ML15244A236

From kanterella
Jump to navigation Jump to search
Safety Evaluation Accepting Util 831104 Response to Generic Ltr 83-28,Item 4.5.2 Re Reactor Trip Sys Reliability on-line Testing
ML15244A236
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 04/27/1987
From:
Office of Nuclear Reactor Regulation
To:
Shared Package
ML15244A235 List:
References
GL-83-028 NUDOCS 8704300330
Download: ML15244A236 (20)


Text

SAFETY EVALUATION REPORT DOCKET NOS. 50-269/27//287 OCONEE NUCLEAR STATION, UNITS 1,2,3 GENERIC LETTER 83-28, TTEM 4.5.2 REACTOR TRIP SYSTEM RELABILITY-ON-LINE TESTTNG INTRODUCTION AND

SUMMARY

Generic Letter 83-28 was issued by NRC on July 8, 1983, indicating actions to be taken by applicants and licensees based on the generic implications of the Salem ATWS events. Item 4.5 states a staff position which requires on-line functional testing of the reactor trip system, including independent testing of the diverse trip features of the reactor trip breakers, for all plants.

Item 4.5.2 requires applicants and licensees with plants not currently designed to permit this peri odic on-line testing to justify not making modifications to permit such testing.

By letter dated November 4, 1983, the licensee, Duke Power Company, responded to the staff position regarding Item 4.5.? of Generic Letter 83-28. Our review of this response finds it to be acceptable.

EVALUATION The licensee states that Duke Power performs on-line testing of the reactor trip system, and the testing will include independent testing of the undervoltage and shunt trip attachments of the reactor trip breakers.

8704300330 870427 PDR ADOCK.05000269 P

PDR_

CONCLUSION The staff finds that the Oconee Nuclear Station, Units 1, 2, 3, is designed to permit on-line functional testing of the reactor trip system, including independent testing of the diverse trip features of the reactor trip breakers.

Thus, the licensee meets the staff position of Item 4.5.2 of Generic Letter 83-28.

EGG-NTA-7462 TECHNICAL EVALUATION REPORT REACTOR TRIP SYSTEM RELIABILITY CONFORMANCE TO ITEM 4.5.2 OF GENERIC LETTER 83-28 ARKANSAS NUCLEAR ONE-1 CRYSTAL RIVER-3 DAVIS-BESSE-1 OCONEE-1, -2 AND -3 RANCHO SECO THREE MILE ISLAND-1 WNP-1 F. G. Farmer Published March 1987 Idaho National Engineering Laboratory EG&G Idaho, Inc.

Idaho Falls, Idaho 83415 Prepared for the U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Under DOE Contract No. DE-ACO7-761D01570 FIN Nos. D6001 and D6002

ABSTRACT This EG&G Idaho, Inc. report provides a review of the submittals for Babcock & Wilcox (B&W) nuclear plants for conformance to Generic Letter 83-28, Item 4.5.2. The report includes the following plants, all B&W, and is in partial fulfillment of the following TAC Nos.:

Plant Docket Number TAC Number Arkansas Nuclear One, Unit 1 50-313 53960 Crystal River Unit 3 50-302 53974 Davis-Besse Unit 1 50-346 53975 Oconee Unit 1 50-269 54005 Oconee Unit 2 50-270 54006 Oconee Unit 3 50-287 54007 Rancho Seco 50-312 54019 Three Mile Island Unit 1 50-289 54034 WNP 1 (OL) 50-460 N/A

FOREWORD This report is provided as part of the program for evaluating licensee/applicant conformance to Generic Letter 83-28, "Required Actions Based on Generic Implications of Salem ATWS Events."

This work is conducted for the U.S. Nuclear Regulatory Commission, Office of Nuclear Reactor Regulation, Division of PWR Licensing-A by EG&G Idaho, Inc.

The U.S. Nuclear Regulatory Commission funded the work under the authorization, B&R 20-19-19-11-3, FIN Nos. D6001 and D6002.

CONTENTS ABSTRACT.........

FOREWORD 9

1. INTRODUCTION...................................................
2. REVIEW REQUIREMENTS.............................................

