ML17058A691
| ML17058A691 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point |
| Issue date: | 03/28/1991 |
| From: | Bettenhausen L, Conte R, Walker T NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML17058A690 | List: |
| References | |
| 50-410-91-80, NUDOCS 9104080193 | |
| Download: ML17058A691 (60) | |
See also: IR 05000410/1991080
Text
MAR 23 591
U.S.
NUCLEAR REGULATORY COMMISSION
REGION I
NINE MILE POINT 2
EMERGENCY OPERATING PROCEDURE
INSPECTION
Report
No.
Facility Docket No.
Facility License
No.
Licen'see:
Facility Name:
Inspection At:
inspection
Conducted:
Team Members:
50"410/91-80
50-410
Niagara
Mohawk Power Corporation
301 Plainfield Road
Syracuse,
NY 13212
Nine Mile Point, Unit 2
Sc,.iba,
NY
January
28 - February
1,
1991
N. Conicella,
Senior Operations
Engineer,
Region I
T. Fish,
Senior Operations
Engineer,
Region I
R.
Laura,
NMP Resident
Inspector
G. Bethke,
Systems Specialist,
COME><
A. Sutthoff,
Human Factors Specialist,
Team Leader:
racy
.
alker, Sr. Operations
Engineer
ate
Reviewed
By:
Richard J.
Conte
hief,
BMR Section
Operations
Branc
,
Date
Approved By:
Lee H. Bettenhausen,
Chief
Operations
Branch
Division of Reactor Safety
Date
9'i04080i5'3
5'20329
AGGCK 05000410
Q
e
EXECUTIVE SUMMARY
The purposes
of the inspection
were to verify that the
NMP2 Emergency Operating
Procedu'res
(EOPs)
are technically correct, that the
NMP2
can
be physically
carried out in the plant,
and that the
NMP2
can
be
implemented
by the
plant staff.
The inspection
team concluded that the
NMP2 EOPs are technically
correct,
can
be physically carried out in the plant,
and
can
be implemented
by
the plant staff.
The inspection
team performed
a technical- review of the
NMP2 Plant Specific
Technical Guideline
(PSTG)
and
and concluded that the various
developed
by the facility were sufficient to meet the intent of the
BWR Owners
Group
(BWROG) Emergency
Procedure
Guidelines
(EPGs).
The
NMP2
EOPs were,
in
general,
technically adequate
and, if implemented properly,
could safely
mitigate the accident conditions they are designed, for.
The licensee
deviated
very little from the
EPG and the deviations
taken were, with one noted
exception,
adequately justified.
The inspection
team questioned
the technical
adequacy
of the justification for the omission of main
steam tunnel
temperatures
as
an entry condition for an
EOP.
A number ov'nconsistencies
and deficiencies
were identified in the
EOP support
procedures
which indicated weaknesses
in the
verification and validation (V8V) process.
The inspection
team performed
a review to determine if the
EOP flowcharts
and
N2-EOP-6,
"NMP2
EOP Support Procedure,"
could be implemented
by the operators
and carried out in the plant.
The operators'erformance
on the simulator and
participation in the plant walkdowns indicated that the operators
were properly
trained,
had
a thorough understanding
of the
EOP bases,
and could correctly
implement the
EOPs in emergency situations.
Inconsistencies
that could lead to
confusion were identified in the
EOP support procedures
during the plant
walkdowns.
These inconsistencies
were further indications of weaknesses
in the
V5V that was performed
on the
N2-EOP-6 attachments
and other procedures
that
support the
EOPs.
The licensee's
method for prestaging
confusion or delays
in the implementation of the procedure.
Additionally, the
licensee's
method of storing jumpers in packets
located inside electrical
panels
could impact the qualification of those electrical
panels.
The
human factors review indicated
the
NMP2
EOPs were generally understandable
and usable
by operators
to mitigate
an emergency.
In addition, it'as
noted
that the
EOP writer's guide reflected
an effort to address
some of the most
significant industry issues
on
EOPs identified in previous inspections.
The
inspectors
noted
some weaknesses
within the writer's guide that appear to have
reduced
the quality of the
EOPs, especially
N2-EOP-6.
The inspection-team
reviewed the licensee's
program for ongoing evaluation of
the
EOPs.
They concluded that the licensee
had established
a sound
program for
ongoing
EOP evaluation
and for implementing
changes to'he
EOPs.
The inspec-
tors were concerned
that the licensee's
controls for issuing temporary
changes
to the
and
EOP support procedures
are too flexible and do not assure
that
changes
to these
procedures will receive- the proper
level of review.
The
inspection
team also reviewed the licensee's
QA involvement in the
EOP program
and concluded that Niagara
Mohawk QA Department is effective in identifying
problems
and assuring
the quality of the
EOPs.
The licensee's
gA program appears
to be effective since
a number of NRC inspect-
ion team concerns
identified in this report
had already
been
independently
identified by the most recent
gA audit.
Overall, the inspection
team also concluded that -the licensee
had devoted
sufficient resources
to the development of the
EOPs.
The result was procedures
that can
be effectively implemented.
The operators'nderstanding
of the
bases
and ability to use the
EOPs were considered
a strength.
There were
some
technical deficiencies
and
h'uman factors issues identified, mostly within the
EOP support procedures.
The majority of the problems
appear to be the result
of weaknesses
within the verification and validation process for the
support procedures.
Additionally, the licensee
was receptive
to the inspection
team's
comments
and committed to appropriately disposition the issues
raised
during this inspection.
DETAILS
~Back round
Following the Three Mile Island (TMI) accident
the Office of Nuclear
Reactor Regulation
developed
the
"TMI Action Plan"
and
NUREG-0737) which required licensees
of operating
reactors
to reanalyze
and accidents
and to upgrade
emergency
operating
procedures
(EOPs)
(Item I.C. 1).
The plan also required the
NRC staff to develop
a
long-term plan that integrated
and expanded efforts in. the writing,
reviewing,
and monitoring of plant procedures
(Item I.C.9).
"Guidelines for the Preparation
of Emergency Operating
Procedures,"
represents
the
NRC staff's long-term program for upgrading
EOPs,
and
describes
the
use of a "Procedure
Generation
Package"
(PGP) to prepare
EOPs.
The licensees
formed four vendor type owner groups corresponding
to the four major reactor types in the United States.
Working with
General Electric and the
NRC, the Boiling Water Reactor
Owners
Group
(BWROG) developed
the
BWR Emergency
Procedure
Guidelines
(EPGs) which are
generic
procedures
that
sec forth the desired
BWROG accident mitigation
strategy.
The
EPGs were to be used
by the licensees
in developing their
PGPs.
Submittal of the
PGP was
made
a requirement
"Supplement
1 to NUREG-0737,
Requirements
for Emergency
Response
Capability."
The generic letter requires
each licensee
to submit
a
which includes:
(i)
Plant-specific technical
guidelines
(ii) A writers guide
(iii)Adescription of the program to be used for the validation of EOPs
(iv) A, description of the training program for the upgraded
From this
PGP, plant specific
EOPs were to have
been developed that would
provide the operator with the directions to mitigate the consequences
of a
broad
range of accidents
and multiple equipment failures.
From January
28
February
1,
1991,
an
NRC team of inspectors
consisting
of three
NRC licensed operator examiners/inspectors,
a reactor
systems
specialist,
a
human factors specialist,
and the resident
inspector
conducted
an inspection of the
EOPs at the Nine Mile Point Nuclear Station
Unit 2 (NMP2).
NMP2 is
a
BWR 5 with a Hark II containment
structure.
The
objectives of the inspection
were to determine if:
the
NMP2
EOPs are
technically correct;
the
NMP2
can
be physically carried out in the
plant;
and that the
NHP2
can
be performed
by the plant staff.
The objectives
would be considered
to be met if the results of the
following reviews were found to be adequate:
comparison of the
NMP2
with the
NMP2 plant specific technical
guidelines
(PSTG)
and the
EPGs;
review of the technical
adequacy
of the deviations
from the
EPGs; control
room and plant walkdowns of the
NMP2 EOPs;
real time evalu-
ation of the
NMP2
on the plant simulator; evaluation of the licensee
program
on continuing improvement of the
NMP2 EOPs;
and performance of a
human factors analysis of the
NMP2 EOPs.
The inspection
focused
on the
adequacy of the
end product,
the
NMP2 EOPs.
