ML14176A870

From kanterella
Jump to navigation Jump to search
Insp Rept 50-261/90-08 on 900416-20.No Violations or Deviations Noted.Major Areas Inspected:Reg Guide 1.97 Conformance & Instrumentation of LWR Cooled Reactor Power Plants to Assess Environ Conditions Following Accident
ML14176A870
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 05/08/1990
From: Conlon T, Merriweather N, Mark Miller
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14176A869 List:
References
RTR-REGGD-01.097, RTR-REGGD-1.097 50-261-90-08, 50-261-90-8, NUDOCS 9005230328
Download: ML14176A870 (14)


See also: IR 05000261/1990008

Text

tNF4 REGb4

UNITED STATES

NUCLEAR REGULATORY COMMISSION

o

AREGION

II

101 MARIETTA STREET, N.W.

ATLANTA, GEORGIA 30323

Report No.: 50-261/90-08

Licensee: Carolina Power and Light Company

P. 0. Box 1551

Raleigh, NC 27602

Docket No.:

50-261

License No.:

DPR-23

Facility Name: H. B. Robinson

Inspection Conducted: April 16-20, 1990

N. Merriweather

Date Signed

M.C . Miller

Date Signed

Approved by(CiY

e&-

-

-

91 '

T. E. Conlon,-Chief

Date Signed

Plant Systems Section

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This special, announced inspection was conducted in the areas of the licensee's

conformance to Regulatory Guide (RG)

1.97,

Instrumentation for Light-Water

cooled Nuclear Power Plants to Assess Plant and Environs Conditions During and

Following an Accident and previously identified open items.

Results:

In the areas inspected, violations or deviations were not identified.

The licensee has performed the necessary installation or modification of plant

instruments to comply with Regulatory Guide 1.97, Revision 3 and/or the SER and

their submittals to NRC.

The program was considered adequate with the

exception of a few minor weaknesses as described below.

Management

acknowledged the concerns and committed to provide both short term and long

term corrective action which was considered acceptable by the inspectors. In

addition, the licensee was extremely cooperative in resolving these technical

905230):.)32'!

900511

PDR

ADOCK 05000261

Q

PD1C

2

RG 1.97 Master Equipment List an excellent reference document to assess the

requirement for RG 1.97 equipment. Although the inspectors considered some of

the licensee's activities in this area to be weak, overall the program was

considered to be average. Weaknesses considered in the licensee's program are

as follows:

Weaknesses:

The electrical drawings are inconsistent.

The calibration program does not require verifying signals from

loops to ERFIS computer output.

Q-list does not identify by tag number all RG 1.97 instruments.

Not all

RG 1.97 instruments and indicators are uniquely

identified and labeled.

Containment water level and pressure recorder is not tagged and

has been out of service for over a year.

The strengths and weaknesses are discussed further in paragraph 2.b.

REPORT DETAILS

1. Persons Contacted

Licensee Employees

  • C. W. Coffman, Project Engineer - Onsite Nuclear Safety
  • T. P. Kinnamn, Engineer Supervisor - Technical Support
  • J. D. Kloosterman, Director - Regulatory Compliance
  • L. Lynch, QC Supervisor
  • R. E. Morgan, Plant General Manager
  • M. F. Page, Manager - Technical Support
  • F. Roy, Engineer - Technical Support
  • J. J. Sheppard, Manager - Operations

R. Shoemaker, Project Engineer - Operations

  • R. M. Smith, Manager - Maintenance
  • D. C. Stadler, Onsite Licensing Engineer
  • K. Williams, Senior Engineer - Technical Support

Other licensee employees contacted during this inspection included

engineers, operators, technicians, and administrative personnel.

NRC Resident Inspectors

  • L. Garner, Senior Resident Inspector

K. Jury, Resident Inspector

  • Attended exit interview

2. Inspection of Licensee's Implementation of Multiplant Action A-17:

Instrumentation for Nuclear Power Plants to Assess Plant and Environs

Conditions During and Following an Accident (Regulatory Guide 1.97)

(25587).

Criterion 13,

"Instrumentation and Control," of Appendix A to 10 CFR

Part 50 includes a requirement that instrumentation be provided to monitor

variables and systems over their anticipated ranges for accident

conditions as appropriate to ensure adequate safety.