2

3. GROUP REVIEW RESULTS............................................4
4. REVIEW RESULTS FOR ARKANSAS NUCLEAR ONE, UNIT 1.................

5 4.1 Evaluation................................................

5 4.2 Conclusion

5. REVIEW RESULTS FOR CRYSTAL RIVER UNIT 3..........................

6 5.1 Evaluation..............................................

6 5.2 Conclusion................................................

6

6.

REVIEW RESULTS FOR DAVIS-BESSE UNIT 1..................

7 6.1 Evaluation

................................................ 7 6.2 Conclusion..............................................

7

7. REVIEW RESULTS FOR OCONEE UNITS 1, 2 AND 3......................

8 7.1 Evaluation................................................

8 7.2 Conclusion................................................ 8

8. REVIEW RESULTS FOR RANCHO SECO..................................

9 8.1 Evaluation................................................

9 8.2 Conclusion...............................................

9

9. REVIEW RESULTS FOR THREE MILE ISLAND UNIT 1.....................

10 9.1 Evaluation............................................... 10 9.2 Conclusion............................................... 10 iv

10.

REVIEW RESULTS FOR WNP 1........................................

11 10.1 Evaluation...............................................11 10.2 Conclusion............................................... 11

11.

GROUP CONCLUSION...............................................

12

12.

REFERENCES....................................................

13 V

0I TECHNICAL EVALUATION REPORT REACTOR TRIP SYSTEM RELIABILITY CONFORMANCE TO ITEM 4.5.2 OF GENERIC LETTER 83-28 ARKANSAS NUCLEAR ONE-1 CRYSTAL RIVER-3 DAVIS-BESSE-1 OCONEE-1. -2 AND -3 RANCHO SECO THREE MILE ISLAND-1 WNP-1

1. INTRODUCTION On July 8, 1983, Generic Letter 83-281 was issued by D. G. Eisenhut, Director of the Division of Licensing, Office of Nuclear Reactor Regulation, to all licensees of operating reactors, applicants for operating licenses, and holders of construction permits.

This letter included required actions based on generic implications of the Salem ATWS events. These requirements have been published in Volume 2 of NUREG-1000, "Generic Implications of ATWS Events at the Salem Nuclear Power Plant."2 This report documents the EG&G Idaho, Inc., review of the submittals of all the B&W plants, including Arkansas Nuclear One, Unit 1, Crystal River Unit 3, Davis-Besse Unit 1, Oconee Units 1, 2 and 3, Rancho Seco, Three Mile Island Unit 1 and WNP 1 for conformance to Item 4.5.2 of Generic Letter 83-28. The submittals from the licensees utilized in these evaluations are referenced in Section 12 of this report.

2.

REVIEW REQUIREMENTS Item 4.5.2 (Reactor Trip System Reliability - System Functional Testing - On-Line Testing) requires licensees and applicants with plants not currently designed to permit on-line testing to justify not making modifications to permit such testing. Alternatives to on-line testing will be considered where special circumstances exist and where the objective of high reliability can be met in another way. Item 4.5.2 may be interdependent with Item 4.5.3 when there is a need to justify not performing on-line testing because of the peculiarities of a particular design.

All portions of the Reactor Trip System that do not have on-line testing capability will be reviewed under the guidelines for this item.

Maintenance and testing of the Reactor Trip Breakers are also excluded from this review, as they are evaluated under Item 4.2. This review of the licensee/applicant submittals will:

1. Confirm that the licensee/applicant has identified those portions of the Reactor Trip System that are not on-line testable. If the entire Reactor Trip System is verified to be on-line testable, no further review is required.
2. Evaluate modifications proposed by licensees/applicants to permit on-line testing against the existing criteria for the design of the protection systems for the plant being modified.
3. Evaluate proposed alternatives to on-line testing of the Reactor Trip System for acceptability based on the following:
a. The licensee/applicant submittal substantiates the impracticality of the modifications necessary to permit on-line testing, and 2
b. High Reactor Trip System availability (comparable to that which would be possible with on-line testing) is achieved in another way. Any such proposed alternative must be described in detail sufficient to permit an independent evaluation of the basis and analysis provided in lieu of performing on-line testing. Methods that may be used to demonstrate that the objective of high reliability has been met may include the following:
i. Demonstration by systematic analysis that testing at shutdown intervals provides essentially equivalent reliability to that obtained by on-line testing at shorter intervals.

