Category:Letter type:RA
MONTHYEARRA-24-0229, Transmittal of Refuel 32 (O3R32) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval2024-09-23023 September 2024 Transmittal of Refuel 32 (O3R32) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval RA-24-0215, Registration for Use of General License Spent Fuel Cask Numbers 177 and 1782024-08-15015 August 2024 Registration for Use of General License Spent Fuel Cask Numbers 177 and 178 RA-24-0197, Subsequent License Renewal Application Response to Request for Additional Information 2024 Annual Update and Subsequent License Renewal Application Supplement 5 Addition2024-07-31031 July 2024 Subsequent License Renewal Application Response to Request for Additional Information 2024 Annual Update and Subsequent License Renewal Application Supplement 5 Addition RA-24-0092, Application to Revise Technical Specification 3.7.7, Low Pressure Service Water (LPSW) System, to Extend the Completion Time for One Required LPSW Pump Inoperable on a One-Time Basis2024-07-29029 July 2024 Application to Revise Technical Specification 3.7.7, Low Pressure Service Water (LPSW) System, to Extend the Completion Time for One Required LPSW Pump Inoperable on a One-Time Basis RA-24-0136, Subsequent License Renewal Application Third Annual Update to the License Renewal Application and Subsequent License Renewal Application Supplement 52024-05-24024 May 2024 Subsequent License Renewal Application Third Annual Update to the License Renewal Application and Subsequent License Renewal Application Supplement 5 RA-24-0152, Duke Energy Carolinas, LLC - Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI2024-05-22022 May 2024 Duke Energy Carolinas, LLC - Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI RA-24-0132, Transmittal of Oconee Unit 2, Refuel 31 (O2R31) Steam Generator Tube Inspection Report2024-05-14014 May 2024 Transmittal of Oconee Unit 2, Refuel 31 (O2R31) Steam Generator Tube Inspection Report RA-24-0030, Duke Energy - Annual Radioactive Effluent Release Report - 20232024-04-29029 April 2024 Duke Energy - Annual Radioactive Effluent Release Report - 2023 RA-24-0083, Annual Report of Changes Pursuant to 10 CFR 50.462024-04-25025 April 2024 Annual Report of Changes Pursuant to 10 CFR 50.46 RA-24-0096, Instrumentation and Control Safety Systems NRC Review of Framatome TXS-Compact Topical Report2024-04-24024 April 2024 Instrumentation and Control Safety Systems NRC Review of Framatome TXS-Compact Topical Report RA-24-0031, Annual Radiological Environmental Operating Report - 20232024-04-23023 April 2024 Annual Radiological Environmental Operating Report - 2023 RA-24-0103, Response to Request for Additional Information (RAI) Regarding License Amendment Request for a One-Time Extension to the Integrated Leak Rate Test Interval2024-04-19019 April 2024 Response to Request for Additional Information (RAI) Regarding License Amendment Request for a One-Time Extension to the Integrated Leak Rate Test Interval RA-24-0094, Request for Approval of Duke Energy Corporation Transition to ANSI/ANS3.1-2014, American National Standard for Selection and Training of Nuclear Power Plant Personnel and Revision 4 of Regulatory Guide 1.8, Rev. 4 Qualification and Traini2024-04-17017 April 2024 Request for Approval of Duke Energy Corporation Transition to ANSI/ANS3.1-2014, American National Standard for Selection and Training of Nuclear Power Plant Personnel and Revision 4 of Regulatory Guide 1.8, Rev. 4 Qualification and Training RA-24-0093, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-0202 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations RA-24-0085, Onsite Property Insurance Coverage2024-04-0101 April 2024 Onsite Property Insurance Coverage RA-24-0086, 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-04-0101 April 2024 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums RA-24-0073, Transmittal of Oconee Unit 2, Refuel 31 (O2R31) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval2024-03-21021 March 2024 Transmittal of Oconee Unit 2, Refuel 31 (O2R31) Inservice Inspection (ISI) Report, Fifth 10-Year ISI Interval RA-24-0071, Passive Containment Isolation Device Inoperability Results in Operation or Condition Prohibited by