ML17055C590
| ML17055C590 | |
| Person / Time | |
|---|---|
| Site: | Nine Mile Point |
| Issue date: | 10/22/1986 |
| From: | Anderson C, Cheung L, Thomas Koshy, Paolino R, Woodard C NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML17055C588 | List: |
| References | |
| 50-410-86-37, IEB-77-05, IEB-77-5, IEB-78-02, IEB-78-04, IEB-78-2, IEB-78-4, IEB-79-01, IEB-79-1, IEC-78-08, IEC-78-8, IEIN-84-21, NUDOCS 8610310127 | |
| Download: ML17055C590 (54) | |
See also: IR 05000410/1986037
Text
U.S.
NUCLEAR REGULATORY COMMISSION
REGION I
Report
No.
50-410/86-37
Docket No.
50-410
License
No.
CPPR-112
Licensee:
Nia ara
Mohawk Power Cor oration
300 Erie Boulevard
West
S racuse
13202
Facility Name:
Nine Mile Point Nuclear
Power Station Unit-2
Inspection At:
Scriba
Inspection
Conducted:
Jul
14-18
Jul
28-Au ust
1
and
Au ust
11-15
1986
Inspectors:
T. Koshy,
Rea
or
n
neer
yzzz Z6
date
f~ C. Woodard,
ctor Engineer
d'd ZZ/EC
date
+dc
R. J. Paoli o,
ead Reactor
Engineer
date
~
L. S.
C eun
eactor
Engineer
date
Approved by:
C.
. Anderson,
Chief, Plant Systems
Section,
EB,
date
Ins ection Period
July
14
18, July 28
August 1,
and August
11 - 15,
1986
Report
No. 50-410/86-37).
Areas Ins ected:
Unannounced
routine inspections
in 'the areas of Instrumen-
tation and Instrumentation
Cable Installation.
Announced inspections
and in-
vestigations
in the review of licensee
actions
taken in the resolution of pre-
viously identified findings, construction deficiencies,
and open items.
Results:
One violation was identified (failure to comply with environmental
requirements
to assure
continued qualification of instrumentation
to perform
its safety function
10 CFR 50 Appendix
B Criterion V).
I
B610310127
B61023
i
<< 05000+10
DETAILS
1.0
Persons
Contacted
Stone
and Webster
En ineerin
Cor
Tom Johnson,
Chief Contruction Supervisor
Jeff Rodabayh,
Principal Field Engineer
Mark Hutchinson,
Construction
Supervisor
Den Robinson,
QC Inspector
R. Askew, Senior
QC Inspector
G. March, Assistant Superintendent,
FQC
Paul
Rutledge,
Test and Start
Up Group Supervisor
"T.
ST Farrell, Assistant Project Engineer
- James
Drake, Jr.
SU/T Special
Project Supervisor
- T. T. Arrington, Resident
Manager
A. Z. Pinter,
QC Engineer
E. J. Magilley, Assistant Superintendent
J
~ Gallagher,
Site Licensing Engineer
M. Sheldon,
Manager Administration Services
l. 2- Nia ara
Mohawk Power Cor oration
Gary Ptak,
Contract Administrator
M. Cummins,
Chief I&C Technician
- L. G. Fenton, Audit Group
"W. Hansen,
Manager Nuclear
QA Operation
~A. Kovac, Audit Supervisor
- R. B. Abbott, Station Superintendent
~A. Loveland,
EQ Engineer
- E ~
R. Klein, Manager Project Engineer
- K. A. Dahlby, Site Material
System
S.
K ~ Agarwal, Special
Projects
Engineer
J.
T.
Conway,
Power Ascension
Manager
A. D. Sassani,
Senior Engineer
M. J.
Ray,
Manager Special
Projects
R. Brady, Reactor
Engineer
J.
Swenszkowski,
QA Auditor
- I. Weakley,
Special
Projects
"D. Quamme,
Project Director
- C. S.
Beckham,
QE Supervisor
"T. B. Lee,
Special
Project
"W. D. Baker, Modification Engineer
"B. G. Hooten,
Executive Director Nuclear Operations
1.3
"P.
D. Eddy, Site Representative
~Attended the August 15,
1986 exit meeting.
,l
V
I
2.0
'Licensee Actions on Previousl
Identified Findin
s
Construction
Deficiencies
and 0 en Items
2,1
(Closed)
IE Bulletin 79-BU-01,79-01B Supplements
1,2,
and
3 relating
to Environmental qualification of 1E Equipment.
This bulletin was
issued to OL applicants.
This bulletin is superseded
by the requirements
of 10 CFR 50;49, the final rule
on Equipment qualification.
This item is closed.
2.2
(Closed)
IE Bulletin 79-BU-01A relating to deficiencies
in Environ-
mental. Qual,ification for ASCO solenoid valves
used in a Harsh Environ-
ment.
As identified in'the bulletin, the licensee
has
used the qual-
ified ASCO NP-1 valves for harsh environment applications.
In order
to prevent the inadvertent
use of thi s deficient solenoid valve,
a
controlled excluded list "Chm 12177-500ee"
is utilized in Category
1
procurement.
This item is closed.
2.3
(Closed)
IE Circular 78-CI-08. relating to Environmental Qualifi-
cation of Safety Related Electrical
Equipment.
This circular was
superseded
by the requirements
the final rule on
Equipment qualification.
This item is closed.
2.4
(Closed)
IE Bulletin 78-BU-04 relating to-environmental
qualification
of NAMCO D2400X and EA-170-302 limit switches
inside containment.
The
licensee
used the qualified
NAMCO limit switches.
The
NRC inspector
verified the qualification report in the Environmental Qualification
files.
The excluded list "Chm 12177-500ee
was also revised to pre-
vent inadvertent
procurement
of deficient
NAMCO limit switches for
safety related application.
This item is closed.
2 '
(Closed)
IE Bulletin 78-BU-02 relating to the
use of unprotected
terminal blocks for safety related application in a
LOCA environment.
In the containment
and in a steam environment
the licensee
has util-
ized qualified Raychem splices
instead of terminal blocks.
This item is closed.
'
2.6
(Closed)
IE Bulletin 77-BU-05 relating to the failure of Electrical
connectors
in a post-LOCA environment.
Based
on the analysis
provided
by GE in letter NMP2-2110,
these
connectors
are not exposed to
a
environment
when they are required to function.
The Main steam line
radiation monitors
sense
high radiation
from fuel damage
due to rod
dropsy
The connectors
located,
on the main
steam line could not be
adversely affected to prevent
them from performing their safety
function.
The connectors
on the Standby Liquid Control
system
(SLC) are
on the
explosive
squib valves.
The design basis for this valve to function
is fai lure to insert control rods.
These
connectors
can perform the
safety function since the desi'gn basis
does not,cause
a harsh environ-
ment.
For all other safety related applications
the licensee
has
used qualified ITT Canon type connectors.
This item is closed.
2.7
(Closed)
IE Notice 84-CI-21 relating to shorter service life of
Agastat
GP series
relays.