If any of the areas
were not
found to be acceptable,
the inspection
would assess
other areas
as
necessary
to understand
the basis for the deficiencies.
The
PGP for NMP2 was submitted to the
NRC in a letter dated
June
29,
1984.
The Safety Evaluation for the
NMP2
was issued
in February
1985.
The
NMP2
EOPs were
implemented i.nitially in October
1986.
These
implemented
Rev.
3 of the
The facility utilized the
NMP2
PSTG, writers guide,
and verification and validation
(V&V) program
as
described
ir the procedures
generation
package
submitted to the
NRC in
June
1984. lo aetermine
the
success
of the implementation of licensee
programs,
a se'ies
of NRC inspections
of EOPs were conducted
in 1988 which
examined the final product of the program,
the
EOPs.
The results of the
NRC inspections
conducted
during
1988 were
summarized
in NUREG-1358,
"Lessons
Learned
from the Special
Inspection
Program for Emergency
Operating
Procedures."
This inspection
was conducted
following the
implementation of a major revision to the
EOPs that implemented
Rev.
4 of
the
as part of the continuing effort of the
NRC to evaluate
EOPs at licensee facilities.
The facility has modified their administrative
program controls
and
EOP development
process
since the initial revision of
the
NMP2
EOPs following issuance
of NUREG-1358.
2.0
Persons
Contacted
k
B
J
R
M.
J.
R
M.
R.
R.
G
P.
J
t
Sylvia, Executive Vice President - Nuclear Division
Firlit, Vice President
Nuclear Generation
Abbott, Unit 2 Plant Manager
McCormick, Unit 2 Plant Manager designate
Wi lczek, Jr.,
Vice President - Nuclear Support
Perry,
Vice President
equality Assurance
Smith, Training Manager
Colomb, Operations
Manager
Seifried,
General
Supervisor
Operations Training
Slade,
Supervisor - Operations
Training Unit 2
Corbin, Supervisor - Simulator Tech.
Walsh,
Licensed Operator. Instructor
Helker, Operations
Supervisor
I
L. Naron, Generation
Engineer
J. Kronenbitter,
Generation
Engineer
(NMPl)
K. Iandolo,
Engineer
C. Kolod, System
Engineer
G. Lapinsky,
Program
Development
~
J. Burton, Supervisor.-
QA Audits
J.
Burgess,
QA Technician
P. Fodi,
18C Technician
M. Goldych, Site Licensing
J.
Pavel,
Li'censing Engineer
K. Korcz, Licensing Engineer
N. Rademacher,
Executive Assistant to Exec.
Vice President
A. Mattessich,
Operations
Assessment
(MATS)
E.
Dunn, Unit 2 Project
Engineer
The inspectors
also contacted
other licensed
and nonlicensed
operators.
Other
R. Brown, Requalification Instructor,
General
Physics
B. Hennigan,
Requalification Instructor,
General
Physics
R. Klein,
Human Factors,
ARD
M. Yeminy, Engineer,
Nuclear
Re viator
Commission
L. Bettenhausen,
Chief, Operations
Branch,
W. Cook, Senior Resident
Inspector
Denotes
those
present
at the exit interview on February
1,
1991.
3.0
Basic
EOP/BWR Owners
Grou
Com arison
~Sco
e
A comparison of the
NMP2
and
BWR Owners
Group
Emergency
Procedure
Guidelines
Revision 4,
was conducted
to ensure that the
licensee
has developed
the procedures
indicated in the
The
EOPs reviewed are listed in Attachment
A of this report.
~Findin
s
The facility developed
EOPs that mimic the types of symptom based
procedures
recommended
by the
The inspection
team found no
deviations
between
the types of procedures
developed
by the facility and
the types of procedures
recommended
by the
Conclusions
The inspection
team concluded that the various types of EOPs developed
by the facility were sufficient to meet the intent of the
4.0
Inde endent
Technical
Ade uac
Review of the
Emer enc
0 crating
Procedures
~Sco
e
The
NMP2
EOPs listed in Attachment
A were reviewed to assure
that the
procedures
are technically adequate
and accurately
incorporate
the
EPGs.
A comparison of the
NMP2
PSTG to the
and
NMP2 EOPs
was
also performed.
Differences
between
the
and
NMP2
PSTG were
assessed
for adequate
technical justification.
Selected
specific values
from the procedures
were reviewed to determine that the values
were
correct.
~Findin
s
4. 1
Com arison of
and
NMP2
PSTG
In general,
the differences
between
the
and the
NMP2
PSTG
have adequate
technical justification.
The inspection
team noted
several
instances
in which the deviations
between
the
EPG and
the
NMP2
PSTG were due to more conservative
requirements
established
by the licensees
The inspection
team identified one deviation that did not appear to
have adequate
technical justification.
The licensee
did not include
main
steam tunnel
temperature
as
an entry condition to N2-EOP-SC,
"Secondary
Containment Control."
The licensee
had deliberately
omitted main steam tunnel
temperature
since the
NMP2 main steam
tunnel is not part of secondary
containment.
One of the purposes
of
Secondary
Containment Control is to limit the reactivity release
from
secondary
containment.
A steam line break in the main
steam tunnel
would bypass
secondary
containment
and could result in
a radioactive
release.
Elevated
main
steam tunnel
temperatures
are indicative of a
problem that should
be addressed
by an
EOP.
The licensee
has
agreed
to review the
need to add the main
steam tunnel
temperature
to
N2-EOP-SC or N2-EOP-RR, "Radioactivity Release
Control."
4.2
Com arison of NMP2 PSTG and
NMP2
In general,
the differences
between
the
NMP2
PSTG and the
NMP2
(variances)
have
adequate
technical justification.
The
PSTG vari-
ances
are properly utilized.
However, the inspection
team identified
several
variances
that did not appear
to be adequately justified or
utilized properly.
The
PSTG section for N2-EOP-PC, specifically the hydrogen control
leg, states
that El.
217 ft. suppression
pool level is the transition
point between
purging the containment directly or purging through the
suppression
pool.
The
EOP states
El.
201 ft. suppression
pool level
as the transition point.
The licensee's justification for the
variance
may not be technically adequate.
The licensee
contends that
the negative
aspect
of the additional
containment pressurization
at
a
higher suppression
pool water level outweighs
the added benefit from
scrubbing
hydrogen through the suppression
pool water.
The licensee
has this item listed as
an
open item in accordance
with N2-ODI-5. 10,
'EOP
Ongoing Evaluation
Program,"
and plans to address
the issue with
the
BWROG in February
1991.
The inspection
team identified several
differences
between
the
PSTG
and the
EOPs that did not have variances
to justify them.
For
example,
the
NMP2
PSTG,
step
PC/H 4.2, directs venting the drywell if
the suppression
chamber
cannot
be vented.
However,
the
EOP itself does
not
direct the drywell to be vented if the suppression
chamber
cannot
be
vented.
The
EOP,
as written, does not accomplish
the, intent of the
PSTG step,
and the
PSTG does
not justify the variance
between
the
PSTG and the
EOP.
The licensee
agreed
to review the unjustified
variances
and
make appropriate
changes.
4.3
Site specific procedure
numbers
are referenced
in the
NMP2
PSTG for
tasks that are accomplished
by the
EOP support procedures.
The
PSTG
is intended to describe
the
EOP strategy,
not the specific procedures
that. accomplish
the actions.
Referencing specific procedure
numbers
in the
PSTG can result in errors if the referenced
procedures
are
modified.
For example,
the
NMP2
PSTG incorrectly references
N2-EOP-6, Attachment
18, for venting the
RPV.
N2-EOP-6, Attachment
12, provides direction for venting the
RPV.
I
Technical
Ade uac
of EOPs
The inspection
team identified several
deficiencies with the tech-
nical
adequacy
of the
EOP flowchart procedures,
the
EOP contingency
procedures
and the
EOP support procedures.
The deficiencies
iden-
tified did not pose
immediate safety concerns;
however, 'they
represented
inconsistencies
that
a more thorough validation and
verification (Y8V) program should
have prevented.
Attachment
B
contains detailed technical
adequacy
comments.
The majority of deficiencies identified by the inspection
team were
found in procedure
N2-EOP-6,
"NMP2
EOP Support Procedure."
The
different attachments
in N2-EOP-6 were not consistently written.
Several
attachments
did not include restoration
steps
or give
adequate
guidance
on the success
criteria for .individual steps.
