MONTHYEARML24018A0862024-02-0101 February 2024 Examination Confirmation Letter No. 50-288/Ol-24-02, Reed College ML24017A0312024-01-18018 January 2024 Reed College, Examination Confirmation Letter 50-288/Ol-24-01 ML23289A1562023-10-25025 October 2023 Reed College 2022 Financial Test for Self-Guarantee for Decommissioning Funding ML23263B1622023-09-20020 September 2023 Reed Research Reactor 2022-2023 Annual Report ML23163A0132023-07-18018 July 2023 Examination Result Letter No. 50-288/OL-23-03, Reed College ML23163A0122023-07-18018 July 2023 Examination Report Letter No. 50-288/OL-23-03, Reed College ML23165A2312023-06-14014 June 2023 Reed Research Reactor (Docket No. 50-288/License No. R-112) 2022 Financial Assurance Update ML23139A1322023-05-16016 May 2023 Reed Research Reactor (Docket No. 50-288/License No. R-112) 2022 Financial Assurance ML23053A2402023-03-0606 March 2023 Examination Confirmation Letter No. 50-288/OL-23-03, Reed College ML23024A1732023-02-27027 February 2023 Examination Confirmation Letter No. 50-288/OL-23-02, Reed College ML23020A9372023-01-20020 January 2023 Reed College, Letter Intended to Fulfill the 14-day Written Report Requirement of Technical Specification 6.7.2, Special Reports, Following Operation in Violation of Limiting Conditions of Operation ML22241A1382022-09-0606 September 2022 Us Nuclear Regulatory Commission Staff Review Re Reed College 2021 Financial Test for Self-Guarantee for Decommissioning Funding ML22230B8022022-08-18018 August 2022 Annual Report for Reed College (Docket 50-288, License No. R-112) for the Period July 1, 2021 Through June 30, 2022 ML22229A5632022-08-17017 August 2022 Reed Research Reactor 2021-2022 Annual Report ML22199A2932022-07-28028 July 2022 Examination Confirmation Letter No. 50-288. OL-23-01, Reed College IR 05000288/20222022022-06-15015 June 2022 Reed College - U.S. Nuclear Regulatory Commission Routine Safety Inspection Report No. 05000288/2022202 IR 05000288/20222012022-06-14014 June 2022 Cover Letter - Reed College Nuclear Regulatory Commission Inspection Report No. 05000288/2022201 (Public) ML22019A1022022-02-0707 February 2022 Examination Confirmation Letter No. 50-288/OL-22-02, Reed College ML21258A3962021-10-0404 October 2021 U. S. Nuclear Regulatory Commission Staff Review Re Reed College 2020 Financial Test for Self-Guarantee for Decommission Funding NRC Ltr Rrr 2020 Financial Self Guarantee Draft ML21242A2362021-09-0808 September 2021 Reed College Regarding U.S. Nuclear Regulatory Commission Staff Review and Approval of the Revised Reed Research Reactor Requalification Plan ML21224A2032021-08-16016 August 2021 Examination Confirmation Letter No. 50-288/OL-22-01, Reed College ML21216A4392021-08-0404 August 2021 Reed College - Reed Research Reactor, Annual Report, July 1, 2020 - June 30, 2021 ML21174A1942021-06-23023 June 2021 Revised Reed Research Reactor Requalification Plan in ML21160A1792021-06-0808 June 2021 Reed College, Submitting Information Inadvertently Omitted from Letter Dated October 28, 2020 (ML21014A437) ML21202A1792021-06-0808 June 2021 Reed College - Submitting Information Inadvertently Omitted from Letter Dated October 28, 2020 (ML21014A437) IR 05000288/20212012021-06-0303 June 2021 Reed College U.S. Nuclear Regulatory Commission Routine Safety Inspection Report 05000288/2021201 ML21028A0922021-01-27027 January 2021 Examination Confirmation Letter No. 50-288/OL-21-02, Reed College ML20295A4242020-11-16016 November 2020 Notification of Mailing Address Change Regarding Submittal of Fingerprint Cards ML20304A3152020-10-28028 October 2020 Self-report of a Violation of Reed Research Reactor'S Requalification Plan ML21014A4372020-10-28028 October 2020 Reed College - Financial Assurance for Reed Institute