Regulatory

Guide 1.97 (RG 1.97) describes a method acceptable to the NRC staff for

complying with the Commission's regulations to provide instrumentation to

monitor plant variables and systems during and following an accident.

The licensee responded to Reg Guide 1.97 (NUREG 0737, Supplement 1) in

letters dated December 31,

1984, July 18,

1985, July 28,

1986,

and

October 20, 1986. A Safety Evaluation Report covering the above responses

was issued to the licensee on March 5, 1987.

The SER concluded that the

licensee's instrumentation for RG 1.97 either conforms to, or an

acceptable justification exists, for deviating from the guidance of

Regulatory Guide 1.97, Revision 3 with

the exception of the

2

instrumentation for containment sump water temperature,

which will be

evaluated by NRC on a generic basis.

This inspection assessed the

licensee's

RG 1.97 instrumentation system using (1) the design and

qualification criteria described in Table 1 of RG 1.97,

Revision 3;

(2)

Technical

Evaluation Report No. EGG-NTA-7113, conformance to

Regulatory Guide 1.97 H. B. Robinson Steam Electric Plant, Unit 2; and

(3) licensees' submittals as described above; and (4) 10 CFR 50. A random

sample of 22 variables from the licensee's submittal were selected to

evaluate the licensee's program. The variables selected were classified

as Category 1 and 2 which require the most stringent design requirements

of all Reg Guide 1.97 instruments.

The instruments reviewed and the

results achieved are discussed in the paragraphs and tables below.

a. Category 1 and 2 Instruments

The instrumentation listed in the following Tables were examined to

verify that the design and qualification criteria of RG 1.97 or the

SER and licensee commitments had been satisfied. The instrumenta

tion was inspected by reviewing drawings, procedures, data sheets,

and other documentation; and performing walkdowns for visual observa

tion of selected installed equipment including CR indicators and

recorders. The following areas were inspected:

(1) Equipment Qualification - The EQ Master Equipment List and the

Q-list were reviewed for confirmation that the licensee had

addressed environmental qualification requirements and seismic

qualification.

A concern was identified in this area as

discussed in paragraph 2.b.

(2) Redundancy -

Walkdowns were performed to verify by visual

observation that selected instruments were installed as

specified and that separation requirements were met.

In

addition, loop drawings for all listed Category 1 instrumenta

tion were reviewed to verify redundancy and channel separation.

(3) Power Sources -

Loop drawings were reviewed to verify the

instrumentation is energized from a safety-related power source.

(4) Display and Recording - Walkdowns were performed to verify by

visual observation that the specified display and recording

instruments were installed.

Loop drawings were reviewed to

verify there was at least one recorder in a redundant channel

and two indicators, one per division (channel).for each measured

variable. A concern was identified in this area as discussed in

paragraph 2.b.

(5) Range - Walkdowns were performed to verify the actual range of

the indicator/recorders was as specified in RG 1.97 or as stated

in the licensee's submittal.

Review of calibration procedures

verified sensitivity and overlapping requirements of RG 1.97 for

instruments measuring the same variable.

3

(6)

Interfaces

-

The loop drawings and Q-list were reviewed to

verify that safety-related isolation devices were used when

required to isolate the circuits--from non-safety systems.

(7) Direct Measurement -

Loop drawings were reviewed to verify that

the parameters are directly measured by the senors.

(8) Service, Testing, and Calibration - The maintenance program for

performing calibrations and surveillances was reviewed and

discussed with the licensee.

Calibration and surveillance

procedures and the latest data sheets for each instrument were

reviewed to verify the instruments have a valid calibration.

A

concern

was identified in this area

as discussed in

paragraph 2.b.

(9) Equipment Identification - Walkdowns were performed to verify

that types A, B and C instruments designated as Categories 1 and

2 were specifically identified with a common designation on the

control panels.

A concern was identified in this area and is

discussed in paragraph 2.b.