For
example,
Attachment
17, "Backfilling MSIVs," does not provide guid-
ance for securing
the backfill.
The inspection
team identified the fact that several
N2-EOP-6
attachments
reference
procedures
that are inadequate
for accomplishing
the specified task.
For example,
N2-EOP-6,
Attachment
18, "Depressur-
izing the
RPV," directs the operator to use the
RCIC system to
depressurize
the
RPV in accordance
with procedure
N2-0P-.35.
However,
N2-OP-35 does not contain procedural
guidance for operating
the
system in the pressure
control
mode.
4.4
Technical
Ade uac
of Calculations
The inspection
team reviewed the engineering
worksheets
for several
setpoints
and figures contained
in the
EOPs to evaluate
the technical
adequacy
of. the calculations.
Additionally, the inspection
team
interviewed the individuals who performed the engineering calcula-
tions.
The calculations that the inspection
team reviewed were found
to be technically adequate.
Conclusions
The inspection
team concluded that the
NMP2
EOPs were,
in general,
tech-
nically adequate
and, if implemented properly, could safely mitigate the
accident conditions for which they are designed.
The licensee
deviated
very little from the
EPG and the deviations
taken were,
in general,
adequately justified.
However,
the inspection
team noted several
proce-
dural inconsistencies
and technical deficiencies,
especially in the
support procedures.
These
problems
were not identified by the
V&V program
indicating weaknesses
in the program, especially with respect
to the
performed
on N2-EOP-6.
5.0
Control
Room and Plant Walkdowns
~Sco
e
The inspection
team walked
down the
and procedures
indicated in
Attachment
A to confirm that the procedures
can
be implemented
by the
staff and carried out in the plant.
The purposes
of the walkdowns were to
verify that instruments
and controls required to be used to implement the
procedures
are consistent
with the installed plant equipment;
ensure that
the indicators,
controls
and annunciators
referenced
in the procedures
are
available to the operator;
and ensure that the tasks
can
be accomplished.
The
EOP flowcharts were walked down in the plant control
room (versus
the
simulator)
and the N2-EOP-6 attachments
were walked
down both in the
control
room and in the plant.
~Findin
s
During
a walkdown of N2-EOP-6 Attachment
19,
inspection
team noted that access
to the
RWCU precoat
room is severely
restricted
by tanks,
pipes
and valves.
About half of this equipment is
required
when using
a two component
mix (resin
and filter media) in the
If
f
10
filter-demineralizers.
The licensee
now uses
a single
component mixture
(e.g.,
ECODEÃ); this eliminates
the
need for half of the equipment in the
room.
This permanently installed equipment,
which is
no longer used,
poses
severe restrictions to the implementation of the alternate
inj'ection procedure.
A modification has
been developed
by the licensee
to
remove the obsolete
equipment.
The licensee
agreed to consider
upgrading
the priority of the modification for earlier implementation.
The inspection
team noted several
welding machines, lifting cages,
gas
bottles
and other portable
equipment either unrestrained
or tied to
safety related
equipment (e.g., cabling).
The problem was particularly
noticeable
on the
261 level of the reactor building.
The inspector
also
noted
flammable material (e.g.,
Poly Bags)
stored in combustible
material
exclusion
zones.
These
problems
were identified to the licensee
and appropriate corrective action
was taken.
The inspection
team noted that
EOP support procedures
(N2-EOP-6 attach-
ments) which involved the installation of jumpers in
1E cabinets (e.g.,
to
defeat interlocks)
had the jumpers prestaged
in the
1E cabinet.>.
The
required jumpers for each of the attachments
were stored
in open top
plastic
bags (e.g.', zip-lock Bags) which were taped to the
ins'~de of the
panel
doors.
In
some cases,
the tape (duct tape)
had
come partially loose
from the door, resulting in the jumper bags
being less
secure
than
intended.
The inspection
team questioned
licensee
personnel
as to the
propriety of having the jumpers stored
in this manner within the panels
and the effect on panel
equipment qualification.
The licensee
agreed to
perform
a technical
evaluation of the jumper storage
method.
In
a related
issue,
the inspection
team noted that the prestaged
jumpers
in relay room and control
room panels
are all numbered for the purpose
of
performing periodic'nventories.
The inspection
team noted that neither
the jumper tags
nor the support
procedure
attachments
specify which jumper
is to. be used for each of the terminal pairs being jumpered in the proce-
dures.
Since the jumpers are cut to length for each set of terminal
pairs,
the potential exists for an operator to use the longer jumpers
first, and
be left with only short jumpers for later sets of terminals
which are
more widely separated.
Several
of the panels
in the control
room and the relay room, which must
be accessed
for the insta'llation of
jumpers
and the lifting of leads during performance
of the
N2-EOP-6
attachments,
have
no external
labeling to indicate the individual bays
within the panel.
Additionally, there
are
no formally available
general
arrangement
drawings of the panel
layouts for the relay
room (i.e., either
as part of the procedures
or posted
as
an operator aid in the relay room).
The inspection
team noted that control
room and relay
room panels
were not
being consistently
locked,
as indicated either in procedures
or by labels
on the panel
doors (e.g.,
P 861,
Bay
E in the relay room).
Several
panels,
which either
had
a label requiring locking, or which the proce-
dures indicated would require
a key for entry, were found and left
unlocked.
0
11
The inspection
team noted that the format of the
N2-EOP-6 attachments
did
not provide
a concise
and timely method for the operators
to ascertain
and
assemble all of the tools
and components
necessary
to perform each proce-
dure in the field.
The procedures
required that the operator
scan the
entire procedure to look for tool
and component
requirements,
which. were
indicated with a "Circle T" in the procedure
margin.
Either by memory or
by writing down each of the requirements
on. a separate
piece of paper,
the
operator would then obtain the necessary
items from the
EOP tool boxes in
the control
room.
Although
some
EOP-support
procedure
items were pre-
staged
in the plant (e.g.,
hoses,
large wrenches,
and terminal jumpers),
the necessity
to determine
the
need for and obtain the other items (e.g.,
fuse
pullers, flashlights,
screwdrivers,
speed
wrenches,
etc.) presented
the
potential for an operator to enter the plant without all of the necessary
tools and introduce
an unnecessary
time delay.
During the walkdowns of N2-EOP-6 attachments,
the inspection
team noted
inconsistencies
in the identification of controls
and components
which had
to be manipulated
in performing the procedures.
Some in-plant components
and controls were identified by component
number only, while others
were
indicated
by combinations of number,
noun
name,
and location.
The licen-
see explained that the more limited descriptions
were applied to
components
with which operators
were most familiar, and that the more
comprehensive
descriptions
were applied to less familiar components.
The
stated
purpose
for this methodology
was to minimize the size
and wordiness
of the procedures..
The inspection
team found at least
two cases
where the
operators initially thought that field components
were operated
from the
.control
room,
when in fact they required local operation (e.g.,
'in Attachment 6).
In other instances,
confusion
was created
by the triple
component
numbering
scheme (e.g.,
2G36-
R022,
and G36-N0112
all referring to the
same
component
in Attachment 19).
In other proce-
dures (e.g.,
step
18. 1.4.b in Attachment 18), the procedure
implied that
valves,
such
as
AOV-10B and
D,
had thei r own control switches,
when in
fact they do not.
The inspection
team noted that the existing process
for
determining
the extent of component identification in the support proce-
dures
was not formalized in the Support. Procedure
Validation Checklist
contained
in N2-EOP-5.
The walkdowns identified several
examples of
components
whose labels did not match the
noun
name of the component
in
the N2-EOP-6 attachments.
Operator aids found throughout the plant included handwritten sections.
The use of handwriting in operator aids
can
lead to illegibility and
may
cause
the aid to be unusable.
Currently,
Procedure
S-SUP-6
, "Control
of Operator Aids," does not prohibit the
use of handwriting in operator
aids.
Attachment
B contains additional specific
comments
on certain
EOP procedure
sections
from the walkdowns.
Conclusions
The inspection
team concluded that,
in general,
the
EOP procedures
could
be implemented
by the staff and carried out in the plant.
However, the
0
12
procedures
displayed inconsistencies
that could lead to. confusion.
The
licensee's
method for prestaging
required
confusion or delays in implementation of the procedure.
Additionally, the
licensee's
method of prestaging certain
EOP tools
and equipment in packets
located inside the electrical
panel
may impact the qualification of those
electrical
panels.
