ML14178A484

From kanterella
Jump to navigation Jump to search
Insp Rept 50-261/94-06 on 940328-0401.No Violations or Deviations Noted.Major Areas Inspected:Implementation of Licensee MOV Program to Meet Commitments in Response to GL 89-10, Safety-Related MOV Testing & Surveillance
ML14178A484
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 05/09/1994
From: Casto C, Girard E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14178A483 List:
References
50-261-94-06, 50-261-94-6, GL-89-10, NUDOCS 9405160209
Download: ML14178A484 (20)


See also: IR 05000261/1994006

Text

,pt REG

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W., SUITE 2900

ATLANTA, GEORGIA 30323-0199

Report No.:

50-261/94-06

Licensee:

Carolina Power and Light Company

P. 0. Box 1551

Raleigh, NC 27602

Docket No.:

50-261

License No.:

DPR-23

Facility Name:

H. B. Robinson

Inspection Conducted:

March 28 - April 1, 1994

Lead Inspector:

C

.

O<

E. Girard

Date Signed

Other Inspectors: M. Hunt

M. Miller

Other Personnel:

R. Cain, Consultant (EG&G Idaho, Incorporated)

Approved by:

5/

p

9

C. Casto, Chibf

Date Signed

Test Programs Section

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This special, announced inspection examined the implementation of the

licensee's motor-operated valve (MOV) program to meet commitments in response

to Generic Letter (GL) 89-10, "Safety-Related Motor-Operated Valve Testing and

Surveillance."

The inspectors utilized the guidance provided in Temporary

Instruction (TI) 2515/109 (Part 2), "Inspection Requirements for Generic

Letter 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance."

As delineated in Part 2 of TI 2515/109, this inspection was the initial review

of the licensee's MOV program implementation in response to GL 89-10.

The inspectors reviewed the GL 89-10 design calculations, test packages, and

diagnostic signature traces for a selected sample of 14 MOVs. They also

examined the licensee's actions in response to related previously identified

open items and a violation.

9405160209 940510

PDR

ADOCK 05000261

0

PDR

2

Results:

Based on the evaluation completed, the inspectors concluded the licensee was

implementing a satisfactory GL 89-10 MOV program. However, program

implementation had not been completed and additional NRC evaluation will be

required. The inspection described in this report identified the following

inspector followup items (IFIs) that require further evaluation:

(Open)

IFI 50-261/94-06-01, Margin for Load Sensitive Behavior.

(Section 2.2)

(Open)

IFI 50-261/94-06-02, Correction of Maximum Settings for Torque

Switch Repeatability. (Section 2.2)

(Open)

IFI 50-261/94-06-03, Actions to Ensure Capabilities of RHR-744

Valves. (Section 2.2)

(Open)

IFI 50-261/94-06-04, Revision of Design Criteria Assumptions

Based on Test Data. (Section 2.3)

(Open)

IFI 50-261/94-06-05, Adequacy of Periodic Verification Methods.

(Section 2.4)

(Open)

IFI 50-261/94-06-06, MOV Post Maintenance Testing. (Section

2.3)

(Open)

IFI 50-261/94-06-07, Mispositioning. (Section 2.10.c)

(Open)

IFI 50-261/94-06-08, Setting Closed-to-Open Bypass Switch

Limit. (Section 2.10.e)

A previously identified violation and ten other open items were closed.

(Closed) Violation 50-261/92-19-01, Inadequate Design Control Involving

Unverified Assumptions Related to DP for Valves FW-2V-6A, B,

and C. (Section 2.10.a)

(Closed) Open Item 50-261/91-201-01, Determination of Design Basis Flow

Rate. (Section 2.10.b)

(Closed) Open Item 50-261/91-201-02, Failure to Review Mispositionable

Valves. (Section 2.10.c)

(Closed) Open Item 50-261/91-201-03, Undersized Actuators for Valves FW

V2-6A, 6B, and 6C. (Section 2.10.d)

(Closed) Open Item 50-261/91-201-04, Setting of Closed-to-Open Bypass

Limit. (Section 2.10.e)

(Closed) Open Item 50-261/91-201-05, Procedures for Controlling Design

Basis Testing. (Section 2.10.f)

3

(Closed) Open Item 50-261/91-201-06, Periodic Verification of MOV

Operability. (Section 2.10.g)

(Closed) Open Item 50-261/91-201-07, Inadequate Documentation and

Corrective Action for MOV Deficiencies. (Section 2.10.h)

(Closed) Open Item 50-261/91-201-08, MOV Setpoint Document Control of

Switch Settings. (Section 2.10.i)

(Closed) Open Item 50-261/91-201-09, MOV Post Maintenance Testing.

(Section 2.10.j)

(Closed) Open Item 50-261/91-201-10, Failure to Periodically Test

Thermal Overloads. (Section 2.10.k)

Strengths

The following strengths were noted during the inspection:

Trending program

All valves practicable to test were tested in accordance with GL 89-10

Tests were well-documented

No violations or deviations were identified in this inspection.

