Forwards Evaluation of Safety & Improvement Implementation Audit During Wk of 900212.Based on 18 Technical Recommendations,Util Satisfactorily Implemented BWROG Group Safety & Performance Improvement Program
ML16148A935
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 11/15/1990
From: Wiens L
Office of Nuclear Reactor Regulation
To: Tucker H
DUKE POWER CO.
Shared Package
ML16148A936 List:
References
TAC-68202, TAC-68203, TAC-68204, NUDOCS 9011210008
Download: ML16148A935 (2)


Text

0 November 15, 1990 Docket Nos.

50-269, 50-270 and 50-287 DISTRIBUTION:

Docket File L. Wiens Mr. H. B. Tucker, Vice President NRC & Local PDRs OGC (info. only)

Nuclear Production Department S. Varga 14/E/4 E. Jordan MNBB 3701 Duke Power Company G. Lainas 14/H/3 ACRS (10)

P.O. Box 1007 R. Ingram Oconee R/F Charlotte, North Carolina 28201-1007 Y. Hsii 8/E/23 L. Reyes, RII R. Jones 8/E/23

Dear Mr. Tucker:

SUBJECT:

SPIP IMPLEMENTATION AUDIT AT THE OCONEE NUCLEAR STATION (TACS 68202, 68203, 68204)

Enclosed is an evaluation report on the Oconee Nuclear Station's implementation of the Babcock & Wilcox Owner's Group's Safety and Performance Improvement Program (SPIP). This evaluation is based on an NRC staff audit at Duke Power Company's (DPCO) Oconee Nuclear Station (ONS) during the week of February 12, 1990.

The audit of SPIP implementation was conducted in two phases: (1) a programmatic audit to evaluate the commitment and involvement of corporate management and the site organization in the SPIP, and the process for disposition of SPIP technical recommendations (TRs), and (2) an implementation audit to perform more detailed review of the implementation and disposition of individual SPIP TRs. The programmatic audit was completed in March 1989, and the results were transmitted to you in a letter dated August 28, 1989. This implementation audit completes Phase 2 of the SPIP.

During the implementation audit, the NRC staff reviewed the implementation and disposition of 18 TRs. Based on the review of these TRs, the staff found that DPCO had (1) adequately strengthened the TR disposition process and file deficiencies identified by the programmatic audit; (2) satisfactorily implemented the majority of the TRs and were in the process of satisfactorily implementing other TRs; (3) performed acceptable analyses to support actions taken with regard to TR determination; and (4) good communication channels between DPCO and ONS personnel.

Therefore, the NRC staff concludes that Duke Power Company and its Oconee Nuclear Station, Units 1, 2 and 3, have satisfactorily implemented the B&W Owner's Group Safety and Performance Improvement Program. This completes our efforts on TACs 68202, 68203, and 68204.

Sincerely, L. A. Wiens, Project Manager 90112ADOC 05000269 Project Directorate 11-3 P

PNU-Division of Reactor Projects I/II Office of Nuclear Reactor Regulation

Enclosure:

As stated LA:PDIIp PM:PDII3 D:PDII3 RIngrad LWiens:lw/sa DMatthews

/

/90 it/Y /90

{/

/90 OFFICIAL RECORD COPY Document Name:

OCONEE SPIP

Mr. H. B. Tucker Oconee Nuclear Station Duke Power Company Units Nos. 1, 2 and 3 cc:

Mr. A. V. Carr, Esq.

Mr. Stephen Benesole Duke Power Company Duke Power Company 422 South Church Street Post Office Box 1007 Charlotte, North Carolina 28242-0001 Charlotte, North Carolina 28201-1007 J. Michael McGarry, III, Esq.

Bishop, Cook, Purcell & Reynolds Mr. Alan R. Herdt, Chief 1400 L Street, N.W.

Project Branch #3 Washington, D.C. 20005 U.S. Nuclear Regulatory Commission 101 Marietta Street, NW, Suite 2900 Mr. Robert B. Borsum Atlanta, Georgia 30323 Babcock & Wilcox Nuclear Power Division Ms. Karen E. Long Suite 525 Assistant Attorney General 1700 Rockville Pike N. C. Department of Justice Rockville, Maryland 20852 P.O. Box 629 Raleigh, North Carolina 27602 Manager, LIS NUS Corporation 2650 McCormick Drive Clearwater, Florida 34619-1035 Senior Resident Inspector U.S. Nuclear Regulatory Commission Route 2, Box 610 Seneca, South Carolina 29678 Regional Administrator, Region II U.S. Nuclear Regulatory Commission 101 Marietta Street, N.W., Suite 2900 Atlanta, Georgia 30323 Mr. Heyward G. Shealy, Chief Bureau of Radiological Health South Carolina Department of Health and Environmental Control 2600 Bull Street Columbia, South Carolina 29201 Office of Intergovernmental Relations 116 West Jones Street Raleigh, North CSrolina 27603 County Supervisor of Oconee County Walhalla, South Carolina 29621