L, to Document Control Desk, NRC, dated November 21, 1994.
General Electric Nuclear Energy, "BWROG Report for Increasing HSIV Leakage Rate Limits and Elimination of Leakage Control Systems,"
NEOC 31858P Revision 2, dated September 1993.
Letter from R.
G.
- Byram, PP&L, to Document Control Desk, NRC, dated Harch 28, 1995.
Letter from R.
G,
- Byram, PP8 L, to Document Control Desk, NRC, dated May 24, 1995.
Letter from C. Poslusny, Jr.,
NRC, to Robert G.
- Byram, PP&L, dated March 3, 1995.
Letter from R.
G.
Byram; PP&L, to Document Control Desk, NRC, dated April 10, 1995.
- Campbell, K.
W.
and J.
C. Tinsley, Estimation of Selected free-field earthquake surface response spectra at selected sites in California and
'entral Chile, U.S, Geological Survey, April 1988.
Memorandum from Yi-Ben Tsai, PG&E Geosciences, to N. J. Harkevich, PG8E Civil Engineering, dated August 12, 1992.
Letter from C. Poslusny, Jr.,
NRC, to R, G.
- Byram, PP&L, dated February 3, 1995.
10.
12.
13
'4.
15.
Letter from R.
G.
- Byram, PP8L, to Document Control
- Desk, NRC, dated February 21,
- 1995, Letter from R.
G.
- Byram, PP8 L, to Document Control
- Desk, NRC, dated June 23, 1995.
Vapor Deposition Velocity Measurements and Consolidation for Iz and CsI, NUREG/CR-2713, S.
L. Nicolosi and P. Baybutt, Hay 1982.
Fission Produce Deposition and Its Enhancement Under Reactor Accident Condition:
Deposition on Primary-System
- Surfaces, BHI-1863, J.
H. Genko, et al.,
Hay 1969.
Transmission of Iodine Through Sampling Lines, 18th OOE Nuclear Airborne Waste Management and Air Cleaning Conference, P. J. Unrein, C. A.
Pelletier, J.
E. Cline and P.
G. Violleque, October 1984.
Deposition of 'I in COE Experiments, IN-1394, Nebeker et al.,
1969.
II
- 16. In-Plant Source Term Measurements at Prarie Island Nuclear Generating
- Station, NUREG/CR-4379, J.
W. Handler, A. C. Salker, S.
T. Croney, D.
W.
- Akers, N.
K. Bihl, L. S. Loret and T.
E.
- Young, September 1985.
17.
MSIV Leakage Iodine Transport Analysis, J.
E. Cline and Associates, Inc.,
1991.
C'
~ f~
Co Pt