SII

REPORT DETAILS

1.0

Persons Contacted

  • A. Canterbury, Manager, Component Engineering

W. Clark, Manager, Maintenance

  • S. Farmer, Manager, Inservice Inspection
  • D. Gudger, Regulatory Affairs

C. Hinnant, Vice President, Robinson Plant

G. Hoffman, Clerk

  • K. Jury, Manager, Licensing/Regulatory Programs
  • R. Krich, Manager, Regulatory Affairs
  • S. McCutcheon, MOV Component Specialist

M. McDaniel, MOV Mechanical Engineer (NED)

W. McGoun, Senior Engineer (NED)

M. Murdock, MOV Engineer (NED)

B. Nauhria, MDV Engineer (RNP NED)

A. Nguyen, Component Engineer

C. Olexik, Manager, Plant Assessment Section

M. Page, Manager, Mechanical Engineering (RNP NED)

E. Paine, Mechanical Evaluation and Analysis Subunit

M. Pearson, Plant Manager

A. Redpath, Engineer, Harris Engineering Support Section

S. Roberts, MDV Electrical Engineer (NED)

R. Steele, Manager, Maintenance Programs

R. Wehage, Manager, Mechani-cal Subunit -(RNP NED)

  • R.. Williamson, MOV Component Specialist

NRC Personnel

  • W Orders, Senior Resident Inspector
  • B. Mozafari, Project Manager, Office of Nuclear Reactor Regulation
  • Denotes personnel that attended the exit meeting.

Acronyms and initialisms used throughout this report are listed in the

last paragraph.

2.0 GENERIC LETTER (GL) 89-10 "SAFETY-RELATED MOTOR-OPERATED VALVE [MDVI

TESTING AND SURVEILLANCE"

(2515/109)

On June 28, 1989, the NRC issued GL 89-10, which requested licen sees and

construction permit holders to establish a program to ensure that switch

settings for safety-related MOVs were selected, set, and maintained

properly. Subsequently, six supplements to the GL have been issued.

NRC

inspections of licensee actions implementing commitments to GL 89-10 and

its supplements have been conducted based on guidance provided in

Temporary Instruction (TI) 2515/109, "Inspection Requirements for Generic

Letter 89-10, Safety-Related Motor-Operated Valve Testing and

Surveillance."

TI 2515/109 is divided into Part 1, "Program Review," and

Part 2, "Verification of Program Implementation.

2

The current inspection is the initial TI 2515/109 Part 2 program

implementation inspection. The TI 2515/109 Part 1 program review for

Robinson was conducted June 10 through 14, 1991, and was documented in

NRC Inspection Report 50-261/91-201, dated July 25, 1991.

The principal focus of this inspection was to evaluate in depth the

implementation of GL 89-10 for a sample of MOVs selected from the

licensee's program. The MOV sample was chosen from a list of valves that

had received differential pressure (DP) testing. The majority of the

valves selected were gate valves with high design-basis DP (DBDP)

operating requirements. The MOVs in the sample were as follows:

Valve No.

MOV Function, Size, and Type

AFW-V2-14A

SDAFW Pump Discharge Valve to Steam Generator A

4 inch double disc gate

AFW-V2-16A

AFW Header Discharge Valve to Steam Generator A

4 inch double disc gate

CC-749B

RHR Heat Exchanger B Cooling Water Isolation Valve

16 inch solid wedge gate

FW-V2-6A

Feedwater Header Section Valve

16 inch solid wedge gate

MS-V1-8A

Steam Admission Valve to SDAFW Turbine

2 inch double disc gate

RHR-744A

RHR Loop to RCS Cold Leg Valve

10 inch flex wedge gate

RHR-744B

RHR Loop to RCS Cold Leg Valve

10 inch flex wedge gate

RHR-759B

RHR HX B Outlet Isolation Valve

10 inch solid wedge gate

SI-845B

CV Spray Additive Tank Discharge Valve

2 inch globe

SI-866A

Loop 3 Hot Leg Injection Valve

2 inch globe

SI-869

Loop 2 and 3 Hot Leg Injection Shutoff Valve

3 inch double disc gate

SI-870A

Boron Injection Tank Outlet Isolation Valve

3 inch double disc gate

SI-880C

CV Spray Pump B Discharge Isolation Valve

6 inch double disc gate

3

V6-16B

SW to Turbine Building Isolation Valve

16 inch butterfly

This inspection also evaluated actions which the licensee had taken to

correct a related violation and weaknesses identified in previous

inspections, as described in Section 3.0 of this report.

Based on the evaluation completed during this inspection, the inspectors

concluded that the licensee was implementing an acceptable MOV program in

response to GL 89-10. Additional NRC evaluation is planned to complete

the evaluation of some areas and to address specific findings identified

as followup items below. Details of the inspection and the findings are

provided in the following sections of this report.

2.1 Design-Basis Reviews

The inspectors reviewed the licensee's Design Basis Differential Pressure

Reports and their referenced documentation together with applicable

operational procedures, system flow drawings, pump curves, the System

Description Procedure, and the Design-Basis Documents and verified that

the maximum flow and differential pressure were determined. The

calculations of differential pressure, electrical degraded grid voltage,

flow, and temperature were reviewed and verified to be complete and

correct. Calculations of thrust and torque were verified to use

appropriate inputs of design DP, degraded voltage, and temperature

corrected motor torque capabilities. The inspectors verified that the

licensee completed the DBDP Reports for all the safety-related systems

and addressed flow. The design-basis fluid flow rate was included in the

"Assumptions Section" of the thrust calculations for each MOV. These

thrust calculations were titled "Mechanical Analysis and Calculation for

[Valve No]."

