Other: ML13220A402, ML13317A969, ML15141A468, ML15272A398, W3F1-2012-0092, Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), W3F1-2012-0093, Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049), W3F1-2013-0006, Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, Order Number EA-12-051, W3F1-2013-0010, (Waterford 3), Entergy Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.3, W3F1-2013-0049, First Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, W3F1-2013-0050, First Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, W3F1-2014-0014, Second Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, W3F1-2014-0015, Second Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, W3F1-2014-0049, Third Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, W3F1-2014-0050, Third Six-Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Waterford Steam Electric Station, Un, W3F1-2015-0003, Fourth Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, W3F1-2015-0004, Fourth Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, W3F1-2015-0068, Fifth Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation
|
MONTHYEARW3F1-2012-0042, Entergys 90-Day Response to the March 12, 2012, Information Request, Action Plan for Completing Emergency Communication and Staffing Assessments2012-06-0707 June 2012 Entergys 90-Day Response to the March 12, 2012, Information Request, Action Plan for Completing Emergency Communication and Staffing Assessments Project stage: Request W3F1-2012-0092, Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2012-10-26026 October 2012 Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other W3F1-2012-0093, Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)2012-10-26026 October 2012 Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049) Project stage: Other W3F1-2013-0010, (Waterford 3), Entergy Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.32013-02-21021 February 2013 (Waterford 3), Entergy Response to NRC Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.3 Project stage: Other ML1306606872013-02-28028 February 2013 CFR Part 26, Subpart I - Managing Fatigue, for Period Ending 2012 Project stage: Request W3F1-2013-0006, Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, Order Number EA-12-0512013-02-28028 February 2013 Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, Order Number EA-12-051 Project stage: Other W3F1-2013-0017, (Waterford 3), Overall Integrated Plan in Response to March 12, 2012, Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2013-02-28028 February 2013 (Waterford 3), Overall Integrated Plan in Response to March 12, 2012, Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Request W3F1-2013-0032, Core Operating Limits Report - Cycle 19 Revision 12013-08-26026 August 2013 Core Operating Limits Report - Cycle 19 Revision 1 Project stage: Request ML13246A3182013-08-28028 August 2013 Request for Additional Information E-mail, Overall Integrated Plan in Response to 3/12/12 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: RAI W3F1-2013-0050, First Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2013-08-28028 August 2013 First Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other W3F1-2013-0049, First Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation2013-08-28028 August 2013 First Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Other W3F1-2013-0055, Response to Request for Additional Information (RAI) for the Overall Integrated Plan (OIP) in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool (SFP) Instrumentation2013-09-26026 September 2013 Response to Request for Additional Information (RAI) for the Overall Integrated Plan (OIP) in Response to the Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool (SFP) Instrumentation Project stage: Response to RAI ML13317A9692013-11-20020 November 2013 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Waterford Steam Electric Generating Station, Unit 3, TAC No.: MF0977 Project stage: Other ML13220A4022013-11-22022 November 2013 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 - Mitigation Strategies Project stage: Other ML13312A7872013-11-25025 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: RAI W3F1-2014-0014, Second Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-02-28028 February 2014 Second Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other W3F1-2014-0015, Second Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation2014-02-28028 February 2014 Second Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Other W3F1-2014-0050, Third Six-Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Waterford Steam Electric Station, Un2014-08-28028 August 2014 Third Six-Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Waterford Steam Electric Station, Unit 3 Project stage: Other W3F1-2014-0049, Third Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation2014-08-28028 August 2014 Third Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Other W3F1-2015-0003, Fourth Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-02-26026 February 2015 Fourth Six Month Status Report for Implementation of Order EA-12-049, Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other W3F1-2015-0004, Fourth Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation2015-02-26026 February 2015 Fourth Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Other ML15141A4682015-05-27027 May 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other W3F1-2015-0068, Fifth Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation2015-08-27027 August 2015 Fifth Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Other W3F1-2015-0073, Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-08-31031 August 2015 Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Request ML15245A3442015-10-0404 October 2015 Relaxation of the Schedule Requirements for Order EA-12-049 Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Approval ML15272A3982015-10-0606 October 2015 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other 2013-08-28
[Table View] |
Text
W3F1-2015-0004 February 26, 2015 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852
SUBJECT:
Fourth Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License With Regard To Reliable Spent Fuel Pool Instrumentation Waterford Steam Electric Station, Unit 3 (Waterford 3)
Docket No. 50-382 License No. NPF-38
References:
- 1.
