Letter Sequence Request |
---|
|
|
MONTHYEAR3F0314-01, Response to Request for Additional Information to Exemptions on Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and Appendix E to Part 50, Revision 12014-03-28028 March 2014 Response to Request for Additional Information to Exemptions on Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and Appendix E to Part 50, Revision 1 Project stage: Response to RAI 3F0814-07, Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and Appendix E to Part 50, Supplement2014-08-28028 August 2014 Exemptions to Radiological Emergency Response Plan Requirements Defined by 10 CFR 50.47 and Appendix E to Part 50, Supplement Project stage: Supplement ML15013A1812015-02-23023 February 2015 Letter with Environmental Assessment and Finding of No Significant Impact Related to Request for Exemptions from Certain Emergency Planning Requirements Project stage: Other ML15013A1732015-02-23023 February 2015 Environmental Assessment and Finding of No Significant Impact Exemptions from Certain Emergency Planning Requirements Project stage: Other ML15058A9062015-03-30030 March 2015 Letter, Exemptions from Certain Emergency Planning Requirements and Related Safety Evaluation Project stage: Approval ML15040A0902015-03-30030 March 2015 Nuclear Generating Plant - FRN for Exemptions on Emergency Plan and Emergency Action Level Scheme. Project stage: Other NRC-2015-0042, Nuclear Generating Plant - FRN for Exemptions on Emergency Plan and Emergency Action Level Scheme.2015-03-30030 March 2015 Nuclear Generating Plant - FRN for Exemptions on Emergency Plan and Emergency Action Level Scheme. Project stage: Other 3F0315-04, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20142015-03-31031 March 2015 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2014 Project stage: Request ML15110A1292015-04-22022 April 2015 Correction to the Emergency Planning Exemptions Safety Evaluation Project stage: Approval 3F0815-01, License Amendment Request No. 318, Revision 0, Permanently Defueled Emergency Plan, Revision 2, and Permanently Defueled Emergency Action Level Bases Manual, Revision 1, for the Independent Spent Fuel Storage Installation2015-08-27027 August 2015 License Amendment Request No. 318, Revision 0, Permanently Defueled Emergency Plan, Revision 2, and Permanently Defueled Emergency Action Level Bases Manual, Revision 1, for the Independent Spent Fuel Storage Installation Project stage: Request 3F1115-01, Notification of Schedule Change for the Post-Shutdown Decommissioning Activities Report2015-11-16016 November 2015 Notification of Schedule Change for the Post-Shutdown Decommissioning Activities Report Project stage: Request 3F1215-01, Request for Exemption from 10 CFR 50.54(w)(1) Regarding Onsite Insurance Coverage2015-12-17017 December 2015 Request for Exemption from 10 CFR 50.54(w)(1) Regarding Onsite Insurance Coverage Project stage: Request 3F0516-02, License Amendment Request No. 322, Revision 0, Independent Spent Fuel Storage Installation (ISFSI)-Only Emergency Plan, and ISFSI-Only Emergency Action Level Bases Manual, for the CR-3 Safstor Period with Spent Fuel on Site2016-05-25025 May 2016 License Amendment Request No. 322, Revision 0, Independent Spent Fuel Storage Installation (ISFSI)-Only Emergency Plan, and ISFSI-Only Emergency Action Level Bases Manual, for the CR-3 Safstor Period with Spent Fuel on Site Project stage: Request 3F0716-02, Permanently Defueled Emergency Plan, Revision 3 and Implementing Procedure, Permanently Defueled Emergency Action Level Bases Manual, Revision 12016-07-19019 July 2016 Permanently Defueled Emergency Plan, Revision 3 and Implementing Procedure, Permanently Defueled Emergency Action Level Bases Manual, Revision 1 Project stage: Other 3F0720-03, ISFSI Only Emergency Plan and Implementing Procedure2020-07-21021 July 2020 ISFSI Only Emergency Plan and Implementing Procedure Project stage: Request 3F0321-01, License Amendment Request, Revision to Independent Spent Fuel Storage Installation (ISFSI)-Only Emergency Plan, Draft a, and ISFSI Only Emergency Action Level Bases Manual2021-03-17017 March 2021 License Amendment Request, Revision to Independent Spent Fuel Storage Installation (ISFSI)-Only Emergency Plan, Draft a, and ISFSI Only Emergency Action Level Bases Manual Project stage: Draft Request 2015-03-31