The problems identified during the walk-down reflected
weaknesses
in the licensee's
validation and verification program,
espe-
cially with respect
N2-EOP-6.
6.0
Simulator
~Sco
e
Six scenarios
were administered
to two shift crews
on the plant specific
simulator.
The simulator scenarios
provided information
on the
operators'bility
to implement the
EOPs in
a real
time situation.
The purposes
of
this exercise
were to determine if the
EOPs provide operators with suffi-
cient guidance
such that their responsibilities
and required actions
during emergencies
both individually and
as
a team are clearly outlined;
verify that the procedures
do not cause
operators
to physically interfere
with each other while performing the
EOPs; verify that the procedures
do not duplicate operator actions
unless
reauired (i.e.,
independent
verification); and verify that transitions
between
procedures
are clear
and easily understood
by the operators.
~Findin
s
In general,
both crews observed
performed well during the three scenarios
that each
crew dealt with.
Both crews displayed
strong
teamwork and
communication skills.
The operators
understood
the
and were able to
effectively implement the procedures.
The inspection
team noted that the operators
inconsistently
used the
attachments
of N2-EOP-6,
"NMP2
EOP Support Procedure."
N2-EOP-6 contains
support
procedures
which are written in, a checklist format.. The procedure
clearly states
that the operators
are to place
a "check" opposite
each
step
as the steps
are completed.
The inspector
observed that the opera-
tors did not in all cases
refer to the attachments
of N2-EOP-6 for
operational
guidance
and that the operatoJ s,
when they did refer to the
procedure,
did not place
a "check" opposite
each
step
as it was completed.
Additionally, from direct questioning of the operators
at the completion
of the scenarios,
the inspection
team noted that the operators
did not
uniformly understand
the expectations
when using the N2-EOP-6 attach-
ments.
Some operators
thought that placing
a "check" opposite
each step
as
a placekeeping
method
was optional.
The inspection
team noted that
one crew did not clearly understand
the
injection system alignment requirements
for establishing
RPV flooding as
13
delineated
in N2-EOP-C4,
"RPV Flooding."
N2-EOP-C4 directs that injection
into the
RPV be controlled to maintain at least
4 SRVs
open
and at least
61 psid across
the
SRVs, the conditions required 'for RPV flooding.
N2-EOP-C4 indicates that the differential pressure
across
the
SRVs should
be
as
low as practicable,
which implies that injection sources
can
be (and
should be)
secured
to establish
the steady state conditions for RPV
flooding.
The crew misunderstood
the flooding directions
and believed
that injection sources
that are
used to establish
the conditions for
flooding cannot
be secured until the minimum core flooding interval time
was satisfied.
The inspection
team noted that several
reactor operators
were hesitant
in reporting
key parameter
changes
to the Station Shift Supervisor
(SSS).
There are certain
parameter
changes
that require
immediate notification of
the
SSS since these
parameters
influence the mitigation strategy of the
EOPs.
An example of a key parameter
change that requires
prompt
notification is the ability to determine reactor level.
One crew failed
to promptly report this parameter
change to the
SSS which resulted
in a
delay in entry into N2-EOP-C4,
"RPV Flooding."
Conclusions
The inspection
team concluded that the operators
were properly trained
in the
use of the
~
The operating
crews displayed
minor knowledge
and ability weaknesses,
but performed well overall.
The inspection
team
noted the operators'nconsistent
usage of .the attachments
of N2-EOP-6
reflecting weaknesses
in the training on EOP-6.
Overall, the operators
had
a thorough understanding
of the
EOP bases
and could correctly
implement the
EOPs in emergency situations.
7.0
Human Factors
Review of the
~Sco
e
A desk top review of the
NMP2
was conducted prior to the on-site
'inspection.
The review consisted
of an assessment
of the quality of N2-
EOP-5,'Production
and Control of NMP2
EOP Revisions"
(EOP writer's guide
and validation
and verification program),
and
a comparison of the
and
EOP support procedures
to ensure
they were generated
in accordance
with
N2-EOP-5.
Observation
of simulator exercises,
interviews with NMP2 staff,
plant walk downs,
and control
room tours were
used to both corroborate
those
items noted during the desk top review and to identify additional
concerns.
~Findin
s
7. 1
N2-EOP-6
NMP2
Su
ort Procedure
Considerable effort has
been di rected
toward the development of
guidance for procedure
structure
and content that supports operator
14
performance
through the application of human factors principles
Lack of application of this guidance to procedure
development
can
result in procedures
that are difficult to use
and
may lead to'rrors.
In some cases,
procedures
that do not complement
human capabilities
may inhibit performance,
rather than
enhance it.
The writer's guide for NMP2
EOPs included minimal guidance for
structure
and content for text procedures
and the validation check-
lists reflected the writer's guide weaknesses.
In addition,
N2-EOP-5
did not contain
a verification checklist for the
EOP support proce-
dures.
The lack of a verification checklist indicated that there
was
no structural
guidance
against
which to verify the procedures.
As
a
result,
N2-EOP-6
was found to have
numerous
inconsistencies
in
structure
and level of detail.
In
some cases,
steps
were technically
incorrect or could not be performed
as written (Section 4.3).
The
attachments
required
numerous transitions
to operating
procedures.
These transition 'steps failed to identify the necessary
sections
or
stens to be performed.
References
to plant labeling throughout
N2-LOP-6 were inconsistent with plant nomenclature
(Section 5.0).
In add tion, the sections
of operating
procedures
referenced
by
N2-EOP-6 were not subject to the validation requirements
of N2-EOP-6.
These
procedures
were not cross
referenced
to the.EOPs
in any way
that would ensure that structure,
content, verification,
and valida-
tion requirements
for EOPs would be applied to the referenced
procedures'.2
Communication
Between
0 erations
and Trainin
Natural
human variation in performance
is controlled by clear
and
consistent training
on the structure,
content,
and expected
execution
of EOPs.
Therefore, it is particularly important that clear two-way
communications
between
operations
departments
and training departments
exist regarding expectations
related to implementation of the
EOPs.
Any discrepancy
between
these
indicates
a weakness
in the
EOP system
and could lead to significant performance
problems
and possible error.
Several conflicts in definitions were identified between
the
NMP2
Operations
Department
EOP documents
and Training Department
documents.
Operators
provided conflicting definitions for important action verbs
used in the
EOPs which indicated
a disconnect
between
operations
and
training department
expectations.
The writer's guide developed
by
operations
personnel
included
some definitions that were missing from
the related
lesson
plan developed
by training..
7.3
N2-EOP-5
Production
and Control of NMP2
EOP Revisions
In order to prepare clear, consistent
EOPs that will support operator
performance
and minimize errors,
a complete
and restrictive writer'
guide is necessary.
A complete writer's guide addresses
every aspect
of the
EOPs;
a restrictive writer's guide defines clearly the precise
methods
and format to be used
in the
EOPs,
applying
human factors
15
principles.
Writer's guides that are
incomplete or nonrestrictive
leave format decisions to the writer's judgment
and preference.
Because
individual writer's judgments
vary, this could result in
increasingly inconsistent
and complex procedures.
In addition,
because
the writer's guide controls the consistent
presentation
of information within the procedures,
an incomplete or
nonrestrictive writer's guide
may lead to flawed verification.
The
resulting procedures
may be inconsistent
in structure
and content
and
therefore
more difficult for operators
to use,
resulting in a poten-
tial for error.
The
NMP2 writer's guide includes
a great deal of detail
and reflects
awareness
of current issues
and guidance
on
EOPs.
For example,
the
structure of caution
statements
is consistent
throughout
the
and
the cautions
do not contain actions.
The writer's guide is not
complete
and restrictive with respect
to
some aspects
of the
EOPs.
Some of the guidance within the writer'.s guide is unclear.
In
addition, the
NMP2
writer'-s guide. includes
some guidance that fails
to restrict procedure
structure.
Some important aspects
of proce-
dures
are not addressed,
such
as the structure of N2-EOP-6 (text
procedures).
Additionally, some of the guidance
included in the
NMP2
writer's guide is in conflict with standard
good practices for EOPs.
The verification and validation checklists
are extremely detailed
and
clearly intended to serve
as
a tool to support thorough
and consis-
tent verification and validation of the
EOPs.
