ML16161A803

From kanterella
Jump to navigation Jump to search
Insp Repts 50-269/87-02,50-270/87-02 & 50-287/87-02 on 870126-30.Violation Noted:Inadequate App R Circuit Analysis.No Deviations Noted
ML16161A803
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 02/11/1987
From: Conlon T, Fillion P, Hunt M, Miller W, Taylor P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML16161A799 List:
References
50-269-87-02-NP, 50-269-87-2-NP, 50-270-87-02, 50-270-87-2, 50-287-87-02, 50-287-87-2, NUDOCS 8704300479
Download: ML16161A803 (20)


See also: IR 05000269/1987002

Text

od

NUCLEAR REGULATORY COMMISSION

REGIONI

101 MARIETTA STREET. N W.. SUITE 2900

ATLANTA, GEORGIA 30323

Report Nos.:

50-269/87-02, 50-270/87-02, and 50-287/87-02

Licensee: Duke Power Company

422 South Church Street

Charlotte, NC 28242

Docket Nos.: 50-269, 50-270, and 50-287

License Nos.:

DPR-38, DPR-47, and

DPR-55

Facility Name: Oconee 1, 2, and 3

.

Inspection Conducted:

Jan uary 26-30 1987

Inspector: L4

7

//

.//._

W. H. Miller, Jr.

Date Signed

on

f -Sgned

PDate

Signed

Accompanying Personn :

D. J. Kubicki, NRC/NRR-PWR B

Approved by:

,7C

.E

on, Cief, Pant Systems Section

Dateigned

Engineering Branch

Division of Reactor Safety

SUMARY

Scope:

This special announced inspection was in the areas of fire protection,

standby shutdown facility (SSF)

and related features required to meet 10 CFR 50,

Appendix R, Sections III.G, III.J, III.L and 111.0.

Results:

One violation was identified -

Inadequate Appendix R Circuit Analysis,

paragraph 5.a(1) and 5.c(3).

No deviations were identified.

8704300479 870422

PDR

ADOCK 05000269

0

PDR

DETAILS

1. Persons Contacted

Licensee Employees

  • H. D. Brandes, Analytical Engineer

S. R. Christopher, Analytical Engineer

G. D. Chronister, Technical Specialist

  • T. Coutu, Operations Engineer
  • T. Curtis, Integrated Scheduling Group

E. G. Frampton, Supervising Design Engineer

  • P. F. Guill, Licensing Engineer
  • C. Harlin, Compliance engineer

T. Hathcock, Technical Specialist

L. T. Harkinson, Design Engineer

  • J. R. Hendricts, Principle Engineer
  • E. L. Hyland, Design Engineer
  • W. G. Itin, Safety Supervisor

T. W. King, Fire Protection Specialist

B. Loftis, I&E Engineer

  • J. T. McIntosh, Superintendent Station Services

S. P. Neshict, Design Engineer

  • T. Owen, Maintenance
  • K. W. Sandel, Design Engineer
  • D. Sweigart, Superintendent Operations
  • H. Tilson, I&E Specialist
  • M. S. Tuckman, Station Manager
  • N. Watson, Mechanical Maintenance Engineer

Other licensee employees contacted included craftsmen, engineers,

technicians,

operators,

mechanics,

security office members

and office

personnel.

NRC Resident Inspectors

  • J. C. Bryant
  • L. D. Wert
  • Attended exit interview

2.

Exit Interview

The inspection scope and findings were summarized on January 30, 1987, with

those persons indicated in paragraph above.

The inspector described the

areas inspected and discussed in detail the inspection findings.

No dis

senting comments were received from the licensee.

The following new items

were identified during this inspection:

-

Violation 269, 270, 287/87-02-01, Inadequate Appendix R Circuit Analy

sis, paragraph 5.a.(1) and 5.c.

2

-

Unresolved Item 269, 270, 287/87-02-02, Determine the Acceptability of

the SSF Dedicated Submersible Pump as Related to an Appendix R Repair,

paragraph 5.b.

-

Unresolved Item 269, 270, 287/87-02-03, Adequacy of Spurious Actuation

Event Evaluation Following Control Room Evacuation, paragraph 5.c.2.

-

Unresolved Item 269, 270, 278/87-02-04,

NRR Resolution to Appendix R

Exemptions, paragraphs 5.a.2. and 8.

-

Inspector Followup Item 269,

270,

287/87-02-05,

Review Licensee's

Part 21 Reevaluation on Ruskin .Fire Dampers, paragraph 9.

-

Unresolved Item 269,

270,

287/87-02-06,

Inadequate Fire Detection

Coverage to Meet Requirements of Appendix R, III.G.3, paragraph 5.a.3.

-

Inspector Followup Item 269/87-02-7, Sprinkler Protection Required for

Instrument Calibration Room in Area 300, paragraph 5.a.3.

3. Licensee Action on Previous Enforcement Matters

This subject was not addressed in the inspection.

0

4.

Unresolved Items

Unresolved items are matters about which more information is required to

determine whether they are acceptable or may involve violations or devia

tions.

Four unresolved items identified during this inspection are dis

cussed in paragraphs 5.a(3), 5.b, 5.c.2, and 8. .

5.

