MONTHYEARML24268A3382024-10-16016 October 2024 Issuance of Amendment No. 253 Regarding the Modification of TS Surveillance Requirement 4.3.6.a Related to Adoption of TSTF-425, Revision 3 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests NMP2L2890, Submittal of Revision 26 to the USAR and Reference Figures, 10 CFR 50.59 Evaluation Summary Report, TS Bases, TRM Requirements Manual Changes, and 10 CFR 54.37(b) Aging Management Review (Excludes Attachment 6)2024-10-0404 October 2024 Submittal of Revision 26 to the USAR and Reference Figures, 10 CFR 50.59 Evaluation Summary Report, TS Bases, TRM Requirements Manual Changes, and 10 CFR 54.37(b) Aging Management Review (Excludes Attachment 6) ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing IR 05000220/20243022024-10-0303 October 2024 Initial Operator Licensing Examination Report 05000220/2024302 ML24190A0012024-09-26026 September 2024 Issuance of Amendment Nos. 252 and 197 Regarding the Revision to Technical Specification Design Features Section to Remove Nine Mile Point Unit 3 Project Designation NMP1L3608, Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-09-20020 September 2024 Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000220/20240052024-08-29029 August 2024 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2024005 and 05000410/2024005) IR 05000220/20240102024-08-22022 August 2024 Age-Related Degradation Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3603, Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan2024-08-20020 August 2024 Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000220/20240022024-08-0505 August 2024 Integrated Inspection Report 05000220/2024002 and 05000410/2024002 ML24215A3002024-08-0202 August 2024 Operator Licensing Examination Approval NMP1L3601, Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-07-31031 July 2024 Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation ML24213A1412024-07-31031 July 2024 Requalification Program Inspection NMP2L2883, Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations2024-07-24024 July 2024 Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations ML24198A0852024-07-16016 July 2024 Senior Reactor and Reactor Operator Initial License Examinations RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations NMP1L3584, License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2024-06-13013 June 2024 License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000220/20244012024-05-30030 May 2024 Security Baseline Inspection Report 05000220/2024401 and 05000410/2024401(Cover Letter Only) ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 NMP1L3591, Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request2024-05-18018 May 2024 Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request NMP1L3589, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-05-16016 May 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable ML24158A2052024-05-15015 May 2024 Annual Radioactive Environmental Operating Report NMP1L3582, 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 22024-05-15015 May 2024 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 2 IR 05000220/20240012024-05-10010 May 2024 Integrated Inspection Report 05000220/2024001 and 05000410/2024001 RS-24-049, Updated Notice of Intent to Pursue Subsequent License Renewal Applications2024-05-0909 May 2024 Updated Notice of Intent to Pursue Subsequent License Renewal Applications RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds 05000410/LER-2024-001, Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum2024-05-0101 May 2024 Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests NMP1L3581, Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report2024-04-30030 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report NMP2L2877, 2023 Annual Environmental Operating Report2024-04-19019 April 2024 2023 Annual Environmental Operating Report NMP2L2878, Core Operating Limits Report2024-04-16016 April 2024 Core Operating Limits Report ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24092A3352024-04-0101 April 2024 NRC Office of Investigations Case No. 1-2023-002 ML24074A2812024-03-14014 March 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3577, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-03-13013 March 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable IR 05000220/20230062024-02-28028 February 2024 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2, (Reports 05000220/2023006 and 05000410/2023006) IR 05000220/20230042024-02-0101 February 2024 Integrated Inspection Report 05000220/2023004 and 05000410/2023004 