However,
because
the
checklists
are essentially
reproductions
of the guidance
in the
writer's guide,
the writer's guide deficiencies
are proliferated
through the
use of these checklists.
Therefore,
the
V8V process
has
bhen
unable to prevent inconsistencies
in structure
and content
within the
7.4
Flowcharts
As mentioned
above,
N2-EOP-5
was weak in
a
number
of important 'areas.
As
a result,
a number of inconsistencies
were found within the
flowcharts.
For example,
action
steps
were found included within
lists and action
symbols were found to include information that did
not require operator action.
In addition, the level of detail of
various
step
in the flowcharts varied
and in some
cases
appeared
to
be insufficient.
Conclusions
The team concluded that the
NMP2
EOPs were generally understandable
and
usable
by operators
to mitigate'n
emergency.
In addition, it was noted
that N2-EOP-5 reflected
an effort to address
some of the most significant
industry issues
on
EOPs in the last few years.
However, there were several
weaknesses
within N2-EOP-5 which resulted
in inconsistent quality of the
EOPs, especially
N2-EOP-6.
16
8.0
On oin
Evaluation of NMP2
~Sco
e
A review of the licensee's
procedures
and discussions
with licensee
personnel
were conducted to determine'he
effectiveness
of the licensee's
ongoing
EOP evaluation
program.
The ongoing evaluation
program
should
ensure
the technical
adequacy
and structural quality of the
EOPs in light
of operational
experience,
training experience,
control
room walkthroughs,
and from changes
in plant design;
technical specifications;
technical
guidelines;
or other plant procedures.
~Findin
s
Procedure
N2-ODI-5. 10,
"EOP Ongoing Evaluation Program," provides the
guidance
required to implement the ongoing evaluation
program.
It appears
.that the procedure
is adequate
and that the items currently listed in the
Open
Items
Logbook, generated
in accordance
with N2-ODI-5. 10,
have
been
properly prioritized and are being properly dispositioned.
Procedure
N2-EOP-5,
"Production
and Control of NMP2
EOP Revisions,"
provides the guidance
required to perform revisions to the
EOPs.
Speci-
fically, the procedure
delineates
the required verification and-validation
process for various types of revisions to the
EOPs.
The procedure
is
comprehensive
and appears
adequate
with the exception of the weaknesses
noted in the
V&V process
for the
EOP support procedures.
=
An
EOP Engineering
Impact Checklist is completed for each modification or
design
change
generated.
The purpose of the checklist is to ensure that
if there is
a potential
impact
on any aspect of the
EOPs or the
PSTG,
the,
appropriate
personnel
are informed
so that the
EOPs or
PSTG can
be revised
if needed.
The checklist itself has
been developed,
but training
on use
of the checklist will not be completed until March 31,
1991.
The check-
list is comprehensive
and appears
to be adequate
to ensure that the
are maintained current.
The inspector
had concerns that AP-2.0, "Production
and Control of Proce-
dures,"
does
not contain controls to ensure that the
EOP coordinator
performs
a review whenever
a temporary/publication
change
notice
(TCN) is
issued to an
EOP or an
EOP support procedure.
It is imperative that the
EOP coordinator performs
a review of all
EOP related procedural
changes
since the
EOPs consist of a mix of
EOP flowcharts,
EOP support procedures,
and specific operating
procedures
(OPs).
Additionally, the inspector
noted that AP-2.0 did not preclude
a
TCN from being issued to an
flowchart.
The licensee
committed to reviewing AP-2.0 and enhancing
controls
as
needed.
Conclusions
The inspector
concluded that the licensee
had established
a
sound
program for ongoing
EOP evaluation
and for implementing
changes
to the
0
17
EOPs.
However, the licensee's
controls for issuing
TCNs to the
and
EOP support
procedures
are too flexible and do not assure
that
TCNs
issued to these
procedures will receive the prope'r level of review.
9.0
ualit
Assurance
Measures
~Sco
e
The inspection
team reviewed the Quality Assurance
(QA) organization,
involvement in the programmatic
approach
of the
EOP program.
The inspec-
tion focused
on those policies,
procedures,
and instructions
necessary
to
provide
a planned
and periodic audit of the
EOP development
and implemen-
tation process.
The inspection
team reviewed the involvement of site
Quality Assurance
in the
EOP program
by interviewing Quality Assurance
Department
personnel
and by reviewing
a sample of past
QA Audits and
surveillances.
~Findin
s
The most recent
QA audit was conducted
in December
1990 in conjunction
with the final conversion of the Nine Mile Point Unit 2
from Revision
3 to Revision
4 of the
The
QA inspectors
used
NRC Temporary
Instruction 2515/92
as
a guide in performing the audit.
The audit was
noteworthy in that it identified over
50% of the technical
adequacy
issues
later .identified by the
NRC inspection
team in their pre-audit review of
the
same
EOP materials.
Many of the concerns identified by both the
Niagara
Mohawk QA auditors
and by the
NRC pre-audit technical
review had
been corrected
by the time the onsite portion of the
NRC
EOP audit
commenced.
A sampling of the audit concerns
showed that they had been
well documented
using the methods
specified in N2-ODI-5. 10,
"EOP Ongoing
Evaluation
Program."
The licensee
had initiated
some corrective actions
prior to this inspection.
The
EOP surveillance
conducted
in June
1990
used procedure
N2-EOP-5,
"Production
and Control of NMP2
EOP Revisions,"
and
"Lessons
Learned
from the Special
Inspection
Program for EOPs,"
as guidance for
conducting the surveillance.
Concerns identified by the surveillance
had either been corrected
or are
scheduled
for correction.
Conclusions
The inspection
team concluded that Niagara
Mohawk QA Department involve-
ment in the
EOP program is satisfactory.
The licensee's
QA program
appears
to be effective since
a number of
NRC inspection
team concerns
identified in this report
had already
been
independently identified by the
most recent
QA audit.
10.0 Initial Examinations
During the course of the inspection,
the
NRC administered
a retake
exami-
nation to one reactor operator
(RO) license applicant.
The applicant
had
18
previously failed the simulator portion of the operating test,
but passed
the remaining portions of the examination.
The retake
examination
consisted
of only the simulator portion of the operating test.
The retake
examination
was administered
in accordance
with NUREG 1021,
Examiner
Standards
(ES)
Rev.
6, dated
June
1,
1990.
The applicant
passed
the retake examination;
therefore,
the applicant
has
now passed all portions of the
RO licensing examination.
Due to the
limited scope of this retake examination,
there
were
no generic
strengths
or weaknesses
noted.
11.0 Licensee Action on Previous
Ins ection Findin
s
CLOSED
410/89-12-01:'uring
an inspection of the implementation of
NRC
and Supplement
1,
BWR Power Oscillations,
conducted
in 1989,
the inspector
had concerns
that the licensee
had not conducted
a thorough
review of all operating
procedures
to incorporate
cautions that would
preclude
the operators
from entering
the unstable
operating
region of the
power-to-flow map.
The licensee
committed to conducting
an in-depth
review of all operating
procedures
to make
changes
as
needed.
A; a result
of the licensee's
review,
20 operating
procedures
were changed to preclude
operation in the unstable
region of the power-to-flow map.
The inspector
reviewed the licensee's
corrective actions
and found them acceptable.
Based
on the above, this item is considered
closed.
CLOSED
410/89-12-02
During an inspection of the implementation of NRC
and Supplement
1,
BWR Power Osci llations conducted
in 1989,
the inspector
had concerns
that the licensee
did not have
an operating
procedure that provided guidance for rapid power reductions.
The licensee
committed to developing
a
new procedure that would provide the guidance
needed to perform rapid power reductions.
The licensee
developed
proce-
dure N2-0P-101D,
which provides
guidance for normal
power
changes
between
45% and
100% power
and
an off-normal section which
contains
the guidance for rapid power reductions.
The inspector
reviewed
the licensee',s
corrective actions
and found them acceptable.
Based
on the
above, this item is considered
closed.
CLOSED
410/89-10-01:
During
a licensed operator examination
conducted
in 1989, the examiner
had concerns
over the technical
basis of the method-
ology for actuating
a reactor
scram in procedure
N2-0P-78,
"Remote Shut-
down System."
The procedure directed the operator to initiate
a scram by
closing the NSIVs.
The licensee
committed to review the technical
basis
and
make revi sions if needed.
The licensee
revised
procedure
N2-OP-78 to
direct the operator to scram the reactor
by deenergizing
and then
closing the MSIVs.