Compliance with 10 CFR 50 Appendix R Sections III.G ana III.L

An inspection was conducted to determine if the fire protection features

provided for structures, systems and components important to safe shutdown

at Oconee were in compliance with Appendix R, Sections III.G and III.L.

Since the Oconee Nuclear Station utilizes the dedicated shutdown system

approach, the scope of this inspection determined if the fire protection

features provided were capable of maintaining either the dedicated SSF or

one train of normal plant hot shutdown systems free from fire damage.

The

fire protection features for the normal plant safe shutdown systems for

which the dedicated shutdown capabilities had been provided were also

reviewed to determine if these features were capable of limiting potential

fire damage to these components.

The resolution of the turbine building

flooding and physical security requirements were not evaluated.

The original Oconee plant design did not subdivide the plant into multiple

fire areas to separate redundant shutdown components nor were redundant

shutdown train cables separated to meet the current separation requirements

of Appendix R Sections III.G. The plant was basically one large fire area.

To meet these separation requirements, Duke designed the SSF to provide an

alternate and independent method of achieving and maintaining hot shutdown

3

for one or more units for a period of approximately three days.

Damage

control and repair operations are required to bring the plant to cold

shutdown.

The principle components of the SSF include:

a detached seismically de

signed structure called the Standby Shutdown Facility (SSF),

SSF reactor

coolant makeup system, auxiliary service water pump, and a totally indepen

dent power source from an SSF diesel- generator and associated electrical

components.

The SSF contains a small control room from which the SSF

components can be operated on monitored.

If the normal reactor coolant

makeup system is lost, the coolant system volume is to be maintained by a

26 gpm motor driven makeup pump, installed in each reactor building, which

takes suction from the fuel transfer tube and spent fuel pool of the affect

ed unit. If the normal and routine emergency feedwater system is lost, the

secondary volume makeup is to be maintained by an SSF auxiliary service

water pump (motor driven) powered by the SSF power system.

This pump is

located in the SSF structure and takes suction from the condenser circulat

ing water piping for Unit 2.

All electrical power and control cables are either located in the SSF or are

routed from the SSF to the reactor building via the west penetration room in

each unit, except the SSF cables to reactor coolant letdown valve HP-4.

Refer to paragraph 5.a.(1) for details on this item.

The west penetration

rooms are separated from the remainder of the plant by walls, floors and

ceilings having a fire resistant rating equivalent to three-hours.

a. Safe Shutdown Capabilities

In order to ensure safe shutdown capabilities, where cables or equip

ment of redundant trains of systems necessary to achieve and maintain

hot standby conditions are located within the same fire area outside

the primary containment Appendix R,Section III.G.2 requires that one

train of hot standby systems be maintained free of fire damage by one

of the following means:

-

Separation of cables and equipment and associated nonsafety

circuits of redundant trains by a fire barrier having a three-hour

rating;

-

Separation of cables and equipment and associated non-safety

circuits of redundant trains by a horizontal distance of more than

20 feet with no intervening combustibles or fire hazards.

In

addition, fire detectors and an automatic fire suppression system

shall be installed in the fire area; or,

-

Enclosure of cable and equipment and associated non-safety cir

cuits of one redundant train in a fire barrier having a one-hour

rating.

In addition, fire detectors and an automatic fire sup

pression system shall be installed in the fire area.

4

Where the protection of systems whose function is required for hot

standby does not satisfy the above requirements of Section III.G.2,

alternative or dedicated shutdown capabilities independent of cables,

systems or components in the area,

room or zone under consideration

shall be provided in accordance with Appendix R,Section III.G.3 and

III.L.

In addition,Section III.G.3 requires that fire detection and

fixed suppression be installed in the area,

room or zone under

consideration.

On the basis of the above Appendix R .criteria, the inspectors made an

audit of cabling and components associated with the dedicated SSF to

determine the adequacy of the separation afforded to the SSF with

respect to plant areas containing both redundant trains of normal

essential hot standby systems.

In addition, the inspectors made an

audit of the fire protection features afforded for those plant areas

which contain both redundant trains and normal essential plant systems

required to achieve and maintain safe shutdown conditions.

(1) Separation of SSF from Normal Plant Shutdown Systems Outside

Containment

The inspectors reviewed the licensee's "Appendix R Cable Routing

Evaluation" which was provided to NRC Region II on September 22,

1986. This evaluation indicated that all of the SSF cables were

routed from SSF building to the Reactor Building via the west

penetration room for each unit. These west penetration rooms are

separated from the east penetration rooms and the remainder of the

plant by walls, floors and ceilings having a fire resistant rating

equivalent to three-hours. Thus, the SSF cables were designed to

be separated from the cables or component of at least one of the

normal plant shutdown trains.

The east penetration room contains

one normal shutdown train and the west penetration room contains

one normal shutdown train plus the SSF shutdown cables.

To verify

that the licensee's cables evaluation was correct, drawings which

indicated the cable routes for the following samples of the SSF

and the redundant or compliment devices of the normal essential

shutdown components for all three units were reviewed:

SSF

Compliment

Function

Device

Device

Pressurizer Level

LT-72

LT-4P1

Steam Generator "A" Level

LT-66

LT-7P

Steam Generator "B" Level

LT-67

LT-7P

Reactor Coolant Makeup

SSF

HPI

RC Makeup Pump

Pump

5

Emergency

SSF Auxiliary

Emergency Turbine

Feedwater

Service Water

Driven Feedwater

Pump

Pumps

Pressurizer Heater

Group B

Groups A & C-K

Bank 2

A walkdown of the SSF cables also was made and the SSF cables

within the Unit 1 west penetration were inspected.

