SRRS: 3D.105 (when utilized for operator initial or continuing training)
Exelon Nuclear Job Performance Measure Local Reset of FW Isolation Signal (_BFR-H.1)
JPM Number: IPi (N-43)
Revision Number: 5 Date: 9/22/2009 Revised By:
Lynn Sanders 9/22/09 Instructor Date Validated By:
Jeremy Blumenthal 4/8/2014 Operations Dept.
Date Approved By:
Brian Lewin 4/8/2014 Operations Representative Date
SRRS: 3D.105 (when utilized for operator initial or continuing training)
JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE: All steps of this checklist should be performed upon initial validation.
Prior to JPM usage, revalidate JPM using steps 8 and 12 below.
See File Copy
- 1.
Task description and number, JPM description and number are identified.
- 2.
Knowledge and Abilities (K/A) references are included.
- 3.
Performance location specified. (in-plant, control room, simulator, or other)
- 4.
Initial setup conditions are identified.
- 5.
Initiating cue (and terminating cue if required) are properly identified.
- 6.
Task standards identified and verified by SME review.
- 7.
Critical steps meet the criteria for critical steps and are identified with an asterisk (*).
- 8.
Verify the procedure(s) referenced by this JPM reflects the current revision:
Procedure _BFR-H.1 Rev: 203 Procedure Rev:
Procedure Rev:
- 9.
Verify cues both verbal and visual are free of conflict.
- 10. Verify performance time is accurate
- 12. When JPM is initially validated, sign and date JPM cover page. Subsequent validations, sign and date below:
Lynn Sanders (Signature on file) 9/25/09 SME / Instructor Date Brian Clark(Signature on file) 9/25/09 SME / Instructor Date Robert Peterson 4/9/2014 SME / Instructor Date
SRRS: 3D.105 (when utilized for operator initial or continuing training)
Revision Record (Summary)
Revision 5 Applied new template TQ-JA-150-02 Rev.1 Verified/ updated KAs and TPOs to current revision Changed Non Licensed Operator to Equipment Operator Updated procedure references with no change to JPM required. Revalidated by Lynn Sanders and Gary Wolfe on 9/17/10.
Validated 9/19/11 by Lynn Sanders and Mike McCue.
Updated procedure references with no change to JPM required. Revalidated on 4/9/2014 by Robert Peterson
SRRS: 3D.105 (when utilized for operator initial or continuing training)
INITIAL CONDITIONS
- 1.
You are an extra NSO.
- 2.
A steamline break inside containment is occurring.
- 3.
A safety injection has occurred.
- 4.
_BFR-H.1, Response to Loss of Secondary Heat Sink, is in progress at Step 7.e.
INITIATING CUE The Unit Supervisor directs you to pull Feedwater Isolation Auxiliary Relay fuses per Step 7.e RNO of _BFR-H.1.
Fill in the JPM Start Time when the student acknowledges the Initiating Cue.
Information For Evaluators Use:
UNSAT requires written comments on respective step.
- Denotes critical steps: 3 & 4 Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section. The comment section should be used to document: the reason that a step is marked as unsatisfactory, marginal performance relating to management expectations, or problems the examinee had while performing the JPM.
Comments relating to procedural or equipment issues should be entered and tracked using the sites appropriate tracking system.
Some operations that are performed from outside of the control room may require multiple steps. These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.
The timeclock starts when the candidate acknowledges the initiating cue.
SRRS: 3D.105 (when utilized for operator initial or continuing training)
RECORD START TIME:
ELEMENT STANDARD SAT UNSAT Comment Number
- 1. Refer to _BFR-H.1, Response to Loss of Secondary Heat Sink.
CUE: Provide the trainee a copy of
_BFR-H.1.
° OPEN _BFR-H.1 to Step 7.e RNO EVALUATOR NOTE Candidate must obtain keys from WEC to open the cabinets. If candidate does not state they are getting the keys, ask the following question:
Question: Where will you obtain keys for the cabinets?
Answer: From the key cabinet in the WEC.