The
NRC inspector
reviewed the following licensee
procedures
to
verify their program to promptly replace
equipment before expiration
of the qualified life.
PP-131
Rev.0
Extraction of Maintenance
and Surveillance
data
required to maintain equipment qualification
AP-8.0 Rev. 1
Assurance of Equipment integrity
AP-8. 1 Rev. 1
Preventive
maintenance
N2-EPM-V13 Rev.0 Replacement
of Agastat relays.
The above corrective actions resolve this issue.
This item is closed.
2.8
(Closed) Construction deficiency 85-00-22 relating to failure of
Magnesium .rotors in MOVs located in a harsh environment.
This sub-
ject was subsequently
addressed
in IE Notice 86-02.
The General
Electric test Report
No.
NEOC-31049
Book No.
503A on the
subject
MOVs confirms the potential operability of these
valves for 7
days in a
LOCA environment.
The licensee
post accident operability
period for affected valves is one day.
Since the containment environ-
ment reaches
normal condition within one day, these
valves
can
be
manually operated
should remote capability be lost.
This item is closed.
r \\
0
~*
ji
2.9
(Closed) Construction deficiency 83-00-06 relating to the
use of in-
correct fission product inventory list.
The license revised
the
fission product inventory list using
new data supplied
by General
Electric.
This data is used to calculate
the accident
and service
environment (install integrated
dose) for safty related
components.
The
NRC inspector verified the revision to the specifications
and the
review of the equipment that was already
on hand.
The accident analysis
report in the
FSAR and the environmental
report were revised.
The
licensee
has
a procedure
(PP-53) for proper documentation
and approval
of similar changes
to the design criteria.
This item is closed.
2.10 (Closed)
Unresolved
Item (50-410/86-13-06)
relating to the adequacy
of the class
lE power supplies
and distribution to provide normal
running voltage to all class
lE motors
and loads within + 10% of
nameplate
voltage rating and to provide not less
than
805 of name-
plate voltage during worst case
motor starting transients
during
technical specification worst case
degraded
grid conditions.
The
inspector
reviewed the licensee
voltage profile test procedure
NNP2
E5.0300.001
and the test data obtained during conduct of the test.
- The test consisted of loading the class
1E buses,
obtaining steady
state voltage measurements,
and then starting various large class
1E
and
non class
1E loads
and measuring
the resulting
lowest voltage dip
on each of the buses.
The inspector also reviewed licensee verifi-
cation of Voltage Profile Study Program Test Results Calculation
EC-137 in which the measured
voltages
were
compared to the profile
study calculated
voltages.
The study verified the previous calcula-
tions and
showed that they were conservative.
The inspector
reviewed licensee verification calculation
EC-136 De-
graded Voltage Relay Set Point.
The EC-136
and
EC-137 calculations
and the actual
voltage
measurements
taken during test
E5.0300.001
provide the licensee with sufficient evidence that class
lE elect-
rical loads will be provided with adequate
voltage for proper
opera-
tion during both steady state
and transient operations
under the
worst case of degraded grid.
This item is closed.
2.11 (Closed) Violation B-2 (83-18-71).
SWEC procedures
used to accomplish
electrical
raceway installations,
installations of seismically-
mounted
equipment,
and power generation
control
complex
(PGCC) in-
stallations
and modifications were deficient with respect
to quan-
titative and/or qualitative acceptance
criteria.
The inspector verified that the licensee
had implemented corrective
actions
in all of the sub-category
open
items which constitute
the
violation by a review of all of the sub-category violation items and
those
NRC inspection reports which reviewed these
items
and closed
them.
The inspector also performed additional
independent verifi-
cation
by inspection of PGCC divisional separation
and inspection of
the separation
barriers
in cable trays
and raceways.
a
lp
Violation B-2 (83-18-71)
sub-category
corrective action items pre-
viously reviewed and,closed
in earlier
NRC Inspection
Reports
( IR)
are
as follows:
Category
2-83 Boltin
Com liance with Seismic
Re uirements
Subcate
or
NRC IR 0 en Item
83-18-20
-21
-22
-23
-79
-105
Category
3-83
PGCC Divisional
Se aration
Closed in
NRC IR No.
- 85-25
85-27
85-19
85-13
86-29
86-09
Subcate
or
NRC IR 0 en Item
Closed in
NRC IR No.
83-18-13
-73
-98
-112
85-12
85-12
86-09
86-18
Category
5-83
Racewa
Ins ection
For Se aration Barriers
Subcate
or
NRC IR 0 en Item
Closed in
NRC IR No.
83-18-01
-02
-98
-100
"103
85-12
85-12
86-09
86-09
86-09
Category
6-83 Ins ection Plan Deficiencies for Acce tance Criteria
Subcate
or
NRC-IR-0 en Item
83-18-05
-06
-07
-18 .
-97
-100
-103
Closed in
NRC IR No.
85-17
85"17
85-17
85-17
86-09
86-09
86-09
~ ~
The inspector
reviewed the following Nine Mile documents relating to
licensee corrective actions for this violation.
NMPC Project Procedure
PP 94,
"Review of Changes
and their
Effect on Qualification of Class
1E Environmental
and Seismic
Category I and II Equipment"
QA Surveillance
Reports W-84-492,
E-84-599,
E-84-553,
E-84-555,
E-84-951
and E-84-631.
These
surveillance
reports
include the following:
QA inspection
requirements,
plans, checklists,
inspection
reports
and audits
Engineering
and Design
Change
Requests
Nonconformance
and Disposition Reports
Seismic,
vendor,
and environmental qualifications
FMAC "Final Report of an Independent
Review of Nine Mile 2
Related
NRC CAT Inspections
and
SALP Report
and Niagara
Mohawk Identified Deficiencies".
Based
upon the foregoing actions
implemented in response
to
CAT Team Inspection Violation B-2, this item is closed.
2. 12 (Closed) Construction Deficiency Item 85-00-24.
This item relates to
a construction deficiency in which Niagara
Mohawk QA, during
a sur-
veillance inspection,
identified unsatisfactory
soldering connections
that were previously accepted
by
a Field Quality Control inspector.
The nonconforming solder connections
were found in Reactor
Water
Cleanup
and Recirculation Control Board Panel
2 CEC*PNL602.
This
deficiency was reported to
NRC in accordance
with 10 CFR 50.55(e)
by
letter dated August 23,
1985.
Investigation
and analysis of the problem by the licensee
revealed
that the improper acceptance
of this panel
was attributable to one
FQC inspector.
The
NRC inspector
reviewed the following licensee
actions
taken to
resolve this issue.
1.
Complete
100% re-inspection
of all solder inspections
performed
by'he problem inspector.
This involved recalling
and
re-inspecting
work covered
by 22 previous inspection reports.
2.
Verifying the performance of other
FQ inspectors
by surveillance
inspection of 20 of their completed
inspections
of solder work.
~ '
p I-
j<e
S
t,h
3.
Evaluating the adequacy of the training program
used in training
and qualifying
FQ inspectors
to inspect
soldered
connections
including updating
and retraining courses
for the inspectors.