Only the

Unit 1 east and west penetration rooms were inspected due to the

high radiation levels in these areas.

Based on this review, it

appeared that the above SSF cables were adequately separated from

the normal shutdown cables.

However, during this review it was

noted that the SSF cabling to the motor operator for reactor

coolant letdown valve HP-4, was located in both the east and west

penetration rooms of each unit. The cabling to the motor operator

for the redundant valve HP-3 was located within the west penetra

tion room. Valves HP-3 and 4 are the control valves on the outlet

side of letdown coolers "A" and "B",

respectively, and can be

controlled from either the main control room or the SSF.

In the

event of an Appendix R design type fire within the east penetra

tion room of any unit, if valve HP-4 is open it could not be

closed.

This could result in the lost of the reactor coolant

system volume. The lost through the letdown system would exceed

the makeup capacity of the 26 gpm SSF reactor coolant makeup pump

provided for each unit.

The east penetration rooms are provided

with a fire detection system but are not provided with an automat

ic fire suppression system to reduce the fire damage potential

within the area.

This improper cable separation is identified as

an example of Violation 269,

270,

287/87-02-01,

Inadequate

Appendix R Circuit Analysis.

The Duke design did not require the cable for the motor operator

to valve HP-4 to be either enclosed within a three-hour barrier or

relocated.

This was apparently due to design's impression that

letdown Cooler A was the cooler normally in use and that valve

HP-4 was normally closed.

However,

in actual practice both

coolers are used intermittently.

(2) Cable Separation Inside Containment

Duke, by letter, dated November 11, 1983, requested an exemption

from the Appendix R Section III.G.2 separation requirements for

redundant shutdown equipment,

components and cabling located

within the reactor buildings.

This exemption is currently being

reviewed by NRC/NRR.

Therefore, the equipment and cable separa-

6

tion provided for the redundant shutdown trains within the reactor

building was not reviewed during this inspection pending comple

tion of NRC/NRR's evaluation of this exemption request.

The

exemption for the reactor building is an example of Unresolved

Item 269,

270,

287/87-02-04,

NRR's Resolution to Appendix R

Exemptions.

(3) Fire Protection of Normal Safe Shutdown Capabilities (Appendix R

Section III.G.3)

An inspection was made to determine if the fire protection fea

tures provided for various areas of the plant containing the

normal plant safe shutdown components and cabling met the require

ments of Appendix R Section III.G.3.

Section III.G.3 requires

automatic fire detection and a fixed fire suppression system to be

installed in plant areas for which alternative or dedicated

shutdown capabilities have been provided.

NRC's Generic Letter

(GL)

86-10, Question 3.4.4 stipulates that where fire detection

and suppression systems have not been installed throughout a fire

area, justification must be provided and documented.

NRC/NRR

staff reviewers have reviewed the licensee's fire hazard analysis,

inspected various plant areas and concluded that there'are appar

ently no unmitigated fire hazards which warrant the installation

of additional fire suppression systems.

However, in the penetra

tion rooms, in concealed spaces above suspended ceiling containing

cable raceways in the auxiliary building and in storage areas in

the auxiliary building, adequate fire detection systems are not

provided.

This identified

as Unresolved

Item 269,

270,

287/87-02-06, Inadequate Fire Detection Coverage to Meet Require

ments of Appendix R Section III.G.3,

pendinq resolution by

NRC /NRP.

During the plant tour it was noted that on elevation 796' of the

auxiliary building, an instrument calibration work area has been

constructed adjacent to Room 303 in Unit 1.

This work area had

been provided with a suspended ceiling which obstructed the

ceiling level sprinkler system.

The licensee has committed to

either:

-

Remove the suspended ceiling over the work area;

-

Extend the sprinkler system below the ceiling; or

-

Install an approved "drop-out" type suspended ceiling.

Pending implementation of one of these options, this item is

identified as Inspector Followup Item (IFI) 269/87-02-07, Sprin

kler Protection Required for Instrument Calibration Room in

Area 300.

j..

7

b. Standby Shutdown Facility (SSF)

The SSF for this site consists of a structure containing a diesel

generator, and Auxiliary Service Water (ASW) pump and additional pumps

instrumentation needed to support operation of the facility during an

Appendix R fire, a flood or a security intrusion.

The facility is to

be placed in operation in the event tof an Appendix R fire which causes

an evacuation or lost of plant control from the control rooms for

Unit 1, 2, and 3. This inspection was devoted to plant conditions

created by an Appendix R fire.

The cooling water for the diesel generator, HVAC and supply for the ASW

pump is taken from the Unit 2 condenser cooling water (CCW)

intake

piping.

To meet long term operation commitments the CCW intake piping

must remain full.

This will provide adequate water for cooling the

diesel engine, and ASW to each of the three units steam generators for

decay heat removal.

However, in the event of an Appendix R fire, it is

assumed that incoming power is lost for the duration of the event.