- 2. Go to AEER Note: 451 elevation, Auxiliary Building
° LOCATE the Auxiliary Electrical Equipment Room CAUTION The next two steps are to be simulated only. After the candidate locates the cabinet, show photos and ask the candidate to use the photos to point out their next actions.
- 3. Pull Feedwater Isolation Aux.
Relays fuses at _PA27J Cue: Fuse 24 is removed Cue: Fuse 27 is removed
° LOCATE _PA27J REMOVE:
Fuse FU-24 Fuse FU-27
- 4. Pull Feedwater Isolation Aux.
Relays fuses at _PA28J Cue: Fuse 24 is removed Cue: Fuse 27 is removed
° LOCATE _PA28J REMOVE:
Fuse FU-24 Fuse FU-27
SRRS: 3D.105 (when utilized for operator initial or continuing training)
ELEMENT STANDARD SAT UNSAT Comment Number NOTE If the trainee elects to contact the MCR to verify FW ISOL ACTD relay lights NOT LIT, then provide the following:
Cue: The Unit Supervisor reports that the FW ISOL ACTD relay lights are NOT LIT.
Cue: This JPM is completed RECORD STOP TIME:
SRRS: 3D.105 (when utilized for operator initial or continuing training)
SUMMARY
Operators Name:
Job
Title:
EO RO SRO FS STA/IA SRO Cert JPM
Title:
Local Reset of FW Isolation Signal (_BFR-H.1)
JPM Number: N043 Revision Number: 5 Task Number and
Title:
R-EF-003 RESET the Engineered Safety Features.
K/A Number and Importance: 059A4.11 3.1/3.3 Suggested Testing Environment: Plant Alternate Path:
Yes No SRO Only:
Yes No Time Critical:
Yes No Reference(s):
_BFR-H.1, Response to Loss of Secondary Heat Sink (Rev. 203)
CRITICAL STEPS (*) 3 & 4 Actual Testing Environment:
Simulator Control Room In-Plant Other Testing Method:
Simulate Perform Estimated Time to Complete: 10 minutes Actual Time Used:
minutes EVALUATION
SUMMARY
Were all the Critical Elements performed satisfactorily?
Yes No The operators performance was evaluated against standards contained within this JPM and has been determined to be:
Satisfactory Unsatisfactory Comments:
Evaluators Name:
(Print)
Evaluators Signature:
Date:
SRRS: 3D.105 (when utilized for operator initial or continuing training)
INITIAL CONDITIONS
- 1.
You are an extra NSO.
- 2.
A steamline break inside containment is occurring.
- 3.
A safety injection has occurred.
- 4.
_BFR-H.1, Response to Loss of Secondary Heat Sink, is in progress at Step 7.e.
INITIATING CUE The Unit Supervisor directs you to pull Feedwater Isolation Auxiliary Relay fuses per Step 7.e RNO of _BFR-H.1.
SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 1 of 10 Exelon Nuclear Job Performance Measure Local Load of EDG JPM Number: IPj (AP21)
Revision Number: 05 Date: 4/25/2014 Revised By:
Robert Peterson 3/25/2014 Instructor Date Validated By:
Jeremy Blumenthal 4/8/2014 Operations Dept.
Date Approved By:
Brian Lewin 4/8/2014 Operations Representative Date
SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 2 of 10 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE: All steps of this checklist should be performed upon initial validation.
Prior to JPM usage, revalidate JPM using steps 8 and 12 below.
See File Copy
- 1.
Task description and number, JPM description and number are identified.
- 2.
Knowledge and Abilities (K/A) references are included.
- 3.
Performance location specified. (in-plant, control room, simulator, or other)
- 4.
Initial setup conditions are identified.
- 5.
Initiating cue (and terminating cue if required) are properly identified.
- 6.
Task standards identified and verified by SME review.
- 7.
Critical steps meet the criteria for critical steps and are identified with an asterisk (*).
- 8.