[Table View] |
|
---|
Category:Letter type:
MONTHYEAR3F0623-01, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-06-0101 June 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G 3F0423-03, 2022 Annual Radiological Environmental Operating Report2023-04-18018 April 2023 2022 Annual Radiological Environmental Operating Report 3F0423-02, 2022 Annual Radioactive Effluent Release Report2023-04-18018 April 2023 2022 Annual Radioactive Effluent Release Report 3F0423-01, 2022 Individual Monitoring NRC Form 5 Report2023-04-0404 April 2023 2022 Individual Monitoring NRC Form 5 Report 3F0323-03, Decommissioning Funding Plan for Independent Spent Fuel Storage Installation2023-03-31031 March 2023 Decommissioning Funding Plan for Independent Spent Fuel Storage Installation 3F0323-02, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20222023-03-29029 March 2023 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2022 3F0323-01, Onsite Property Insurance Coverage2023-03-0202 March 2023 Onsite Property Insurance Coverage 3F0123-01, Proof of Financial Protection2023-01-26026 January 2023 Proof of Financial Protection 3F1222-01, Nuclear Power Station - License Amendment Request 262 Addition of License Condition 2.C.21, License Termination Plan2022-12-12012 December 2022 Nuclear Power Station - License Amendment Request 262 Addition of License Condition 2.C.21, License Termination Plan 3F0522-03, Notification of Revised Decommissioning Cost Estimate2022-05-26026 May 2022 Notification of Revised Decommissioning Cost Estimate 3F0522-01, Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 20222022-05-17017 May 2022 Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 2022 3F0422-02, 2021 Annual Radiological Environmental Operating Report2022-04-0606 April 2022 2021 Annual Radiological Environmental Operating Report 3F0322-01, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20212022-03-30030 March 2022 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2021 3F0322-03, Drug and Alcohol Testing Error at HHS-Certified Laboratory, Per 10CFR26.719(c)(1)2022-03-10010 March 2022 Drug and Alcohol Testing Error at HHS-Certified Laboratory, Per 10CFR26.719(c)(1) 3F0322-02, 2021 Individual Monitoring NRC Form 5 Report2022-03-0707 March 2022 2021 Individual Monitoring NRC Form 5 Report 3F0222-01, ADP CR3, LLC - Update to Irradiated Fuel Management Program Pursuant to 10 CFR 50.54(bb)2022-02-0909 February 2022 ADP CR3, LLC - Update to Irradiated Fuel Management Program Pursuant to 10 CFR 50.54(bb) 3F0222-02, Onsite Property Insurance Coverage2022-02-0909 February 2022 Onsite Property Insurance Coverage 3F0122-01, License Amendment Request to Remove from the Facility Operating License, Appendix B, Environmental Protection Plan (Non-Radiological) Technical Specifications2022-01-26026 January 2022 License Amendment Request to Remove from the Facility Operating License, Appendix B, Environmental Protection Plan (Non-Radiological) Technical Specifications 3F0122-02, Proof of Financial Protection2022-01-17017 January 2022 Proof of Financial Protection 3F0122-03, Complex - Environmental Protection Plan Report: 2021 Sea Turtle Rescue and Recovery Summary Report2022-01-17017 January 2022 Complex - Environmental