Shine Medical Technologies, Inc., - Proposed Review Schedule, Notice of Hearing, Opportunity to Petition for Leave to Intervene, and Order Imposing Procedures
ML15037A249
Person / Time
Site: SHINE Medical Technologies
Issue date: 03/03/2015
From: Steven Lynch
Division of Policy and Rulemaking, Research and Test Reactors Branch B
To: Bynum R
SHINE Medical Technologies
Lynch, Steven 415-1524
References
TAC MF2307
Download: ML15037A249 (5)


Text

March 3, 2015 Richard Vann Bynum, PhD Chief Operating Officer SHINE Medical Technologies, Inc.

2555 Industrial Drive Monona, WI 53713

SUBJECT:

SHINE MEDICAL TECHNOLOGIES, INC. - PROPOSED REVIEW SCHEDULE, NOTICE OF HEARING, OPPORTUNITY TO PETITION FOR LEAVE TO INTERVENE, AND ORDER IMPOSING PROCEDURES REGARDING APPLICATION FOR CONSTRUCTION PERMIT (TAC NO. MF2307)

Dear Dr. Bynum:

By letter dated March 26, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13088A192), SHINE Medical Technologies, Inc. (SHINE) submitted part one, consisting primarily of its environmental report, of a two-part construction permit (CP) application for review by the U.S. Nuclear Regulatory Commission under Title 10 of the Code of Federal Regulations (10 CFR), Part 50, Domestic Licensing of Production and Utilization Facilities. By letter dated May 31, 2013 (ADAMS Accession No. ML13172A361), SHINE submitted the second and final part of its two-part application for a CP. By letter dated September 25, 2013 (ADAMS Accession No. ML13269A378), SHINE supplemented its application with a discussion of preliminary plans for coping with emergencies, as required by 10 CFR 50.34(a)(10), therefore, completing its application for a construction permit. SHINEs construction permit, including its environmental report, may be viewed in its entirety in ADAMS, Accession No. ML13172A324.

By letter dated June 25, 2013, the NRC staff determined that part one of SHINEs application for a CP was complete and acceptable for docketing (ADAMS Accession No. ML13150A280),

assigning the application Docket No. 50-608. By letter dated December 2, 2013 (ADAMS Accession No. ML13316B387), the NRC staff informed SHINE that part two of its CP application, as supplemented, contained the remainder of the preliminary safety analysis report (PSAR) required by 10 CFR 50.34(a), was submitted in accordance with the requirements of 10 CFR 2.101(a)(5), and was placed, in its entirety, under Docket No. 50-608.

This letter forwards the NRC staffs safety and environmental review schedule for the SHINE CP application (Enclosure 1). The NRC staff will follow the enclosed schedule to complete the reviews of SHINEs PSAR and environmental report required by 10 CFR Parts 50 and 51, Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions. Milestones for hearing activities are not included in the enclosed schedule because such dates would be established by the Commission or the Atomic Safety and Licensing Board.

The NRC staff will make every effort to meet the scheduled milestones. The NRC staff will provide updates to the enclosed schedule (1) after all requests for additional information have been addressed, (2) after the closing of the comment period for the draft environmental impact

R. Bynum statement, and (3) when a hearing has been scheduled.

Also, in accordance with the provisions of 10 CFR 2.104, a notice of hearing and opportunity to petition for leave to intervene on the application will be forwarded to the Federal Register for publication. Enclosed is a copy of that notice, including an order imposing procedures for access to sensitive unclassified non-safeguards information for contention preparation.

If you have any questions, please contact me at Steven.Lynch@nrc.gov or 301-415-1524.

Sincerely,

/RA by Alexander Adams for/

Steven Lynch, Project Manager Research and Test Reactors Licensing Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No.: 50-608

Enclosures:

1. Construction Permit Application Review Schedule
2. Notice of Hearing cc w/encls.: See next page

cc:

Jim Costedio Bill McCoy Licensing Manager 1326 Putnam Avenue SHINE Medical Technologies, Inc. Janesville, WI 53546 2555 Industrial Drive Monona, WI 53713 Alfred Lembrich 541 Miller Avenue Kirsten Cutler, Ph.D. Janesville, WI 53548 National Security and International Affairs Office of Science and Technology Policy Gerald and Muriel Bumgarner Executive Office Building 1735 S Osborne Ave 1650 Pennsylvania Avenue Janesville, WI 53546 Washington, DC 20503 Rilla Hamilton National Nuclear Security Administration, NA-212 U.S. Department of Energy 1000 Independence Ave SW Washington, DC 20585 Paul Schmidt Manager Radiation Protection Section Wisconsin Department of Health Services P.O. Box 2659 Madison, WI 53701-2659 Eric P. Heggelund Environmental Analysis and Review Specialist State of Wisconsin Department of Natural Resources 3911 Fish Hatchery Road Fitchburg, WI 53711 TRTR Newsletter University of Florida Department of Nuclear Engineering Sciences 202 Nuclear Sciences Center Gainesville, FL 32611 Mark Freitag City Manager P.O. Box 5005 Janesville, WI 53547-5005

Pkg: ML15037A271 Letter: ML15037A249 FRN: ML15037A108 Memo to ADM: ML15037A157 *concurrence via e-mail ADM-012 OFFICE NRR/DPR/PRLB NRR/DPR/LA OGC NRR/DPR/PRLB NRR/DPR/PRLB NAME SLynch DHarrison MYoung AAdams SLynch DATE 02/05/15 02/19/15 02/27/2015 03/3/15 03/3/15 SHINE Medical Technologies, Inc.

Construction Permit Application Review Schedule Scheduled Milestone Status Completion Date Receipt of Construction Permit Application (Part 1 of 2) March 2013 Complete Receipt of Construction Permit Application (Part 2 of 2) May 2013 Complete Docketing of Construction Permit Application (Part 1 of 2) July 2013 Complete Environmental Scoping Meeting July 2013 Complete Environmental Site Audit August 2013 Complete Issuance of Request for Additional Information on August 2013 Complete Environmental Report Docketing of Construction Permit Application (Part 2 of 2) December 2013 Complete Issuance of Request for Additional Information on Preliminary Safety Analysis Report and Environmental September 2014 Complete Report Issuance of Supplemental Requests for Additional January 2015 Complete Information on Preliminary Safety Analysis Report and March 2015 Pending Environmental Report Completion of Draft Environmental Impact Statement May 2015 Pending Completion of Safety Evaluation Report with Open Items May 2015 Pending Advisory Committee on Reactor Safeguards June 2015 Pending Subcommittee Meeting Advisory Committee on Reactor Safeguards Full July 2015 Pending Committee Meeting Publication of Safety Evaluation Report October 2015 Pending Publication of Environmental Impact Statement October 2015 Pending Mandatory Hearing on Construction Permit Application TBD Pending ENCLOSURE 1