Verify the procedure(s) referenced by this JPM reflects the current revision:
Procedure 1BOA ELEC-3 Rev: 107 Procedure 1BOA ELEC-5 Rev: 106 Procedure Rev:
- 9.
Verify cues both verbal and visual are free of conflict.
- 10. Verify performance time is accurate
- 12. When JPM is initially validated, sign and date JPM cover page. Subsequent validations, sign and date below:
Robert Peterson 4/25/2014 SME / Instructor Date SME / Instructor Date SME / Instructor Date
SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 3 of 10 Revision Record (Summary)
- 1. Revision 00-03 previous revisions prior to new TQ procedure.
- 2. Revision 04 added notes, cautions, and updated for new TQ procedure.
- 3. Revision 05 Revised to a loss of offsite power and restoring power from 1A DG.
SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 4 of 10 INITIAL CONDITIONS
- 1. Unit 1 lost offsite power to Bus 141.
- 2. 1A DG started but ACB 1413 failed to automatically close.
- 3. The crosstie from Bus 241 is unavailable.
- 4. Bus 141 is required to be energized for a vital load.
- 5. The crew has implemented 1BOA ELEC-3, Loss of 4KV ESF Bus, and is currently at Attachment B, step 2.
INITIATING CUES
- 1. The Unit Supervisor has directed you to energize Bus 141 from the 1A DG, using 1BOA ELEC-3.
Information For Evaluators Use:
UNSAT requires written comments on respective step.
- Denotes critical steps: 14, 15 & 17 Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section. The comment section should be used to document: the reason that a step is marked as unsatisfactory, marginal performance relating to management expectations, or problems the examinee had while performing the JPM.
Comments relating to procedural or equipment issues should be entered and tracked using the sites appropriate tracking system.
Some operations that are performed from outside of the control room may require multiple steps. These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.
The timeclock starts when the candidate acknowledges the initiating cue.
SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 5 of 10 RECORD START TIME:
ELEMENT STANDARD SAT UNSAT Comment Number 1
Refer to 1BOA ELEC-3, Attachment B, step 2.
CUE: Provide 1BOA ELEC-3, Attachment B.
Locate and open 1BOA ELEC-
- 3.
2 Obtain Keys from Center Desk.
CUE: You have the necessary keys.
Obtain U1 Pri-5 keys and B-core masters from Center Desk.
3 Check DG 1A shutdown.
CUE: RUNNING IDLE light is LIT and you can hear the DG running.
Check RUNNING IDLE light NOT LIT.
CUE: There is an EO standing by in the 1A DG room with a radio.
4 Check lockout relays for ACBs.
CUE: Lockout relays for ACBs 1412, 1413 and 1414 are NOT Tripped.
Lockout relays for ACBs 1412, 1413 and 1414 are NOT Tripped.
5 Check DG voltage.
CUE: EO reports 1A DG voltage indicates 4150 volts on meter.
DG voltage is greater than 4000 volts.
6 Request Unit 1 to verify position of ACB 1413 control switch.
CUE: NSO reports ACB 1413 control switch is in After Trip.
ACB 1413 control switch is in After Trip.
7 Check if Bus 141 is energized.
CUE: EO reports the RUNNING LOADED light is NOT LIT.
RUNNING LOADED light is LIT.
SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 6 of 10 ELEMENT STANDARD SAT UNSAT Comment Number 8
Locally verify all breakers on Bus 141 are open.
CUE: ALL breakers OPEN lights are LIT on Bus 141.
All breakers are OPEN on Bus 141.
EVALUATOR NOTE:
Candidate may open the door to the spare breaker cubicle, but may NOT break the plane of the doorway.
DO NOT ALLOW THE CANDIDATE TO OPEN THE DOOR TO ACB 1412 or 1413.
EVALUATOR NOTE:
Candidate must identify proper High Voltage clothing to wear and describe where to get it:
If Candidate does not state they will don HVS gear, ask the following questions:
Question: What clothing will you wear for your next actions?
Answer: Oberon suit, flash hood, rubber gloves with leather gauntlets.