4.
Reworking all identified unsatisfactory
solder connections.
5.
NMP-2 site
QA Evaluation
and Verification Report of Documen-
tation
and Supporting Inspections
dated July 16,
1986 relative
to the subject 50-55(e) construction deficiency item.
The solder connections
in Panel
2 CEC"PNL602 which led to this con-
struction deficiency item were inspected
by the
NRC inspector in
addition to similar connections
in panels
2 CEC~PNL601
and
2 CEC~PNL871.
No unsatisfactory
solder connections
were observed.
This item is closed.
2. 13 (Closed)
Unresolved
Item 50-410/83-08-02.
This item relates
to
a
discrepancy
between
the
NMP-2 commitment to Regulatory
Guide
1. 100
August
1977
and
and
FSAR commitments
on Page
3. 10B-2
relative to the seismic qualification of certain
equipment within the
GE scope of supply.
The inspector verified the licensee's
corrective actions
taken to
resolve this discrepancy
by Amendment
22 page
3. 10B-2 of the
FSAR dated
November
1985 which now clarifies in paragraph
3. 10.2. 1B
"Methods of showing
Equipment
Compliance with IEEE 344-1975
and
Regulatory Guide
1. 100".
This item is closed
2. 14 (Closed) Construction Deficiency Item 50-410/86-00-04.
Cooper
sup-
plied standby diesel
generator
2
EES*EG 61 did not meet its 10-second
starting requirement
due to the slow retraction of the fuel control
cylinder.
This cylinder is extended
in the fuel-off condition and is
retracted
in the fuel-on condition by
a combination of air pressure
and
an internal
compression
spring.
The actual starting time was
13
seconds
for the first start
and less
than
10 seconds
for successive
starts.
This deficiency was reported to
NRC in accordance
with 10 CFR 50.55(e).
Analyses of the problem by the licensee
and the manufacturer
revealed
that the fuel cylinder liner material
was being eroded
by the
harder
compressor
spring material
causing galling and binding.
Corrective actions
taken
by the licensee
were to replace
the fuel
control cylinders
on both Division I and II emergency diesels with
harder Armaloy lined cylinders provided by the manufacturer
to re-
solve this problem.
'
tP
F'
R
The inspector confirmed the licensee's
documentation
of the replace-
ment including NMPC-gA Evaluation
and Verification of the replace-
ments.
This item is closed.
2.15 (Closed) Construction Deficiency Item 50-410/86-00-07.
This defici-
ency is related to an excessive
vibration problem with the low pres-
sure fuel oil supply lines
on the Division I and II standby
emergency
diesel
generators
(EDG).
This vibration led to
a pin hole leak
in the Division I 2 EGS"EGl fuel oil line.
This deficiency was re-
ported to the
NRC by the licensee
in accordance
with 10 CFR 50.55(e)
on
May 8,
1986.
Evaluation of the deficiency and its causes
by the licensee
and the
EDG supplier (Cooper) led to replacement
of the
damaged
fuel oil
lines
on both the Division I and II EDG units and to the installation
of plastic coated fuel line support brackets.
This work was
completed
by the licensee
under Engineering
Design
and Coordination
Reports
C46953
and C47192.
The inspector verified the work performed to correct this deficiency
by physical
inspection of Division I
EDG 2 EGS*EGl and by
a review of
the completed
EEDCR reports including the site
gA Evaluation
and
Verification Report.
This item is closed.
2. 16 (Closed) Violation Item 50-410/86-08-02.
This
item relates
to violations of licensee
FSAR and Electrical Specifi-
cation
E061A Class
1E cable separation
procedure
requirements.
The
inspector
had identified Class
1E electrical
cable
2EGPNGX001
on the
west side of the control building at the control
room elevation of
cable penetration
2WX564G01 which did not have sufficient separation
from non-division class
cables
out of penetration
2WC564N02.
The inspector
found that the licensee
had recently performed work to
the penetration
seals
which required slackening of cables
in the
area which led to the cable separation
violation.
The
inspector confirmed the licensee's
corrective action by a physical
inspection of cable separation
in the areas
of the violation.
The
inspector
found that the licensee
had achieved
the required
separa-
tion of the cable identified in the violation and eight additional
cables
by the installation of Si 1-Temp fire wrap and metal barriers.
This item is closed.
eC
10
2.17 (Closed) Violation 50-410/86-13-08.
Licensee specification
C081 for
instrument installation required that instrument lines shall
be
tagged with identification marking
on both sides of a wall or floor.
Contrary to this the inspector identified three
instances
where in-
strument lines were not properly identified on either side of their
drywell penetration.
The inspector
reviewed licensee
actions
taken to resolve the problem
as follows:
Specification
C081
was revised to permit identification tagging
of instrument lines outside the drywell to be approximately
6
feet from the penetration
in the vicinity of the excess
flow
The specification
was further revised
so that
instrument lines passing
through the biological shield wall need
be tagged only'outside
the wall and lines underneath
the sup-
pression
pool water level
need not be tagged.
2.
The licensee
under Engineering
and Design
Change
Request
F13539A
performed work to tag all instrument lines both inside and out-
side the drywell in accordance
with the revision to specifi-
cation
C081A.
The inspector
performed
a random audit of licensee identification
tagging of the instrument lines by inspection of the following lines
inside the drywell containment:
and
2 ISC-750-335-3,.
No discrepanices
were observed.
The inspector also
reviewed the
NMPC Site
QA Evaluation
and Verification of satisfactory
completion of the tagging in accordance
with specification
C081A,
Revision
5 and
E 8
OCR F13539A.
This item is closed.
2. 18 (Closed) Construction Deficiency Items 82-00-17 83-00-03,
83-00-07,
83-00-17.
These construction deficiency items are Environmental
gualification failures, of operational
components
in the post
Recombiner units supplied
by Rockwell International.
These
items
and their reporting are
summarized
as follows:
Item
82-00-17
Descri tion
Bar ton Pressure
Transducer
Models D4R29098
Re ort to
NRC
10 CFR 21 by letter
10/21/82
by
letter 11/19/82
I
1
h
11
83-00-03
83"00-07
83-00-17
Square
D Disconnect
switch P/N 9422-RC-1
Microswitch
P/N 12TSI-2
ITE Gould Ciruit
Breaker
P/N EF-3-3015
10 CFR 21 by letter
11/3/82
by
telephone
1/26/83
by
1 etter 9/1/83
by
letter 3/26/83
The inspector
reviewed the Rockwell qualification report 290(}R000031,
dated October
16,
1985,
and the warranty of the Hydrogen
Recombiner
unit including modifications
and replacement
components
to meet the
Environmental gualification requirements
of IEEE 323-1974.
The inspector verified actions
taken
by the licensee
in accordance
with Rockwell Technical
Services Bulletin 82ESG-8933 for
modifications
needed for environmental qualification.