With the lost of all off-site power including the Keowee underground

feed, the only power available for operation of equipment is from the

SSF diesel generator. 'Upon

lost of off-site power, the CCW pumps are

inoperative and only a natural siphon will keep the CCW intake piping

full.

Several conditions could occur within three to four hours should

the natural siphon be lost.

1. The SSF water supply could become overheated due to the recircula

tion of diesel cooling water.

2. The SSF ASW pump could experience runout as the primary loop

temperature decreases.

3. Service water for the SSF systems could lose flow due to air

collection at the common suction high point.

4. Other conditions related to design basis events and security

events could cause the conditions described in 1, 2, and 3.

To ensure that there will be adequate cooling water in the Unit 2 CCW

intake piping, the licensee has designed a portable SSF-Dedicated

Submersible Pump for installation within 31 hours3.587963e-4 days <br />0.00861 hours <br />5.125661e-5 weeks <br />1.17955e-5 months <br />.

The pump is de

signed to be submerged in the intake canal within 3j hours after the

SSF is placed in operation. The pump is powered from the SSF diesel

generator through temporarily installed cables and the submersible pump

discharge is connected to the CCW high point vent for refilling of the

CCW intake piping.

The procedure for this pump installation is dis

cussea at the end of this section.

The licensee must begin installation of this pump immediately upon the

-

decision to man the SSF to bring the unit(s) to hot shutdown. Since it

is assumed all off-site power is not available for 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />

8

(Appendix R,Section III.G) the CCW pumps would be inoperative, thus

creating possible conditions to cause the natural siphon in the intake

piping to be lost.

The licensee has stated that the installation of the SSF dedicated

submersible pump is not considered an Appendix R fire damage repair.

The installation of this pump will require further review by the NRC to

determine if the actions required within the first 3j hours meet the

definition of repairs as stated in Section III.G.1 of Appendix R. This

required action is identified as Unresolved Item (269, 270, 287/87-02),

Determine the Acceptablility of the SSF Dedicated Submersible Pump as

Related to an Appendix R Repair.

It should be noted that the Oconee Standby Shutdown Facility was

declared inoperative on October 15,

1986,

and remained inoperative

until December 14, 1986.

During this period, it was determined that

the fire conditions listed earlier in this paragraph could occur should

operation of the SSF be required and the Unit 2 CCW flow be interrupted

or lost.

During this time that the SSF was inoperative, several

modifications were made to correct unsatisfactory operational condi

tions.

An alternate path for the diesel service (cooling) water to

divert the heated water from the Unit 2 CCW intake piping was estab

lished.

An air eductor was installed using ASW pump discharge to pull

a vacuum at the ASW pump suction high point.

The third modification

was the addition of a dedicated submersible pump to make up the water

that is removed from the CCW intake piping by the diverting of the

diesel generator cooling water and the makeup water pumped to the steam

generator secondary side by the ASW pump.

While these modifications correct potential SSF operational problems,

the importance of the installation of the dedicated submersible pump

within 31 hours3.587963e-4 days <br />0.00861 hours <br />5.125661e-5 weeks <br />1.17955e-5 months <br /> is stressed during training on the loss of the CCW

system. Additionally, there is no means to determine from the SSF if

siphon flow exists in the CCW intake water piping during SSF operation.

The licensee developed two special procedures for the installation of

the dedicated submersible pump. These are identified as follows:

-

MP/O/B/1300/59, Pump Submersible Emergency SSF Water Supply

Installation

-

IP/O/B/375/03, Procedure to Provide Power for SSF Submersible

Pump

These procedures detail the necessary actions required to move the

submersible pump assembly to the intake structure, install the neces

sary electrical cabling, and connect the discharge hoses in order to

restore the water level in the CCW intake piping.

The inspector

examined the designated equipment and the proposed routing for moving

the pump and installing the electrical cables.

Close coordination of

the various required activities should be maintained to insure that the

0~~

9

task is completed within the time frame requirements. The task appears

possible if the above actions are observed.

c. Associated Circuits

An inspection was conducted of associated circuits as defined in

GL 81-12, dated February 20, 1981, Supplement to GL 81-12 and Oconee's

letter of March 18, 1981 to the NRC. This portion of the inspection

was based on the associated circuit portion of the Oconee Fire Protec

tion Plant/Safety Evaluation Report (FPP/SER), dated April 23, 1983.

For the associated circuit inspection, it should be noted that Oconee

has a SSF which is a dedicated and independent system that can be used

to achieve hot shutdown.

The three areas of concern affiliated with associated circuits as

defined in the above referenced GL are:

-

A common power source (common bus) where the shutdown equipment

and the power source is not electrically protected from the

circuit of concern by coordinated breakers,

fuses, or similar

devices; or

-

A connection to circuits of equipment whose spurious operation

(spurious signal) would adversely affect the shutdown capability;

or

-

A common enclosure with the shutdown cables, and

Type (1) are not electrically protected by circuit breakers, fuses

or similar devices, or

Type (2)

will allow propagation of the fire into the enclosure.

(1) Associated Circuits by Common Power Supply (Common Bus)

Circuits and cables associated by common power supply are non-safe

shutdown cables whose fire-induced failure will cause the loss of a

power source (buss, distribution panel, or MCC) that is necessary to

support safe shutdown. This problem could exist for power, control or

instrumentation circuits.