NMP1L3570, Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-02-0101 February 2024 Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation 05000410/LER-2023-001, Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater2024-01-30030 January 2024 Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater NMP1L3569, CFR 50.46 Annual Report2024-01-26026 January 2024 CFR 50.46 Annual Report ML24004A2122024-01-0808 January 2024 Senior Reactor and Reactor Operator Initial License Examinations ML23354A0012024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0059 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000220/LER-2023-002, Average Power Range Monitors Declared Inoperable Due to Trip of Reactor Recirculation Pump 122023-12-15015 December 2023 Average Power Range Monitors Declared Inoperable Due to Trip of Reactor Recirculation Pump 12 NMP1L3566, Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station2023-12-14014 December 2023 Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station 2024-09-04
[Table view] Category:Safety Evaluation
MONTHYEARML24268A3382024-10-16016 October 2024 Issuance of Amendment No. 253 Regarding the Modification of TS Surveillance Requirement 4.3.6.a Related to Adoption of TSTF-425, Revision 3 ML24190A0012024-09-26026 September 2024 Issuance of Amendment Nos. 252 and 197 Regarding the Revision to Technical Specification Design Features Section to Remove Nine Mile Point Unit 3 Project Designation ML24145A1862024-05-30030 May 2024 Authorization and Safety Evaluation of Alternative Relief Request I5R-12 Concerning the Installation of a Full Structural Weld Overlay on RPV Recirculation Inlet Nozzle N2E ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23291A4642023-12-0707 December 2023 Issuance of Amendment No. 251 Regarding the Adoption of Title 10 the Code of Federal Regulations Section 50.69, Risk-Informed Categorization and Treatment of SSC for Nuclear Power Plants ML23289A0122023-12-0606 December 2023 Issuance of Amendment No. 250 Regarding the Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23151A3472023-08-21021 August 2023 Issuance of Amendments to Adopt TSTF-295-A, Modify Note 2 to Actions of PAM Table to Allow Separate Condition Entry for Each Penetration ML23131A4242023-06-23023 June 2023 Issuance of Amendment No. 249 Regarding the Revision to Technical Specification 3.3.1 to Adopt Technical Specifications Task Force Traveler TSTF-568 ML23156A6832023-06-22022 June 2023 Authorization and Safety Evaluation of Alternative Relief Request I5R-14 ML23156A6822023-06-22022 June 2023 Authorization and Safety Evaluation of Alternative Relief Request I5R-11 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23103A1912023-04-20020 April 2023 Request for Threshold Determination Under 10 CFR 50.80 ML23082A3502023-04-17017 April 2023 Issuance of Amendment No. 192, Revision of Surveillance Requirements Associated with Emergency Diesel Generator Testing ML23094A1422023-04-0505 April 2023 Approval of Alternative Request I5R-13 to Utilize Specific Provisions of Code Case N-716-3 ML23025A4122023-02-28028 February 2023 Issuance of Amendment No. 248 to Revise Alternative Source Term Calculation for Main Steam Isolation Valve Leakage and Non-MSIV Leakage ML22339A0582022-12-21021 December 2022 Relief Request Associated with Pump Periodic Verification Tests of Core Spray System Pumps ML22293B8052022-11-30030 November 2022 Constellation Energy Generation, Llc_Fleet - Request to Authorize Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22090A0862022-04-29029 April 2022 Amendments to Adopt TSTF-541,Rev.2,Add Exceptions to Surveillance Requirements for Valves,Dampers Locked in Actuated Position ML22094A0012022-04-15015 April 2022 Constellation Energy Generation, LLC - Proposed Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles (Epids L-2021-LLR-0057 and L-2021-LLR-0058) ML22061A0402022-03-11011 March 2022 Relief Request Associated with Excess Flow Check Valves ML22033A3102022-03-0404 March 2022 Issuance of Amendment No. 190, Changes to Reactor Pressure Vessel Water Inventory Control Technical Specification Requirements ML21347A0382022-01-13013 January 2022 Issuance of Amendments to Revise Reactor Coolant Leakage Requirements ML21277A2482021-11-16016 November 2021 Letter with Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (Public Version) ML21295A7342021-11-15015 November 2021 Issuance of Amendment No. 187 Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML21256A1792021-11-0202 November 2021 Issuance of Amendment No. 246 Changes to Reactor Pressure Vessel Water Inventory Control Technical Specification