MONTHYEARML24303A2372024-10-29029 October 2024 Forthcoming Public Meeting Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force (TSTF) ML24303A1712024-10-29029 October 2024 Forthcoming Quarterly Public Meeting Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML24268A3272024-09-24024 September 2024 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft Traveler TSTF-604, Revise Ventilation System Actions ML24207A1462024-07-25025 July 2024 Forthcoming Quarterly Public Meeting Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML24207A1592024-07-25025 July 2024 Forthcoming Public Meeting Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force (TSTF) ML24113A1522024-04-22022 April 2024 Forthcoming Quarterly Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML24032A4692024-02-0101 February 2024 Forthcoming Quarterly Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML24009A2622024-01-0909 January 2024 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft Traveler TSTF-600, Revise the Reactor Coolant System (RCS) Pressure Isolation Valve (PIV) Leakage Testing Frequency ML24009A2632024-01-0909 January 2024 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft Traveler TSTF-599, Eliminate Periodic Surveillance Test of Simultaneous Start of Redundant Diesel Generators ML23299A2502023-10-26026 October 2023 Forthcoming Quarterly Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML23250A0672023-09-0707 September 2023 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft Traveler TSTF-601, Extend Shield Building Completion Time After Refueling ML23243B0342023-08-31031 August 2023 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft Traveler TSTF-601, Extend Shield Building Completion Time After Refueling ML23234A1742023-08-22022 August 2023 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft Traveler TSTF-593, Revise Design Features ML23222A1882023-08-10010 August 2023 Forthcoming Quarterly Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML23117A3512023-04-27027 April 2023 Forthcoming Quarterly Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML23107A2592023-04-17017 April 2023 Forthcoming Public Meeting Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force (TSTF) ML23075A3182023-03-16016 March 2023 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft Traveler TSTF-596, Expand the Applicability of the Surveillance Frequency Control Program (SFCP) ML23040A0902023-02-0909 February 2023 Forthcoming Quarterly Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML23033A5382023-02-0202 February 2023 Forthcoming Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML22312A4462022-11-0808 November 2022 Forthcoming Quarterly Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML22291A1962022-10-18018 October 2022 Forthcoming Public Meeting Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force (TSTF) ML22291A1982022-10-18018 October 2022 Forthcoming Public Meeting Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force (TSTF) ML22290A1252022-10-17017 October 2022 Forthcoming Public Workshop Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force (TSTF) ML22244A2002022-09-0101 September 2022 Meeting with the Technical Specifications Task Force (TSTF) Regarding Traveler TSTF-591, Revise Risk Informed Completion Time (RICT) Program ML22244A2202022-09-0101 September 2022 Forthcoming Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft TSTF-588, Remove List of COLR Methods ML22221A0542022-08-0909 August 2022 Forthcoming Quarterly Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML22119A2482022-04-29029 April 2022 Forthcoming Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML22056A2932022-02-24024 February 2022 2/24/2022 Meeting Handout - Active Traveler Summary Report ML22041A5402022-02-10010 February 2022 Forthcoming Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML22024A4532022-01-24024 January 2022 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft Traveler TSTF-591, Revise Risk Informed Completion Time (RICT) Program ML22024A4572022-01-24024 January 2022 Notice of Forthcoming Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML22011A1702022-01-11011 January 2022 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft Traveler TSTF-585, Provide an Alternative to the LCO 3.0.3 ONE-HOUR Preparation Time ML22010A2452022-01-10010 January 2022 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft Traveler TSTF-591, Revise Risk Informed Completion Time (RICT) Program ML22007A1992022-01-0707 January 2022 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft Traveler TSTF-585, Provide an Alternative to the LCO 3.0.3 ONE-HOUR Preparation Time ML21363A0772021-12-29029 December 2021 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft Traveler TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML21357A0952021-12-23023 December 2021 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft Traveler TSTF-591, Revise Risk Informed Completion Time (RICT) Program ML21316A2532021-11-12012 November 2021 Forthcoming Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML21300A3322021-10-27027 October 2021 Forthcoming Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML21300A3902021-10-27027 October 2021 Forthcoming Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML21266A4162021-09-23023 September 2021 Forthcoming Teleconference with the Technical Specifications Task Force (TSTF) Regarding Surveillance Requirements That Reference the Inservice Testing Program and 10 CFR 50.69 Categorization ML21252A5622021-09-0909 September 2021 Forthcoming Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft TSTF-588, Remove List of COLR Methods ML21203A0152021-07-22022 July 2021 Forthcoming Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML21147A1032021-05-27027 May 2021 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft TSTF-585, Revise LCO 3.0.3 ML21133A4882021-05-13013 May 2021 Forthcoming PRE-SUBMITTAL Teleconference with the Technical Specifications Task Force (TSTF) Regarding Draft TSTF-585, Revise LCO 3.0.3 ML21123A1442021-05-0303 May 2021 Forthcoming Teleconference with the Technical Specifications Task Force (TSTF) Regarding TSTF-576, Revise Safety/Relief Valve Requirements ML21118A8142021-04-28028 April 2021 Forthcoming Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML21043A2002021-02-12012 February 2021 Forthcoming Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force ML21007A0362021-01-0707 January 2021 Forthcoming Teleconference with the Technical Specifications Task Force (TSTF) Regarding TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML20329A3652020-11-24024 November 2020 Forthcoming Teleconference with the Technical Specifications Task Force (TSTF) Regarding TSTF-576, Revised Safety/Relief Valve Requirements ML20314A0382020-11-0909 November 2020 Forthcoming Public Teleconference Between the U. S. Nuclear Regulatory Commission and the Technical Specifications Task Force 2024-09-24
[Table view] |
Text
Verification of item within a specified Completion Time Discussion Topic at March 2020 Quarterly Meeting Question from TTC instructor: There are several TS Required Actions that include verification (Verify) of something within a specified completion time. For Required Actions that involve a verification within a specific Completion Time, can entering the subsequent Condition for not meeting that Required Action be delayed until the Completion Time is reached, even if the situation being verified is currently not met?