The problem of associated circuits of

concern by common power supply is resolved by ensuring adequate elec

trical coordination between the safe shutdown power source supply

breaker and the component feeder breakers or fuses.

Coordination of overcurrent devices on the normal plant buses was

reviewed by the inspectors.

The overcurrent protective devices were

applied according to good engineering practice and NRC concerns about

the possibility of fire induced faults causing loss of shutdown capa

bility were resolved.

10

Specifically, coordination was checked on the following buses:

-

4160 Volt buses:

BlT, B2T

-

4160 Volt buses:

B11, B21, 812, 822, B13, B23

-

4160 Volt buses:

1TE, 1TC, lTD, 2TE, 2TC, 2TD, 3TE, 3TC, 3TD

-

600 Volt buses:

1X8, 2X8, 3X8

-

Motor control centers:

1XS1, 1XS2, 1XS3, 2XS1, 2XS2, 2XS3, 3XS1,

3XS2, 3SX3

-

208/120 Volt power panels:

1SKL, 2SKL, 3SKL, 1SKJ, 2SKJ, 3SKJ,

1SKK, 2SKK, 3SKK

-

125 Volt DC distribution center:

iDCA, 1DCB, 2DCA, 2DCB, 3DCA,

3DCB

(2) Isolation Switches and Double Fusing

For valves that are controlled from both the main control panel and the

SSF panel,

there is interconnecting wiring between the two panels and

field devices.

Therefore,

these circuits must be designed with

isolation switches and double (parallel) fuses. The inspector reviewed

the elementary diagrams for valves controlled from the SSF and found

that they meet the NRC requirements with respect to isolation switches

and double fuses.

(3) Associated Circuits Causing Spurious Operation

Circuits associated because of spurious operation are those that can,

by fire-induced failures cause safe shutdown equipment or nonsafe

shutdown equipment to maloperate in a way that defeats the function of

safe shutdown systems or equipment. Examples include the uncontrolled

opening or closing of valves, or of circuit breakers,

due to

fire-induced damage to nonsafe shutdown instrument and control circuits

that affect the control circuit interlocks of the safe shutdown

components.

The reactor inspector reviewed the licensee's analysis of

possible fire-induced spurious signals and open circuits that could

defeat the safe shutdown systems. Special attention was focused on the

following piping and valves:

Piping

Valves

RC letdown

HP-1, HP-2, HP-3, HP-4 and HP-5

RCP seal injection

HP-20, HP-21

return

Core decay head removal

LP-1, LP-2

supply

Alternate decay heat

LP-103, LP-104

removal line

Pressurizer PORV block

RC-4

valve

Pressurizer steam sample

RC-5

Pressurizer water sample

RC-6

RCS venting

RC-155 through RC-160

In reviewing the licensee's analysis, it

was determined that fire in

the turbine auxiliary building area could damage the power cables to

reactor coolant (RC)

letdown motor operator valve (MOV)

HP-4, which is

on the outlet line of letdown Cooler B. Thus, a fire propagating to

the east penetration room could disable the ability to close valve HP-4

providing a flow path that would negate the makeup pump capability of

the SSF RC makeup pump.

Additional review revealed that the cables for MOV's LP-1 and LP-2

(located in the decay heat removal line from the RC hot leg) were

located in the same fire area (west penetration room).

A fire in this

area could cause the spurious opening of these valves while the RC

pressure is above 350 PSI which would exceed the design capability of

the low pressure piping downstream of these valves.

The inspectors were advised that the analysis of spurious operation of

the letdown valve (HP-4)

and decay heat removal valves (LP-1 and LP-2)

under the conditions identified had not been considered.

The licensee was advised that the two conditions identified appeared to

be

a violation which

was identified as Violation 269,

270,

287/87-02-01, Inadequate Appendix R Circuit Analysis. The licensee took

the following corrective actions to remedy the condition cited. The RC

letdown cooler "B" was valved out (isolated) by closing valve HP-2 and

de-energizing it

(opening the power feed breaker).

This was done on

all three units. The spurious operation of valves LP-1 and LP-2 in the

decay heat removal system was controlled -by opening the feeder breaker

to LP-1 in each unit.

These actions appear to be appropriate for the

conditions identified. The impact on the overall unit operation should

be evaluated to insure that Technical Specifications (TS)/operating

conditions have been satisfied.

These actions should be identified in

appropriate procedures.

(4)

The Common Enclosure Concern

The common enclosure concern is found when redundant trains are routed

together with a non-safety circuit which crosses from one raceway or

enclosure to another, and the non-safety circuit is not electrically

protected or fire can destroy both redundant trains due to inadequate

fire protection means.

The common enclosure concern at Oconee was not a concern in that the

SSF cables were separate from the plant redundant cables and their

associated non-safety-related cables.

Therefore, this item was not

inspected.

d. Dedicated Shutdown Capability

A safety evaluation report was issued in a letter, dated April 28,

1983, documenting NRR review of the licensee dedicated shutdown system

and its conformance to 10 CFR 50, Appendix R, Section III.G.3 and

III.L.