Requirements ML21280A0782021-10-27027 October 2021 Proposed Alternative to Use of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Case N-893 (Epids L-2020-LLR-0147 and L-2020-LLR-0148) ML21230A2062021-09-0303 September 2021 Proposed Alternative to Use ASME OM Code Case OMN-28 ML21216A2202021-08-0505 August 2021 Proposed Alternative to Eliminate Certain Documentation Requirements for Pressure Retaining Bolting ML21166A1682021-06-25025 June 2021 ML21140A1532021-06-0303 June 2021 Correction to April 22, 2021 Safety Evaluation for Requests for Alternative to the Inservice Testing Requirements of the ASME OM Code for the Fifth 10-Year Program Interval ML21082A2212021-04-29029 April 2021 Issuance of Amendment No. 186, Adoption of TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B ML21109A2162021-04-22022 April 2021 Proposed Alternative to Inservice Testing Requirements of the ASME OM Code for the Fifth 10-Year Interval ML21105A3382021-04-22022 April 2021 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Concerning Examination Coverage of Certain Class 1 and 2 Component Welds ML21033A5302021-04-0101 April 2021 Issuance of Amendments to Adopt Technical Specifications Task Force TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems ML21049A0062021-03-16016 March 2021 Issuance of Amendment No. 245 for Relaxation of Surveillance Frequency for Instrument-Line Flow Check Valve ML21049A0242021-02-23023 February 2021 Alternative Request to the Requirements of the ASME OM Code for the Testing Intervals for the Instrument-Line Flow Check Valves ML21013A0052021-02-0404 February 2021 Issuance of Amendments to Adopt Technical Specifications Task Traveler TSTF-568, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 ML21028A6732021-02-0303 February 2021 Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L-2020-LLR-011 ML20332A1152021-01-29029 January 2021 Issuance of Amendment No. 183 Regarding Risk-Informed Categorization and Treatment of Structures, Systems, and Components ML21005A0612021-01-14014 January 2021 Proposed Alternatives to Extend the Safety Relief Valve Testing Interval (EPID L-2020-LLR-0014 Through L-2020-LLR-0018) ML20287A1302020-11-0505 November 2020 Review of Quality Assurance Program Changes ML20241A1902020-10-20020 October 2020 Issuance of Amendment No. 182 to Change Allowable Main Steam Isolation Valve Leak Rates ML20269A2002020-09-30030 September 2020 Request to Use a Provision of Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI (EPID L2020-LLR-0117 ML20232A1712020-09-0101 September 2020 Request to Use Alternative Code Case OMN-26 ML20141L6362020-07-10010 July 2020 Issuance of Amendments Based on TSTF-427,Allowance for Nontechnical Specification Barrier Degradation on Supported System Operability,Rev 2 ML20134H9402020-07-0808 July 2020 Issuance of Amendments Revising the High Radiation Area Administrative Controls ML20141L0532020-06-0202 June 2020 Relief from the Requirements of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code ML20113F0412020-04-30030 April 2020 Proposed Alternative to the Submittal Schedule for Certain Reports (COVID-19) ML20021A0702020-04-0606 April 2020 Issuance of Amendments to Delete License Conditions for Decommissioning Trusts 2024-09-26
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 29, 2016 Mr. Bryan Hanson President and Chief Nuclear Officer Exelon Generation Company, LLC 4.300 Winfield Road Warrenville, IL 60555
SUBJECT:
NINE MILE POINT NUCLEAR STATION, UNIT 2 - SAFETY EVALUATION BY THE OFFICE OF NUC,LEAR REACTOR REGULATION FOR RELIEF REQUEST MSS-VR-01, REVISION 1 (CAC NO. MF5773)
Dear Mr. Hanson By letter to the U.S. Nuclear Regulatory Commission (NRC) dated February 16, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15047A003), Exelon Generation Company, LLC (the licensee) submitted Revision 1 to Relief Request (RR) MSS-VR-01 for the third interval of the 10-year inservice testing (IST) program at Nine Mile Point Nuclear Station, Unit 2 (NMP2). RR MSS-VR-01, Revision 0, was authorized by the NRC staff for the NMP2 third interval of the 10-year IST program by letter dated December 29, 2008 (ADAMS Accession No. ML083500039). The request proposes an alternative to the test intervals specified in the American Society of Mech,anical Engineers (ASME) Code for Operation and Maintenance of Nuclear Power Plants (OM Code).
Specifically, pursuant to Title 10 of the Code of Federal Regulations (:10 CFR) 50.55a(z)(1 ), the licensee requested to use the proposed alternative in RR MSS-VR-01, Revision 1, on the basis
. that the alternative provides an acceptable level of quality and safety.