Question: Where will you obtain it?
Answer: They are kept in the 451 Operating Task Coordinators Room (aka The War Room) on the north side of the WEC.
9 Remove Close Circuit fuse for ACB 1412.
CUE: Open the door to the spare cubicle and point out the location of fuse.
Close door to spare cubicle.
Std: Fuse FU-25 in Bus 141 Cubicle 16 is removed.
Candidate will point out the fuse block in the upper right side of the cubicle.
10 Refer to 1BOA ELEC-5, Attachment A.
CUE: Provide 1BOA ELEC-5, Attachment A.
Locate and open 1BOA ELEC-
- 5.
11 Check breaker racked in.
CUE: Do not open ACB 1413 door. Breaker is all the way back in the cubicle.
Breaker is racked in.
SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 7 of 10 ELEMENT STANDARD SAT UNSAT Comment Number 12 Check relay targets NOT UP.
CUE: No relay target flag is dropped.
Points out that relay targets are NOT dropped on the relays on ACB 1413 13 Check Trip and Close circuit fuse boxes installed.
CUE: Trip and Close Fuse boxes are installed, The Trip and Close fuse boxes are installed.
EVALUATOR NOTE:
Alternate Path begins at this step.
IF spare breaker is in the room behind the switchgear, lift the FME cover and have candidate point out components on breaker. Replace FME cover after use.
IF spare breaker is NOT in the room, use provided photos.
- 14 Check if closing springs are charged.
BKR CUE: Indicator is as you see it. (Discharged)
PHOTO CUE: SHOW Photo that shows the closing spring is NOT CHARGED.
Operator points out that the spring charging indicator shows the closing spring is NOT charged.
EVALUATOR NOTE:
The charging lever and the OPEN and CLOSE reach rods are in a locker on 426 outside the switchgear rooms. If candidate did not point them out on the way in, and does not state where they are, ask:
Question: Where are the charging lever and reach rod?
Answer: in a locker outside the switchgear room.
- 15 Locally charge closing springs with the charging lever.
CUE: Closing spring is CHARGED.
Operator uses the manual charging lever and points out the slot next to the spring charging indicator where the lever is inserted and pumped until the indicator shows the closing spring is charged.
SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 8 of 10 ELEMENT STANDARD SAT UNSAT Comment Number 16 Verify C/S is in After Trip.
CUE: Unit 1 NSO reports ACB 1413 MCR C/S is in After Trip.
Operator contacts the Unit NSO and requests the C/S for ACB 1413 to be in After Trip.
EVALUATOR NOTE:
If the candidate does not point out the CLOSE coil on the spare breaker or photo, ask:
Question: Where will you connect the reach rod?
Answer: Under the CLOSE coil on the breaker.
- 17 Locally close the breaker with the CLOSE Reach Rod.
BKR CUE: Metal arrow is pointing to CLOSED.
PHOTO CUE: SHOW Photo and state the arrow is pointing to CLOSED.
Operator uses the proper reach rod (labeled CLOSE) on the proper coil (labeled CLOSE) to close the breaker, and verifies the breaker position pin indicates breaker is CLOSED.
18 Contact the Unit 1 NSO and inform him that ACB 1413 is CLOSED.
CUE: Unit 1 NSO acknowledges ACB 1413 is closed.
CUE: This JPM is completed.
Operator contacts the unit to tell them ACB 1413 IS CLOSED.
RECORD STOP TIME:
SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 9 of 10 JPM
SUMMARY
Operators Name:
Job
Title:
Title:
Local Load of EDG JPM Number: IPj (AP21)
Revision Number: 05 Task Number and
Title:
AP-010 Locally operate a 4KV or 6.9KV breaker manually K/A Number and Importance: 062A2.11 Imp Factor: 3.7/4.1 Suggested Testing Environment: In-Plant or EM Lab Alternate Path:
Yes No SRO Only:
Yes No Time Critical:
Yes No
References:
1BOA ELEC-3 Rev 106 1BOA ELEC-5 Rev 107 CRITICAL STEPS (*): 14, 15 & 17 Actual Testing Environment:
Simulator Control Room In-Plant Testing Method:
Simulate Perform Estimated Time to Complete: 15 minutes Actual Time Used:
minutes EVALUATION
SUMMARY
Were all the Critical Elements performed satisfactorily?