The Oconee dedicated shutdown system is identified as the SSF

and provides an independent means to achieve and maintain the reactor

coolant system in hot shutdown conditions for one or all three units.

The SSF is placed into operation if

a fire results in the installed

normal

and emergency plant systems becoming inoperable.

A masonry

structure located adjacent to and outside the plant, houses the major

equipment and controls for safe shutdown.

The SSF consist of an

emergency diesel generator, starting batteries and supporting auxiliary

systems, (i.e., lube oil, cooling water, air conditioning).

Normal AC

power supply is via 4160 volt from plant switchgear B2T-4.

Either

separate source of power is capable of supplying SSF electrical loads.

The SSF has a control room and panels for monitoring and controlling

primary and secondary volumes for each unit.

Reactor coolant system

pressure control and pressurizer level can be maintained by manual

control of a bank of pressurizer heaters and letdown flow from the

plant to the spent fuel pool at the SSF control room.

Makeup water to the reactor coolant system and sealing water to the

reactor coolant pumps

(RCP)

seals is provided by a 26 gpm positive

displacement makeup pump. Each unit has it own pump and take a suction

from its own unit spent fuel pool.

The makeup pump discharges to the

RCP seal injection line.

Steam generator volume control is accom

plished using the SSF auxiliary service water pump (ASW) which gets its

water supply from the condenser circulating water system. Decay heat

removal is accomplished using mainsteam code safety valves.

The inspector reviewed operating personnel training, shift staffing and

the use of plant procedures as these activities relate to safe shutdown

and the use of the systems associated with the SSF to achieve this

goal.

These areas were also reviewed to determine if the requirements

of Appendix R,Section III.L for placing the units in hot shutdown

13

conditions and subsequently cooling the plant to cold shutdown

conditions can be accomplished.

(1) Shift Staffing

The inspectors held discussions with operating engineers,

and

operations

personnel

and

reviewed Operation Management

Procedure 1-2,

Rules of Practice.

This procedure defines the

shift staffing requirements for different plant operating condi

tions and exceeds the minimum shift crew that is identified in

Technical Specifications, Table 6.1.1.

The inspectors conducted a walkthrough of OP/O/A/1600/11, Standby

Shutdown Facility Emergency Operation. The walkthrough started in

the Unit 1 and 2 Control Room where a fire was postulated to have

occurred and required abandoning the shared control room and

manning the SSF for both Units.- A loss of off-site power was also

postulated.

The inspectors teamed up with those plant operators

that are necessary to place the SSF into operation and observed

the procedures step to accomplish placing the units in hot shut

down.

Based on the assignment of operators to place the SSF into

operations and the additional operatihg personnel available, shift

staffing appears to be adequate.

(2) Operating Procedures

The inspector reviewed the below listed procedures which places

the SSF equipment and systems in a standby status.

The basic

purpose of these procedures is to provide a normal lineup for SSF

mechanical and electrical systems. These procedures also fill and

vent the RCS makeup system and steam generator makeup system.

Precautions and operating system limits are provided for each

procedure.

No items of concern were identified with the following

procedures:

-

OP/O/A/1600/08, SSF Reactor Coolant Makeup System

-

OP/O/A/1600/09, SSF Auxiliary Service Water System

-

OP/O/A/1600/10, Operation of the SSF Diesel Generator

The inspectors reviewed AP/1/A/1700/08, Loss of Control Room and

OP/O/A/1600/11,

SSF

Emergency Operations to verify that the

procedures identifies the systems to accomplish the performance

goals identified in Appendix R,Section III.L for takina a Unit or

Units to hot shutdown conditions.

Dedicated systems necessary to

accomplish the performance goals have been incorporated into these

procedures.

The inspectors examined the process variables used to monitor

system performance while achieving and maintaining hot shutdown

14

conditions.

The direct reading instrumentation within the SSF

exceeds the minimum monitoring capability identified in IE

Notice 84-09 or approval has been received from NRR for exemption

such as source range indication and steam generator pressure

indication.

The walkthrough of OP/O/A/1600/11 was also conducted to verify

that:

-

communications between various stations are adequate and

operable

-

radio sets, flash lights, procedures, keys and other supplies

are readily available for use

-

identification plate on valves, and instrumentation agree with

those called for in the procedure steps

-

steps of the procedure are clear and can be accomplished

-

equipment and valves can be operated

The principle procedures used to subsequently cooldown the unit(s)

and achieve cold shutdown conditions within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> were re

viewed. OP/0/A/1102/24, Operational Guidelines Following Fire in

Auxiliary Building, Turbine Building or Vital Area.

The main

purpose of this procedure is to assess the damage to those plant

systems which will be used to maintain subcritical conditions in

the reactor during cooldown,

systems for maintaining reactor

coolant inventory and remove decay heat. This procedure restores

system valve alignment, electrical power source as necessary in

preparation for their operation.

Once system operational status is restored then OP/O/A/1102/25,

Cold Shutdown Following a Fire, can be used to lower RCS tempera

ture and pressure sufficiently to establish the Low Pressure

Injection system operations.

Final cold shutdown is achieved

using this system.

During the review of the operating procedures, it was noted that

procedure OP/O/A/1600/11 requires the operators to close the

mainsteam boundary line valves prior to leaving the control room.