The licensee had been notified of the effects of elevated temperature on

motor torque through a Potential 10 CFR Part 21 Notice dated May 13, 1993

and Technical Update 93-03 (March 1993) issued by Limitorque Corporation.

The inspectors examined Design Guide DG-V.67, "Electrical Evaluation of

AC Powered Motor-Operated Valves," and Calculation EE107-CS-58, "AC MOV

Calculated Available Torques for Various Voltage Scenarios," and verified

that the effects of elevated temperature were properly addressed for the

licensee's MOVs.

The inspectors concluded the licensee had adequately implemented the

design-basis recommendations of GL 89-10 for design-basis reviews.

2.2 MOV .Sizing and Switch Setting

The inspectors reviewed the licensee's Design Guide DG-I.11, "Design

Guide for Limitorque Motor-Operated Valve Mechanical Evaluations,"

Revision 6, dated July 27, 1993, which specified the use of a standard

industry equation for calculating thrust for gate and globe valves.

Except in the case of valves provided by Westinghouse, the licensee used

a valve factor of 0.40 for gate valves and 1.10 for globe valves for

4

development of the initial thrust setting window. For Westinghouse

valves, the licensee used data provided by the valve manufacturer, where

available, or assumed a valve factor of 0.55 in the opening and closing

direction. The valve's mean seat diameter was used to calculate the

valve disc seat area.

Further, a stem friction coefficient of 0.20 was

used to calculate the minimum required torque. The minimum required

thrust was increased for diagnostic equipment inaccuracies and torque

switch repeatability by adding the values of these error factors.

During review of the licensee's thrust calculations, it was noted that a

margin was not included for load sensitive behavior (also known as "rate

of loading").

Licensee personnel stated that their evaluation of test

data did not indicate an appropriate amount of margin to be set aside for

load sensitive behavior. They stated that the previously mentioned

additions of the diagnostic and torque switch repeatability accuracies

(rather than using the square root of the sum of the squares method) to

the calculated minimum thrust requirement increased the conservatism of

their minimum required thrust settings and would account for load

sensitive behavior. The licensee's justification that this margin will

be adequate for MOVs that cannot be tested at or near design-basis

differential pressure is to be evaluated in a-subsequent NRC inspection

and is identified as Inspector Followup Item 50-261/94-06-01, Margin for

Load Sensitive Behavior.

The inspectors noted that the calculated maximum thrust limit was not

reduced for torque switch repeatability. However, the limit did include

a 10 percent safety margin. This margin would be adequate to address

torque switch repeatability except at numerical switch settings of 1,

where the repeatability error may be as great as 20 percent (Reference

Limitorque Maintenance Update 92-2 for repeatability error). At the end

of this inspection, the licensee initiated a procedural change to provide

for the repeatability error. The matter will be evaluated further in a

subsequent NRC inspection and is identified as Inspector Followup Item

50-261/94-06-02, Correction of Maximum Settings for Torque Switch

Repeatability.

In reviewing the licensee's calculations, the inspectors found that the

motor torque provided for valves RHR-744A and B was marginal and that

744A had recently failed to open during a surveillance test. When the

licensee had re-evaluated motor torque as a result the Part 21 report and

Limitorque Technical Update referred to in Section 2.1 above, they

initially determined that RHR-744A and B did not have adequate torque in

the opening direction. The licensee recalculated the minimum available

torque for the opening stroke per Limitorque Technical Update 93-03 and

found the torque marginally adequate under degraded voltage conditions.

A check of Adverse Condition Reports (ACRs) by the inspectors found that

valve RHR-744A had failed to open during surveillance test OST-252,

conducted February 1, 1994, during a plant outage. The inspectors

reviewed the licensee's identification and disposition of this event

documented in ACR 94-00249.

The operators on shift during the event had

attempted to reset the breaker and thermal overloads before an

investigation of the failure, possibly removing evidence of the root

0I

cause. The shift log indicated the valve was actuated and correctly

opened following the resetting. The valve operated properly in

troubleshooting performed following the failure and documented on Work

Request 94-ACMG1 completed February 7, 1994. The cause was not

identified in the ACR. The inspectors were informed that the open torque

switch setting had been found at a setting that had been acceptable

previously, but that no longer applied. The setting was raised to the

current requirement, which was the maximum allowed by the limiter plate,

as specified in the Electronic Database System (EDBS).

The inspectors

verified that the EDBS specified this setting and that Work Request 94

ACMG1 documented this as-left setting. Considering the failure

experienced on valve RHR-744A and the marginal capabilities of both RHR

744 valves, the inspectors questioned whether additional actions were

being taken to ensure the valves remained operable. In response,

licensee personnel provided copies of Plant Improvement Requests 94

019/00 and 93-059/00. The former was for replacement of the motor feeder

cables, which would result in increased motor torque margin. The latter

increased the range of open torque switch bypass, which would aid in

assuring that the maximum actuator torque would be available for opening.

The inspectors considered these appropriate actions. The licensee's

completion of actions to ensure the capabilities of the valves is

identified as Inspector Followup Item 50-261/94-06-03, Actions to Ensure

Capabilities of RHR-744 Valves.