Protection Plan Report: 2021 Sea Turtle Rescue and Recovery Summary Report 3F1021-01, Report of Investigation Pursuant to 10 CFR 20, Appendix G2021-10-21021 October 2021 Report of Investigation Pursuant to 10 CFR 20, Appendix G 3F0921-02, Reporting Related to the National Pollutant Discharge Elimination System (NPDES) Permit Id FL0A00004 (Minor) (Rev. C)2021-09-29029 September 2021 Reporting Related to the National Pollutant Discharge Elimination System (NPDES) Permit Id FL0A00004 (Minor) (Rev. C) 3F0921-01, to License Amendment Request, Revision 0, ISFSI Security Plan, Revision a2021-09-14014 September 2021 to License Amendment Request, Revision 0, ISFSI Security Plan, Revision a 3F0721-01, Report of Investigation Pursuant to 10 CFR 20, Appendix G2021-07-13013 July 2021 Report of Investigation Pursuant to 10 CFR 20, Appendix G 3F0621-02, Reporting Related to the National Pollutant Discharge Elimination System (NPDES) Permit Id FL0A00004-001-IW1S2021-06-16016 June 2021 Reporting Related to the National Pollutant Discharge Elimination System (NPDES) Permit Id FL0A00004-001-IW1S 3F0421-05, 2020 Individual Monitoring NRC Form 5 Report2021-04-27027 April 2021 2020 Individual Monitoring NRC Form 5 Report 3F0421-04, ADP CR3, LLC - Supplement to Application for Order Approving Indirect Transfers of Control of Licenses in Connection with Internal Corporate Reorganization2021-04-13013 April 2021 ADP CR3, LLC - Supplement to Application for Order Approving Indirect Transfers of Control of Licenses in Connection with Internal Corporate Reorganization 3F0421-03, Proof of Financial Protection2021-04-0707 April 2021 Proof of Financial Protection 3F0421-01, 2020 Annual Radioactive Effluent Release Report2021-04-0606 April 2021 2020 Annual Radioactive Effluent Release Report 3F0421-02, 2020 Annual Radiological Environmental Operating Report2021-04-0606 April 2021 2020 Annual Radiological Environmental Operating Report 3F0321-07, (XEG)-DOE/NRC Forms 741 742 and 743C2021-03-30030 March 2021 (XEG)-DOE/NRC Forms 741 742 and 743C 3F0321-06, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20202021-03-29029 March 2021 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2020 3F0321-01, License Amendment Request, Revision to Independent Spent Fuel Storage Installation (ISFSI)-Only Emergency Plan, Draft a, and ISFSI Only Emergency Action Level Bases Manual2021-03-17017 March 2021 License Amendment Request, Revision to Independent Spent Fuel Storage Installation (ISFSI)-Only Emergency Plan, Draft a, and ISFSI Only Emergency Action Level Bases Manual 3F0321-02, License Amendment Request, Rev. 0, ISFSI Security Plan, Rev. a2021-03-17017 March 2021 License Amendment Request, Rev. 0, ISFSI Security Plan, Rev. a 3F0321-05, Onsite Property Insurance Coverage2021-03-15015 March 2021 Onsite Property Insurance Coverage 3F0321-03, Report of Investigation Pursuant to 10 CFR 20, Appendix G2021-03-0909 March 2021 Report of Investigation Pursuant to 10 CFR 20, Appendix G 3F0221-02, Report of Investigation Pursuant to 10 CFR 20, Appendix G2021-02-17017 February 2021 Report of Investigation Pursuant to 10 CFR 20, Appendix G 3F0221-01, ADP CR3, Llc., Crystal River Energy Complex - Environmental Protection Plan Report: 2020 Sea Turtle Rescue and Recovery Summary Report2021-02-0202 February 2021 ADP CR3, Llc., Crystal River Energy Complex - Environmental Protection Plan Report: 2020 Sea Turtle Rescue and Recovery Summary Report 3F0121-02, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E2021-01-19019 January 2021 Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E 3F0121-01, Report of Investigation Pursuant to 10 CFR 20, Appendix G2021-01-19019 January 2021 Report of Investigation Pursuant to 10 CFR 20, Appendix G 3F1120-02, and Crystal River Nuclear