This does not conform to GL 86-10, Question 3.8.4, which states

that the only manual action in the control room prior to evacua

tion is usually limited to reactor trip unless assurance is

provided that subsequent spurious actuations will not result from

a postulated "Appendix R Fire".

The licensee, stated in a letter

to the NRC,

dated September 20,

1982, that hot shorts or spurious

actuation due to fire within the first 10 minutes of the event are

not part of the design basis.

During this time interval, the

plant would be in the transition from normal plant systems to the

15

SSF components. Apparently no evaluation has been made to justify

the assumption that the mainsteam boundary line valves would

remain closed to maintain secondary side volume.

This item is

being referred to NRR for further evaluation and is identified as

Unresolved Item 269,

270, 287/87-02-03, Adequacy of Spurious

Actuation Events Evaluation Following Control

Room Evacuation,

pending NRR resolution.

(3) Damage Control Measures

10 CFR 50, Appendix R, requires that nuclear stations maintain the

ability to repair major fire damage and be in the cold shutdown

within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.

The licensee has developed guidelines that

described the organization, resources and procedures needed to

meet this requirement. These guidelines identify the responsibi

lities of various personnel in determining the inoperable equip

ment, repairs required, repair priorities and repair evaluations.

Also, these guidelines define manpower, call out of personnel and

manpower qualification.

The repair support equipment and repair

materials required are identified as part of these guidelines.

The following repair procedures were reviewed:

MP/O/A/3009/12,

Emergency Plan for Replacement of HPI,

LPI,

LPSW Motors Following a Fire in Turbine

Building or Auxiliary Building

MP/0/A/1300/20,

Pump Ingersol Rand - High Pressure Injection

Removal AND Replacement of Pump AND Motor

MP/O/A/1300/40,

Pumps - Alignment and Coupling to Motor

MP/0/A/2000/3,

ONS and Keowee Hydro Station Motor Inspection

and Maintenance

IP/0/A/3010/08,

Fire Damage Control Procedure

The replacement equipment (motors, switchgear, control stations,

electrical cables) and the necessary special tools were examined

at the designated storage locations.

The proposed routes for

moving equipment into place and installing replacement power and

control cables were reviewed and found to be satisfactory.

All

proposed actions appeared feasible but will require close coordi

nation of equipment and man power control.

(4)

Review of SSF Surveillance Procedures

The inspectors reviewed the following procedures and verified that

the inspections and tests required by the Draft Technical Specifi

cations on the SSF components,

submitted to the NRC by letter,

dated July 26, 1985, had been incorporated into the procedures:

16

PT/0/A/600/20,

SSF Instrumentation (Weekly)

PT/O/A/600/21,

SSF Diesel Generator Operation

(Monthly)

PT/O/A/600/23,

SSF Fuel Oil Inventory (Monthly)

PT/(1, 2 & 3)/A/0150/

Operational Valve Functional Test

22A

(Quarterly)

PT/(1, 2 & 3)/A/0150/22B,

Shutdown Valve Functional Test

(Refueling Outage)

PT/(1, 2 & 3)/A/0400/

SSF Reactor Coolant Makeup

07,

Pump Performance Test (Quarterly)

PT/(1, 2 & 3)/A/0400/05,

SSF Auxiliary Service Water

Performance Test (Quarterly)

PT/O/A/0400/04,

5SF Diesel Engine Service Water

Performance Test (Quarterly)

PT/O/A/0400/06,

5SF HVAC Service Water Pump

Performance Test (Quarterly)

PT/0/A/0400/03,

Diesel Engine Fuel Oil Transfer

Performance Test (Quarterly)

PT/0/A/0400/11,

SSF Diesel Generator Performance

Test (Quarterly)

PT/(1, 2 & 3)/A/'50/22C,

Refueling Valve Functional Test

(Refueling Outage)

MP/0/A/5050/32,

5SF Diesel Annual Preventive Mainte

nance (Annual)

IP/0/A/370/(1A,

1B & IC),

Reactor Coolant Makeup Pump Instru

mentation (Refueling Outage)

IP/0/A/370/(2A, 2B, & 2C),

Reactor Coolant System Instrumen

tation (Refueling Outage)

IP/0/A/375/1A,

5SF Auxiliary Service Water Pump

Instrumentation (Annual)

,P/0/A/380/5,

SSF Diesel Generator Fuel Oil Tanks

(Annual)

IP/O/A/385/1A,

SSF 125V DCBatteries (Daily)

17

IP/O/A/385/1B,

SSF 125V DC Battery Capacity Test

(Monthly)

IP/O/A/385/1D,

SSF 125V DC Battery Monthly Surveil

lance (Monthly)

CP/O/B/4002/18,

Chemistry Procedure for Sampling SSF

Fuel Oil Tanks (Day Tank - Monthly

and Underground Tank - 60,Days)

(5) Operating Personnel Training

The inspectors held discussions with Senior Training Instructors

to determine what training is being provided concerning the

operations of the SSF.

It was determined that personnel who are

receiving training in this area included senior reactor operators

(SRO),

reactor operators

(RO)

and nuclear equipment operators

(NEO).

The licensee has scheduled classroom study, system walk

down qualifications concerning SSF systems.

In addition, SSF

operating'procedures are reviewed as part of the on-going operator

requalification programs.