This minimizes the transient
placed
on the reactor.
The inspector
reviewed the licensee's
corrective actions
and found them
acceptable.
Based
on the above, this item is considered
closed.
CLOSED
410/89-10-02
During
a licensed operator examination
conducted
in 1989,
the examiner
had concerns that the
EOP equipment
box 'required to
19
accomplish alternate
control rod insertion
by venting exhaust
header did
not contain all the equipment
necessary
to accomplish that task.
The
licensee
committed to verifying that all
EOP equi'pment'oxes
contained
the
equipment
necessary
to accomplish
the required task.
The licensee
developed
procedure
N2-PM-M4, "Monthly Audit of EOP Support
Equipment,"
which ensures
that each
EOP equipment
box contains
the necessary
equipment
and procedures
to accomplish
the .tasks
required
by the
EOPs.
The results
of the in-plant walkdowns of the
EOP support procedures
indicated that the
licensee's
corrective actions
were effective in assuring that equipment
was available to perform
EOP tasks.'ased
on the above, this item is
considered
closed.
CLOSED
410/90-16-01
During
a licensed operator
examination
conducted
in 1990, the examiner
performed
a review of the status of corrective
actions. performed
by the licensee
to correct deficiencies
noted during the
July 1989 Licensed Operator Requalification
Program Evaluation.
The
examiner
had concerns that three short-term corrective actions
and
one
long-term corrective actions
had not been
completed.
The licensee
has
since confirmed the completion of all the corrective actions
planned via
a
letter dated August 20,
1990,
and telephone
conversation
with the
NRC
staff on November 7,
1990.
The*inspector
reviewed the licensee's
correc-
tive actions
and found them acceptable.
Based
on the above, this item is
considered
closed.
12.0 Exit Interview
At the conclusion of the inspection
on February
1,
1991,
an exit meeting
was conducted with those
persons
indicated in paragraph
2.
The in'spection
~>'scope
and findings were summarized..
The licensee
did not identify as
proprietary
any of the materials
provided to or reviewed
by the inspectors
during the inspection.
Licensee'management
was
aware of the commitments
made
by the licensee's
staff during this inspectio'n
and agreed that all deficiencies
noted
by
the
NRC inspection
team would be addressed.
Attachments:
Attachment
A Documents
Reviewed
Attachment
B Detailed Technical
Adequacy
and Walkdown Comments
Attachment
C - Human Factors
Examples
Attachment
D - Simulation Facility Report
20
ATTACHMENT A
DOCUMENTS
REVIEWED-=
Flowchart
- N2-EOP-RPV
" N2-EOP-PC,
- N2-EOP-SC,
- N2-EOP-RR,
~ N2-EOP-MSL
- N2-EOP-C1,
- N2-EOP-C2,
- N2-EOP-C3,
" N2-EOP-C4,
- N2-EOP-CS,
" N2-EOP-C6,
RPV Control,
Rev.
4
Primary Containment Control,
Rev.
4
Secondary
Containment Control,
Rev.
4
Radioactivity Release
Control,
Rev.
4'
MSIV Leakage Control,
Rev.
4
Alternate
Level Control,
Rev.
4
Emergency
RPV Depressurization,
Rev.
4
Steam Cooling,
Rev.
4
RPV Flooding,
Rev.
4
Level/Power Control,
Rev.
4
F~ooding,
Rev.
4
Emer enc
Su
ort and Related
Procedures
- Att.
Att.
Att.
Att.
- Att.
Att.
- Att.
Att.
- Att.
- Att.
- Att.
Att.
Att.
- Att.
Att.
Att.
- Att.
Att.
Att.
- Att.
Att.
Att,.
At%.
Att.
Att.
Att.
2.0-
3.0 "
4.0-
5.0-
6.0-
7.0-
8.0-
9.0-
10.0-
11.0 "
12.0-
13.0-
14.0-
15.0-
16.0-
17.0-
18.0-
19.0-
20.0-
21.0-
22.0-
23.0-
24.0-
25.0-
26.0-
27.0-
NZ-EOP-6,
NMP2
Att. 1.0-
Support Procedure,
Rev.
0
RPV Water Level/High Drywell Pressure
Associated
Actuations
Defeating
Low RPV Press
Isolation Interlocks
Throttling
ECCS Injection
Throttling RCIC Injection
RHR Service
Water Crosstie
RHR Firewater
System Crosstie
ECCS Keepfull
Pump Injection
Condensate
Transfer Injection
SLS Test Tank Transfer Injection
Depressurizing
the
RPV Using the Condenser
Defeating
RWCU Isolation Interlocks
Venting the
RRCS Manual Initiation
Alternate Control
Rod Insertions
SLC Hydro
Pump Injection
Use of SJAE with Aux Boiler Steam
Backfilling MSIVs
Depressurizing
the
Defeating
L8
FWS Interlocks
Containment
Venting
Containment
Sprays
Containment
Level Determination
(above el
224 ft)
DW Unit Cooler Oper.
w/LOCA Signal
Containment
Purging
Defeating
HVR LOCA Isolation Signals
Restoration of H2/02 Analyzers
21
Att. 28.0
Determining Reactor. Building Temperatures
- Att. 29.0
Determining Suppression
Chamber Overpressure
N2-0P-13,
Reactor Building Closed
Loop Cooling,
Rev.
2
- N2-0P-30,
Control
Rod Drive, Rev.
3
- N2-0P-31,
Residual
Heat Removal,
Rev.
7
N2-0P-32,
Low Pressure
Rev.
3
" N2-0P-33,
High Pressure
Rev
~
4
N2-0P-35,
Reactor
Core Isolation Cooling,'ev.
3
- N2-0P-36A,
Rev.
2
- N2-0P-37,
Reactor
Water Cleanup
System,
Rev.
3
N2-0P-60,
Drywell Cooling,
Rev.
1
N2-0P-61A,
Primary Containment Ventilation, Purge,
and Nitrogen System,
Rev
~
3
N2-0P-61B,
Standby
Gas Treatment,
Rev.'5
N2-0P-62,
Rev.
4
N2-0P-101C,
Plant Shutdown,
Rev.
6
N2-0P-101D,
Rev.
0
Administrative Controls
AP-2.0, Production
ana Control of Procedures,
Rev.
20
AI-1.0, Site Procedures
Writer's Guide
N2-EOP-5,
EOP Writer's Guide,
Rev.
1
S-SUP-6,
Control of Operator Aids, Rev.
1
N2-0DI-1.06, Verbal Communications,
Rev.
1
N2-0DI-1.08, Operations
Policy for Emergency
Procedures,
Rev.
4
N2-0DI-1.09,
EOP Users
Guide,
Rev.
4 (cancelled)
N2-ODI-5. 10,
EOP Ongoing Evaluation
Program,
Rev.
0
Other
Plant Specific Technical
Guidelines Input Parameters,
Rev.
2
NMP2
EOP Basis
Document
Calculations
Reviewed
Figure
PC-2 Drywell Spray Initiation Limit
Figure
PC-4 Primary Containment
Pressure
Limit
Figure
PC-8 Maximum Primary Containment
Water Level Limit
Suppression
Chamber
Spray Initiation Pressure
Limit (SCSIP)
" Denotes
those
procedures
walked-down
22
ATTACHMENT B
DETAILED TECHNICAL ADEQUACY AND WALKDOWN COMMENTS
N2-EOP-C4,
"RPV Flooding" does
not provide clear guidance for determining
that
RPV water level indication
has
become available.
Additionally, the
do not provide guidance
on when to backfill
RPV water level indication
reference
legs to restore
indication.
The definition in the
EOP bases
for "Gross
Fuel Failure" is three
times
normal
main
steam line radiation or three times
normal coolant activity.
It appears
the licensee
has
equated
these
two parameters
when in
actuality they may not indicate the
same
degree
of fuel failures
N2-EOP-PC,
"Primary Containment Control" directs the operator to operate
the hydrogen
recombiner in accordance
with N2-0P-62,
Recombiner."
However,
N2-OP-62 contains
and oxygen limitations
that c.re more restrictive than what N2-EOP-PC requires.
The licensee
has tnis item l'isted as
an open
item in accordance
with N2-ODI-5. 10.
The fire hoses
which are required for the performance
of N2-EOP-6,
Attachment 6,
"RHR Firewater
System Crosstie,"
are
staged
'in
a locker in
the reactor building stairwell which is
1 floor below where they are
needed.