Plant - Application for Order Approving Indirect Transfers of Control of Licenses in Connection with Internal Corporate Reorganization2020-11-19019 November 2020 and Crystal River Nuclear Plant - Application for Order Approving Indirect Transfers of Control of Licenses in Connection with Internal Corporate Reorganization 3F0920-02, Request to Transfer the Quality Assurance Program Approval Form for Radioactive Material Packages2020-09-15015 September 2020 Request to Transfer the Quality Assurance Program Approval Form for Radioactive Material Packages 3F0920-01, License Transfer - Notification of Transfer Date2020-09-15015 September 2020 License Transfer - Notification of Transfer Date 3F0720-03, ISFSI Only Emergency Plan and Implementing Procedure2020-07-21021 July 2020 ISFSI Only Emergency Plan and Implementing Procedure 3F0720-02, License Transfer - Insurance Required of a Licensee Under 10 CFR 140.11(a)(4) and 10 CFR 50.54(w)2020-07-15015 July 2020 License Transfer - Insurance Required of a Licensee Under 10 CFR 140.11(a)(4) and 10 CFR 50.54(w) 3F0520-01, Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 20202020-05-18018 May 2020 Safety Analysis Report, Quality Assurance Program and 10 CFR 50.59 - 10 CFR 72.48 Report - May 2020 3F0420-03, Supplemental Information in Support of Crystal River Unit 3 License Transfer Application - Amended License Conditions2020-04-22022 April 2020 Supplemental Information in Support of Crystal River Unit 3 License Transfer Application - Amended License Conditions 3F0420-01, 2019 Annual Radioactive Effluent Release Report2020-04-0707 April 2020 2019 Annual Radioactive Effluent Release Report 3F0420-02, 2019 Radiological Environmental Operating Report2020-04-0707 April 2020 2019 Radiological Environmental Operating Report 3F0320-04, Decommissioning Funding Plan for Independent Spent Fuel Storage Installation2020-03-19019 March 2020 Decommissioning Funding Plan for Independent Spent Fuel Storage Installation 2023-06-01
[Table view] |
Text
Crystal River Nuclear Plant 15760 W. Power Line Street Crystal River, FL 34428 Docket 50-302 Operating License No. DPR-72 10 CFR 50.82(a)(7)
November 16, 2015 3F1115-01 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Crystal River Unit 3 - Notification of Schedule Change for the Post-Shutdown Decommissioning Activities Report
References:
CR-3 to NRC, dated December 2, 2013, Post-Shutdown Decommissioning Activities Report, (ADAMS Accession No. ML13340A009)
Dear Sir:
Pursuant to 10 CFR 50.82(a)(7), Duke Energy Florida, LLC, formerly known as Duke Energy Florida Inc., (DEF) is submitting notification that DEF is planning to perform certain activities that constitute a schedule change from those actions and schedules described in the Crystal River Unit 3 (CR-3) Post-Shutdown Decommissioning Activities Report (PSDAR) and associated Site-Specific Decommissioning Cost Estimate (DCE).
Specifically, the change is as follows:
The Independent Spent Fuel Storage Installation (ISFSI) construction and loading project is now scheduled to be completed by February 2018 versus the January 2019 date identified in the PSDAR and DCE.
The ISFSI schedule is reflected in multiple locations in the PSDAR and DCE. Specifically in footnote 3 to Table 2.2, Decommissioning Cost Summary, and in Section 2.1.2, Period 2:
Dormancy. It is also described in the DCE, in footnote 3 to Table 2, Decommissioning Cost Summary, in Section 2.2, Period 2 - Dormancy, in Section 4.2, Project Schedule, Figure 4.2, Decommissioning TimeLine, and in footnote 3 to Table 6.1, Decommissioning Cost Summary.
This schedule change did not result in any significant change in cost than what is described in the DCE. DEF will continue to provide the NRC Project Manager with periodic project schedule updates.