The inspectors reviewed the licensee's

lesson 'plans,

system walkthrough qualification standards and

training schedules and found these documents to be well organized,

detailed and comprehensive.

The operations department also

conducts training as outlined in Operation Management

Procedure 3-1, Operations Training.

This procedure requires that

training be provided with respect to significant operational

experiences,

major changes to existing operating guidelines,

procedures or equipment.

Training packages are put together in

the aforementioned areas and sign-off that the material has been

reviewed by operators is provided.

The inspectors reviewed

training packages recently aiven on the SSF capability and found

them to be comprehensive.

6. Compliance with 10 CFR 50, Appendix R, Section 111.0, Oil Collection System

Appendix R,Section III.0 requires the reactor coolant pumps to be equipped

with an oil collection system if the containment is not inerted during

normal operations.

The system is required to be designed, engineered and

installed such that failure will not lead to fire during normal or design

basis accident condititions, and that the system will withstand the safe

shutdown earthquake.

All leakage from potential pressurized and unpres

surized leakage sites is to be collected and drained to a vented closed

container that can hold the entire lube oil system inventory.

The drain

pipe is required to be sized to accommodate the largest potential oil leak.

The tank vent requires a flame arrestor if the flash-point characteristics

of the oil presents the hazard of fire flash-back.

An inspection of the Oconee reactor coolant pump oil collection systems was

made during an inspection conducted on September 30 - October 4, 1985 and as

documented by Report Nos.

269, 270, 287/85-34, the collection systems were

18

found to meet the Appendix R requirements.

However, the systems within

Unit 3 was found to be in need of minor maintenance.

Subsequently, the

licensee has issued procedure MP/0/A/3009/09, Motor Reactor Coolant Pump

Preventative Maintenance, which requires that during a refueling outage the

oil collection system will be subjected to a routine preventative mainte

nance program and the drain tank will be verified to be empty before unit

startup. This should assure that the systems will be properly maintained.

Within the area inspected, no violations or deviations were identified.

7. Compliance with 10 CFR 50, Appendix R, Section III.3, Emergency Lighting

Appendix R,Section III.J., requires emergency lighting units with at least

an eight-hour battery power supply to be provided in all areas needed for

operation of safe shutdown equipment and operation of safe shutdown equip

ment and in access and egress routes thereto.

A total of approximately 47 eight-hour battery powered emergency lighting

units have been installed in plant areas needed for operation of shutdown

equipment and components and in the access and egress routes to these areas.

The number of lighting units is low at Oconee due to the SSF and NRC/NRR

previously approved emergency lighting exemptions.

However, the installa

tion and arrangement of a random sample of the installed lighting units were

reviewed by the inspectors and found to meet Appendix R Section III.J.

The emergency lighting units are inspected monthly to verify operability of

the units and to check the battery supply and position of the lamp heads.

Annually, a sample of four lights are operated for eight-hours to verify

that the units will operate for the required time.

These tests and inspec

tions are conducted using surveillance procedure IP/0/B/3000/20,

PM of Self

Contained Battery Packs on Emergency Lights.

This procedure .was reviewed

and found to include all of the required inspection and test requirements.

Within the areas examined, no violations or deviations were identified.

8. Licensee Identified Items

During the licensee's Appendix R evaluation several deviations from the

Appendix R requirements were identified.

Exemption requests with justifi

cations have been sent to the NRC/NRR on these items. These exemptions, as

listed below, will remain outstanding pending NRR resolution:

-

Separation of SSF cables from other electrical cables within the Cask

Decon Rooms,

-

Separation of shutdown cables inside reactor buildinc,

-

Fire barrier separation between east and west penetration rooms,

-

Cork insulation in the seismic gap of fire barriers.

19

This is identified as Inspector Followup Item (269,

270, 287/87-02-04),

NRR

Resolution to Appendix R Exemptions.

9. Part 21 Issue - Closure of Fire Dampers Under Airflow Conditions

By letter dated November 6, 1984, Ruskin, a manufacturer and distributor of

fire dampers, notified the industry that under certain airflow conditions,

fire dampers installed in ventilation openings would not close.

The licensee's position on the potential problem is that in the event of a

fire, the fire brigade would ascertain if fire spread had occurred through

these dampers and would take action to assure that fire damage would be

minimized.

The NRC/NRR staff's position is that the successful functioning of fire

dampers, such as in the wall separating the penetration rooms, is necessary

to assure that one division of shutdown systems is free of fire damage.

In

addition, fire brigade size is insufficient to permit timely discovery of

fire spread through nonfunctional dampers.

The licensee is to reassess their evaluation to this problem.

This is

identified as Inspector Followup Item (269,

270, 287/87-02-05), Review of

Licensee's Part 21 Reevaluation on Ruskin Fire Dampers, and will be reviewed

during a subsequent NRC inspection.

10.

Inspector Followup Item

(Closed) IFI 269, 270, 287/85-34-01, Procedures to be Provided for Periodic

Preventative Maintenance of the Reactor Coolant Pump Motor Lube Oil Collec

tion System and Verification that Oil Collection System Drain Tanks are

Empty.

These items have been included in Procedure MP/O/A/3009/09,

Motor

Reactor Coolant Pump - PM. This item is closed.