ii. Demonstration that reliability equivalent to that obtained by on-line testing is accomplished by additional redundant and diverse components or by other features.

iii. Development of a maintenance program based on early replacement of critical components that compensates for the lack of on-line testing. Such a program would require analytical justification supported by test data.

iv. Development of a test program that compensates for the lack of on-line testing, e.g., one which uses trend analysis and identification of safety margins for critical parameters of safety-related components. Such a program would require analytical justification supported by test data.

4.

Verify the capability to perform independent on-line testing of the reactor trip system breaker undervoltage and shunt trip attachments on CE plants. Information from licensees and applicants with CE plants will be reviewed to verify that they require independent on-line testing of the reactor trip breaker undervoltage and shunt trip attachments.

3

3.

GROUP REVIEW RESULTS The relevant submittals from each of the B&W reactor plants were reviewed to determine compliance with Item 4.5.2. First, the submittals from each plant were reviewed to establish that Item 4.5.2 was specifically addressed. Second, the submittals were evaluated to determine the extent to which each of the B&W plants complies with the staff guidelines for Item 4.5.2.

4

4. REVIEW RESULTS FOR ARKANSAS NUCLEAR ONE, UNIT 1 4.1 Evaluation Arkansas Power and Light Company (AP&L), the license for Arkansas Nuclear One, provided their response to Item 4.5.2 of the Generic Letter on November 5, 1983. In that response, the licensee states that AP&L performs on-line testing of the Reactor Trip System, including independent testing of the shunt and undervoltage trip attachments.

4.2 Conclusion We find that the licensee's statement that they currently perform on-line testing of the RTS meets the staff position on Item 4.5.2 of the Generic Letter and is, we believe, acceptable.

5

5. REVIEW RESULTS FOR CRYSTAL RIVER UNIT 3 5.1 Evaluation Florida Power Corporation (FPC), the licensee for Crystal River Unit 3, responded to Item 4.5.2 of the Generic Letter on November 4, 1983.

In that response, the licensee states that FPC performs on-line testing of the Reactor Trip System, and that the RTS circuitry will be modified to permit independent on-line testing of the shunt and undervoltage trip attachments..

5.2 Conclusion We find that the licensee's statement that they currently perform on-line testing of the RTS and will modify the RTS circuitry to permit independent on-line testing of the shunt and undervoltage trip attachments meets the staff position on Item 4.5.2 of the Generic Letter and is, we believe, acceptable.

6

6. REVIEW RESULTS FOR DAVIS-BESSE UNIT 1 6.1 Evaluation Toledo Edison, the licensee for Davis-Besse Unit 1, responded to Item 4.5.2 of the Generic Letter on December 9, 1983. In that response the.

licensee states that Davis-Besse 1 performs on-line testing to the Reactor Trip System, with the exception of the SCRs. It is not clear from the licensee's response that Davis-Besse 1 has the capability to perform independent on-line testing of the shunt and undervoltage trip attachments.

6.2 Conclusion We find that the licensee's statement that they currently perform on-line testing of the RTS meets the staff position on Item 4.5.2 of the Generic Letter and is, we believe, acceptable, provided the licensee confirms that Davis-Besse 1 has the capability to perform independent on-line testing of the shuntand undervoltage trip attachments.

7

7. REVIEW RESULTS FOR OCONEE UNITS 1, 2 AND 3 7.1 Evaluation Duke Power Company, the licensee for Oconee Units 1, 2 and 3, responded to Item 4.5.2 of the Generic Letter on November 4, 1983. In that response, the licensee states that Duke performs on-line testing of the Reactor Trip System, and that the testing will include independent testing of the reactor trip breaker shunt and undervoltage trip attachments.