STSB staff interpretation is that the verifications provide the safety bases for staying in that condition. If the verification is not met at any time during the recurrent CT, the plant needs to be placed in a safer condition (a more limiting condition and CT). The STSB staff would like to get the TSTFs perspective on this interpretation and how it relates to how licensees apply these verifications.
BACKGROUND/EXAMPLES FROM TTC INSTRUCTOR:
- 1) When the Completion Time is Immediately, it is clear that if the action being verified is not met, the subsequent Condition for not meeting that Required Action is entered immediately.
i)
A good example is BWR/4 TS 3.5.3 Action A.1 for RCIC. If HPCI is not OPERABLE, then the Required Action is not met and Condition B is entered immediately.
- 2) When the Completion Time is Once per.., it usually is mandating some kind of on-going surveillance or parameter monitoring. If the surveillance fails or the parameter exceeds a limit, then a new Condition applies.
i)
A clear example is BWR/4 TS 3.6.2.1, Suppression Pool temperature, Required Action A.1, Verify suppression pool average temperature £ [110]°F Once per hour. If SP temperature exceeds [110]°F at any time, then Condition D is entered immediately.
ii) Example 1.3-7 deals with this situation. It specifically states: If after Condition A is entered, Required Action A.1 is not met within either the initial 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> or any subsequent 8-hour interval from the previous performance (plus the extension allowed by SR 3.0.2), Condition B is entered. This seems to imply that as soon as it is determined that the affected subsystem is NOT isolated, Condition B is entered immediately. However, it could mean that as long as the RA is met within the time limit, Condition B would not need to be entered. I believe its the former interpretation.
iii) Another specific example is BWR/4 TS 3.8.4, DC Sources, Required Action A.2. The bases states that: Required Action A.2 requires that the battery float current be verified as less than or equal to [2] amps. This indicates that, if the battery had been discharged as the result of the inoperable battery charger, it is now fully capable of supplying the maximum expected load requirements.
The [2] amp value is based on returning the battery to [95]% charge and assumes a [5]% design margin for the battery. If at the expiration of the initial [12] hour period the battery float current is not less than or equal to [2] amps this indicates there may be additional battery problems and the battery must be declared inoperable. This seems to indicate that as long as the float current is less than 2 amps before 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> has elapsed, Condition D or E need not be entered. In other words, A.2 may not be met initially, but Condition D or E need not be entered as long as the float current is restored during the initial 12-hour completion time.
- 3) When the Completion Time is a specified duration (e.g., 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />), it becomes even more confusing. Here are the BWR/4 TSs of interest:
Verification of item within a specified Completion Time Discussion Topic at March 2020 Quarterly Meeting i)
TS 3.4.4, RCS LEAKAGE, Required Action B.2 allows 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to Verify source of unidentified LEAKAGE increase is not service sensitive type 304 or type 316 austenitic stainless steel.
ii) TS 3.5.2, RPV Water Inventory Control, RAs C.1, C.2 and C.3 allow 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to verify that Secondary Containment can be established, Secondary Containment penetrations can be closed and Standby Gas Treatment can be placed in service; within the DRAIN TIME.
iii) TS 3.7.4, Main Control Room Environmental Control (MCREC)] System, Required Action B.2 allows 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to Verify mitigating actions ensure CRE occupant exposures to radiological, chemical, and smoke hazards will not exceed limits.
iv) TS 3.8.6, Battery Parameters, Required Action C.2, allows 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> to Verify no evidence of (battery cell) leakage If Condition C is entered due to electrolyte level below the top of the plates and the licensee determines that the cell is leaking within a few minutes, can they delay entering Condition F for the full 12-hour completion time? In this case, if they enter Condition F, TS 3.8.4 would not be met and TS 3.8.4 RA B.1 to restore the battery has a 2-hour completion time. If not restored, TS 3.8.4 RA D.1 requires them to be in Mode 3 in the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. If they could use the full 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> of TS 3.8.6 RA C.2, they would have a much better chance to complete some compensatory actions (e.g., jumper out the cell or replace the cell) and avoid a plant shutdown.