McGuire Nuclear Station UFSAR Appendix 18A. Tables Appendix 18A. Tables

McGuire Nuclear Station UFSAR Table 18-1 (Page 1 of 3)

(09 OCT 2015)

Table 18-1. Summary Listing of the Programs, Activities and TLAA Topic Application Location UFSAR/ITS Location Alloy 600 Aging Management Program B.3.1 18.2.1 Battery Rack Inspections B.3.2 ITS SR 3.8.4.3 SLC 16.8.3.3 SLC 16.9.7.12 SLC 16.9.7.17 18.3.1 Boraflex Monitoring Program B.3.3 SLC 16.9.24 Borated Water Systems Stainless Steel Inspection B.3.4 18.2.2 Bottom-Mounted Instrumentation Thimble Tube Inspection Program B.3.5 18.2.3 Chemistry Control Program B.3.6 18.2.4 ITS 5.5.10 ITS 5.5.13 SLC 16.5.7 SLC 16.8.3 SLC 16.9.7 Containment Inservice Inspection Plan - IWE B.3.7 18.2.5 Containment Leak Rate Testing Program B.3.8 ITS 3.6.1 ITS 5.5.2 Control Rod Drive Mechanism Nozzle and Other Vessel Closure Penetrations Inspection Program B.3.9 18.2.1 Crane Inspection Program B.3.10 18.2.7 Divider Barrier Seal Inspection and Testing Program B.3.11 ITS SR 3.6.14.2 ITS SR 3.6.14.4 ITS SR 3.6.14.5 Environmental Qualification 4.4 3.11 Fire Protection Program B.3.12 SLC 16.9.1 SLC 16.9.2 SLC 16.9.4 SLC 16.9.5 18.2.8 Flood Barrier Inspection B.3.13 18.2.9 Flow Accelerated Corrosion Program B.3.14 18.2.10 Boric Acid Corrosion Control Program B.3.15 18.2.11 Galvanic Susceptibility Inspection B.3.16 18.2.12 Heat Exchanger Activities B.3.17 18.2.13

McGuire Nuclear Station UFSAR Table 18-1 (Page 2 of 3)

(09 OCT 2015)

Topic Application Location UFSAR/ITS Location Ice Condenser Inspections B.3.18 ITS 3.6.12.6 18.2.14 Inaccessible Non-EQ Medium Voltage Cables Aging Management Program B3.19 18.2.15 Inservice Inspection Plan B.3.20 18.2.16 Inspection Program for Civil Engineering Structures and Components B.3.21 18.2.17 Leak-Before-Break 4.7.2 5.2.1 License Renewal Program for High-Range Radiation and Neutron Flux Instrumentation Circuits Not Applicable ITS 3.3.1 ITS 3.3.3 Liquid Waste System Inspection B.3.22 18.2.18 Metal Fatigue 4.3 5.2.1 and 3.9.2 Non-EQ Insulatated Cables and Connections Aging Management Program B.3.23 18.2.19 Pressurizer Spray Head Examination Not Application 18.2.20 Preventive Maintenance Activities B.3.24 18.2.21 Reactor Coolant Pump Flywheel 4.7.1 3.5.2.1 5.2.6.3 Reactor Coolant System Operational Leakage Monitoring Program B.3.25 ITS 3.4.13 ITS 3.4.15 Reactor Vessel Integrity Program B.3.26 18.2.22 Reactor Vessel Internals Inspection B.3.27 18.2.23 Reactor Vessel Neutron Embrittlement 4.2 5.4.3 Selective Leaching Inspection B.3.28 18.2.24 Service Water Piping Corrosion Program B.3.29 18.2.25 Standby Nuclear Service Water Pond Dam Inspection 3.3.30 ITS SR 3.7.8.3 Steam Generator Surveillance Program B.3.31 ITS 5.5.9 18.3.2 Sump Pump Systems Inspection B.3.32 18.2.26 Technical Specification SR 3.6.16.3 Visual Inspection B.3.33 ITS SR 3.6.16.3 Treated Water Systems Stainless Steel Inspection B.3.34 18.2.27 Underwater Inspection of Nuclear Service Water Structures B.3.35 18.2.28

McGuire Nuclear Station UFSAR Table 18-1 (Page 3 of 3)

(09 OCT 2015)

Topic Application Location UFSAR/ITS Location Ventilation Area Pressure Boundary Sealants Inspection Not Applicable 18.2.29 Waste Gas System Inspection B.3.36 18.2.30

McGuire Nuclear Station UFSAR Table 18-2 (Page 1 of 1)

(24 APR 2014)

Table 18-2. Deleted Per 2014 Update