For the reasons described in CR-3s, Update to Irradiated Fuel Management Program Pursuant to 10 CFR 50.54 (bb), dated December 3, 2013 (ADAMS Accession No. ML13340A008), ISFSI construction costs will not be paid for from DEFs Decommissioning Trust Fund (DTF) at this time; however, the loading project costs will be paid for from DEFs DTF.
An evaluation of estimated impacts from accelerating the project due to the change in schedule described above concludes that the change would not jeopardize CR-3s ability to demonstrate financial assurance as indicated in Attachment 11 to CR-3s Financial Status Report for 2014
(ADAMS Accession No. ML15092A113). DEF remains committed to utilizing SAFSTOR with license termination completion in 2073.
There are no new regulatory commitments made within this submittal.
If you have any questions regarding this submittal, please contact Mr. Mark Van Sicklen, Licensing Lead, Nuclear Regulatory Affairs, at (352) 563-4795.
Sincerely, Ronald R. Reising, Senior Vice President Operations Support RRR/mvs xc: NRR Project Manager Regional Administrator, Region I
Crystal River Nuclear Plant 15760 W. Power Line Street Crystal River, FL 34428 Docket 50-302 Operating License No. DPR-72 10 CFR 50.82(a)(7)
November 16, 2015 3F1115-01 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Crystal River Unit 3 - Notification of Schedule Change for the Post-Shutdown Decommissioning Activities Report
References:
CR-3 to NRC, dated December 2, 2013, Post-Shutdown Decommissioning Activities Report, (ADAMS Accession No. ML13340A009)
Dear Sir:
Pursuant to 10 CFR 50.82(a)(7), Duke Energy Florida, LLC, formerly known as Duke Energy Florida Inc., (DEF) is submitting notification that DEF is planning to perform certain activities that constitute a schedule change from those actions and schedules described in the Crystal River Unit 3 (CR-3) Post-Shutdown Decommissioning Activities Report (PSDAR) and associated Site-Specific Decommissioning Cost Estimate (DCE).
Specifically, the change is as follows:
The Independent Spent Fuel Storage Installation (ISFSI) construction and loading project is now scheduled to be completed by February 2018 versus the January 2019 date identified in the PSDAR and DCE.
The ISFSI schedule is reflected in multiple locations in the PSDAR and DCE. Specifically in footnote 3 to Table 2.2, Decommissioning Cost Summary, and in Section 2.1.2, Period 2:
Dormancy. It is also described in the DCE, in footnote 3 to Table 2, Decommissioning Cost Summary, in Section 2.2, Period 2 - Dormancy, in Section 4.2, Project Schedule, Figure 4.2, Decommissioning TimeLine, and in footnote 3 to Table 6.1, Decommissioning Cost Summary.
This schedule change did not result in any significant change in cost than what is described in the DCE. DEF will continue to provide the NRC Project Manager with periodic project schedule updates.
For the reasons described in CR-3s, Update to Irradiated Fuel Management Program Pursuant to 10 CFR 50.54 (bb), dated December 3, 2013 (ADAMS Accession No. ML13340A008), ISFSI construction costs will not be paid for from DEFs Decommissioning Trust Fund (DTF) at this time; however, the loading project costs will be paid for from DEFs DTF.
An evaluation of estimated impacts from accelerating the project due to the change in schedule described above concludes that the change would not jeopardize CR-3s ability to demonstrate financial assurance as indicated in Attachment 11 to CR-3s Financial Status Report for 2014
(ADAMS Accession No. ML15092A113). DEF remains committed to utilizing SAFSTOR with license termination completion in 2073.
There are no new regulatory commitments made within this submittal.
If you have any questions regarding this submittal, please contact Mr. Mark Van Sicklen, Licensing Lead, Nuclear Regulatory Affairs, at (352) 563-4795.
Sincerely, Ronald R. Reising, Senior Vice President Operations Support RRR/mvs xc: NRR Project Manager Regional Administrator, Region I