Notice of Forthcoming Close Meeting with Tennessee Valley Authority on Browns Ferry Nuclear Plant Planned Submittal of Extended Power Uprate License Amendment Request - for the Replacement Steam Dryer
ML15097A230
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 04/08/2015
From: Farideh Saba
Plant Licensing Branch II
To: Shana Helton
Plant Licensing Branch II
Saba F DORL/LPL2-2 301-415-1447
References
TAC MF4851, TAC MF4852, TAC MF4853
Download: ML15097A230 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 8, 2015 MEMORANDUM TO: Shana R. Helton, Chief Plant Licensing Branch 11-2 FROM:

SUBJECT:

DATE AND TIME:

LOCATION:

PURPOSE:

PARTICIPANTS:

Division of Operator Reactor Licensing Office of Nuclear Reactor Regulation Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operator Reactor Licensing Office of Nuclear Reactor Regulation FORTHCOMING CLOSED MEETING WITH TENNESSEE VALLEY AUTHORITY (TVA) ON BROWNS FERRY NUCLEAR PLANT PLANNED SUBMITTAL OF EXTENDED POWER UPRATE (EPU) LICENSE AMENDMENT REQUEST (TAC NOS. MF4851, MF4852, AND MF4853)

Wednesday, April 22, 2015, in two sessions:

9:00 a.m. - 11 :00 a.m. and 1 :00 p.m. - 3:00 p.m. (Eastern Time)

U.S. Nuclear Regulatory Commission (NRC)

One White Flint North, Room 0-07B04 11555 Rockville Pike Rockville, Maryland 20852 TVA will provide information regarding the steam dryer replacement for Browns Ferry for its planned EPU. The information provided in the slides for this meeting are considered proprietary by the General Electric Hitachi (GEH), as stated in the submitted affidavit.

Participants include staff from NRC, the Office of Nuclear Reactor Regulation (NRR), TVA staff, and GEH staff.

NRC/NRR Shana Helton Farideh Saba Tim Lupold Kamal Manely Chakrapani Basavaraju Chris Jackson David Alley Anthony Minarik Ed Schrull Dan Green Gerry Doyle Pete Donahue Eric Frevold Dan Pappone Tao Wu Scott Gowdy

S. Helton CONTACTS: Farideh Saba farideh. saba@nrc.gov 301-415-1447 Anthony Minarik Anthony.Minarik@nrc.gov 301-415-6185 To receive a summary of this meeting and begin receiving other plant-specific e-mail distributions, you must subscribe to the Operating Reactor Correspondence electronic distribution for this plant via http://www.nrc.gov/public-involve/listserver/plants-by-region.html.

Once subscribed, if you wish to discontinue receiving electronic distribution, you may unsubscribe at any time by visiting the same Web address above.

Docket Nos. 50-259, 50-260, and 50-296

Enclosure:

Agenda cc w/enclosure: Distribution via Listserv

AGENDA FORTHCOMING NUCLEAR REGULATORY COMMISSION CLOSED MEETING WITH TENNESSEE VALLEY AUTHORITY (TVA)

REGARDING TVA'S PLANNED SUBMITTAL OF EXTENDED POWER UPRATE (EPU)

LICENSE AMENDMENT REQUEST FOR Introduction BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2. AND 3, WEDNESDAY, APRIL 22. 2015

  • EPU Overview and Schedule Replacement Steam Dryer (RSD) Overview RSD Design RSD analysis Power Ascension Monitoring lnpection Plan Meeting adjourned
  • Note that the meeting will be in two sessions, one in the morning and one in the afternoon.

The afternoon meeting will start at the point that the morning session ends.

Enclosure

ML15097A230 OFFICE DORL/LPL2-2/PM DORL/LPL2-2/LAiT DORL/LPL2-2/LA NAME FSaba LRonewicz BClavton DATE 4/7/15 4/7/15 4/7/15