CATEGORY 1 INSTRUMENTS

Variable

Instrument Number, Channel or Train

Neutron Flux

RE-582

RI-590 & 592

RR-594

RE-583

RI-591 & 593

RR-594

Reactor Coolant Pressure (Wide Range)

PT-402

PI-402

PR-444

PT-501

PI-501

4

Variable

Instrument Number, Channel or Train

(cont'd)

Core Exit Temperature

TE-472-496

TE-523-528

TM-578

TM-579

TR-581

TI-579(A)

TI-580(B)

Refueling Water Storage Tank Level

LT-948

LI-948

LT-969

LI-969

ERFIS

Containment Hydrogen Concentration

AET-8100-1

(PAM Panel)

AI-8100-1

AR-(Not Tagged)

PT-8100-1

AET-8110-2

)AI-8110-2

AR-(Not Tagged)

PT-8110-2

Steam Generator Level (Narror Range)

LT-474

LI-474

LT-475

LI-475

LT-476

LI-476

FR-478

LT-484

LI-484

LT-485

LI-485

LT-486

LI-486

FR-478

LT-494

LI-494

LT-495

LI-495

LT-496

LI-496

FR-478

5

Variable

Instrument Number, Channel or Train

(cont'd)

Steam Generator Pressure

PT-474

PI-474

PT-475

PI-475

PT-476

PI-476

PT-484

PI-484

PT-485

PI-485

PT-486

PI-486

PT-494

PI-494

PT-495

PI-495

PT-496

PI-496

ERFIS

Reactor Coolant System Hot Leg

TE-413

Temperature

TI-413C

TR-413

TE-423

TI-423

TR-413

TE-433

TI-433

TR-413

Reactor Coolant Cold Leg

TE-410

Temperature

TI-410

TR-410

TE-420

TI-420

TR-410

TE-430

TI-430

TR-410

Pressurizer Level

LT-459

LI-459

LR-459

LT-460

LI-460

LR-459

LT-461

LI-461

LR-459

6

Variable

Instrument Number, Channel or Train

(cont'd)

Containment Pressure

PT-956

(PAM Panel)

PI-956

PR-(Not Tagged)

PT-957

PI-957

PR-(Not Tagged)

Containment Water Level

LT-801(A-E)

LI-801

LR-(Not Tagged)

LT-802(A-E)

LI-802

LR-(Not Tagged)

CATEGORY 2 INSTRUMENTS

Variable

Instrument Number, Channel or Train

Primary Safety Relief Valves

RC-551A

Position (Accoustical Flow Switches)

RC-551B

RC-551C

Primary Power

PCV-455C

Operate Relief

PCV-456

Valves (PORV) Position

Limit Switches

Residual Heal Removal (RHR)

TE-606

Heat Exchanger Outlet

TR-604

Temperature

Residual Heat Removal

FT-605

Flow

FI-605

Heat Removal by the

HVH-1

Containment Fan Heat

HVH-2

Removal System

HVH-3

Fan Motor Status

HVH-4

(Switches & Indicating Lights)

Containment Spray

FT-958A

Flow

FI-958A

FT-958B

FI-958B

7

Containment Cooling

DPS-1698A

Service Water Low Flow

ANN-A2-8

(Annunciator - ANN)

DPS-1698B

ANN-A2-1

DPS-1698C

ANN-A2-24

DPS-1698D

ANN-A2-32

Charging Flow

FT-122

FI-122A

Containment Isolation

All Valves

Valves Position

Limit Switches

b. Discussion and Conclusion

The inspectors concluded that the licensee has made the necessary

installation and/or modifications of plant instruments to comply with

Regulatory Guide 1.97, Revision 3 as described in their responses to

NRC and as discussed in the SER. The implementation of their RG 1.97

program was considered adequate in most areas, with the exception of

a few minor weaknesses in the areas of Q-list identification, ERFIS

calibration, equipment identification, drawings, and maintenance. To

resolve these weaknesses the licensee management committed to certain

short term and long term corrective actions.

The inspectors

considered these commitments acceptable to resolve all concerns. A

brief discussion of the areas reviewed and the results achieved

including any licensee commitments are summarized below:

(1) Q-1ist

The inspectors reviewed the Q-list for those Reg Guide 1.97

instruments identified in the tables above. In many instances,

the Q-list did not specifically list Category 1 and 2

instruments by "Tag Number".

Instead the Q-list specified

equipment on the process flow drawings as being classified Q.