Dba Reed College and Financial Statements for the Reed Institute June 30, 2020 and 2011 9 ML20290A6802020-10-27027 October 2020 U.S. Nuclear Regulatory Commission Staff Review Reed College 2019 Financial Assurance (Self-Guarantee)(EPID No. L-2019-LLL-0034 ML20265A3972020-09-21021 September 2020 Reed College - Response to Notice of Violation 05000288/2020201 ML20266G5442020-09-21021 September 2020 Reed College - Change of Management Staff ML20247J6032020-09-0303 September 2020 Examination Confirmation Letter No. 50-288/OL-21-001, Reed College IR 05000288/20202012020-09-0202 September 2020 Reed College - U.S. Nuclear Regulatory Commission Routine and Confirmatory Order Follow-Up Inspection Report No. 05000288/2020201 ML20216A6772020-08-0303 August 2020 Reed Research Reactor Annual Report July 1, 2019 -- June 30, 2020 (Rev. 1) ML20189A3002020-07-0808 July 2020 Completion of Required Actions Under Confirmatory Order EA-19-071 Related to U.S. Nuclear Regulatory Commission Investigation Reports 4-2016-022 and 4-2017-023 ML20175A8322020-06-23023 June 2020 Reed College - Change of Management Staff ML20162A1902020-06-10010 June 2020 Reed College - Actions Under Confirmatory Order EA-19-071 ML20136A4062020-04-27027 April 2020 Transmittal of Proposed Security Plan at Reed College ML20098F1312020-04-0202 April 2020 NRC Reed TR 20200402 Request for Rvw Officials Ellis and Sams 4.2.20 ML20108F5312020-04-0101 April 2020 Reed College, Notification of Personnel Change Update ML20010G1772020-01-14014 January 2020 Examination Confirmation Letter No. 50-288/OL-20-02, Reed College ML19317D7912019-10-30030 October 2019 Financial Assurance and Financial Statements for the Reed Institute June 30, 2019 and 2018 ML19282A3882019-10-0202 October 2019 Reed College - Requesting Termination of Quality Assurance Program Approval Form for Radioactive Material Packages No. 0949, Revision 0, Docket No.71-0949 IR 05000288/20192012019-08-16016 August 2019 Reed College - U.S. Nuclear Regulatory Commission Security Inspection Report 05000288/2019201 ML19225C1642019-07-31031 July 2019 Transmittal of Security Plan at Reed College ML19211C0072019-07-24024 July 2019 Reed College, Transmittal of Annual Report July 1, 2018 - June 30, 2019 ML19155A1752019-06-13013 June 2019 U.S. Nuclear Regulatory Commission Staff Review Reed College 2018 Financial Assurance (Self-Guarantee) Docket No. 50 288 ML23130A2532019-04-29029 April 2019 Reed College, Management Change Update 2024-02-01
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML20290A6802020-10-27027 October 2020 U.S. Nuclear Regulatory Commission Staff Review Reed College 2019 Financial Assurance (Self-Guarantee)(EPID No. L-2019-LLL-0034 ML15170A2732015-06-25025 June 2015 Reed College - Request for Additional Information Regarding the Amendment to the Technical Specifications for the Reed Research Reactor ML15027A2972015-01-29029 January 2015 Reed College, Request for Additional Information Regarding the Annual Financial Assurance Review of the Self Guarantee Test (TAC No. M79578) ML14121A5462014-05-16016 May 2014 Reed College - Request for Additional Information Regarding Amendment to the Technical Specifications for the Reed Research Reactor ML1031900022010-11-15015 November 2010 Reed College - Request for Additional Information Regarding License Amendment for Special Nuclear Material Possession Limit Increase ML1025700892010-09-27027 September 2010 Reed College - Request for Additional Information, License Amendment, Special Nuclear Material Possession Limit ML0527101052005-09-26026 September 2005 RAI Letter - Security Measures - Frantz 2020-10-27
[Table view] |
Text
January 29, 2015 Dr. Melinda Krahenbuhl, Director The Reed Research Reactor Reed College 3203 SE Woodstock Blvd.