The modifi-
cations
were
as follows:
Item
82-00-17
83-00-03
83-00-07
83-00-17
Modification Descri tion
Replace
Barton pressure
Transducer with qualified
Gould series
3200 Transducer
Modify disconnect
switch electrical
circuitry to eliminate the disconnect
switch
Modify the microswitch electrical
ci rcuitry to el iminate the
microswi tch
Modify the circuit breaker electrical
circuitry and components
to replace
the
circuit breaker with qualified Gould A4J10
fuses
and 60356J
fuse blocks.
The inspector
reviewed the licensee final verification of the 50.55e
Recombiner Corrective Actions Implementation
Report
No.
E
86-00051 dated January
29,
1986.
The report verified both equipment
modifications and drawings revision to reflect the changes.
The
inspector verified equipment modifications by inspection of the
Division 2 Hydrogen
Recombiner Unit and power supply cabinet
and also
confirmed the equipment
and
system
drawi'ng revision.
This item is closed'
/
Al ~
12
2.19 (Closed)
Unresolved
Item (50-410/83-08-04).
This item is related to
the seismic qualification of the Gould supplied Class
1E Motor Con-
trol Centers
(MCC) and to certain wiring deficiencies within the
units.
The wiring deficiencies
were previously addressed
and cor-
rected
by the licensee
and are closed out in
NRC inspection report
85-44.
The inspector
found that the licensee
had addressed
the seismic
qualification question
by requiring that Wyle Laboratories
conduct
additional
seismic tests with MCC units simulating the installations
at NMP-2.
The seismic qualification tests
report disclosed
the
need
for additional
support brackets within the
MCC units and properly
welding the
MCC Unit bases
to the floor sills.
The inspector
reviewed the licensee's
Seismic Certification Report
and inspected
the licensee's
installation of the additional
seismic
supports
and
base welding in accordance
with the seismic qualifica-
tion report.
The inspector also reviewed licensee site
gA Evaluation
and the Verification report for seismic qualification dated
January
20,
1986.
This item is closed.
2.20 (Closed) Construction Deficiency Unresolved
Item 50-410/85-00-29.
This item relates
to an improperly sized excitation
impedance
match-
ing resistor in the
HPCS diesel
generator control circuitry.
This
deficiency was reported to the
NRC in accordance
with 10 CFR 50.55e
by letter January
13',
1986.
The licensee
and the
HPCS supplier
(Stewart
and Stevenson)
'evaluation disclosed that the resistor
sup-
plied with the voltage regulator would not permit sufficient signal
adjustment
to the generator exciter to achieve
the full 2600kw
1950kvar rated output of the generator.
Optimization of the imped-
ance matching resistor
led to replacing the
50
ohm with a
25
ohm
resistor.
The inspector
reviewed licensee
documents
covering the change includ-
ing
DR 07441 (replacement),
gCIR 2-86-1584
and 2-86-2145 (g-C in-
spections),
and
PR 01689 (revision of drawings).
The inspector also
verified the resistor
replacement
including qualification, location
and mounting.
This item is closed.
2.21 (Closed) Construction Deficiency Item 86-00-10 'his construction
deficiency relates
to cracks in Bendix supplied Division I and II
emergency diesel
generators
fuel injector delivery valve holder fit-
tings (P/N 10-328469-3).
This deficiency was reported
by the lic-
ensee
in accordance
with 10 CFR 50.55(e)
by letter
on May 30,
1986.
Examination
and analysis of the problem by the licensee
revealed that
the fittings were not made in accordance
with the design drawing.
An improper radius of the fitting created
excessive
stress
in the
fitting at
a sharp
edge causing
the cr'acking.
( \\.
1(
A
441
13
Bendix supplied proper replacement fittings.
These
were inspected
by
the licensee
and installed'.
The inspector
reviewed the licensee
documentation
of the replacement
and the site
gA Evaluation, Verifi-
cation
and acceptance
of the replacement.
This item is closed.
2.22 (Closed) Construction Deficiency Item 86-00-12.
This contruction
deficiency relates
to improperly fitted air start valve seat inserts
for two valves in the Division I emergency
diesel
generator.
It was
reported to
NRC by the licensee
in accordance
with 10 CFR 50.55(e)
on
June
25,
1986.
These valve seats
are supplied
by Cooper
Energy
Services
as
an integral part of the cylinder head.
The valve seat inserts
on cylinders
3 and
7 were found to be loose
(one due to an undersize
and one
due to an oversize fitting problem).
The licensee
inspected
and tested all the remaining air start valve
seats
inserts
in both division
1 and
2 diesels
and found them to be
acceptable.'he
deficient valve seats
inserts
were replaced with
proper fitting inserts.
The inspector
reviewed the licensee's
documentation
of the inspection
and replacement
and reviewed the Site
QA Evaluation, verification and
acceptance
of the replacement.
This item is closed.
2.23 (Closed)
Unresolved
Item 86-13-10 'his item relates
to Stone
and
Webster
(SWEC) Balance of Plant
ESF Actuation Logic diagrams
12177-
LSK-27-19G and
19H in which
SWEC identifications corresponding
to the
GE identifications were not correlated.
(The inspector
had pre-
viously verified that
SWEC had correlated all other similar documents
with both the
GE and
SWEC identifications).
The inspector confirmed
licensee
actions
taken to correct this deficiency through Engineering
Change
Notices
ECN 602,
606 and 607.
This item is closed.
2.24 (Closed) Construction Deficiency Item 50-410/86-00-03.
This defici-
ency is related to factory installed jumpers across
reactor protect-
ion "Thermal
High Trip output relays
K19 and
K20.
. These jumpers
would inhibit reactor protection
system
response
to
a thermal trip.
This deficiency was reported to the
NRC by the licensee
in accordance
with 10 CFR 50.55(e)
on March 26,
1986.
Evaluation of the safety
consequences
of the loss of thermal trip
were
made
and reported
by
GE letter dated April 24,
1986.
GE"con-
cluded that "this condition would not have adversely affected the
safety of operation of the plant at any time throughout the expected
P
i
E'
0
4
a ~
'
lifetime of the plant were it to have
remained uncorrected.
It is
therefore
recommended
that Niagara
Mohawk Power Corporation act
on
this conern
as not reportable
per
The licensee
advised
NRC accordingly
on April 25,
1986.
The inspector
reviewed licensee
actions
taken to correct the problem
including
GE Field Deviation Disposition Report K61-4895,
NMP-2 De-
ficiency Report 09955
and Engineering
and Design Coordination
Report
E & CDR C46438 which removed the jumpers thus enabling
the
RPS ther-
mal trips.
This item is closed.
2.25 (Closed)
Construction Deficiency Item 84-00-46.
This deficiency
relates
to licensee identified incorrect wiring of torque switches
on Clow Corporation
supplied Limitorque valves.
These deficiencies
were reported to the
NRC in accordance
with 10 CFR 50.55(e)
by letter
dated
May 17,
198S.
The inspector
reviewed the following licensee
documentation
of the
deficiencies,
investigations,
and correction of the problems.