Yes No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be:
Satisfactory Unsatisfactory Comments:
Evaluators Name:
(Print)
Evaluators Signature:
Date:
SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 10 of 10 INITIAL CONDITIONS
- 1. Unit 1 lost offsite power to Bus 141.
- 2. 1A DG started but ACB 1413 failed to automatically close.
- 3. The crosstie from Bus 241 is unavailable.
- 4. Bus 141 is required to be energized for a vital load.
- 5. The crew has implemented 1BOA ELEC-3, Loss of 4KV ESF Bus, and is currently at Attachment B, step 2.
INITIATING CUES
- 1. The Unit Supervisor has directed you to energize Bus 141 from the 1A DG, using 1BOA ELEC-3.
SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 1 of 8 Exelon Nuclear Job Performance Measure Local Operation of PZR PORV Block Valve (1RY8000B failure)
JPM Number: IPk Revision Number: 4 Date: 7/13/2010 Revised By:
Robert Peterson 7/13/2010 Instructor Date Validated By:
Jeremy Blumenthal 4/8/2014 Operations Dept.
Date Approved By:
Brian Lewin 4/8/2014 Operations Representative Date
IP k - rev 3 SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 2 of 8 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE: All steps of this checklist should be performed upon initial validation.
Prior to JPM usage, revalidate JPM using steps 8 and 12 below.
See File Copy
- 1.
Task description and number, JPM description and number are identified.
- 2.
Knowledge and Abilities (K/A) references are included.
- 3.
Performance location specified. (in-plant, control room, simulator, or other)
- 4.
Initial setup conditions are identified.
- 5.
Initiating cue (and terminating cue if required) are properly identified.
- 6.
Task standards identified and verified by SME review.
- 7.
Critical steps meet the criteria for critical steps and are identified with an asterisk (*).
- 8.
Verify the procedure(s) referenced by this JPM reflects the current revision:
Procedure 1BOA Pri-5 Rev: 106 Procedure 2BOA Pri-5 Rev: 109 Procedure Rev:
- 9.
Verify cues both verbal and visual are free of conflict.
- 10. Verify performance time is accurate
- 12. When JPM is initially validated, sign and date JPM cover page. Subsequent validations, sign and date below:
SME / Instructor Date SME / Instructor Date SME / Instructor Date
IP k - rev 3 SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 3 of 8 Revision Record (Summary)
Revision 3 Revised to current format Revision 4 Made Unit 1 specific.
IP k - rev 3 SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 4 of 8 INITIAL CONDITIONS
- 1. You are the Aux Building EO.
- 2. The Main Control Room has been declared uninhabitable due to smoke.
- 3. 1BOA PRI-5 has been entered and the RSP has been activated.
INITIATING CUES
- 1.
PZR pressure is 2200# and lowering
- 2.
The 1C and 1D RCPs are secured
- 3.
The U-1 US directs you to locally close the U-1 PZR PORV Block valves per 1BOA PRI-5, step 15.
Fill in the JPM Start Time when the student acknowledges the Initiating Cue.
Information For Evaluators Use:
UNSAT requires written comments on respective step.
- Denotes critical steps: 2 & 4 Number any comments in the Comment Number column on the following pages. Then annotate that comment in the Comments section. The comment section should be used to document: the reason that a step is marked as unsatisfactory, marginal performance relating to management expectations, or problems the examinee had while performing the JPM.
Comments relating to procedural or equipment issues should be entered and tracked using the sites appropriate tracking system.
Some operations that are performed from outside of the control room may require multiple steps. These items may be listed as individual steps in this JPM. It is acceptable for the candidate to direct the local operator to perform groups of procedure steps instead of calling for each individual item to be performed.