The NRC staff has completed its review of the subject request as documented in the enclosed Safety Evaluation (SE). The SE concludes that the prqposed alternatives described in RR MSS-VR-01, Revision 1, provide an acceptable level of quality and safety for testing of the NMP2 main steam safety relief valves. Accordingly, the NRC staff concludes that the licensee has adequately addressed all of the regulatory requirements set forth in 10 CFR 50.55a(z)(1) for RR MSS-VR-01, Revision 1, and is in compliance with the ASME OM Code requirements.
All other ASME OM Code requirements for which relief was not specifically requested and approved remain applicable.
B. Hanson If you have any questions concerning this matter, please contact the NMP2 Senior Project Manager, Mrs. Brenda Mozafari, at (301) 415-2020 or Brenda.Mozafari@nrc.gov .
. Sincerely, o~d~
Travis L Tate, Chief Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-410
Enclosure:
Safety Evaluation cc w/enclosure: Distribution via Listserv
UNITED STATES NUCLEAR R~GULATORY. COMMISSION WASHINGTON, D.C. 20555..0001 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION INSERVICE TESTING PROGRAM RELIEF REQUEST MSS-VR-01, REVISION 1 THIRD 10-YEAR INTERVAL EXELON GENERATION COMPANY, LLC NINE MILE POINT NUCLEAR STATION. UNIT 2 DOCKET NO. 50-410
1.0 INTRODUCTION
By letter to the U.S. Nuclear Regulatory Commission (NRG) dated February 1~. 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15047A003), Exelon Generation Company, LLC (Exelon or the licensee), submitted Revision 1 to Relief Request (RR) MSS-VR-01 for the third interval of the 10-year inservice testing (IST) program at Nine Mile Point Nuclear Station, Unit 2 (NMP2). RR MSS-VR-01, Revision 0, was authorized by the NRG staff for the NMP2 third interval of the 10-year IST program by letter dated December 29, 2008 (ADAMS Accession No. ML083500039). The request proposes an alternative to test intervals specified in the American Society of Mechanical Engineers (ASME) Code for Operation and Maintenance of Nuclear Power Plants* (OM Code).
Specifically, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(z)(1), the licensee requested to use the proposed alternative in RR MSS-VR-01, Revision 1, on the basis that the alternative provides an acceptable level of quality and safety.
2.0 REGULATORY EVALUATION
Section 50.55a(f) of 10 CFR, "lnservice testing requirements," requires, in part, that IST of certair:i ASME Code Class 1, 2, and 3 pumps and valves be performed in accordance with the specified ASME OM Code and applicable addenda incorporated by reference in the regulations.
Exceptions are allowed where alternatives have been authorized by the NRG pursuant to paragraphs (z)(1) or (z)(2) of 10 CFR 50.55a. In proposing alternatives, the licensee must demonstrate that: (1) the proposed alternatives provide an acceptable level of quality and safety (10 CFR 50.55a(z)(1)), or (2) compliance would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety (10 CFR 50.55a(i)(2)).
Section 50.55a allows the NRC to authorize alternatives from ASME OM Code requirements upon making the necessary findings.
Enclosure
Based on the above, and subject to the following technical evaluation, the NRC staff finds that regulatory authority exists for the licensee to request and the Commission to authorize the alternative relief requested by the licensee.
3.0 TECHNICAL EVALUATION
3.1 Applicable ASME OM Code Edition and Addenda The third interval of the NMP2 IST program complies with the ASME OM Code of Nuclear Power Plants, 2004 Edition with no Addenda. The NMP2 third interval of the 10-year IST program interval began on January 1, 2009, and is scheduled to end on December 31, 2018.
3.2 ASME OM Code Requirements The licensee requested relief from Mandatory Appendix I, 1-1320, which requires that Class 1 pressure relief valves be tested at least once every 5 years with a minimum of 20 percent of the valves from each valve group tested within any 24-month interval. This 20 percent shall consist of valves that have not been tested during the current 5-year interval, if they exist. The test interval for any individual valve shall not exceed 5 years.
