March 2, 2016
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR SALEM NUCLEAR GENERATING STATION, UNIT NOS. 1 and 2 (REPORT 05000272/2015006 and 05000311/2015006)
Dear Mr. Braun:
On February 9, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of Salem Nuclear Generating Station, Unit Nos. 1 and 2 (Salem).
The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2015 through December 31, 2015.
This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Salem Units 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. Consistent with Inspection Manual Chapter 0305, Operating Reactor Assessment Program, the NRC determined that the performance of Salem Units 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Salem Unit 1 was in the Regulatory Response Column of the ROP Action Matrix until September 15, 2015, due to a White PI for Unplanned Scrams per 7,000 Hours Critical. Salem Unit 1 transitioned to the Licensee Response Column on the issue date of the NRC Supplemental Inspection Report 05000272/2015009 and Assessment Follow-Up Letter (ADAMS Accession No. ML15258A467),
dated September 15, 2015. That report documented a Supplemental Inspection conducted in accordance with Inspection Procedure (IP) 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area, for the White PI that was successfully completed on August 7, 2015. Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2017.
Routine inspections performed by resident inspectors are not included in the inspection plan.
In addition to baseline inspections, the NRC will conduct IP 71003, Post-Approval Site Inspection For License Renewal, to verify the license conditions added as part of the renewed operating license, regulatory commitments, selected aging management programs (AMPs), and time-limited aging analyses (TLAAs) are implemented and/or completed in accordance with 10 CFR Part 54. As discussed below, the NRC will also perform Temporary Instruction (TI), Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. This Order requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. This Order requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. The audit was completed for Salem, and the information gathered will aid staff in development of the Final Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Final Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing TI 2515-191, Inspection of the Implementation of Mitigating Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communications/Staffing/Multi-Unit Dose Assessment Plans, early in 2017.
During the assessment period, the NRC issued one Severity Level IV traditional enforcement violation for impeding the regulatory process (untimely event notification). However, in accordance with NRC Inspection Manual Chapter 0305, Section 13.02.b, the NRC will not conduct IP 92702, Follow-up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, and Alternative Dispute Resolution Confirmatory Orders, because the issue has already been reviewed through baseline inspection.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact Fred Bower at (610) 337-5200 with any questions you have regarding this letter.
Sincerely,
/RA/
Michael L. Scott, Director Division of Reactor Projects
Docket Nos. 50-272 and 50-311 License Nos. DPR 70 and DPR 75
Enclosure: Salem Inspection/Activity Plan
cc w/encl: Distribution via ListServ
SUNSI Review
Non-Sensitive Sensitive
Publicly Available Non-Publicly Available
OFFICE R1/DRP R1/DRP R1/DRP R1/DRP
NAME PFinney/ MSD for per email MDraxton/ MSD FBower/ FLB MScott/ MLS
DATE 02/ 22 /16 02/23 /16 02/ 23 /16 02/ 25 /16
Page 1 of 4 02/23/2016 12:24:02 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Salem Inspection / Activity Plan 01/01/2016 - 12/31/2017 71124
- RADIATION PROTECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/07/2016 03/11/2016 1, 2 IP Occupational ALARA Planning and Controls 71124.02 03/07/2016 03/11/2016 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 03/07/2016 03/11/2016 1, 2 IP Occupational Dose Assessment 71124.04 03/07/2016 03/11/2016 1, 2 IP Radiation Monitoring Instrumentation 71124.05 03/07/2016 03/11/2016 EP
- EP EXERCISE EVALUATION
1, 2 IP Exercise Evaluation 7111401 05/16/2016 05/20/2016 71124
- RADIATION PROTECTION
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 04/11/2016 04/15/2016
IP Occupational ALARA Planning and Controls 71124.02 04/11/2016 04/15/2016
IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 04/11/2016 04/15/2016
IP Occupational Dose Assessment 71124.04 04/11/2016 04/15/2016
IP Radiation Monitoring Instrumentation 71124.05 04/11/2016 04/15/2016 71003
- U1 LR COMMITTMENTS - OUTAGE
1 IP Post-Approval Site Inspection for License Renewal 71003 04/18/2016 04/22/2016 ISI
- U1 INSERVICE INSPECTION
1 IP Inservice Inspection Activities - PWR 7111108P 04/18/2016 04/29/2016 71124
- RADIATION PROTECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 05/16/2016 05/20/2016 1, 2 IP Occupational ALARA Planning and Controls 71124.02 05/16/2016 05/20/2016 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 05/16/2016 05/20/2016 1, 2 IP Occupational Dose Assessment 71124.04 05/16/2016 05/20/2016 1, 2 IP Radiation Monitoring Instrumentation 71124.05 05/16/2016 05/20/2016 71124
- ENVIRONMENTAL
1 IP Radiological Environmental Monitoring Program 71124.07 06/06/2016 06/10/2016 7111117T
- MODS INSPECTION