The inspectors determined this method was not satisfactory and

the licensee agreed to correct the Q-list.

The licensee agreed

to specifically list all RG 1.97 Category 1 and 2 instruments by

tag numbers.

This corrective action will be completed in two phases.

The

short term phase is to add within three months all Category 1

and Category 2 safety-related variables to the Q-list. The long

term phase is to add all non-safety related Category 2 variables

to the Q-list within 18 months.

8

(2) Calibration Program for RG 1.97 Instruments

The inspectors reviewed the instrument calibration program,

calibration procedures, and data sheets for RG 1.97 instruments.

These documents were found to be satisfactory except for the

calibration method used for the ERFIS computer.

The licensee's

method is to calibrate the ERFIS computer inputs and the

instruments loops independently of each other.

This does not

require the technicians to verify the computer reading during

the loop calibration.

The inspectors did not consider this

practice to be acceptable for the following instrument channels

described in their submittal:

o

Containment Spray Addition Tank Level (Al)

o

Steam Generator Pressure (Al)

o

Condensate Storage Tank (CST) Level (Al)

O

Refueling Water Storage Tank Level (Al).

o

Containment Isolation Valve Position (Bl)

o

RCDT Temperature or Pressure (C3)

o

En ineered Safety Features (ESF) Actuated Valve Position

(D3)

O

Liquid Hold-up Tank Level (D3)

O

Gas Decay Tank Pressure (D3)

o

Emergency Ventilation Damper Position (D2)

o

DC Bus Voltage and Current (MCC A/B) (D2)

O

Plant Vent Flow Rate (E3)

For those instruments identified above the licensee specifically

states in their submittal that trend information or indication

on demand will be provided by the ERFIS computer. Based on the

above statements it appears that the licensee has taken credit

for ERFIS providing recording or indication for RG 1.97

instrument loops.

Based on this assessment the inspectors

concluded that the output of the loops to the ERFIS computer

should be calibrated to verify accuracy of the computer output

the same as the other recorders or indicators in the instrument

loop.

Subsequent to the inspection, during a conference call

with NRC staff on May 3, 1990,

the licensee made verbal

commitments to validate the ERFIS outputs for the containment

water level and containment pressure channels prior to the end

of the next refueling outage and to revise procedures by

December 31,

1991,

to validate 132 limit switches of 66

containment isolation valves and .25 various other instruments

including the containment water level and containment pressure

channels. The NRC staff considered this to be acceptable based

on the licensee's current plans to upgrade procedures.

(3)

Drawings

The controlled wiring drawings

(CWD)

and the Hagan instrument

loop drawings were reviewed by the inspectors to verify adequacy

and determine power requirements. The inspectors noted that the

licensee did not have a CWD for the Post Accident Monitoring

(PAM) panel detailing 120 VAC power. However, the licensee did

have a sketch (no.

M872-E-3640)

from the plant modification

package detailing the power to and within the PAM panel.

The

inspectors did not consider this as an acceptable way to control

drawings.

The inspectors verified the power requirements by

walking down the PAM panel and reviewing other documentation.

The licensee acknowledged the inspectors concerns and agreed to

review and revise the CWDs as appropriate for the PAM panel by

July 27, 1990.

In addition, the licensee agreed to review and

revise as appropriate all other Hagan drawings within a year.

This will entail reviewing approximately 30 to 50 drawings.

(4) Equipment Identification and Labeling

The inspectors toured the control room and examined the selected

RG 1.97 instruments for proper range and identification. During

the inspection the inspectors noted: (a) that not all type A, B

and C variables designated as Category 1 and 2 were uniquely

identified on the control boards as RG 1.97; and (b) that not

all instruments located on the PAM panel were always identified

with equipment ID numbers.

The Reg Guide requires that type A, B and C, Category 1 and 2

variables be marked with a common designation.

The only

instruments that were marked were the indicators and recorders

with a blue border.

Other components such as switches,

annunciators and valve position indicators for containment

isolation valves were not marked for type A, B and C, Category 1

and 2 variables on the control boards.

The inspectors

questioned the licensee regarding their position on the

designation of instruments for RG 1.97. The licensee indicated

that because of the size of the control boards and considering

the fact that the switches are specifically addressed in EOP's,

that it was not desirable or necessary to color designate with a

blue border those specific components on the control boards. The

licensee also considered it would clutter the control board and

could lead to operator confusion.