Technical Specifications2024-02-29029 February 2024 Passive Containment Isolation Device Inoperability Results in Operation or Condition Prohibited by Technical Specifications RA-24-0072, Inappropriate Procedural Guidance for Planned Online Maintenance Results in Event or Condition That Could Have Prevented Fulfillment of a Safety Function Licensee2024-02-29029 February 2024 Inappropriate Procedural Guidance for Planned Online Maintenance Results in Event or Condition That Could Have Prevented Fulfillment of a Safety Function Licensee RA-24-0053, Registration for Use of General License Spent Fuel Cask Number 1762024-02-20020 February 2024 Registration for Use of General License Spent Fuel Cask Number 176 RA-23-0325, Submittal of Procedures CSD-EP-HNP-0101-01, 02, CSD-EP-ONS-0101-01, CSD-EP-RNP-0101-01, and EP-RNP-EPLAN-ANNEX2024-01-0808 January 2024 Submittal of Procedures CSD-EP-HNP-0101-01, 02, CSD-EP-ONS-0101-01, CSD-EP-RNP-0101-01, and EP-RNP-EPLAN-ANNEX RA-23-0320, Notification of Deviation from MRP-227, Revision 1-A Baffle-to-Former Bolt Inspection Frequency2023-12-14014 December 2023 Notification of Deviation from MRP-227, Revision 1-A Baffle-to-Former Bolt Inspection Frequency RA-23-0318, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0404 December 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RA-23-0182, Duke Energy Carolinas, LLC - License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program for a One-Time Extension of the Units 1, 2 and 3 Type a Leak Rate Test Frequency2023-11-16016 November 2023 Duke Energy Carolinas, LLC - License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program for a One-Time Extension of the Units 1, 2 and 3 Type a Leak Rate Test Frequency RA-23-0284, RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RA-23-0304, Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 2 Cycle 32 (Revision 0)2023-11-14014 November 2023 Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 2 Cycle 32 (Revision 0) RA-23-0281, Procedure EP-ALL-EPLAN, Duke Energy Common Emergency Plan, Revision 5, Summary of Changes2023-11-0101 November 2023 Procedure EP-ALL-EPLAN, Duke Energy Common Emergency Plan, Revision 5, Summary of Changes RA-23-0275, Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI)2023-10-12012 October 2023 Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI) RA-23-0268, Transmittal of Sixth 10-Year Inservice Testing Interval Program Plan2023-09-29029 September 2023 Transmittal of Sixth 10-Year Inservice Testing Interval Program Plan RA-23-0234, Update to the Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations for Oconee Nuclear Station (ONS)2023-09-28028 September 2023 Update to the Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations for Oconee Nuclear Station (ONS) RA-23-0225, Procedure AD-EP-ALL-0109, Offsite Protective Action Recommendations, Revision 9, and the Joint Information Center (JIC) Relocation, Summary of Changes2023-09-20020 September 2023 Procedure AD-EP-ALL-0109, Offsite Protective Action Recommendations, Revision 9, and the Joint Information Center (JIC) Relocation, Summary of Changes RA-23-0228, Registration for Use of General License Spent Fuel Cask Number 1752023-09-14014 September 2023 Registration for Use of General License Spent Fuel Cask Number 175 RA-23-0223, Registration for Use of General License Spent Fuel Cask Numbers 173 and 1742023-08-23023 August 2023 Registration for Use of General License Spent Fuel Cask Numbers 173 and 174 RA-23-0222, On-Shift Staffing Analysis (Ossa), Revision 12023-08-23023 August 2023 On-Shift Staffing Analysis (Ossa), Revision 1 RA-23-0211, Reply to a Notice of Violation (NOV) 05000270/2023010-022023-08-17017 August 2023 Reply to a Notice of Violation (NOV) 05000270/2023010-02 RA-23-0154, Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2023-07-20020 July 2023 Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) RA-23-0136, Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2023-07-20020 July 2023 Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) RA-23-0186, Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 2 Cycle 31 (Revision 3)2023-07-18018 July 2023 Transmittal of Core Operating Limits Report (COLR) for Oconee Unit 2 Cycle 