Engineering
and Design Coordination
Report
(E&DCR)
F 20,541
Nonconformance
and Disposition Report
No. 11,892
Inspection
Reports of work performed
under
E & DCR F20,541-
Reports
E5A83 102 and
ESA48845
Closed
E & DCRs F20,532
and F12,709 which provided the drawing
changes
for the Limitorque-changes
in
N & DR 11,892
License site
gA Evaluation
and Verification Report dated July 3,
1986 in which the correction disposition
was found complete
and
acceptable.
This item is closed.
2.26 (Closed) Construction Deficiency 86-00-15.
This construction def-
iciency relates
to a problem with the moderate
energy line crack
(leak) detection
temperature
switches
which are
used to respond to an
'ir
temperature
rise resulting
from a leak in the
RHR system.
The
licensee
found that the response
time for these
switches is too long
to detect
and isolate moderate
energy cracks within the time frame
consistent with the equipment qualification analysis.
This defici-
ency was reported to the
NRC in accordance
with 10 CFR 50.55(e)
on
July 8,
1986.
L
15
The inspector
reviewed the following licensee
documentation
of the
evaluation,,modifications,
and
QA verification of the modifications.
1.
May 23,
1986 and Problem Report
dated
May 12,
1986.
These
documents
are the basis of the
"Description of the Problem
and Analysis of Safety Implica-
tions".
2.
E&DCR Y04011A which provided the engineering directions to
replace
the existing temperature
switches with faster
response
PYCo units.
3.
SWEC Inspection
Report
16A80902 which shows acceptable
replace-
ment in accordance
with E8DCR Y04011A.
4.
NMP-2 site
QA Evaluation
and Verification documentation
of the
Correction of Construction Deficiency 86-00-15 dated August 13,
1986.
Based
upon the licensee's
corrective actions this item is closed
2.27 (Closed) Construction Deficiency Item 86-00-16.
This deficiency
relates to improperly-installed
GE supplied
PYCo temperature
sen-
sing elements
which are
used to detect
pipe line breaks (leaks)
in
the
RHR,
RCIC,
RWCS and
MSS systems.
These detectors
were installed
enclosed within pipe sleeves
that prevent air from directly impinging
upon them.
At the time of qualification, these
elements
were exposed
to air.
Early detection of pipe line breaks
and their early isola-
tion are essential
to minimize blowdown which could expose
safety-
related
equipment to temperatures'nd
pressures
outside their environ-
mental qualification envelope.
This deficiency was reported to
NRC in accordance
with 10 CFR 50.
55(e)
on July 10,
1986.
The inspector
reviewed the licensee's
analysis of the deficiency,
corrective actions taken,
and
QA/QC verification and acceptance
as
contained
in the following documents.
1.
SWEC Letter Report of the 50.55(e)
problem to Niagara
Mohawk
dated July 2,
1986.
2.
E 5
OCR 203135 analysis
and report of the problem
PYCo type
thermocouples
dated
June
6,
1986.
1
h
16
3.
E&DCR Y18911B,
Y18935 and Y1835B which provided the cor-
rective actions.
This included relocation of temperature
ele-
ments, cutting/relocating
supports
and/or cutting
a section of
the pipe insulation to expose
the sensing
elements
to air.
4.
gA/gC inspection
and acceptance
of completed work for E&DCR's
in 3 above.
2.28
Based
upon the licensee's
corrective actions, this item is closed.
(Closed) Construction Deficiency Report 84-00-36.
This deficiency
was related to the operation of curtain-type fire dampers
supplied
by
Pacific Air Products.
During operability tests for gA-Category II
&-IIIdampers, it was Noted that
some
dampers -failed to satisfacto-
rilyy
close
under air flow and pressure
conditions.
The licensee,
therefore,
evaluated
similar dampers
in category-I
systems.
In order
to verify the operability of dampers
in category-I
a test
program was
implemented.
Of the fifty-one (51) dampers
tested
under this program,
forty-four were found satisfactory.
The'remaining
seven
required
modification.
The modification was completed
and the dampers
were
successfully
tested to indicate proper operability.
This item is closed.
2.29 (Closed)
IE Bulletin 80-BU-16 relating to potential misapplication of .
Rosemount transmitters with either
A or
D output codes.
This was
perviously closed
as
a construction deficiency item in inspection
report 50-410/82-12.
This item is closed.
2.30 (Closed)
Finding (86-08-04) relating to damaged
instrument tubing
K117 and impulse line of 2RHS * PDT24B.
The licensee
has performed
the corrective actions through Deficiency Report ¹21062.
The in-
spector verified that the licensee's
training program offers added
emphasis
for employee
awareness
to preclude similar act of negli-
gence.
Moveover, the startup organization
has committed to perform
a
final walkdown prior to fuel load to assure
that instrument tubing is
free from any damage.
This item is closed.
2.31 (Closed)
Finding 86-08-05 relating to noncompliance with slope require-
ments in installation drawings.
The licensee
has re-inspected
65% of
all line segments
for the Reactor
Pressure
Vessel
level
and recircu-
lation system
and performed corrective actions/analysis
to confirm
the absence
of a negative
slope
and effective positive slope.
General Electric has identified the
RPV level
and Recirculation
system to be most sensitive to slope requirements.
FDDRs KG1-2724,
0688,
0701,
0708,
0448 provide adequate justification and corrective
action to alleviate the above concern.
This item is closed,
k
~
%
ff
W
I
l
)
17
2.32 (Closed)
IE Bulletin No. 86-BU-02 relating to the erratic behavior of
Static 0 Ring differential pressure
switches belonging to series
102
and
103.
The licensee
does not utilize the above referred type of
Static
0 Ring pressure
switches.
This item is closed
2.33 (Closed)
IE Circular 80-CI-16 relating to operational
deficiencies
in
Rosemaunt
Model
510
DU trip units and Model
1152 pressure
transmit-
ters.
The licensee
has clarified from GE, the supplier that two
Rosemount
model
510DU trip units were reworked
by the manufacturers.
This was the only remaining concern identified by inspection report
82-12.
This item is closed.
2.34 (Closed) Construction deficiency 86-00-06 relating to loose conduit
fitting that connects
environmental
seals to the various instruments.
The licensee
has modified the installation
away from the travel
direction
and tightened the loose fittings.
The
NRC inspector re-
viewed the corrective actions
performed
under
Noncomformance
Dis-
position Report 816884,
14791
and verified the field installations.
No discrepancies
were observed.
This item is closed.
2.35 (Closed)
Unresolved
Item 50-410/86-13-09.
This item relates to lic-
ensee
actions required to verify scram pilot valve voltages,
to con-
firm the selection of Electrical Protection
Assembly
(EPA) trip set-
tings,
and Technical Specification allowable voltage values in order
to assure
protection of the
scram solenoids within the
105-125
VAC
tolerance
range.
The inspector confirmed licensee
action taken
as
follows:
Scram pilot valve voltages
have
been verified, voltage calcul-
ations
12177
EC-125 Revisions
2 and
3 further verify that the
EPA voltage trip settings
as
shown in the technical specifi-
cation will provide adequate
protection for the
scram pilot
solenoids within the specified voltage tolerance
range of 105 to
125
VAC for all conditions of operation.