7.2 Conclusion We find that the licensee's statement that they currently perform on-line testing of the RTS meets the staff position on Item 4.5.2 of the Generic Letter and is, we believe, acceptable.

8

8. REVIEW RESULTS FOR RANCHO SECO 8.1 Evaluation Sacramento Municipal Utility District (SMUD), the licensee for Rancho Seco, provided a response to Item 4.5.2 of the Generic Letter on November 4, 1983. In that response, the licensee states that SMUD performs, or has committed to make modifications to allow performance of, on-line testing of the Reactor Trip System, including independent testing of the shunt and undervoltage trip attachments to the reactor trip breakers.

8.2 Conclusion We find that the licensee's statement that they will have the capability to perform on-line testing of the RTS meets the staff position on Item 4.5.2 of the Generic Letter.

9

9. REVIEW RESULTS FOR THREE MILE ISLAND UNIT 1 9.1 Evaluation GPU Nuclear Corporation, the licensee for Three Mile Island Unit 1 (TMI-1), responded to Item 4.5.2 of the Generic Letter on November 8, 1983. In that response, the licensee states that GPU performs on-line testing of the Reactor Trip System, including independent testing of the shunt and undervoltage trip attachments to the reactor trip breakers.

9.2 Conclusion We find that the licensee's statement that they currently perform on-line testing of the RTS meets the staff position on Item 4.5.2 of the

'Generic Letter and is, we believe, acceptable.

10

10.

REVIEW RESULTS FOR WNP 1 10.1 Evaluation Washington Public Power Supply System, the applicant for WNP 1, responded to Item 4.5.2 of the Generic Letter on March 30, 1984.

In that response, the applicant states that the WNP 1 design will permit and that WPPS will perform on-line testing of the Reactor Trip System.

10.2 Conclusion We find that the applicant's statement that they will perform on-line testing of the RTS meets the staff position on Item 4.5.2 of the Generic Letter and is, we believe, acceptable.

1.1

11.

GROUP CONCLUSION We conclude that the licensee/applicant responses for the listed B&W plants for Item 4.5.2 of Generic Letter 83-28 are acceptable, with the exception that Davis-Besse 1 must provide the confirmation addressed in the plant specific review.

12

12. REFERENCES
1. NRC Letter, D. G. Eisenhut to all licensees of Operating Reactors, Applicants for Operating License, and Holiers of Construction Permits,
  • Required Actions Based on Generic Implications of Salem ATWS Events (Generic letter 83-28)," July 8, 1983.
2. Generic Implications of ATWS Events at the Salem Nuclear Power Plant NUREG-1000, Volume 1, April 1983; Volume 2, July 1983.
3. Arkansas Power and Light Company letter to NRC, J. R. Marshall to
0. G. Eisenhut, Director, Division of Licensing, NRC, "Arkansas Nuclear One Response to Generic Letter 83-28," November 5, 1983.
4. Florida Power Corporation letter to NRC, G. R. Westafer to D. G. Eisenhut, Director, Division of Licensing, NRC, "Crystal River Unit 3 Response to Generic Letter 83-28," November 4, 1983.
5. Toledo Edison letter to NRC, R. P. Crouse to Director of Nuclear Reactor Regulation, NRC, December 9, 1983.
6.

Duke Power Company letter to NRC, H. B. Tucker to H. R. Denton, Director, Office of Nuclear Reactor Regulation, November 4, 1983.

7. Sacramento Municipal Utility District letter to NRC, R. J. Rodriquez to D. G. Eisenhut, Director, Division of Licensing, NRC, "Required Actions Based on Generic Implications of Salem ATWS Events (Generic Letter 83-28)," November 4, 1983.
8. GPU Nuclear Corporation letter to NRC, H. D. Hukill to D. G. Eisenhut, Director, Division of Licensing, NRC, "Required Actions Based on Generic Implications of Salem/ATWS Events," November 8, 1983.
9. Washington Public Power Supply System letter to NRC, G. C. Sorenson to Director of Nuclear Reactor Regulation, "Nuclear Project No. 1, Response to Generic Letter 83-28, Salem ATWS Event," March 30, 1984.

13