Forthcoming Public Meeting Between the U.S. Nuclear Regulatory Commission and the Technical Specifications Task Force - Agenda
ML15300A480
Person / Time
Site: Technical Specifications Task Force
Issue date: 10/30/2015
From: Michelle Honcharik
Licensing Processes Branch (DPR)
To:
Honcharik M
Shared Package
ML15300A522 List:
References
Download: ML15300A480 (3)


Text

Agenda for TSTF/NRC Meeting November 12, 2015 9:30 a.m. - 4:00 p.m.

I. Administrative (9:30 a.m. - 9:40 a.m.) (NRC)

A. Introductions B. Agenda Review C. Other Administrative Issues II. Process Issues (9:40 a.m. - 10:30 a.m.)

A. Status of Changes to the NRC Traveler Review Process (NRC)

1. Discussion of Changes to Traveler Contents (TSTF)
2. Necessity of the Federal Register Notice of Availability (All)
3. Information Needed to Support NRC Prioritization (All)

B. TSTF Communication to Licensees Regarding Adoption of Travelers (TSTF)

C. Discussion of the Desirability of Creating Model Safety Evaluations for pre-CLIIP Travelers (All)

D. Status of NRC Process for Evaluating Questions on Approved Travelers (NRC)

E. Status of NEI 15-03 review (NRC)

F. Status of Revision to IMC-0326, Appendix C.13 (NRC)

G. NRC Response to TSTF Suggestion to Add the Guidance in the Perry Safety Evaluation Regarding Redundant Support Systems to IMC-0326 (NRC)

H. Other Process Issues BREAK III. Issues with Previously Approved Travelers (10:45 a.m. - 12:00 p.m.)

A. NRC Response to TSTF Presentation on the Treatment of Fuel Handling Accidents in the Technical Specifications (NRC)

1. Status of Resolution of Issues Regarding TSTF-51, "Revise Containment Requirements during Handling Irradiated Fuel and Core Alterations," and TSTF-471, "Eliminate Use of Term CORE ALTERATIONS in ACTIONS and Notes," (NRC)

B. Status of Industry/NRC Discussions on Plant-Specific Adoption of TSTF-505, "Provide Risk-Informed Extended Completion Times" (TSTF)

C. Clarification of Requirements for TSTF-425, "Relocate Surveillance Frequencies to Licensee Control," Submittals (All)

1. Discussion of Bracketed Bases Information Concerning Excess Flow Check Valves.

D. NRC Response to Proposed TSTF-493, "Clarify Application of Setpoint Methodology for LSSS Functions," Supplement (NRC)

ENCLOSURE

E. Status of NRC Letter Regarding TSTF-412, "Provide Actions for One Steam Supply to Turbine Driven AFW/EFW Pump Inoperable" (NRC)

F. Status of NRC Letter Regarding Travelers that Contain Commitments (NRC)

LUNCH IV. Active Traveler Review Status (1:00 p.m. - 2:00 p.m.)

A. Changes to the Active Traveler Status Report (TSTF)

B. Discuss Status of All Travelers Currently Under NRC Staff Review (All)

1. TSTF-454, Rev. 3, Extend PCIV Completion Times (NEDC-33046) a) NRC schedule for providing second-round RAI.
2. TSTF-529, Rev. 3, Clarify Use and Application Rules a) NRC schedule for providing draft model safety evaluation.
3. TSTF-537, Rev. 0, Increase CIV Completion Time; Update of TSTF-373 a) NRC schedule for providing second-round RAI.
4. TSTF-541, Rev. 0, Add Exceptions to Surveillance Requirements When the Safety Function is Being Performed a) Response to RAI due November 11.
5. TSTF-542, Rev. 1, Reactor Pressure Vessel Water Inventory Control a) NRC schedule for providing second-round RAI
6. TSTF-545, Rev. 3, TS Inservice Testing (IST) Program Removal a) NRC schedule for issuing Notice of Availability b) Status of NRC consideration of withdrawal of the EGM and potential modification of the RIS. (NRC)
7. TSTF-547, Rev. 0, Clarification of Rod Position Requirements a) NRC schedule for providing draft model safety evaluation.
8. TSTF-551, Rev. 1, "Address Transient Secondary Containment Conditions" a) NRC schedule for providing RAI.
9. TSTF-553, Rev. 0, "Add Action for Two Inoperable CREATCS Trains" a) NRC schedule for acceptance and schedule letter.

V. Technical Issues (2:00 p.m. - 3:30 p.m.)

A. Discussion of Traveler under Development, TSTF-554, "Revise Reactor Coolant Leakage Requirements" (All)

1. NRC statement in September 18, 2015 10 CFR 50.55a proposed rulemaking regarding operational leakage (NRC)

B. Discussion of Separating the Calibration Frequency of Sensors and Channels under the Surveillance Frequency Control Program (TSTF)

C. Potential Traveler Regarding Spent Fuel Pool Neutron Absorber Monitoring Program (TSTF)

BREAK VI. Future Planning (3:45 p.m. - 4:00 p.m.)

A. Future Traveler submittals (TSTF)

1. TSTF-546, "Revise APRM Channel Adjustment Surveillance Requirement"
2. TSTF-552, "Diesel Generator Frequency and Voltage Tolerances (WCAP-17308)"

(following draft SE issuance)

3. TSTF-554, "Revise Reactor Coolant Leakage Requirements"
4. Traveler to Remove Mode 2 Requirement from LCO 3.0.3 B. Next Meeting (All)
1. 2016 Meeting Schedule VII. Designated Time for Public Comments VIII. Closing Remarks (All)