Technical Specification
Paragraph
4.8.4.5
has
been revised to
provide allowable voltage values for all conditions of operation.
Licensee actions
taken
appear to provide assurance
that the
scram pilot solenoids
are adequately
protected.
This item is closed.
il
t
18
2.36 (Closed)
Unresolved
Item 85-03-02 relating to unqualified flow trans-
mitters
and lack of documentation
to indicate that manufacturer
corrective action
has
been
performed.
The licensee
has completed
the corrective actions in replacing flow
transmitters with the qualified Rosemount
1153 transmitters.
The
inspector
reviewed documents
N&D Nos.
12134,
E&DCR ¹F02057
and
verified field installations at random.
NMP-2 has the following procedures
to document unqualified equipment
and track the corrective
actions.
PP.76
Control of
SWEC Supplied
Equipment requiring
qualification.
II
QS. 15. 1
Nonconformance
and Disposition Report.
QS. 14.2
Inspection
Report System.
This item is closed.
2.37 (Closed) Construction Deficiency 86-00-17 relating to cracked contact
levers
on
NAMCO EA180 limit switches
mounted
on MSIV.
The licensee
has
done
a complete inspection of all Category I
NAMCO
EA170 and
EA180 series of limit switches.
All the cracked levers
were replaced.
Engineering
& Design Coordination
Report ¹C4112B
documents
the corrective action.
This item is closed.
2.38 (Closed)
Unresolved
Item 86-18-04 pertaining to the
NRC Electrical,
Instrumentation
and Control
Systems
Branch ( EICSB) site audit of
January 7,8 & 9,
1986.
The purpose of the site visit was to verify
that the installation of electrical
instrumentation
and control
equipment
conforms to applicable design criteria regarding phyical
separation
between
redundant
safety related circuits and between
safety-related
and non-safety related circuits.
In addition,
the site
review included verification that the actual installation
was con-
sistent with the staff's understanding
of the design
based
on applic-
able
FSAR schematics
and diagrams.
Specific concerns
were identified by the
NRC EICSB staff in six areas
for followup by Region I personnel
as follows:
1.
Verification that the
one inch and (as applicable)
six inch se-
paration is maintained
between
non divisional cabling
and div-
isional cabling
and between different divisional cabling within
panel
nos.
602,
603,
608B, 852,
880A, 880B,
880C & 880D.
4
,IJ
11
r,
19
The inspector
reviewed Deficiency Report nos.
13124,
19045,
17421,
17420
and Quality Control Inspection
Report
nos - (QCIR)
2-86-6637,
2-86-5225,
2-86-5965,
2-86-5970
and 2-86-6032.
Identifying corrective actions
taken to correct separation
deficiencies.
In addition,
a visual observation of work was
performed
by the inspector to verify corrective actions.
Panel
no.
H13-6088 internal
separation
is exempt from meeting
the literal requirements
of Regulatory Guide 1.75 per General
Electric document
no.
304A2638 Revision 0,
sheet
no.
33 and
licensee
procedure
no.
E-062A, section 8.2.9 line 8.47 -8.50
and
FSAR item 8, Table 421.47-1
Amendment
17.
This item is closed.
Verification of RRCS divisional cabling separation
of
1 inch
between
channels
A and
B of Division
1 and channels
A and
D of
Division 2.
Addressed
in item
1 above
(Panel
602/603).
Verification of nomenclature
associated
with RCIC System trip
units located in Panel
629.
The inspector
reviewed Deficiency Report
No.
12193 identifying
problem marker plates
and replacement .with correct marker plate
per
E&OCR ¹C-46469.
The marker plate
was revised per
FDDR
No.
KG1-4941 Revision
0 and
GE engraving drawing No.
137C6497
Revision 3.
This item is closed.
Verification that conduit and cabling designations'ithin
Remote
Shutdown
Panel
are correct.
The inspector
reviewed the Nonconformance
and Disposition Report
(N 4 0) No.
11545 identifying nonconformities in color coding of
Division and non-division conduit and improper location of
marker sleeves
on right bank of switches
No.
SW2-2RSSN81
for
Remote
Shutdown
Panel
405.
The verification of the corrective
action per
EKOCR ¹F-40545 included application of GE FDI-TYLR
marker tapes.
The switch marker sleeves
were determined to be
acceptable
with engineering
authorized "use-as-is".
This item is closed.
4v
0
20
5.
Verification of Installation of acoustic monitoring system,
scram discharge
instrume'nt
volume and the turbine first stage
pressure
transmitters.
The inspector
reviewed vendor level switch drawings
and
drawing
159C4361
change
1 & 2 verifying installation of scram
discharge
volume instrumentation.
For the turbine first stage
pressure
transmitter
the inspector verified that the installed
pressure
transmitter
was
2MSS * PT16C&0.
The acoustic monitor
has
been installed.
Preoperational
test
No. 86 was performed
with the test data
reviewed
and approved
by
SORC
on April 24,
1986.
This item is closed.
6.
Verification of nomenclature utilized in main
steam line flow
transmitter instrument racks.
The inspector
reviewed
GE drawings
EK-401G,
M; FSK-3-1A,
H and
design specification
No.
22A5257 identifying design
requirements
for locally mounted instruments of the nuclear
steam
supply
system
and loop diagram
No.
2MSS-A & B identifying the
mar k Nos.
for instruments of the main
steam line flow verifying nomencla-
ture
used is consistent with applicable designations.
This item is closed.
2.39 (Open) Construction Oeficiency 86-00-14.
This deficiency relates
to
possible insufficient control voltage present at
some
120
VAC and
125
VAC control device terminals
such that the devices
may not operate
when considering
the minimum design voltages at the distribution
system.
The inspector confirmed that the licensee
had performed
a control
circuit length verification study in response
to
INPO Finding
DC 3-1,
item
C in order to evaluate
the terminal voltages available for
operation.
In performing the control circuit length verification
study the following parameters
were considered:
Minimum voltage required for the operation of the device
on
equipment
connected
to the circuit
Minimum voltage available at the power source
Cable size
and length
As
a result of the study,
the licensee
concluded that
some circuits
exhibited excessive
voltage drop to the powered devices.
In order
to provide adequate
voltage,
the licensee either modified the circuit
to reduce electrical
resistance
or used interposing relays.
1
'%
0
21
The inspector
reviewed licensee
engineering
and design
change
req-
uests
Y07801,
Y07801B,
Y07801E,
and Y07804 which covered the modifi-
cations to assure
adequate
control voltage.
All work on these
E&DCRs
has
been
completed evaluated
and verified by NMP-2 Site
gA except for
work on the
RCIC system
under
E&OCR Y07804.
To prevent recur rence of
this problem
NMP-2 engineering will review all future
MOV,
SOV and
MOD circuits to ensure
that the minimum voltage requirements
of these
devices
are satisfied.
2.40
The licensee
has committed to complete
E&OCR Y07804 relating to the
RCIC system prior to initial criticality. It is noted that this
system
serves
no safety function prior to initial criticality.