The timeclock starts when the candidate acknowledges the initiating cue.
IP k - rev 3 SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 5 of 8 RECORD START TIME:
ELEMENT STANDARD SAT UNSAT Comment Number
- 1. Refer 1BOA PRI-5, step 15 Note: Provide the examinee with a copy of 1BOA PRI-5, step 15.
Cue (if asked): MCC locations are in the units electrical penetration area:
131X2B - AB 414, S-11 132X2 - AB 426, S-11 o LOCATE and OPEN 1BOA PRI-5 o Utilize plant knowledge, operator aid, or contact WEC/MCR for MCC location.
EVALUATOR NOTE:
Steps 2 and 3 may be done in either order, depending on which route the candidate uses to get to the MCC.
In JPM steps 2 & 3, read the Closing Cues in sequence
- 2. Locally isolate 1RY455A Cue: The Local/Remote switch for 1RY8000A is to the LEFT (LOCAL)
Cue: Both lights are lit for 1RY8000A.
Cue: The RED light is lit for 1RY8000A.
At MCC 131X2B, cub A5:
- Place LOCAL/REMOTE switch to LOCAL.
- CLOSE 1RY8000A NOTE Alternate path is initiated in the following step.
IP k - rev 3 SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 6 of 8 ELEMENT STANDARD SAT UNSAT Comment Number
- 3. Locally isolate 1RY456 Cue: The Local/Remote switch for 1RY8000B is to the LEFT (LOCAL)
Cue: Both lights are lit for 1RY8000B.
Cue: Both lights are now out for 1RY8000B and the breaker has tripped.
Cue (if asked): The breaker will NOT reset.
At MCC 132X2, cub C4:
- Place LOCAL/REMOTE switch to LOCAL.
- CLOSE 1RY8000B
- 4. Remove Control Power fuses for 1RY456 Cue: Fuse 46 has been removed.
Cue: Fuse 47 has been removed.
Cue: (if asked) PZR Pressure is 2221 psig and rising slowly.
At 1DC11J, REMOVE control power to fail close 1RY456:
- Remove FU-46
- Remove FU-47 Cue: This JPM is completed.
RECORD STOP TIME:
IP k - rev 3 SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 7 of 8 JPM
SUMMARY
Operators Name:
Job
Title:
EO RO SRO FS STA/IA SRO Cert JPM
Title:
Local Operation of PZR PORV Block Valve (1RY8000B failure)
JPM Number: IP k (N-113a)
Revision Number: 4 Task Number and
Title:
4D.OA-27 Respond to Control Room Evacuation.
K/A Number and Importance: 068AA1.28 3.8 / 4.0 Suggested Testing Environment: In Plant Alternate Path:
Yes No SRO Only:
Yes No Time Critical:
Yes No Reference(s):
1BOA Pri-5, Rev 106, Control Room Inaccessibility CRITICAL STEPS (*) 2 & 4 Actual Testing Environment:
Simulator Control Room In-Plant Other Testing Method:
Simulate Perform Estimated Time to Complete: 30 minutes Actual Time Used:
minutes EVALUATION
SUMMARY
Were all the Critical Elements performed satisfactorily?
Yes No The operators performance was evaluated against standards contained within this JPM and has been determined to be:
Satisfactory Unsatisfactory Comments:
Evaluators Name:
(Print)
Evaluators Signature:
Date:
IP k - rev 3 SRRS: 3D.105 (when utilized for operator initial or continuing training)
Page 8 of 8 INITIAL CONDITIONS
- 1. You are the Aux Building EO.
- 2. The Main Control Room has been declared uninhabitable due to smoke.
- 3. _BOA PRI-5 has been entered and the RSP has been activated.
INITIATING CUES
- 1.
PZR pressure is 2200# and lowering
- 2.
The _C and _D RCPs are secured
- 3.
The U-_ US directs you to locally close the U-_ PZR PORV Block valves per
_BOA PRI-5, step 15.