31 (Revision 3) RA-23-0184, Registration for Use of General License Spent Fuel Cask Numbers 171 and 1722023-07-10010 July 2023 Registration for Use of General License Spent Fuel Cask Numbers 171 and 172 RA-23-0142, Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require2023-07-0707 July 2023 Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require RA-23-0146, Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI)2023-06-20020 June 2023 Subsequent License Renewal Application, Appendix E, Responses to Requests for Additional Information (Rai), and Request for Confirmation of Information (RCI) RA-23-0135, Submittal of 30 Day Report Per 10 CFR 26.719(c), Unsatisfactory Performance of Health and Human Services Certified Laboratory2023-06-0707 June 2023 Submittal of 30 Day Report Per 10 CFR 26.719(c), Unsatisfactory Performance of Health and Human Services Certified Laboratory RA-23-0041, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-30030 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations RA-23-0128, Refuel 32 (O1R32) Steam Generator Tube Inspection Report2023-05-18018 May 2023 Refuel 32 (O1R32) Steam Generator Tube Inspection Report RA-23-0018, Relief Request (RA-23-0018) to Utilize Code Case N-853 PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material Susceptible to Primary Water Stress Corrosion Cracking Section XI, Division 12023-05-0404 May 2023 Relief Request (RA-23-0018) to Utilize Code Case N-853 PWR Class 1 Primary Piping Alloy 600 Full Penetration Branch Connection Weld Metal Buildup for Material Susceptible to Primary Water Stress Corrosion Cracking Section XI, Division 1 RA-23-0111, Withdrawal of License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2023-04-27027 April 2023 Withdrawal of License Amendment Request to Revise Technical Specification 5.5.2, Containment Leakage Rate Testing Program, for Permanent Extension of Type a and Type C Leak Rate Test Frequencies RA-23-0104, Response to Request for Additional Information (RAI) Regarding Oconee Unit 3, Refuel 31 (O3R31) Steam Generator Tube Inspection Report2023-04-26026 April 2023 Response to Request for Additional Information (RAI) Regarding Oconee Unit 3, Refuel 31 (O3R31) Steam Generator Tube Inspection Report RA-23-0047, Duke Energy Annual Radiological Environmental Operating Report - 20222023-04-26026 April 2023 Duke Energy Annual Radiological Environmental Operating Report - 2022 RA-23-0044, Aduke Energy Annual Report of Changes Pursuant to 10 CFR 50.462023-04-26026 April 2023 Aduke Energy Annual Report of Changes Pursuant to 10 CFR 50.46 RA-23-0099, Subsequent License Renewal Application Second Annual Amendment to the License Renewal Application2023-04-25025 April 2023 Subsequent License Renewal Application Second Annual Amendment to the License Renewal Application 2024-09-23
[Table view] |
Text
M. Christopher Nolan
(~ DUKE 526 South Church Street Charlotte, NC 28202 ENERGYdD MaiOng Address:
Mail Code EC2ZF /P.O. Box 1006 Charlotte, NC 28201-1006 704-382-7426 10 CFR 50.46(a)(3)
Serial: RA-16-0033 September 22, 2016 U.S. Nuclear Regulatory Attn: Document Control Desk Washington, DC 20555-0001 OCONEE NUCLEAR STATION, UNIT NOS. 1, 2 AND 3 DOCKET NOS. 50-269, 50-270 AND 50-287 I RENEWED LICENSE NOS. DPR-38, DPR-47 AND DPR-55
Subject:
DUKE ENERGY Regulatory Commitment Change Related to Loss of Coolant Accident Reanalysis to Address Fuel Pellet Thermal Conductivity Degradation
References:
- 1. Letter from Duke Energy (Ernest J. Kapopoulos, Jr.) to USNRC (Document Control Desk), "Duke Energy Carolinas, LLC (Duke Energy): 10 CFR 50.46 -
30-Day Report for Oconee Nuclear Station, Units 1, 2 and 3; Estimated Impacts to Peak Cladding Temperature due to Fuel Pellet Thermal Conductivity Degradation," dated, December 17, 2014(Ml14353A214)
- 2. Letter from Duke Energy (Regis T. Repko.) to USNRC (Document Control Desk), "Oconee Nuclear Station, Units 1, 2 and 3, Response to Request for Additional Information Re: 10 CFR 50.46 - 30 Day Report on Estimated Impacts to Peak Cladding Temperature due to Fuel Pellet Thermal Conductivity Degradation," dated, March 31 , 2015(ML15090A303)
- 3. Letter from AREVA (Gayle Elliott) to USNRC (Document Control Desk),