This concern
had already
been
documented
by the licensee
and
will be evaluated
to determine if the
hoses
can
be moved to
a location
closer to the
system interconnections.
N2-EOP-6,
Attachment 7,
"ECCS Keepfull
Pump Injection," specifies
the.
High Pressure
(HPCS) discharge
pressure
gage, be used to
determine that
ECCS keepfull pressure
is higher than
RPV pressure.
The
HPCS pressure
instrument line is upstream of the
HPCS discharge
piping
check valve, but the
ECCS keepfull flow enters
the
HPCS discharge
piping
downstream of the check valve.
Therefore,
the pressure
gage listed in
the procedure
would be isolated
from the
ECCS keepfull
pump and would
not provide accurate
indication
ECCS keepfull
pump discharge
pressure.
N2-EOP-6, Attachment 7,
"ECCS Keepfull
Pump Injection," step
7. 1.5,
does
not ensure that the
system is properly aligned for injections
Both
2CSH"MOV107 and
2CSH*V54 could be closed resulting in no flowpath for the
pumps
The licensee
agreed to add
a step to open
2CSH"V54
~
N2-EOP-6, Attachment 9,
"SLS Test Tank Injection," does
not contain
restoration
steps to replace
the squib valves.
The purpose of N2-EOP-6, Attachment
12, "Venting the
RPV," indicates that
the procedure
provides direction for venting the
RPV with the
RCIC system
and the
HX (steam
condensing)
system,
but the body of the procedure
does not contain, either of these
methods.
These
methods
are not used for
venting the
RPV,
so the licensee
agreed
to correct the purpose
to delete
the references
to
RCIC and
HX.
23
N2-EOP-6, Attachment
17, "Backfilling MSIVs," does
not contain restoration
steps
to restore
the leads lifted and the jumpers installed to execute
the
procedure.
Additionally, the procedure
does not provide clear guidance
for determining
the status of the NSIV backfill and determining
when the
backfill should
be secured.
The procedure
is written to rely on operator
experience
and judgement to determine
the status of the backfill.
N2-EOP-6, Attachment
18, "Depressurizing
the
RPV," directs that
RCIC be
operated
in accordance
with N2-0P-35,
"Reactor
Core Isolation Cooling,"
to keep the
RPV vented.
'The intent of the step is to operate
RCIC in the
full flow test
mode;
however,
N2-OP'-35
does
not contain
a section that
directs operation of RCIC in the full flow test
mode.
Operators
were
generally
aware of how to perform this routine task.
N2-EOP-6,
Attachment
19,
"RWCU Boron Injection," requires actions to'e
performed in the
RWCU precoat
room.
Access to the
RWCU precoat
room is
severely restricted
by tanks',
pipes
and valves.
About half of this
equipment is required to use
a two component
mix (resi n and filter
media) in the
RWCU filter-demineralizers.
The licensee
now uses
a
single component mixture (e.g.,
ECODEX), thus eliminating the
need for
half of the
equipment= in the
room.
A modification had
been
developed -by
the licensee
to remove the obsolete
equipment.
Steps
19.10 through 19.16 of N2-EOP-6, Attachment
19,
tion," do not provide clear direction to backwash
the
second demineral-
izer used for boron addition.
The substeps
within step
19.9 of N2-EOP-6, Attachment
19,
Injection," could lead to confusion
as to when to commence
the filter-
demineralizer
precoat cycle.
Auxiliary operators
performing the walkdowns expressed
a lack of famili-
arity with the
RWCU Allen-Bradley computer terminal which is used to
reprogram
the timing sequence
of the
system
when implementing
N2-EOP-6,
Attachment
19,
There are
no
new flex gaskets
staged for installing the blank flanges
on"
the,
SBGT system
when implementing
N2-EOP-6, Attachment 21, "Containment
Venting:"
N2-EOP-6, Attachment
21, "Containment Venting," contains
no direction to
shut the
SBGT system
fan discharge
damper which is normally open prior
to removing the spoolpiece.
The mechanical
maintenance
tool box in
SBGT room
B which contains
items
necessary
for the performance
of N2-EOP-6, Attachment
21, "Containment
Venting," does
not contain
an inventory list and is apparently
under the
control of maintenance.
As a result,
there is
no assurance
that the
equipment
required to install the
spool
piece will be readily available
when required.
18.
N2-EOP-6, Attachment 23,
"Containment
Level Determination
(above el.
224
ft.)," contains
a "Note" which precludes
determination of containment
water level if containment, pressure
is greater
than
40 psig.
It appears
that this note is not necessary
and could mislead the operators
during
implementation of N2-EOP-C6,
Flooding," which directs
actions
based
on containment water level
up to containment
pressures
of at
least 50.7 psig.
The licensee
agreed to evaluate
the
need for the note
and make corrections
as required.
I
25
ATTACHMENT C
HUMAN FACTORS
EXAMPLES
The following examples
are provided to clarify the types of problems identified
in the areas of human factors concerns
described
in Section
7 of this report.
These
examples
are not intended to be viewed as
an inclusive list of all
such
problems
found in the
NMP2 EOPs,
but rather
as
a set of limited examples
of the
types of inadequacies
found through the
human factors analysis.
1.
N2-EOP-6
NMP2
SUPPORT
PROCEDURE
The writer's guide lacks sufficient guidance for structure
and content
of N2-EOP-6.
For example,
Section
10.2 of N2-EOP-5 indicates that each
attachment
should contain action steps,
but provides
no guidance for
'the structure of an action step.
It also indicates that "cautions
and
notes
may be contained
throughout the action steps,"
but provides
no
guidance for structure
or placement of cautions
and notes.
The N2-EOP-5 Support
Procedure
Validation guestionnaire
(used to validate
N2-EOP-6 attachments)
reflects the weaknesses
in the writer's guide.
The
validation checklist asks
the validator "was the terminology consistent
with that used
on the control panels
or other procedures?"
However,
without clear guidance
on the requirements
for terminology used in the
procedure,
consistency
could
mean anything
from an exact representation
of
control panel
labeling 'to noun
names for equipment that the verifier
subjectively judges to hold the
same
meaning
as the plant labeling.
In
addition,
the checklist lacks any way to control
such important aspects
of
as the consistency
of step structure
or level of detail,
as .does the
writer's guide.
N2-EOP-6 contains
numerous
inconsistencies
in structure
and level of
detail.
For example,
in Attachment
19, the format for the "purpose"
section differs from that used in Attachment
15, although the content is
similar.
Also, Attachment
19,
step
19.8 begins with the conditional
phrase "if it is not already running'."
Several
other steps
in this
attachment
are applicable only under certain conditions;
however,
they do
not include the relevant conditional
phrase (e.g.,
19.3
and 19.5).
In
addition,
references
to filter/demineralizers
in this attachment
are not
consistent.
The references
include: "Filter Demineralizers
(F/Ds)" ( step
19. 1); "Filter/Demineralizers" (step 19.3);
and "F/D" (step 19.4).
The
sections
of N2-OP-37 referenced
from Attachment
19 also. include the
references
"filter/demineralizers" (G.'.2), "Flt/Demin" (G. 1.2.2),
and
"filter/demin" (G. 1.2.3).
'
References
to operating
procedures
often failed to indicate the section
or specific steps
to be performed.
For example,
Attachment
19,
step
19.9.f, directs action to start the precoat cycle per N2-0P-37,
section
F.50,
paragraph
5.4,
then directs
the operator to ignore the steps
about
resin addition
and step
5. 14.
Failure to specifically reference
the
4
f
26
appropriate
steps
requires
the operator to read through irrelevant steps
and decide which steps
are necessary.
Direct reference
to the appropriate
step
numbers
would ease
the task and ensure
performance
of the correct
steps.
Numerous
steps
include plant nomenclature
references
that do not match
that found on the plant labels (e.g.,
Attachment
19, step 19.4, references
for filter-demineralizers).
This problem was
even
more prevalent through-
out the referenced
operating
procedure
sections (e.g.,
N2-0P-37, G;1.2.2).
Communication
Between
0 erations
and Trainin
Conflicts in important. definitions were found between
Operations
Depart-
ment documents
and Training Department
documents.