This
item remains
open pending completion of E&OCR Y07804.
(Closed) Construction Deficiency 83-00-04 relating to an
inconsistency of separation criteria notes in the General
Electric
wiring/fabrication drawing.
The licensee
has
documented
the above
deficiencies
in Nonconformance
Reports
53,
55
& 56.
The inspector
reviewed the relevant excerpts of the following documents
to verify
the licensee's
corrective actions
and compliance to the criteria.
Reference:
1.
FSAR Ch.8 Section
3 Amendment
26
2.
FSAR Table 421.47-1
Amendment
17
3.
Specification for Electrical Installation
& Field Modification
to PGCC,
E062A Rev.2 dated
December
2,
1985
4.
FODR ¹KG1-3898
5.
Surveillance
Report 85-00887
6.
GE letter NMP2-5024 dated
May 3,
1983
Ref:
2 note
2 covers the
use of Sil-Temp tape
as
a barrier within the
panel
wherever separation
distance
cannot
be mentioned.
The use
of,
flexible/rigid conduit or steel barriers
as
a separation barrier is
covered in note.
3 of the
same reference.
Based
on the above,
the
NRC inspector
randomly inspected corrective actions in H13-P601
&
P602.
No deficiencies
were found.
This item is closed.
2.41 (Closed) Construction deficiency 84-00-14 relating to nonconformances
to separation criteria in Power Generations
Control
Complex
(PGCC).
The nonconformances
extended
to between divisions,
between
channels,
and between divisions and channels.
1
I<5
E
22
In order to facilitate installation,
compliance
and verification
General Electric has clarified their separation
requirements
in a
criteria document titled "Power Generation
Control
Complex Separation
Practices
Handbook" dated
February
21,
1985.
This is
a supplement to
"Specification for Electrical Installation
& Field Modification to
PGCC" E062A, Rev.2, dated
December
2,
1985.
The inspector
reviewed the following documents:
1.
Nonconformance
Report 53, which documents
the subject problem.
2.
Test Report
on Electrical Separation
& Verification 1.613-5001
Rev.B.
by Wyle lab.
3.
Verification and Closure of Nonconformance
Report No.53.
As per
FSAR table 421.47-1
Note
2 and
3 (Amendment 17),
NMP2 uses
Si 1
Temp tape, flexible/rigid conduit or steel
enclosures
as
a barrier
whenever separation
distances
cannot
be maintained.
Based
on the
above
documents
the inspector
randomly selected
cabinets
H13-P609,
631
& 602 and verified the installation against
the revised
separa-
tion/compatibility table in GE
FDDR 03898..
No deficiencies
were
observed.
This item is closed.
2.42 (Closed) Construction deficiency 84-00-32 relating to lack of se-
paration distance/barriers/isolation
devices
in HPCS switchgear
and
control panels.
The inspector verified the selected
corrective
actions
performed
under
FODR KG1-2396,
2398 and
2974 based
on the
following documents:
1.
Specification for Electrical Installation
E061A Rev. 11 March 21,
1986.
2.
FSAR Chapter
8 Section
3 Amendment
26
3.
FSAR Table 421.47-1
Amendment
17.
No deficiencies
were identified.
This item is closed.
3.0
Instrumentation Installation
Com onents
and
S stem
3.1
Installation Work Observation
The. inspector
examined
work performance
pertaining to the instal-
lation of safety related
instruments
in the High Pressure
System to determine
whether
the requirements
of applicable specifi-
cations,
NRC requirements
and licensee
commitments
were
made in the
areas
of instrument installation,
procurement,
and quality control
inspection.
l
C4
.23
3.2
Items examined for this inspection
include:
a)')
c)
d)
e)
g)
k)
Safety related'HPCS
pump suction
and discharge
pressure
trans-
mitters
2CSH~PT-102
and
PT-105
(GE No.
E22-N052
and N051)
mounted in
GE instrument rack H22-P024 in the Reactor Building
at elevation 175'outheast
corner.
Safety related
HPCS flow transmitters
2 CSH"FT-144 and
145
(GE
No.
E22-N005
and N056),
HPCS flow, both located in GE instrument
rack H22-P024 in the Reactor Building at elevation 175',
South-
east corner.
Safety related
suppression
pool water level transmitters
2CSH*
LT-123 and LT-124, located in the Reactor Building at elevation
175',
Southeast
corner.
Safety related
B1F venturi flow element
2CSH*FE-105, lo-
cated in the
pump
room in the Reactor Building at elevation
175'.
Stone
and Webster flow diagram
FSK-27-4B "High Pressure
Core
Spray"
Revi sion 6, dated Apri 1 29, .1985.
Stone
and Webster flow diagram
FSK-27-4C "High Pressure
Core
Spray" Revision 7, dated April 29,
1985.
Stone
and Webster Specification
No.
NMP2-C011M for Pipe Insert
Type Venturi Flow Sections,
addendum
5 dated
February
17,
1982
and data
sheet for 2CSH"FE-105 (16" BIF Model 0183-16).
GE Drawings
No 188C 7360, Specification for Transmitters
E22-
N005,-N051,-N056,
Sheet
1 Revision 5, dated
June
24,
1985,
sheet
2 5 3, Revision 3, dated June
15,
1984.
GE Drawings
No.
184 C4775
Level Transmitters with Pressure
Seal
System,
transmitters
E22-N055C
and
N055G; Sheets
1 and 2,
Re-
vision
4 dated
May 9,
1984.
GE Drawings No.
163 C1563,
Gage
Pressure
Transmi,tters,
E22-N052,
sheets
1 and 2, Revision
10 dated July 16,
1981.
Isometric drawings for flow transmitters
2 CSH*FT 104 and
FT
105:
12177-DK-410ED,
Revision
3 dated January
24,
1986.
12177-DK-410EB,
Revision
3 dated January
29,
1986.
12177-DK-410EC-1,
Revision
1, dated July 27,
1983
12177-DK-410EE-2,
Revision 2, dated
November 9,
1984.
'
't
lh
1
t
24
1)
Isometric drawings for level transmitters
2 CSH*LT 123 and
LT
124
n
12177-DK-410DH, Revision
1, dated
November
14,
1984.
m)
Isometric drawings for pressure
transmitters
2 CSH~PT 103:
12177-DK-410DY-2, Revision 2, dated
June
10,
1986.
12177-DK-410DZ-1,
Revision
1, dated July 25,
1983.
12177-DK-410EA-l, Revision
1, dated July 25,
1983.
n)
Isometric drawing for pressure
transmitter
2 CSH"PT 105:
12177-DK-410DS-4,
12177-DK-410DT-1,
12177-DK-410DU-1,
12177-DK-410EJ-1,
Revision 4, dated January
29,
1986.
Revision
1, dated July 29,
1983.
Revision
1, dated July 29,
1983.
Revision
1, dated July 29,
1983.
3.3
~Findin
s
The inspector noticed that one
Rosemount
conduit seal
(model
No.
353Cl) was installed for each of the transmitters identified in sec-
tion 3.2.a,
b,
and c.