3.3 Component Identification Relief was requested for the following Unit 2 Class 1 main steam safety relief valves (SRVs):
2MSS*PSV120 2MSS*PSV121 2MSS*PSV122 2MSS*PSV123 2MSS*PSV124 2MSS*PSV125 2MSS*PSV126 2MSS*PSV127 2MSS*PSV128 2MSS*PSV129 2MSS*PSV130 2MSS*PSV131 2MSS*PSV132 2MSS*PSV133 2MSS*PSV134 2MSS*PSV135 2MSS*PSV136 2MSS*PSV137 3.4 Licensee's Basis for Requesting Relief The licensee stated in its application:
Section ISTC-3200, "lnservice Testing," states that inservice testing shall commence when the valves are required to be operable to fulfill their required function(s). Section ISTC-5240, Safety and Relief Valves, directs that safety and relief valves shall meet the inservice testing requirements set forth in Appendix I of the ASME OM Code. Appendix I, Section l-1320(a) of the ASME OM Code states that Class 1 pressure relief valves shall be tested at least once every 5 years, starting with initial electric power generation. This section also states a minimum of 20% of the pressure relief valves are tested within any 24-month interval and that the test interval for any individual valve shall not exceed 5 years.
The required tests ensure that the SRVs, which are located on each of the main steam lines between the reactor vessel and the first isolation valve within the drywell, will open at the pressures assumed in the safety analysis.
However, given the current 24-month operating cycle at NMP2, Exelon Generation Company, LLC (Exelon) is required to remove and test approximately half of the SRVs every refueling outage in order to ensure that all valves are removed and tested in accordance with the ASME OM Code requirements. This ensures compliance with the ASME OM Code requirements for testing Class 1 pressure relief valves within a 5 year interval. With the current 5 year interval, NMP2 is required to remove all 18 SRVs over 2 refuel cycles (i.e., 4 years).
Approval of extending the test interval to 6.5 years would reduce the number of SRVs removed during an individual outage, such that the full scope of 18 SRVs are replaced over 3 refuel cycles (i.e., 6 years, plus 6 months grace). Without Code relief, the incremental outage work due to the inclusion of the additional 2 - 3 SRVs per outage would be contrary to the principle of maintaining radiation dose As Low As Reasonably Achievable (ALARA). The removal and replacement of the additional 2 - 3 SRVs per outage without Code relief results in an additional exposure of approximately 2 - 4 Rem [roentgen equivalent man]
each outage. Additionally, the grace period allows for flexibility in the scheduling of as-left and as-found set-pressure testing, which is based on a test to test frequency.
The NRC staff previously authorized RR MSS-VR-01 for NMP2 to increase the SRV test interval from 5 years to 3 refueling cycles (approximately 6 years), but did not include the 6-month grace. Revision 1 of RR MSS-VR-01 would replace the currently approved test interval of 3 refueling cycles (approximately 6 years} with a test interval of 6 years, and would further allow a 6-month grace period for performing the tests. These revisions are consistent with the test interval and grace period described in ASME Code Case OMN-17. Due to outage scheduling, the additional 6 months is necessary to avoid unnecessary testing.
3.5 Licensee's Proposed Alternative Testing The licensee stated its application:
As an alternative to the Code required 5-year test interval per Appendix I, paragraph 1-1320(a), Exelon proposes that the subject Class 1 pressure relief valves be tested at least once every three refueling cycles (approximately 6 years/72 months) with a minimum of 20% of the valves tested within any 24-month interval. This 20% would consist of valves that have not been tested during the current 72-month interval, if they exist. The test interval for any individual valve would not exceed 72 months except that a 6-month grace period is allowed to coincide with refueling outages to accommodate extended shutdown periods and certification of the valve prior to installation.
As-found testing using steam and subsequent valve maintenance are currently performed at an off-site test facility. Subsequent to completion of as-found testing, each SRV in the removed complement is disassembled to perform inspections and a complete valve overhaul. Any SRV that failed the as-found set-pressure test is inspected to determine the cause of the test failure. Valve overhaul is performed to ensure that parts are free of defects resulting from time related degradation or service induced wear. All identified adverse conditions
are corrected, the disc and seats are lapped, and the valve is reassembled.
Each SRV is then recertified for service through inspection and testing consistent with ASME OM Code requirements, including set-pressure, seat tightness, stroke time and disc lift verifications, solenoid coil pick up/drop out, and air actuator integrity tests.
After recertification testing, the SRVs are stored at the test facility for future use.
The storage area is inspected and maintained to ANSl/ASME N45.2.2 requirements, which will minimize the potential for any valve degradation.