NRC Order Number EA-12-051, Order to Modify Licenses with Regard to Reliable Spent Fuel Pool (SFP) Instrumentation, dated March 12, 2012 (ADAMS Accession No. ML12054A682)
- 2.
NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-12-051, Reliable SFP Instrumentation, Revision 0, dated August 29, 2012 (ADAMS Accession No. ML12221A339)
- 3.
Nuclear Energy Institute (NEI) 12-02, Industry Guidance for Compliance with NRC Order EA-12-051, To Modify Licenses with Regard to Reliable SFP Instrumentation, Revision 1, dated August 2012 (ADAMS Accession No. ML12240A307)
- 4.
Entergy letter to NRC, Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable SFP Instrumentation (Order Number EA 051), dated October 26, 2012 (ADAMS Accession No. ML12300A446)
- 5.
Waterford Steam Electric Station, Unit 3, letter to NRC, Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051),
dated February 28, 2013 (ADAMS Accession No. ML13063A263).
Entergy Operations, Inc.
17265 River Road Killona, LA 70057-3093 Tel 504-739-6660 Fax 504-739-6678 mchisum@entergy.com Michael R. Chisum Vice President - Operations Waterford 3
W3F1-2015-0004 Page 2 of 3
- 6.
Waterford Steam Electric Station, Unit 3 letter to NRC, First Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License With Regard To Reliable Spent Fuel Pool Instrumentation dated August 28, 2013 (ADAMS Accession No. ML13241A280)
- 7.
Waterford Steam Electric Station, Unit 3 letter to NRC, Second Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License With Regard To Reliable Spent Fuel Pool Instrumentation dated February 28, 2014 (ADAMS Accession No. ML14059A087)
- 8.
Waterford Steam Electric Station, Unit 3 letter to NRC, Third Six Month Status Report for Implementation of Order EA-12-051, Commission Order Modifying License With Regard To Reliable Spent Fuel Pool Instrumentation dated August 28, 2014 (ADAMS Accession No. ML14247A294)
Dear Sir or Madam:
On March 12, 2012, the NRC issued NRC Order EA-12-051 (Reference 1) to Entergy Operations, Inc. (Entergy). The Order (Reference 1) was immediately effective and directs Waterford Steam Electric Station, Unit 3 (Waterford 3), to have a reliable indication of the water level in associated spent fuel storage pools.
Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an Overall Integrated Plan (OIP). Reference 2 endorses industry guidance document NEI 12-02, Revision 1 (Reference 3). Reference 4 provided the initial status report regarding SFP instrumentation, and Reference 5 provided the OIP.
NRC Order EA-12-051 requires submission of a status report at six-month intervals following submittal of the Overall Integrated Plan with regard to the requirements for reliable spent fuel pool instrumentation for Waterford 3. References 6, 7, and 8 provided the first, second, and third six-month status reports for Waterford 3, respectively. The purpose of this letter is to provide, as an attachment, the fourth six month status report for the implementation of Order EA-12-051.
There are no new commitments identified in this submittal. Should you have any questions concerning the content of this letter, please contact John Jarrell, Regulatory Assurance Manager, at (504) 739-6685.
W3F1-2 Page 3 I declar Februa MRC/A Attachm cc:
2015-0004 of 3 re under pen ry 26, 2015.
AJH ment: Water Implem the Re Attn: Directo U. S. NRC RidsNrrMail Mr. Mark L.
U. S. NRC, RidsRgn4M NRC Projec Michael.Ore NRC Senior Frances.Ra Chris.Speer nalty of perju rford Steam mentation of equirements or, Office of lCenter@nrc Dapas, Reg Region IV MailCenter@n ct Manager f enak@nrc.go r Resident In mirez@nrc.g r@nrc.gov ury that the f Electric Stat f Order EA-1 for Reliable Nuclear Rea c.gov gional Admin nrc.gov for Waterford ov nspector for gov foregoing is t tion, Unit 3,12-051, Orde e Spent Fuel actor Regula nistrator d 3 Waterford 3 true and cor Fourth Six M er Modifying l Pool Instru ation 3
rrect. Execu Month Status g Licenses w mentation uted on s Report for with Regard t the to
Attachment W3F1-2015-0004 Waterford Steam Electric Station, Unit 3, Fourth Six Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to the Requirements for Reliable Spent Fuel Pool Instrumentation
Attachment to W3F1-2015-0004 Page 1 of 4 Waterford Steam Electric Station, Unit 3, Fourth Six Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to the Requirements for Reliable Spent Fuel Pool Instrumentation 1
Introduction Waterford Steam Electric Station, Unit 3 (Waterford 3), developed an Overall Integrated Plan (Reference 1 in Section 8) documenting the requirements to install reliable spent fuel pool level instrumentation (SFP LI) in response to NRC Order EA-12-051 (Reference 2). This attachment provides a planned update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.