From the evaluation completed, the inspectors concluded that the licensee

had satisfactorily implemented sizing and switch settings for the valves

with diagnostic thrust measured near DBDP. The adequacy of sizing and

switch settings for other valves will be determined after the licensee

has completed program implementation. Two followup items (-01 and -02)

were identified which appeared to represent weaknesses in the licensee's

sizing and switch setting criteria and require further evaluation. A

third followup item was identified for confirmation of the licensee's

action to correct the marginal capabilities of valves RHR-744A and B.

2.3 Design-Basis Capability

The licensee had identified 64 MOVs within its GL 89-10 program. The

inspectors were informed that all of the valves had been set and design

basis DP tests had been performed for those valves where it was

practicable (48 valves).

The inspectors reviewed the licensee's test procedures, completed test

packages, and VOTES diagnostic static and dynamic test traces for the

MOVs listed in Section 2.0, except valves CC-749B, RHR-744B, and SI-880C.

Independent calculations were performed by the inspectors, using the

licensee's test results, to assess MOV capabilities and determine if the

licensee's assumptions were justified. The results of these reviews are

discussed in the following paragraphs.

Valve factors obtained from the test data were examined by the

inspectors. The closing gate valve factors ranged up to 0.7 (Valve MS

V1-8A).

Based on this, the valve factor assumptions which the licensee

  • 0I6

used in calculating thrust settings for gate valves was not always

bounding. In the initial valve setups a valve factor of 0.40 had often

been used by the licensee. The inspectors' review suggested this was too

low. Licensee personnel agreed that a valve factor greater than 0.40

would be appropriate if an initial setup was required in the future for a

new valve or replacement. It was the inspectors' understanding that

Design Guideline DG-I.11 would be revised to include the best available

data for valve factors. The inspectors considered the feedback of best

available data for valve factor into the licensee's Design Guideline

important and identified this as Inspector Followup Item 50-261/94-06-04,

Revision of Design Criteria Assumptions Based on Test Data.

The inspectors verified that the operability reviews were performed on

MOVs prior to returning them to service after differential pressure

testing. The review requirement was documented in TMM-035, Attachment

6.1, "Analysis of MOV Diagnostic Data."

In accordance with the

procedure, site engineering personnel determined the valve stem thrust at

flow cut-off (adjusted for running loads) from diagnostic test results

and calculated a valve factor. This valve factor was used to calculate

design-basis thrust requirements. The design-basis thrust requirements

were then compared to the thrust measured at torque switch trip to verify

a satisfactory margin and confirm operability. At a later date valve

factor, load sensitive behavior, and stem factor were calculated by the

licensee's Nuclear Engineering Department (NED) and then compiled into a

complete package for each tested MOV.

In examining the operability reviews described in the previous paragraph

the inspectors found that design-basis thrust in the open direction had

not been determined for valves AFW-V2-14A, RHR-759B, and MS-V1-8A, which

had active safety functions in the opening and closing directions.

Calculations of opening requirements performed by the inspectors using

the licensee's data demonstrated that these valves had adequate opening

capabilities for design-basis conditions and that there was no

operability concern. Further, the inspectors noted that adequate post

return to service determinations were performed later by NED which

adequately evaluated design-basis performance in the open direction. To

ensure that any future site operability reviews of diagnostic test

results included valve opening requirements, the licensee initiated a

change to their procedure TMM-035. The inspectors reviewed the revised

procedure (Rev. 6) and found that it appeared adequate.

Summary information on all valves in the licensee's test program

indicated that adequate diagnostic thrust measurements could not be

obtained for 13 of the 48 valves dynamically tested. The tests on these

13 valves were performed at or near design-basis differential pressure.

Licensee personnel indicated they were developing justifications for

setup of these valves as-well-as for the MOVs that were not practicable

to test at or near design-basis DP. The justifications will be addressed

in a subsequent NRC inspection of the licensee's program implementation.

The justifications will be addressed in a subsequent NRC inspection of

the licensee's program implementation. The licensee's prompt analysis

and feedback of the results of testing to ensure the operability of

07

valves that could not be adequately tested will be evaluated in that

inspection.

Based on the review and evaluation completed, the inspectors concluded

that the licensee had adequately implemented design-basis testing in

accordance with GL 89-10. A followup item (-04) was identified to verify

that the licensee appropriately revises the valve factors assumed in its

design criteria, based on testing results. Additional NRC evaluation of

the licensee's implementation of actions to assure the design-basis

capabilities of MOVs is planned. The evaluation will include actions for

valves that could not be adequately tested to demonstrate design-basis

capabilities, such as valves that were not practicable to test at or near

full DP and valves that that were tested at less than DBDP without thrust

measurements.

2.4

Periodic Verification of MOV Capability

Recommended action "d" of the generic letter requests the preparation or

revision of procedures to ensure that adequate MOV switch settings are

determined and maintained throughout the life of the plant. Section "j"

of the generic letter recommends surveillance to confirm the adequacy of

the settings. The interval of the surveillance was to be based on the

safety importance of the MOV as well as its maintenance and performance

history, but was recommended not to exceed five years or three refueling

outages. Further, GL 89-10 recommended that the capability of the MOV be

verified if the MOV was replaced, modified, or overhauled to an extent

that the existing test results are not representative of the MOV.

The licensee's MOV coordinator stated that static diagnostic tests were

to be used to periodically verify MOV capabilities as follows:

The periodic verification is to begin Refueling Outage (RFO) 16

(one outage following completion of all design-basis differential

pressure testing).

