MONTHYEARML15342A4332013-03-26026 March 2013 NRC-006A - Shine Medical Technologies, Inc., Construction Permit Application, Cover Letter and General and Financial Information (March 26, 2013), ADAMS Accession No. ML13088A192 Project stage: Other ML13172A3612013-05-31031 May 2013 Part Two of the Shine Medical Technologies, Inc. Application for Construction Permit Project stage: Request ML13172A2622013-05-31031 May 2013 Shine Medical Technologies V. 0 - Chapter 01 - the Facility Project stage: Request ML13218A9832013-08-16016 August 2013 Shine Medical Technologies, Inc. - Acknowledgement of Receipt of Part Two of the Application for Construction Permit Project stage: Other ML13218A9842013-08-16016 August 2013 FRN: General Notice. Shine Medical Technologies, Inc. - Acknowledgment of Receipt of Part Two of the Application for Construction Permit Project stage: Other ML13233A3562013-08-28028 August 2013 Shine Medical Technologies, Inc. - Status of the Acceptance Review of Part Two of the Application for Construction Permit Project stage: Acceptance Review ML13269A3782013-09-25025 September 2013 Shine Medical Technologies, Inc., Submittal of Preliminary Emergency Plan Project stage: Other ML13316B3872013-12-0202 December 2013 Shine Medical Technologies, Inc., Cover Letter for Acceptance for Docketing of Part Two of the Application for Construction Permit Project stage: Acceptance Review ML13316B3492013-12-0202 December 2013 FRN: General Notice. Shine Medical Technologies, Inc., Acceptance for Docketing of Part Two of the Application for Construction Permit Project stage: Acceptance Review ML14119A0432014-03-17017 March 2014 Affidavit for Shine Medical Technologies, Inc. Discussion Notes Associated with March 20, 2014 Meeting Project stage: Request ML14121A5342014-05-0808 May 2014 Shine Medical Technologies, Inc., Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML14195A1592014-09-19019 September 2014 Shine Medical Technologies, Inc. - Request for Additional Information Regarding Application for Construction Permit Project stage: RAI ML14356A5282014-12-0303 December 2014 Shine Medical Technologies, Inc. Application for Construction Permit Response to Request for Additional Information Project stage: Response to RAI ML14356A4502014-12-0303 December 2014 Shine Medical Technologies V. 0 - Chapter 01 - the Facility Project stage: Request ML15005A4072015-01-0606 January 2015 Shine Medical Technologies, Inc., Request for Additional Information Regarding Application for Construction Permit Project stage: RAI ML15043A3172015-02-0606 February 2015 Shine Medical Technologies V. 0 - Chapter 01 - the Facility Project stage: Request ML15043A3952015-02-0606 February 2015 Shine Medical Technologies, Inc. - Application for Construction Permit - Response to Request for Additional Information Project stage: Response to RAI ML15037A2492015-03-0303 March 2015 Shine Medical Technologies, Inc., - Proposed Review Schedule, Notice of Hearing, Opportunity to Petition for Leave to Intervene, and Order Imposing Procedures Project stage: Other ML15037A1082015-03-0404 March 2015 Federal Register Notice - Notice of Hearing, Opportunity to Petition for Leave to Intervene, and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information for Contention Preparation on a Construction Permit F Project stage: Request ML15092A3222015-03-23023 March 2015 Shine Medical Technologies V. 0 - Chapter 01 - the Facility Project stage: Request ML15092A4072015-03-23023 March 2015 Shine Medical Technologies, Inc., Application for Construction Permit, Response to Request for Additional Information 11.1-9 Project stage: Response to RAI ML15055A1162015-03-25025 March 2015 Shine Medical Technologies, Inc., - Request for Additional Information Regarding Application for Construction Permit Project stage: RAI ML15120A0922015-04-10010 April 2015 Shine Medical Technologies V. 0 - Chapter 01 - the Facility Project stage: Request ML15120A2412015-04-10010 April 2015 Shine Medical Technologies, Inc., Application for Construction Permit, Response to Request for Additional Information Project stage: Response to RAI ML15099A6072015-04-15015 April 2015 Shine Medical Technologies, Inc., - Request for Additional Information Regarding Application for Construction Permit(Tac Nos. MF2305, MF2307, and MF2308) Project stage: RAI ML15131A1552015-05-0101 May 2015 Shine Medical Technologies V. 0 - Chapter 01 - the Facility Project stage: Request ML15131A4622015-05-0101 May 2015 Shine Medical Technologies, Inc. Application for Construction Permit, Response to Request for Additional Information Project stage: Response to RAI ML15147A1962015-05-14014 May 2015 Enclosure 2 Attachment 1 - PSAR Markups Project stage: Request ML15147A2032015-05-14014 May 2015 Shine Medical Technologies, Inc., Application for Construction Permit, Response to Request for Additional Information Project stage: Response to RAI ML15140A7342015-05-20020 May 2015 Shine Medical Technologies, Inc. Application for Construction Permit, Response to Request for Additional Information 13a2.2-5 Project stage: Response to RAI ML15161A3432015-05-21021 May 2015 Shine Medical Technologies, Inc. Preliminary Safety Analysis Report Revisions Resulting from Request for Additional