1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 7111117T 07/18/2016 07/22/2016 1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 7111117T 08/01/2016 08/05/2016 EXM12/12
- SALEM INITIAL EXAMINATION
1 FY17-SALEM INITIAL OPERATOR LICENSING EXAM U01930 11/14/2016 11/18/2016
FY17-SALEM INITIAL OPERATOR LICENSING EXAM U01930 12/12/2016 12/23/2016 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 4 02/23/2016 12:24:02 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Salem Inspection / Activity Plan 01/01/2016 - 12/31/2017 71124
- RADIATION PROTECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 08/22/2016 08/26/2016 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 08/22/2016 08/26/2016 1, 2 IP Occupational Dose Assessment 71124.04 08/22/2016 08/26/2016 1, 2 IP Radiation Monitoring Instrumentation 71124.05 08/22/2016 08/26/2016 711107T
- TRIENNIAL HEAT SINK
1, 2 IP Heat Sink Performance 7111107T 11/14/2016 11/18/2016 71124
- RADIATION PROTECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 12/12/2016 12/16/2016 1, 2 IP Occupational ALARA Planning and Controls 71124.02 12/12/2016 12/16/2016 1, 2 IP Occupational Dose Assessment 71124.04 12/12/2016 12/16/2016 1, 2 IP Occupational Exposure Control Effectiveness 71151-OR01 12/12/2016 12/16/2016 1, 2 IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 12/12/2016 12/16/2016 TI-191
- FUKUSHIMA LESSONS-LEARNED
1, 2 IP Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 2515/191 02/20/2017 02/24/2017 71124
- RADIATION PROTECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 04/03/2017 04/07/2017 1, 2 IP Occupational ALARA Planning and Controls 71124.02 04/03/2017 04/07/2017
IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 04/03/2017 04/07/2017
IP Occupational Dose Assessment 71124.04 04/03/2017 04/07/2017 1, 2 IP Radiation Monitoring Instrumentation 71124.05 04/03/2017 04/07/2017 EP
- EP PROGRAM INSPECTION
1, 2 IP Alert and Notification System Testing 7111402 05/15/2017 05/19/2017 1, 2 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 05/15/2017 05/19/2017 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 05/15/2017 05/19/2017 1, 2 IP Performance Indicator Verification 71151 05/15/2017 05/19/2017 7111108P
- U2 INSERVICE INSPECTION
2 IP Inservice Inspection Activities - PWR 7111108P 04/24/2017 05/05/2017 71124
- RADIATION PROTECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 05/01/2017 05/05/2017 1, 2 IP Occupational ALARA Planning and Controls 71124.02 05/01/2017 05/05/2017
IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 05/01/2017 05/05/2017 1, 2 IP Occupational Dose Assessment 71124.04 05/01/2017 05/05/2017 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 3 of 4 02/23/2016 12:24:02 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Salem Inspection / Activity Plan 01/01/2016 - 12/31/2017 71124
- RADIATION PROTECTION
1, 2 IP Radiation Monitoring Instrumentation 71124.05 05/01/2017 05/05/2017 71152B
- PI&R BIENNIAL
1, 2 IP Problem Identification and Resolution 71152B 05/22/2017 05/26/2017 1, 2 IP Problem Identification and Resolution 71152B 06/05/2017 06/09/2017 71124
- RADIOACTIVE EFFLUENTS
1, 2 IP Radiation Monitoring Instrumentation 71124.05 06/12/2017 06/16/2017 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 06/12/2017 06/16/2017 CDBI
- COMPONENT DESIGN BASIS INSPECTION
1, 2 IP Component Design Bases Inspection 7111121 06/12/2017 06/16/2017 1, 2 IP Component Design Bases Inspection 7111121 06/26/2017 06/30/2017 1, 2 IP Component Design Bases Inspection 7111121 07/10/2017 07/14/2017 7111111B
- SALEM REQUAL INSP WITH P/F RESULTS
1, 2 IP Licensed Operator Requalification Program 7111111B 09/12/2017 09/16/2017 1/22EXM
- SALEM INITIAL EXAM
1 FY18-SALEM INITIAL OPERATOAR LICENSING EXAM U01949 12/11/2017 12/15/2018 71124
- RADIATION PROTECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 08/21/2017 08/25/2017 1, 2 IP Occupational ALARA Planning and Controls 71124.02 08/21/2017 08/25/2017 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 08/21/2017 08/25/2017 1, 2 IP Occupational Dose Assessment 71124.04 08/21/2017 08/25/2017 1, 2 IP Radiation Monitoring Instrumentation 71124.05 08/21/2017 08/25/2017 71124.08
- RADWASTE
1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 10/16/2017 10/20/2017 7111108P
- U1 INSERVICE INSPECTION
1 IP Inservice Inspection Activities - PWR 7111108P 10/23/2017 11/03/2017 71124
- 71124 PROGRAM SALEM 1 OUTAGE
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 10/23/2017 10/27/2017 1, 2 IP Occupational ALARA Planning and Controls 71124.02 10/23/2017 10/27/2017
IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 10/23/2017 10/27/2017 1, 2 IP Occupational Dose Assessment 71124.04 10/23/2017 10/27/2017
IP Radiation Monitoring Instrumentation 71124.05 10/23/2017 10/27/2017 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 4 of 4 02/23/2016 12:24:02 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Salem Inspection / Activity Plan 01/01/2016 - 12/31/2017 71124
- RADIATION PROTECTION AND PI
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 12/04/2017 12/08/2017 1, 2 IP Occupational ALARA Planning and Controls 71124.02 12/04/2017 12/08/2017 1, 2 IP Occupational Dose Assessment 71124.04 12/04/2017 12/08/2017 1, 2 IP Occupational Exposure Control Effectiveness 71151-OR01 12/04/2017 12/08/2017 1, 2 IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 12/04/2017 12/08/2017 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.