Scheduling is controlled through the licensee's AMMS database, with

the static diagnostic test to be performed in association with

Preventive Maintenance Procedure PM-423 (electrical inspection).

The period between verifications is now set at two RFOs but may be

changed.

Capabilities of valves that cannot be statically diagnostic tested

due to sensor problems (e.g., reversal) will be verified by partial

diagnostic testing using the calibrator as auxiliary sensor and

measuring motor current. For Accumulator discharge MOVs even the

calibrators cannot be practically mounted and only motor current

will be checked (Note: Removal of these valves from the program is

being evaluated by the licensee).

The capabilities of only a portion of the valves will be verified

during RFO 16.

The remaining valves will be verified either RFO 17

8

or 18.

The valves to be verified during each of these outages has

not been fully established.

The inspectors viewed the AMMS for valve AFW-V2-16A and confirmed that

this GL 89-10 MOV was scheduled for static diagnostic testing as

preventive maintenance at a two RFO frequency. They informed the

licensee that the adequacy of static diagnostic testing and other methods

involving less than design-basis conditions for periodic verification of

MOV capabilities had not been established but is an industry issue

recognized by the NRC. The adequacy of the methods used by the licensee

for periodic verification of valve capabilities is identified as

Inspector Followup Item 50-261/94-06-05, Adequacy of Periodic

Verification Methods.

The inspectors reviewed the requirements that would apply to maintenance

operations, which were specified in Appendix A of Procedure MMM-003,

Rev. 39, Maintenance Work Requests. The inspectors found that static

diagnostic testing was specified to verify required thrust following

limit switch removal or replacement (for limit closed rising stem

valves), operator overhaul, packing maintenance, and valve overhaul or

replacement.

The inspectors indicated the adequacy of static testing to

verify thrust was not adequately justified for valve replacement or

overhaul.

The inspectors were informed that the licensee plans to revise

MMM-003, Appendix A. The licensee was informed that the adequacy of the

revisions to post maintenance testing requirements would be identified as

Inspector Followup Item 50-261/94-06-06, MOV Post Maintenance Testing.

The inspectors were informed that post modification testing would be

specified for a given modification consistent with post maintenance test

requirements. They reviewed the requirements-specified by the licensee's

Nuclear Plant Modification Program, Rev. 4, and found that it contained

rather general criteria for testing all components.

Licensee personnel

stated that proper post modification testing would be assured by

requiring that the Nuclear Engineering Department MOV group review

significant design changes involving safety-related MOVs. The inspectors

verified that a memo, dated February 16, 1993, had been issued to clarify

that the MOV group was to review design changes that could effect MOV

capabilities. The memo specifically referenced the licensee's commitment

to establishing and maintaining a design basis meeting GL 89-10

recommendations.

The licensee's implementation of GL 89-10 recommendations in this area

will require further evaluation to assure adequate post maintenance

testing is specified and to assure that the methodology specified for

periodic verification is adequate. The issues will be examined in a

subsequent inspection and are identified above as inspector followup

items.

.

2.5 MOV Failures, Corrective Actions, and Trending

Recommended action "h" of the generic letter requests that licensees

analyze and justify each MOV failure and corrective action. The

9

documentation should include the results and history of each as-found

deteriorated condition, malfunction, test, inspection, analysis, repair,

or alteration. All documentation should be retained and reported in

accordance with plant requirements. It is also suggested that the

material be periodically examined (every two years or after each

refueling outage after program implementation) as part of the monitoring

and feedback effort to establish trends of MOV operability.

The inspectors reviewed the four Adverse Condition Reports (ACR) related

to MOV problems listed below:

ACR No.

CONDITION 93-168

During DP Test SP 1181, SI-866A failed to close against SI pump

pressure. SI-866A is required to open to perform its safety

function.

Corrective Action: A burr was found in the yoke area of the

anti-rotation device and removed. The anti-rotation device was

replaced. The MOV was retested and met all test requirements.93-175

When SI-845B was tested after refueling maintenance had been

performed, the valve would not operate due to a locked motor.

Corrective Action:

Residue grease from the original greases

used in the operators had leaked into the motor due to a

cracked bearing seal.

The motor was replaced and the valve

tested. The corrective actions were satisfactory.93-194

An operability determination concern related to RHR-744A was

not processed properly by operations personnel.

Corrective Action:

There was no fuel in the vessel at the time

and no operability determination was-required at the time. A

review of this ACR was conducted with the personnel involved,

stressing the importance of communication and followup.93-290

Feedwater block valves had dual indication when they were

tested per the Special Procedure 1178 (DP Testing of V2-6A, B,

& C. The valves did not completely close even though they were

set per the calculated values.

Corrective Action:

Due to the effects of an increased valve

factor caused by "rate of loading", the valves only closed to

95 percent. To overcome this condition the torque switch

bypass in the close direction was installed to assure closure

under design conditions.

The inspector reviewed four MOV Failure Trending Reports that covered the

period from January 1, 1991, to December 31, 1993.

The reports were

developed from information contained in Work Requests and were intended

to identify common mode MOV failures and provide tracking information for

future MOV performance evaluations. These reports divided information

regarding the identified MOV failures into coded failure categories. The

reports included tables and charts that provided information for

10

comparison of failures of MOVs included in the GL 89-10 program to those

that are not part of the program.

The program for trending appeared to be a thorough well planned effort

that providing useful information to support the GL 89-10 program. The

trending program was considered a strength.