3.6 Staff Evaluation The NMP2 main steam SRVs are ASME Code Class 1 pressure relief valves that provide overpressure protection for the reactor coolant pressure boundary to prevent unacceptable radioactive release and exposure to plant personnel. ASME OM Code, Mandatory Appendix I requires that Class 1 pressure relief valves be tested at least once every 5 years. However, Mandatory Appendix I does not require that pressure relief valves be disassembled and inspected as part of the 5-year test requirement. In lieu of the 5-year test interval, the licensee proposed to implement requirements similar to ASME OM Code Case OMN-17, which allows a test interval of 6 years, plus a 6-month grace period. The ASME Committee on OM developed Code Case OMN-17 and published it in the 2009 Edition of the ASME OM Code. However, ASME OM Code Case OMN-17 imposes an additional special maintenance requirement to disassemble and inspect each pressure relief/safety valve to verify that parts are free from defects resulting from time-related degradation or service-induced wear coincident with each required test during the interval. The purpose of this maintenance requirement is to reduce the potential for pressure relief valve set-point drift.
ASME OM Code Case OMN-17 has not yet been added to Regulatory Guide 1.192, "Operation and Maintenance Code Case Acceptability, ASME OM Code," nor included in 10 CFR 50.55a by reference. However, the NRG has allowed licensees to use ASME OM Code Case OMN-17, provided all requirements in the Code Case are met. Consistent with the special maintenance requirement in ASME OM Code Case OMN-17, each main steam SRV at NMP2 will be disassembled and inspected to verify that internal surfaces and parts are free from defects or service induced wear prior to the start of the next test interval. This maintenance will also help to reduce the potential for set-point drift and increase the reliability of these SRVs to perform their design requirement functions. Consistent with the special maintenance requirement in ASME OM Code Case OMN-17, critical components will be inspected for wear and defects.
Additionally, the NRG staff review of recent set-point testing results shows that the SRV maintenance practices employed at NMP2 have been effective, as evidenced by no test failures over the last two refueling outage test cycles.
Based on the historical performance of the set-point testing of the main steam SRVs at NMP2 and disassembly and inspection of the main steam SRVs prior to use, the NRG staff finds that the proposed alternative test frequency for the testing of the main steam SRVs at NMP2, in lieu of the requirements of the 2004 Edition, no Addenda, Mandatory Appendix I, Section 1320, of the ASME OM Code, provides an acceptable level of quality and safety.
4.0 CONCLUSION
As set forth above, the NRC staff has determined that the proposed alternatives described in RR MSS-VR-01, Revision 1, provide an acceptable level of quality and safety for the NMP2 main steam SRVs. Accordingly, the NRC staff concludes that the licensee has adequately addressed all of the regulatory requirements set forth in 10 CFR 50.55a(z)(1) for RR MSS-VR-01, Revision 1, and is in compliance with the ASME OM Code requirements.
All other ASME OM Code requirements for which relief was not specifically requested and approved remain applicable.
Principal Contributor: John Billerbeck Date: January 29, 2016
B. Hanson If you have any questions concerning this matter, please contact the NMP2 Senior Project Manager, Mrs. Brenda Mozafari, at (301) 415-2020 or Brenda.Mozafari@nrc.gov.
Sincerely,
/RA/
Travis L. Tate, Chief Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-410
Enclosure:
Safety .Evaluation cc w/enclosure: Distribution via Listserv DISTRIBUTION:
PUBLIC CSantos, OEDO LPL 1-1 R/F RidsACRS_MailCTR Resource RidsNrrDorlLpl1-1 Resource RidsRgn1 MailCenter Resource RidsNrrLAKGoldstein Resource RidsNrrDeEpnb Resource RidsNrrPMNineMile Point Resource JBillerbeck, NRR ADAMS Access1on No.: ML15345A006 *b1y memo OFFICE DORL/LPLl-1/PM DORL/LPLl-1/LA DE/EPNB/BC* DORL/LPL 1-1/BC DORL/LPL 1-1/PM NAME BMozafari KGoldstein DAiiey TT ate BMozafari (LRonewicz for)
DATE 01/12/16 01/28/16 12/08/15 01/29/16 01/29/16 OFFICIAL RECORD COPY