December 8, 2016
SUBJECT:
COOPER NUCLEAR STATION - NRC MATERIAL CONTROL AND ACCOUNTING PROGRAM INSPECTION REPORT 05000298/2016406
Dear Mr. Limpias:
On November 17, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Cooper Nuclear Station. The inspection covered a key attribute of the Security Cornerstone of the NRCs Reactor Oversight Process, Material Control and Accounting of Special Nuclear Material. The enclosed inspection report documents the inspection results, which were discussed on November 17, 2016, with Mr. D. Buman, Director, Engineering, and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings were identified.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice and Procedure," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRCs document system, (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION IV
1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511 In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security-Related Information-Withhold Under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390(b)(1).
Sincerely,
/RA/
Heather J. Gepford, Ph.D., CHP, Chief
Plant Support Branch 2
Division of Reactor Safety
Docket No. 50-298 License No. DPR-46
Nonpublic Enclosure:
Inspection Report 05000298/2016406 w/Attachment: Supplemental Information
cc w/o enclosure: Electronic Distribution
ML16344A473 Entire Report:
SUNSI Review By: JODonnell Non-Sensitive Sensitive Publicly Available Non-Publicly Available Keyword: NRC-002 MD 3.4 Non-Public A.3 Cover Letter Only:
SUNSI Review By: JODonnell Non-Sensitive Sensitive Publicly Available Non-Publicly Available Keyword: NRC-002 SUNSI Review Complete OFFICE HP:PSB2 C:PSB2 C:PBC C:PSB2
NAME JODonnell HGepford GWarnick HGepford
SIGNATURE
/RA/
/RA/
/RA/
/RA/
DATE 12/7/16 12/7/16 12/8/16 12/8/16 Letter to Oscar from Heather J. Gepford, dated December 8, 2016
SUBJECT: COOPER NUCLEAR STATION - NRC MATERIAL CONTROL AND ACCOUNTING PROGRAM INSPECTION REPORT 05000298/2016406
Distribution w/enclosure:
Security Specialist/NSIR (Eric.Wharton@nrc.gov)
Security Specialist/NSIR (Niry.Simonian@nrc.gov)
Chief, Security Performance Evaluation Branch/NSIR (Clay.Johnson@nrc.gov)
Security Specialist/NSIR (Douglas.Garner@nrc.gov)
Branch Chief, RI DRS/EB1 (Mel.Gray@nrc.gov)
Branch Chief, RII DRS/PSB1 (Binoy.Desai@nrc.gov)
Branch Chief, RIII DRS/PSB (Steven.Orth@nrc.gov)
NMSS/FCSE/MCAB, (Glenn.Tuttle@nrc.gov)
Regional Administrator (Kriss.Kennedy@nrc.gov)
Deputy Regional Administrator (Scott.Morris@nrc.gov)
DRP Director (Troy.Pruett@nrc.gov)
DRP Deputy Director (Ryan.Lantz@nrc.gov)
DRS Director (Anton.Vegel@nrc.gov)
DRS Deputy Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (Patricia.Voss@nrc.gov)
Administrative Assistant (Amy.Elam@nrc.gov)
Distribution w/o enclosure:
Public Affairs Officer (Victor.Dricks@nrc.gov)
Project Manager (Thomas.Wengert@nrc.gov)
Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Project Engineer, DRS/IPAT (Eduardo.Uribe@nrc.gov)
Senior Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)
RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov)
SAIC (Gayle.Walker@nrc.gov)
RSLO (Bill.Maier@nrc.gov)
RidsOeMailCenter Resource