Based on the documents reviewed and discussions with the personnel

involved in activities that support corrective actions and trending, the

inspectors concluded that the licensee has an acceptable method for

correcting and tracking MOV failures and deficiencies.

2.6 Schedule

In GL 89-10, the NRC requested that licensees complete all design-basis

reviews, analyses, verifications, tests, and inspections that were

initiated in order to satisfy the generic letter recommendations by

June 28, 1994, or three refueling outages after December 28, 1989,

whichever is later. The licensee committed to the generic letter

schedule and, as three refueling outages have already occurred, the

June 28, 1994, completion date applies.

The licensee identified 48 valves in the GL 89-10 program that were

determined practicable to DP test. The inspectors were informed that all

of these valves had been tested, that preliminary analyses of all test

results had been performed, and that remaining final analyses were in

process. The completion of testing and preliminary analyses was verified

by the inspectors for their selected sample of MOVs. Based on their

review for the sample and their discussions with licensee personnel, the

inspectors believe the licensee is progressing satisfactorily to meet the

specified completion schedule.

2.7 Pressure Locking and Thermal Binding

The Office for Analysis and Evaluation of Operational Data has completed

a study of pressure locking and thermal binding of gate valves. It

concluded that licensees have not taken sufficient action to provide

assurance that pressure locking and thermal binding will not prevent a

gate valve from performing its safety function. The NRC regulations

require that licensees design safety-related systems to provide assurance

that those systems can perform their safety functions. In GL 89-10, the

staff requested licensees to review the design basis of their safety

related MOVs.

The licensee submitted a Licensee Event Report 82-011 which identified

the pressure locking phenomenon which occurred August 11, 1982 during RHR

System Component tests. Motor-operated valve SI-861A would not fully

open. Valves SI 861-A and B were modified by drilling a 3/8 inch hole in

the high pressure discs as directed by Modification No. 677. A study

that followed identified 12 other valves that required modifications to

prevent disc warpage caused by the effect of pressure locking. These

modifications were performed during the steam generator replacement

outage under Modification No. 792.

Thermal binding was identified on three feedwater block valves in the

late 1980s. Operating procedures were changed to require the manual

cycling of these valves during cool down of the system. The licensee

reports that no further problems with thermal binding have been

experienced.

The licensee's evaluation of INPO SOER 84-07 determined that the

modifications to the Safety Injection valves to overcome pressure locking

agreed with the INPO recommendation.

Review of Information Notice 92-016

by the licensee determined that no further corrective actions were

required. The NRC will issue additional recommendations regarding

pressure locking and thermal binding in the future.

2.8 Motor Brakes

The licensee had identified ten MOVs that were equipped with brake

mechanisms. The engineering evaluations (EEs) for the continued operation

of these MOVs was reviewed by the inspectors. These engineering

evaluation reports are listed as follows:

EE No.

Valve No.93-160

SI-865A, B, and C, Safety Injection Accumulator A, B, and C

Discharge Isolation Valves93-161

SI-880A, B, C, and D Containment Spray Pump A and B Discharge

Isolation Valves93-162

CC-716 A and B RC Pump Cooling Water Inlet Isolation Valves,

and CC-730 RC Pump Cooling Water Return Isolation Valve

In EE-93-160 valves SI-865A, B, and C were determined to be capable of

performing their intended safety function based on the fact that the

valves are open under normal operating conditions and are therefore ready

to allow the accumulators to discharge into the RC system if needed.

EE-93-161 and EE-93-162 contained the necessary evaluations to determine

that the brakes will function after a seismic event and are electrically

acceptable for operation at degraded voltages. The degraded voltage

operation acceptance was based partly on the testing performed at

Northeast Utilities, Millstone Unit One.

The inspectors found that the above evaluations appeared to be complete

in that all aspects of the brake mechanism were considered and evaluated

for possible failure modes and the impact the failure would have on the

operation of the MOV.

12

2.9 Quality Assurance Program Implementation

The inspectors reviewed MOV Program Assessment Report No. R-SP-92-08

which was performed during April 20-23, 1992, which was an assessment of

the effectiveness of the MOV program. The assessment result indicated

aneed for increased management commitment and attention to the MOV

program. These findings were based on the incomplete resolution of nine

weaknesses identified during the NRC Part 1 inspection.

Engineering and Technical Support Assessment Report No. R-ES-93-01

conducted September 15-27, 1993, identified two weaknesses regarding the

MOV program with regard to evaluation of test data prior to returning

valves to service and independent verification causing delays in MOV

testing. This report also included resolution of findings identified in

Report No. R-SP-92-08.

Both reports identified strengths in addition to the weaknesses and

appeared to be in depth audits that were performed by knowledgeable

personnel.

The audits addressed the weaknesses to the organizations

responsible to bring attention to the finding and get the proper

solutions. The inspectors concluded that the assessments were adequate

and a contributor to the MOV program improvement.

.

2.10 Followup of Previous Inspection Findings

The inspectors reviewed the status of open findings identified in the

previous GL 89-10, Part 1 inspections. These findings included a

violation and 10 "open items".

The licensee had provided written

responses to the violation and open items in letters to the NRC dated

August 20, 1992, and September 23, 1991, respectively. The results of

the inspectors' review are described below:

a.