2 Milestone Accomplishments The following milestone(s) have been completed since July 31, 2014 and are current as of January 31, 2015.
Third Six-Month Status Report August 2014 Fourth Six-Month Status Report Complete with submission of this document in February 2015 Design Engineering - Completed
Attachment to W3F1-2015-0004 Page 2 of 4 3
Milestone Schedule Status The following provides an update to the milestone schedule to support the Overall Integrated Plan (Reference 1). This section provides the activity status of each item, and the expected completion date noting any change. The dates are planning dates subject to change as design and implementation details are developed.
Milestone Target Completion Date Activity Status Revised Target Completion Date Submit 60 Day Status Report Oct 2012 Complete N/A Submit Overall Integrated Plan Feb 2013 Complete N/A Submit 6 Month Updates:
Update 1 Aug 2013 Complete N/A Update 2 Feb 2014 Complete N/A Update 3 Aug 2014 Complete N/A Update 4 Feb 2015 Complete N/A Update 5 Aug 2015 Not Started No Change Milestone Target Completion Date Activity Status Revised Target Completion Date Modifications:
Engineering and Implementation Design Engineering Oct 2014 Complete N/A Implementation Outage Nov 2015 Not Started No Change Procedures:
Create Procedures Nov 2015 In Progress No Change Training:
Develop Training Plan May 2015 Not Started No Change Implement Training Nov 2015 Not Started No Change Submit Completion Report:
Feb 2016 Not Started No Change Respond to NRC ISE RAIs March 2015 In Progress No Change
Attachment to W3F1-2015-0004 Page 3 of 4 4
Changes to Compliance Method There are no changes to the compliance method as documented in the Overall Integrated Plan (Reference 1).
5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Waterford 3 expects to comply with the order implementation date and no relief/relaxation is required at this time.
6 Open Items from Overall Integrated Plan and Interim Staff Evaluation Waterford 3 has received an Interim Staff Evaluation that includes 18 RAIs. Responses to the RAIs are due March 31, 2015. The following table provides a status of any RAIs documented in the Interim Staff Evaluation.
RAI #
Response Status 1
To be uploaded to ePortal by 3/31/15 2
To be uploaded to ePortal by 3/31/15 3
To be uploaded to ePortal by 3/31/15 4
To be uploaded to ePortal by 3/31/15 5
To be uploaded to ePortal by 3/31/15 6
To be uploaded to ePortal by 3/31/15 7
To be uploaded to ePortal by 3/31/15 8
To be uploaded to ePortal by 3/31/15 9
To be uploaded to ePortal by 3/31/15 10 To be uploaded to ePortal by 3/31/15 11 To be uploaded to ePortal by 3/31/15 12 To be uploaded to ePortal by 3/31/15 13 To be uploaded to ePortal by 3/31/15 14 To be uploaded to ePortal by 3/31/15 15 To be uploaded to ePortal by 3/31/15 16 To be uploaded to ePortal by 3/31/15 17 To be uploaded to ePortal by 3/31/15 18a To be uploaded to ePortal by 3/31/15 18b To be uploaded to ePortal by 3/31/15 7
Potential Interim Staff Evaluation Impacts There are no potential impacts to the Interim Staff Evaluation identified at this time except for those identified in Section 6.
Attachment to W3F1-2015-0004 Page 4 of 4 8
References The following references support the updates to the Overall Integrated Plan described in this Attachment.
- 1. Waterford Steam Electric Station, Unit 3 letter to NRC, Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051),
dated February 28, 2013 (ADAMS Accession No. ML13063A263).
- 2. NRC Order Number EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 (ADAMS Accession No. ML12054A682).
- 3. Waterford Steam Electric Station, Unit 3 - Interim Staff Evaluation and Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) (TAC No. MF0946), dated November 25, 2013 (ADAMS Accession No. ML13312A787).
- 4. November 26, 2013, Public Meeting Summary for the Discussion Between the NRC Staff and Industry Concerning Responses to Staff Interim Evaluations for Spent Fuel Pool Instrumentation, dated December 26, 2013 (ADAMS Accession No. ML13347B030).