Information Responses Project stage: Request ML15140A7222015-05-21021 May 2015 Shine Medical Technologies, Inc., Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15140A7312015-05-21021 May 2015 Shine Technologies, Inc. - Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15140A7262015-05-21021 May 2015 Shine Technologies, Inc. - Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15140A7252015-05-21021 May 2015 Shine Technologies, Inc. - Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15140A7242015-05-21021 May 2015 Shine Technologies, Inc. - Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15140A7232015-05-21021 May 2015 Shine Medical Technologies, Inc. - Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15175A2132015-06-16016 June 2015 Shine Medical Technologies V. 0 - Chapter 06 - Engineered Safety Features Project stage: Request ML15175A1312015-06-16016 June 2015 Shine Medical Technologies, Inc. Application for Construction Permit Revision to Sections 13b.3 and 19.4 of the Preliminary Safety Analysis Report Project stage: Request ML15183A2902015-06-19019 June 2015 Shine Medical Technologies, Inc. Application for Construction Permit - Response to Request for Additional Information Project stage: Response to RAI ML15183A2722015-06-19019 June 2015 Enclosure 2 Attachment 1 - ATKINS-NS-DAC-SHN-15-03, Rev. 1 - MCNP 6.1 Validation with Continuous Energy ENDF/B-VII.1 Cross Sections for Shine Medical Technologies Project stage: Request ML15222A2012015-07-23023 July 2015 Shine Medical Technologies, Inc. Application for Construction Permit Response to Request for Additional Information 6b.3-30 Project stage: Response to RAI ML15236A1272015-08-0707 August 2015 Shine Medical Technologies, Inc. Application for Construction Permit Submittal of Atkins-NS-TR-SHN-15-06, Revision 1 Project stage: Request ML15239A1012015-08-26026 August 2015 E-mail Transmitting Draft Request for Additional Information Supporting Shine PSAR Project stage: Draft RAI ML15219A1822015-08-27027 August 2015 Shine Medical Technologies Inc., Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15219A3032015-08-27027 August 2015 Shine Medical Technologies Inc., Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15219A3852015-08-27027 August 2015 Shine Medical Technologies Inc., Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15244A5062015-08-27027 August 2015 E-mail from Steven Lynch to Jim Costedio Transmitting Draft Request for Additional Information Supporting Shine PSAR Project stage: Draft RAI ML15219A2632015-08-27027 August 2015 Shine Medical Technologies Inc., Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML15219A4252015-08-27027 August 2015 Shine Medical Technologies Inc. - Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance 2015-03-25
[Table View] |
Text
From:
Lynch, Steven To:
Jim Costedio (Jim.Costedio@shinemed.com)
Cc:
Gavrilas, Mirela; Adams, Alexander; Kotzalas, Margie; Tripp, Christopher; Adams, Mary
Subject:
Draft Request For Additional Information Supporting SHINE Preliminary Safety Analysis Report Date:
Thursday, August 27, 2015 12:30:00 PM Attachments:
SHINE Draft Benchmark Request for Additional Information.pdf
- Jim, By letter dated June 19, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15183A290), SHINE Medical Technologies, Inc. (SHINE) responded, in part, to the U.S. Nuclear Regulatory Commission (NRC) staffs March 25, 2015, request for additional information (RAI) (ADAMS Accession No. ML15055A116) to complete the review of SHINEs preliminary safety analysis report supporting a construction permit application.
In the course of reviewing SHINEs RAI responses, the NRC staff has determined that SHINEs response to RAI 6b.3-26 is insufficient and additional information is required to complete the review of SHINEs preliminary safety analysis report in order to prepare a safety evaluation report. Therefore, the NRC has prepared the attached draft RAI in order for SHINE to ensure that the request is clear and understandable. SHINE should contact Steven Lynch with any questions regarding this draft request as soon as possible to arrange a time to discuss the RAI with the appropriate NRC technical staff.
The NRC staff asks that SHINE also review this draft RAI to ensure that proprietary information has not inadvertently been included. Should any proprietary information be identified, contact Steven Lynch within the next ten days. If SHINE does not identify proprietary information within the next ten days, this draft RAI will be made publicly available.
This draft RAI supplements the NRCs previous RAIs related to SHINEs construction permit application dated September 11, 2013, September 19, 2014, January 6, 2015 (ADAMS Accession Nos. ML13231A041, ML14195A159, ML15005A407, respectively),
March 25, 2015, and April 15, 2015 (ADAMS Accession No. ML15099A607).
In order to support the efficient review of SHINEs construction permit application submitted application, SHINE should contact Steven Lynch to discuss an appropriate response time for this request for additional information.
Steve Lynch Project Manager Office of Nuclear Reactor Regulation Division of Policy and Rulemaking, Research and Test Reactors Licensing Office: O-12F08 MS: O-12D20 Phone: 301-415-1524