(Closed) Violation 50-261/92-19-01, Inadequate Design Control

Involving Unverified Assumptions Related to DP for Valves FW-2V-6A,

B, and C.

The licensee's August 20, 1992, letter acknowledged the violation,

described the corrective actions taken, and stated the steps taken

to avoid further violations. The inspectors verified that new

thrust values had been calculated as the result of the identified

higher differential pressures and that the torque switch setting had

been increased to meet the high thrust requirements. The inspectors

reviewed differential pressure calculations and examined the

assumptions used to determine the DP values.

New larger electrical

cables were installed which resulted in a higher motor torque.

These valves were identified as being subject to thermal binding as

discussed in Section 2.7 of this report. General Procedure GP-007,

Plant Cooldown From Hot Shutdown to Cold Shutdown, directs that

these valves be cycled at three different intervals during cool down

of the plant. The licensee has taken adequate corrective actions

for this violation. This item is closed.

13

b.

(Closed) Item 50-261/91-201-01, Determination of Design Basis Flow

Rate.

This item identified the licensee's failure to consider the effects

of flow in either the design-basis review or the in the testing.

GL 89-10 recommended the evaluation of factors such as flow.

In its September 23, 1991, letter responding this item, the licensee

indicated that design flow was not an important consideration, since

it did not have a quantifiable effect. The inspectors agreed that

there was no currently quantifiable effect but noted that flow has

been observed to effect required thrust and should be considered in

testing and evaluations. In particular, it is important to have

significant flow to simulate design-basis conditions adequately in

the testing. The inspectors' current review found that the licensee

had determined and added the design-basis flow rate to the

assumption Section of the "Mechanical Analysis and Calculation" in

the thrust calculation package for each MOV. Additionally, the

licensee had used substantial system flows in the MOV tests.

The

inspectors concluded that this adequately addressed the issue.

c.

(Closed) Item 50-261/91-201-02, Failure to Review Mispositionable

Valves.

This item identified that the licensee had determined that it was

not necessary to review the capability of mispositioned valves to be

repositioned to their safety position, if redundant valves or

systems existed. This was contrary to a recommendation of GL 89-10.

As indicated in its response letter, the licensee's determination is

consistent with an owner's group position. The matter is currently

under.evaluation by the NRC and, pending an NRC decision, this issue

remains open. The original open item will be closed and re

identified as Inspector Followup Item 50-261/94-06-07,

Mispositioning, for tracking by NRC Region II.

d.

(Closed) Item 50-261/91-201-03, Undersized Actuators for Valves FW

V2-6A, 6B, and 6C.

This item is closed based on the information reviewed by NRC

inspectors during the close out of Violation 50-261/92-19-01.

e.

(Closed) Item 50-261/91-201-04, Setting of Closed-to-Open Bypass

Limit.

This item questioned the licensee's practice of setting closed-to

open torque bypass limit switches at 5 percent of the valve opening

stroke, as this might not adequately encompass the unseating of some

valves. Additionally, concern was expressed regarding the

licensee's failure to balance torque switches (to assure actuation

at similar opening and closing torques) and its use of torque

wrenches for setting the torque switches.

14

The licensee's response to this finding indicated that diagnostic

data obtained during MOV testing would be reviewed to ensure the

open torque switch bypass limit was set appropriately to allow

proper functioning of the valve. It further stated that new

installations would require torque switch balancing and that the

need for routine balancing would be considered.

The inspectors found that the licensee had issued Plant Improvement

Request 93-059100 (dated April 30, 1993) which recommended

increasing the closed-to-open bypass from 5 percent to 95 percent.

Therefore, the torque switch would be bypassed for 95 percent of the

valve's opening stroke and be placed back into the circuit for the

remaining 5 percent of the opening stroke. This change in open

torque switch control was not fully implemented.

The inspectors had previously observed a demonstration of the

licensee's use of torque wrenches to set torque switches at the

licensee's Harris facility. The practice applied by the licensee

was found to be acceptable.

Further NRC review of the licensee's torque bypass changes and

torque switch balancing practices will be conducted in a subsequent

inspection. The original open item will be closed and re-opened as

Inspector Followup Item 50-261/94-06-08, Setting Closed-to-Open

Bypass Switch Limit, for tracking by NRC Region II.

f.

(Closed) Item 50-261/91-201-05, Procedures for Controlling Design

Basis Testing.

This item identified the following apparent deficiencies in the

procedures used to control design-basis testing:

(1) Dynamic diagnostic testing had been performed without

accompanying static testing.

(2) Test results had not been fully assessed almost three months

after the tests had been completed.

(3) Test flow and differential pressure were not recorded in a way

that was readily available to the test results evaluator.

In their review of design-basis testing during this inspection the

inspectors determined that the apparent deficiencies identified

through this open item had been adequately addressed by the

licensee. Timely operability reviews had been documented, static

diagnostic testing accompanied dynamic testing, and recorded test

parameters were readily available. This item is closed.

15

g.

(Closed) Item 50-261/91-201-06, Periodic Verification of MOV

Operability.

This item questioned the licensee's planned lubrication and cleaning

of MOVs before periodic testing.

This practice would preclude

evaluation of the as-found valve condition.