For example,
the
writer's guide definition of the term "execute"
states
"perform the
actions prescribed
in the identified step"
(N2-EOP-5,
page
125)
~
The
definition of "execute"
from Lesson
Plan 02-REQ-006-344-2-20
is to "leave
the step containing the executive instruction
and take the action, speci-
fied in the identified step,
continuing
on through the subsequent
steps
of
that section" (p. 23).
In addition,
the definitions
shown in the writer'
guide
and the lesson
plan differ substantially for the terms "vent" and
"prevent."
P
Operators
had conflicting definitions for important action verbs.
When
asked to define the term "verify," some operators
indicated that the
word essentially
meant "if it isn't so,
make it so."
Others indicated
that the verb did not imply action
even if the expected
condition was
not found.
Others indicated that the necessary
action
was implied if an
operator
was licensed,
but not for a non-licensed
operator.
The writer's guide includes
a number of important definitions for action
verbs that are not included in the related
EOP lesson
plan.
For
example,
the verbs "verify," "close,"
and "control" are not included in
Lesson
Plan 02-REQ-006-344-2-20.
N2-EOP-5
PRODUCTION AND CONTROL OF
NMP2
REVISIONS
The writer'
guide contains
some guidance that is unclear
and not easily
understandable.
For example,
page
43 contains
the criteria for using
a
decision table for creating conditional
steps
rather than using questions
and decision
symbols.
Neither the
NRC team
human factors specialist
nor
the
NMP2
EOP coordinator could understand
this criteria as written.
Also
on page
43, the writer's guide describes
the criteria for including
multiple conditional
statements
in one decision table.
Again, neither of
the two individuals could understand
the guidance.
The writer's guide includes
some directions that are not sufficiently
restrictive to ensure
consistency
and fails to provide guidance for a
number of aspects
of the procedures.
For example:
l
27
The writer's guide briefly mentions
notes
on page
5; however, it
does not'rovide
a definition nor does it clearly describe
the
structure
and placement for notes within the .EOPs.
The writer's guide indicates
on page
57 that references
to tables
" ...
may either
be enclosed
in parentheses
or incorporated into step
wordings."
The writer's guide indicates
the
use of a requirement flag with
symbolic cross-references
(page 46), but fails to address
the proper
placement
or structure of the symbolic cross-references.
a
Although the writer'
.guide addresses
the acceptable
terms for
indicating branches
and cross references,
no method of emphasis
is
provided for this important
EOP component.
Guidance is not provided for the
use of the conjunctive "or," the
requirements
for use of plant nomenclature
in the procedures,
or
the
use of parentheses.
The writer's guide does
not address
the
need for consistent
use of
acronyms or terminology when referring to the
same
equipment or
system.
The writer's guide fails to provide usable criteria for the level
of detail to be included in the procedure
and does
not address
the
need to structure
steps with the
same
meaning identically.
The writer's guide includes
some guidance that is in conflict with NRC
guidance (e.g.,
and
and generally
accepted
good practices for EOPs.
-For example,
the writer's guide allows
the
use of embedded
logic statements
(p. 44).
In addition, it allows
notes,
actions,
and lists to be formatted identically.
The flowpath
structure for concurrent
steps
allows one of the concurrent
paths to
terminate without
a flowline connecting it to the next step to be
performed.
The writer's guide also fails to prohibit the
use of qualifier
phrases
such
as those
beginning with the term "except."
Some differences
were identified between
the
EOP writer's guide
and the
guidance
included in pro'cedure AI-1.0, "Site Procedures
Writer's Guide."
For example,
the definition for the term "vent" differed in each.
Also,
used for the
same
system varied within the
and operating
procedures
(e.g.,
WCS vs.'WCU).
4.
Flowcharts
A, number of inconsistencies
were identified throughout the flowcharts.
For example:
Action steps
are included within lists throughout the flowcharts
(e.g.,
N2-EOP-RP,
section
RL, section
RP,
and section
RQ;
N2-EOP-
Cl; and
N2-EOP-CS).
t
28
Decision table contingent action sections
("THEN ...I') also include
information that does
not require operator action (symbolic refer-
ences) (e.g.,
N2-EOP-RPV,
section
RQ;
N2-EOP-RR;
N2-EOP-MSL;
N2-EOP-Cl;
and N2-EOP-C5).
Symbolic references
(which require
no direct action) are included
with action steps
in action
symbols (e.g.,
N2-EOP-PC;
section
DWT).
Action symbols are also
used for symbolic references
which require
no direct action (e.g.,
N2-EOP-SC;
N2-EOP-Cl;
and N2-EOP-C5).
Specific terminology is used inconsistently.
For
example,
N2-EOP-C5
and
N2-EOP-C6
use the term "Maximum Primary Containment
Mater Level
Limit" in the conditional
section of the first step
and
use "the
curve" in the contingent action section of the
same
step.
The level of detail of action steps varies throughout the flowcharts and
in places
appears
insufficient, particularly with regard to the
use of the
term "if necessary"
(e.g.,
N2-EOP-PC,
section
PCP;
N2-EOP-C2;
N2-EOP-C4;-
and N2-EOP-C6).
For example:
The action statement
below step "L" in N2-EOP-C4 does
not clearly
state
how many systems
must be started
and if systems
once started
can
be secured
to establish
conditions before the minimum core
flooding interval time starts.
This caused
confusion
amongst
the
operators
during the simulator
scenarios
(Section 6.0).
Section
SPL of N2-EOP-PC directs
N2-OP-31
and N2-OP-33 to be used to
control level.
However,
the
EOP does
not state
which sections of
these
procedures
to use.
Phrases
beginning with the phrase "irrespective of ..." are
used
throughout the procedures,
though the subsequent
information appeared
unnecessary
to the performance
of the step
and most likely was
common
operator
knowledge.
Logic terms are
sometimes
used inappropriately (e.g
, "if" in N2-EOP-
RPV, section
RP;
"when" N2-EOP-C6
and N2-EOP-SC).
Qualifiers following
actions
are
used widely, leading to
a potential for the action being
completed prior to the qualifier being
read (e.g.,
N2-EOP-PC,
section
SPL;
N2-EOP-RPV,
section
RP;
N2-EOP-SC;
N2-EOP-C2;
and N2-EOP-C5).
Elements
not found .in the writer's guide are included within the flow-
charts (e.g.,
note in N2-EOP-C2; calculation tables
in N2-EOP-C4).
The flowpaths in N2-EOP-PC are not logically placed with respect to the
containment
parameters
that are monitored.
The flowpaths,
reading
from
left to right on the flowchart, are; drywell temperature,
suppression
pool
water level, containment
pressure,
and oxygen concentration,
and
suppression
pool temperature.
A more logical placement of flowpaths for
c
29
ease
of monitoring parameters
would be to group suppression
pool water
parameters
together
and drywell parameters
together.
"Yes" and "No" exits from decision
symbols are reversed
from the normal
format in two continuous decision
symbols in section
RQ of N2-EOP-RPV.
During simulator scenarios
operators incorrectly answered
the second
decision
symbol,
due to misreading
the. exit labeling.
That is, the
operator
read "Yes" in the "No" location in the
second
symbol,
as if the
exit placement
were identical to the preceding decision
symbol.
30
ATTACHMENT D
SIMULATION FACILITY REPORT
Facility Licensee:
Facility Name:=
Facility Docket Nos.:
EOP Scenarios
Administered on:
Niagara
Mohawk Power Corporation
Nine Mile Point Nuclear Station, Unit 2
50-410
January
29,
1991
This form is to be used only to report observations.
These observations
do not
constitute audit or inspection findings and are not, without further verifi-
cation
and review, indicative of non-compliance
with 10 CFR 55.45(b).
These
observations
do not affect
NRC certification or approval of'he simulation
facility other
than to provide information which may be used in future'evalu-
ations.
No licensee
action is required in response
to these
observations.
During the preparation
and administration of the
EOP i.nspection
scenarios,
the
following items were observed:
ITEM
DESCRIPTION
The
SLC manual out-of-service
push button does
not cause
an inop
2.)
The
RCIC system isolates
on high temperature
when
a loss of Division
1 or
2 power occurs.
3.)
4.)
5.)
The
ECCS injection flow check valves
open
when the'flow path (injec-
tion valve) is isolated.
The instructor station monitored parameter for suppression
pool level
deviates
by one foot from the
SPDS indicated
suppression
pool level.
The instructor station terminals occasionally
lock-up."
wp
% ~
~I