The licensee
stated that all of these
conduit
seals
were installed per Stone
and Webster
Engineering
and Design
Coordination report
E 5
DCR No.
F02590B,
and the
Raychem splices
(part of the conduit seal)
were installed in accordance
with Raychem
Instruction
WCSF-N, Revision
1 dated August 1983.
Section
2. 1.6 of
the
Raychem Instruction requires
a minimum of 2 inches installed seal
length over qualified wire insulation for areas
subject to accident
conditions
and
a minimum of one inch for non-accident
conditions.
Stone
and Webster
EKDCR No. C-03975A identified all "accident areas".
The instruments identified in section
2.2 -a,
b and c are located in
non-accident
areas.
The inspector
measured
each of the seal
lengths over the qualified
wire insulation
and found each to be approximately
two inches except
those for level transmitters
2 CSH"LT 123 and
LT 124,
each of which
has
a length of approximately three inches.
The inspector verified the mounting configurations of the instru-
ments,
flow direction of the instrument valves
and the required
slope
of the impulse lines.
Within scope of this inspection,
no unacceptable
conditions were
identified.
f
~ 'I
II
25
4.0
Instrument
Cable
and Termination-Work Observation
4.1
The inspector
observed
work performance,
partially completed
work and
completed
work pertaining to the installation of instrument cables
and terminations to determine whether the requirements
of the appli-
cable specifications,
instruction
and procedures
are being met in
areas
relating cable type and size,
routing,- raceway identification
and cable terminations.
4.2
Items examined for this determination
include:
a 4
b.
C.
d.
e.
h.
Instrument cable routing and termination
from level transmitters
2CSH*LT-123, LT-124; flow transmitters
2CSH*FT-104 and
FT-105
and pressure
transmitters
2CSH"PT-105
and PT-102 in the Reactor
Building at elevation 175'o
GE instrument rack H13-P625A lo-
cated in the instrument
room.
GE elementary
diagrams
807E172TY,
sheets
5 and 7, for trans-
mitters
2CSH"FT-104 and FT-105,
2CSH*LT-123 and LT-124, pressure
transmitters
PT-102
and
105, Revision
19, dated
May 31,
1985.
A
Ston'e
and Webster wiring diagram
12177-EE-11GB-2 for level trans-
mitters
2CSH LT-123 and LT-124, Revision 2, dated August 16,
1984.
Stone
and Webster wiring diagram
12177-EE-4M-3 for instrument
rack 2CES~RAK024,
Revision 3, dated January
18,
1985.
Stone
and Webster
connection
diagram
12177-EE-3WB-3 for trans-
mitters
2CSH*LT-123 and LT-124, Revision
3 dated
June
16,
1986.
Cable pull record for cables:
2CSHNPX001 dated
November
16,
1983,
2CSHNPX004 dated
November
16,
1983,
2CSHNPX006 dated
September
14,
1984,
2CSHNPX007 dated
September
14,
1984
Termination records for the "from end" of cables
2CSHNPX001
dated
September.21,
1983,
2CSHNPX004 dated
September
21,
1983,
2CSHNPX006 dated October
1,
1984,
2CSHNPX007 dated October
1,
1984
Termination records for the "to end" of cables
2CSHNPX001 dated
November 9,
1983,
2CSHNPX004 dated
November 9,
1983,
2CSHNPX006
dated October
1,
1984,
2CSHNPX007 dated October
1,
1984
4
'
l
'
<<4
-'k*
V
4
.4
A
26
i.
Cable installation
QC inspection reports
E4009708 for
2CSHNPX004,
E5A43384 for 2CSHNPX001,
ESA8312 for 2CSHNPX001
&
2CSHNPX004,
E4078694 for 2CSHNPX001
& 2CSHNPX004,
ESA40610 for
2CSHNPX001
& 2CSHNPX004,
E5A43020 for 2CSHNPX006
& 2CSHNPX007
E5A42951 for 2CSHNPX006
& 2CSHNPX004,
E6A44308 for 2CSHNPX001
&
2CSHNPX004,
E4077045 for 2CSHNPX001
& 2CSHNPX004,
E4009706 for
2CSHNPX001
& 2CSHNPX004,
E6A43435 for 2CSHNPX001
& 2CSHNPX004,
E6A43114 for 2CSHNPX001
& 2CSHNPX004
j.
Cable termination inspection reports
E5A40630 for 2CSHNPX001FR,
E5A43298 for 2CSHNPX006FR,
&
2CSHNPX007FR
ESA45852 for 2CSHNPX001TO,
E5A49358 for
2CSHNPX006TO,
& 2CSHNPX007TO.
4.3
The inspector verified the correctness
of the terminations,
traced
sections of the raceway
and verified the raceway
numbers.
Within the
scope of this inspection
no unacceptable
conditions were identified.
5.0
Documentation to Perform Corrective Action on Safet
Related
Instrumentation
During the plant tour the inspector identified a significant number of
Rosemount Transmitters with loose side covers.
Discussions with the
licensee
indicate that the tightening of the side covers is deferred
pending completion of startup activities.
However,
the licensee
indicated
that all Rosemount transmitters with loose covers were being tracked
on
a
Deficiency Report.
The inspector
requested
a copy of the Deficiency
Report listing and randomly selected
six Rosemount Transmitters with loose
side covers for verification of the Deficiency Report,.
Two of the
Rosemount Transmitters
selected,
2RHS*PT114
& 2CSH~PT105
were not included
on the Deficiency Report;
Deficiency reports
were not generated
as
required
by Nine Nile Point
2 procedures
N2-SAP-112A "Deficiency reporting
System"/N2-SAP-121
Deficiency Tracking System".
Procedure
No. N2-IMP-EQM-9005 requires that specific maintenance activi-
ties
be performed
when removing or tightening
Rosemount
and Transmitter
side covers.
The subject Deficiency Report
No.
17783 lacked specific
guidance for verifying that the Rosemount Transmitters
are restored to the
environmentally qualified state.
The licensee
was informed that this was
a violation of 10 CFR 50, Appendix 8, Criterion V.
6.0
Facilit
Tours
and Meetin
s
The inspectors
made routine tours throughout the facility to observe
work in progress,
housekeeping,
status of construction,
and actions
taken in the resolution of previously identified items.
i
1
0
27
7.0
Unresolved
Items
Unresolved
items are matters
about which more information is required in
order to determine whether they are acceptable
or items of noncompliance.
Unresolved item(s) are discussed
in Details,
Section 2.0.
~Ei
M
The inspector
met with licensee
and construction
representatives
(denoted
in paragraph
1.0) at the conclusion of the inspection
on August 15,
1986
at the construction
site.
The inspector
summarized
the
scope of the inspection,
the inspection
findings and confirmed with the licensee that the documents
reviewed
by
the team did not contain
any proprietary information.
The licensee
agreed
that the inspection report
may be placed in the Public Document
Room
without prior licensee
review for proprietary information ( 10 CFR 2.790).
No written material
was provided to the licensee
by the team.
P
C
C
C