Portland, OR 97202-8199
SUBJECT:
REED COLLEGE - REQUEST FOR ADDITIONAL INFORMATION REGARDING THE ANNUAL FINANCIAL ASSURANCE REVIEW OF THE SELF-GUARANTEE TEST (TAC NO. M79578)
Dear Dr. Krahenbuhl:
As required by Title 10 of the Code of Federal Regulations (10 CFR) Part 50.75(e)(1)(iii)(C), and 10 CFR Part 30, Appendix E, Reed College submitted a self-guarantee test letter, dated September 17, 2014, (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML14279A025), to indicate how reasonable assurance will be provided to ensure the availability of funds for the decommissioning of the Reed College Research Reactor facility (Facility Operating License No. R-112). The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the self-guarantee test letter and has determined that the following additional information is needed:
- 1) a self-guarantee agreement (originally signed duplicate),
- 2) an auditors special report confirming CEO or CFO letter and reconciling amounts in the CEO or CFO letter with licensees financial statements, and
- 3) the licensees audited financial statements for the most recent fiscal year, including the auditors opinion on the financial statements Additional information related to these documents may be found in NUREG-1757, Consolidated Decommissioning Guidance: Financial Assurance, Recordkeeping, and Timeliness, Volume 3, Revision 1, and can be accessed on the NRC Website:
(http://www.nrc.gov/reading-rm/doc-collections/nuregs/staff/sr1757/v3/).
Please provide your responses to the requested information within 30 days of the date of this letter. Information included in your response that is considered sensitive or proprietary, or that you seek to have withheld from the public, must be marked in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding. Information related to security should be submitted in accordance with 10 CFR 73.21, Protection of Safeguards Information:
Performance requirements. The NRC staff will continue its evaluation of Reed Colleges self-guarantee submittal when the additional information is provided.
M. Krahenbuhl If you have any questions, or need additional time to respond to this request, please contact me at 301-415-0893, or by electronic mail, at Geoffrey.Wertz@nrc.gov.
Sincerely,
/Alexander Adams for RA/
Geoffrey Wertz, Project Manager Research and Test Reactors Licensing Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-288 License No. R-112 cc: See next page
Reed College Docket No. 50-288 cc:
Mayor of the City of Portland 1220 Southwest 5th Avenue Portland, OR 97204 Reed College ATTN: Dr. Nigel Nicholson, Dean of Faculty 3203 SE Woodstock Boulevard Portland, OR 97202-8199 Reed College ATTN: Mr. John Kroger, President 3203 SE Woodstock Boulevard Portland, OR 97202-8199 Division Administrator Nuclear Safety Division Oregon Department of Energy 625 Marion Street NE Salem, OR 97301-3737 Program Director Radiation Protection Services Public Health Division Oregon Health Authority 800 NE Oregon Street, Suite 640 Portland, OR 97232-2162 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611
ML15027A297; *concurred via e-mail NRR-088 OFFICE NRR/DPR/PRLB/PM* NRR/DPR/PRLB/LA NRR/DIRS/IFIB* NRR/DPR/PRLB/BC NRR/DPR/PRLB/PM*
NAME GWertz ELee MDusaniwskyj AAdams (AAdams for GWertz)
DATE 01/27/2015 01/28/2015 01/29/2015 01/29/2015 01/29/2015