The licensee's response letter stated that Preventive Maintenance

Procedure PM-420 had been revised to require lubrication only prior

to baseline testing. Additionally, the inspectors were informed

that the AMMS database which initiates the lubrication requires that

the MOV coordinator be contacted to assure that testing is performed

prior to the lubrication and cleaning. The inspectors verified the

above corrective actions through a review of PM-420, Rev. 9, and the

AMMS database requirement for the lubrication.

The issue is

resolved.

h.

(Closed) Item 50-261/91-201-07, Inadequate Documentation and

Corrective Action for MOV Deficiencies.

This item identified two cases in which deficient conditions

appeared inadequately documented and evaluated. The first case

involved tightening the packing of valve RHR-744B from 46 to 138

foot pounds without an engineering review or post modification test

and failing to adequately evaluate the reported movement of this

valve during actuation. The second case involved inadequate

evaluation of stem galling on valve V2-6A.

The licensee's response letter stated that Maintenance Work Request

91-AIDQ1 provided testing (June 14, 1991) that verified the packing

adjustment on valve RHR-744B had not significantly increased

actuator loading. In addition, the response stated that the valve

had been observed during stroking and did not exhibit any abnormal

movement. The inspectors reviewed and verified the above Work

Request, which contained the results of current traces performed on

the valve.

They also interviewed the licensee's MOV coordinator,

who indicated that he had observed the valve in operation and saw no

abnormal movement. Finally, the inspectors verified that the

licensee had conducted design-basis DP testing of the valve and

found that it operated satisfactorily. On this basis the original

finding is considered closed. However, this valve and valve RHR

744A, were identified as marginal valves as described in Section 2.2

above and further licensee actions to ensure that these valves

perform satisfactorily are to be verified in a subsequent NRC

inspection.

SII

16

i.

(Closed) Item 50-261/91-201-08, MOV Setpoint Document Control of

Switch Settings.

This item identified that procedure CM-111 did not provide torque

switch, limit switch, or thrust settings for numerous MOVs. The

technicians who set MOVs were obtaining the values to be used

verbally from the MOV coordinator.

The licensee's response stated that MOV switch settings and thrust

values would be controlled through its automated Equipment Database

System (EDBS), eliminating the need for the verbal transfer of

information.

The inspectors verified that the EDBS contained the

setting entries and that procedure CM-111, Rev. 21, directed use of

the EDBS for the settings. This resolves the finding.

j. (Closed) Item 50-261/91-201-09, MOV Post Maintenance Testing.

The licensee's procedure did not require that thrust margin be

verified following maintenance that could affect MOV performance.

The licensee's response letter indicated that using thrust data to

verify performance was under review. In the current inspection the

inspectors found that post maintenance testing requirement guidance

was specified by Appendix A of procedure MMM-003, Rev. 9. Thrust

verification appeared satisfactorily controlled except where

significant valve maintenance was performed.

For example, static

(no DP) thrust testing was specified following packing maintenance,

valve overhaul or replacement, and operator overhaul.

For valve

overhaul or replacement use of static testing may not be adequate.

As discussed in Section 2.4 above, the adequacy of post maintenance

testing will require further NRC review and has been designated

Inspector Followup Item 50-261/94-06-06, replacing Open Item 50

261/91-201-09.

k.

(Closed) Item 50-261/91-201-10, Failure to Periodically Test Thermal

Overloads.

This item identified that there was no periodic testing to verify

proper setting of the thermal overloads on MOV circuits.

The licensee's response letter indicated this issue was under

advisement.

The licensee tested all the TOLRs for 94 safety related MOVs.

The

TOLRs for six MOVs were replaced due to failures. Three of the

failures were determined to be opening at a value .greater than the

range of the TOLR. Three others were borderline when the tolerance

was taken into account could have been out of range. These were

replaced as a conservative action. The licensee had not determined

the interval that will be used for TOLR testing but plans some form

of testing in the future.

17

3.0

EXIT INTERVIEW

The inspection scope and findings were summarized on April 1, 1994, with

those persons indicated in Section 1. The inspectors described the areas

inspected and discussed in detail the inspection results. Proprietary

information is not contained in this report. No dissenting comments were

received from the licensee. Eight inspector followup items were

identified. These items are listed in the summary at the beginning of

this report, which gives the status of all items inspected.

4.0 ACRONYMS AND INITIALISMS

AC

Alternating Current

ACR

Adverse Condition Report

AFW

Auxiliary Feedwater

AMMS

Automated Maintenance Management System

CC

Component Cooling System

CFR

Code of Federal Regulations

CS

Charging System

CST

Control Switch Trip

CV

Containment Volume

DBDP

Design Basis Differential Pressure

DP

Differential Pressure

EDBS

Electronic Database System

EE

Engineering Evaluation

FW

Feedwater

GL

Generic Letter

HX

Heat Exchanger

IFI

Inspector Followup Item

INPO

Institute for Nuclear Power Operations

MOV

Motor-Operated Valve

MS

Main Steam System

NED

Nuclear Engineering Department

NRC

Nuclear Regulatory Commission

RC

Reactor Coolant

RCS

Reactor Coolant System

RFO

Refueling Outage

RHR

Residual Heat Removal System

RNP

Robinson Nuclear Plant

SDAFW

Steam Driven Auxiliary Feedwater (Turbine)

SI

Safety Injection

SOER

Significant Operating Event Report

TI

Temporary Instruction

TOLR

Thermal Overload Relay

VOTES

Valve Operation Test and Evaluation System

Soeo eea euain