"Request for Review and Approval of BAW-10192PA-OO, Supplement 1, Revision 0 "BWNT LOCA - BWNT Loss-of-Coolant Accident Evaluation Model for Once-Through Steam Generator Plants," dated, November 25, 2015 (ML15337A242)
- 4. NRC Staff Regulatory Audit Report Regarding Topical Report BAW-1019PA-OO, Supplement 1, Revision O,"BWNT LOCA - BWNT LOSS-of-COOLANT Accident Evaluation Model for Once Through Steam Generator Plants," dated, August 22, 2016(ML16182A322) (Proprietary)
U.S. Nuclear Regulatory Commission RA-16-0033 Page 2 of 4 In Reference 1, Duke Energy Carolinas, LLC (Duke Energy) submitted a report describing a significant error identified in the emergency core cooling system (ECCS) evaluation model, and an estimate of the effect of the error on the predicted peak cladding temperature (PCT) for Oconee Nuclear Station (ONS) Units 1, 2 and 3. This report was submitted pursuant to 10 CFR 50.46(a)(3), and contained a regulatory commitment to perform a Large Break Loss of Coolant Accident (LBLOCA) reanalysis, accounting for the effects of fuel pellet thermal conductivity degradation (TCD). In Reference 2, this reanalysis commitment date was revised to 15 months after NRC approval of a supplement to BAW-10192P-A.
AREVA submitted the TCD supplement to BAW-1092P-A on November 25, 2015 per Reference
- 3. In April 2016, the NRC staff performed an audit of the TCD supplement and associated documentation. The audit (Proprietary) is contained in Reference 4.
The AREVA schedule to complete the ONS LBLOCA TCD reanalysis is approximately 30 months from the date of NRC approval of the TCD supplement to BAW-10192P-A. This duration takes into consideration AREVA ability to perform TCD reanalysis for the B&W fleet.
Based on this anticipated schedule, a revised commitment date of 32 months after NRC approval of a supplement to BAW-10192P-A is established. This date takes into consideration completion of the AREVA LBLOCA reanalysis using an NRG-approved evaluation model that explicitly accounts for the effects of TCD, and includes a two-month duration for Duke to perform an Owner Acceptance review of the Oconee LBLOCA TCD reanalysis, and develop the reanalysis implementation package including any necessary licensing submittals. This commitment supersedes that made in Reference 2.
The revised commitment per this letter:
The Oconee Large Break LOCA reanalysis incorporating the Thermal Conductivity Degradation (TCD) error correction will be performed within 32 months after NRC approval of the TCD supplement to BAW-10192P-A.
If you should have any questions regarding this submittal, or require additional information, please contact Art Zaremba, Manager - Nuclear Fleet Licensing, at 980-373-2062.
I declare under penalty of perjury that the foregoing is true and correct. Executed on 09/22/2016.
Elnitsky nior Vice President - Nuclear Engineering
Enclosure:
U.S. Nuclear Regulatory Commission RA-16-0033 Page 3 of 4 xc:
C. Haney, Regional Administrator U. S. Nuclear Regulatory Commission - Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, GA 30303-1257 R. Hall, Senior Project Manager (ONS)
U. S. Nuclear Regulatory Commission One White Flint North, Mail Stop 8 G9A 11555 Rockville Pike Rockville, MD 20852-2738 E.L. Crowe NRC Senior Resident Inspector Oconee Nuclear Station
U.S. Nuclear Regulatory Commission RA-16-0033 Enclosure Original Regulatory Commitment and Schedule "Duke Energy will perform a Large Break LOCA reanalysis for the highest PCT case at Middle-of-Life for Oconee Nuclear Station, Units 1, 2, and 3 by September 17, 2015. The effects of fuel pellet thermal conductivity degradation will be accounted for by use of a fuel temperature uncertainty adjustment factor based on COPERNIC2."
Revision 1 to Original Regulatory Commitment and Schedule "The Oconee Large Break LOCA reanalysis incorporating the Thermal Conductivity Degradation (TCD) error correction will be performed within 15 months after NRC approval of the supplement to BAW-10192P-A."
Revision 2 to Original Regulatory Commitment and Schedule
" The Oconee Large Break LOCA reanalysis incorporating the Thermal Conductivity Degradation (TCD) error correction will be performed within 32 months after NRC approval of the TCD supplement to BAW-10192P-A."