The inspectors requested

that if this position was not already documented that the

licensee should document their justification or reasons for not

marking all type A, B, and C category 1 and 2 variables on the

control boards.

The licensee agreed to document their

justification for not marking these variables and include this

information in their plant files within three months. The

10

inspectors noted that the recorder for both containment water

level and containment pressure did not have an equipment ID

number.

This was found to be inconsistent with other Reg

Guide 1.97 instruments located in the control room.

The

licensee was made aware of the concern and committed to identify

all instruments on the

PAM panel with equipment numbers

consistent with the plant equipment ID numbering system.

The

licensee indicated that the labeling of these instruments would

be completed within three months.

(5) Maintenance of Req Guide 1.97 Equipment

During the control room walkdown, the inspectors noted that the

recorder for both containment water level and pressure on the

PAM panel was tagged out of service. Further investigation of

this matter revealed that the recorder has been out of service

since March 1989. The licensee provided the inspectors a copy

of a project improvement report (PIR)

which proposes that the

recorder should be replaced in 1991 due to lack of replacement

parts and obsolescence. However, it does not make reference to

the work request or the fact that the recorder is out of

service.

The licensee informed the inspectors that they have

redundant indicators in the control room for both variables and

that all channels are inputted into the ERFIS computer. Thus,

adequate information has always been available in the control.

However, to resolve the concern the inspectors have about the

ERFIS computer calibration, the licensee committed to have both

the containment water level and containment pressure channel

calibrated with the ERFIS computer outputs verified prior to

startups from the next refueling outage.

The expected

completion date for implementation of the modification to

replace the PAM recorder will be in 1991.

3. Action on Previous Inspection Findings (92701)

(Closed) Inspector Followup Item 50-261/90-18-01,

Periodic Testing/

Surveillance of Appendix R Protective Devices Associated with Appendix R

Coordination Study

The licensee had initiated Plant Change Notice (PCN) 87-026/00, approved

on December 27, 1988, which evaluated the need for additional maintenance

surveillance testing,

and administrative controls for Appendix R

protective devices in associated circuits of concern (ACC).

The PCN

recommended testing every refueling outage 10 percent of all 480V

switchgear power circuit breakers and 480/208/120V Molded Case Circuit

Breakers that are required to function in the licensee's Appendix R

associated circuit analysis. For each breaker not meeting the acceptance

criteria, an additional 10 percent of that breaker type would be tested

until either no failures occur or until all ACC breakers of that type have

been tested. The PCN also recommended that procedures be developed to

control the replacement of fuses in Appendix R circuits.

To accomplish

all of the above recommendations,

the PCN suggested that two new

procedures should be developed for fuse control and molded case circuit

breaker testing.

In addition, an existing plant procedure should be

revised to ensure that 10 percent of all types of Appendix R 480V

switchgear breakers are tested each outage.

The proposed testing of

molded case circuit breakers would include testing the thermal element at

300 percent of the trip rating for appropriate time delay and testing the

instantaneous element for appropriate pickup current. The recommendations

of PCN-87-026/00 have not been completed due to lack of funding for

calendar years 1989 and 1990.

However, during this inspection the

licensee committed to incorporate this item on the work management

prioritization system as an NRC commitment.

This will ensure that this

item receives proper management attention for scheduling the completion of

this item.

4. Exit Interview

The inspection scope and results were summarized on April 20, 1990, with

those persons indicated in paragraph 1.

The inspectors described the

areas inspected and discussed in detail the inspection results discussed

above.

Proprietary information is not contained in this report.

Dissenting comments were not received from the licensee.

Subsequent to the inspection, the licensee made certain verbal commitments

to the NRC in telephone conferences on April 26 and May 3, 1990.

These

commitments specifically relate to the licensee's proposed corrective

actions and expected completion dates for the weakness identified during

the inspection.

These commitments are also described in the report

details.

5. Acronyms and Initialisms

AET

Analyzer Element (H2)

AI

Analyzer Indicator

AR

Analyzer Recorder

ANN

Annunciator

DPS

Differential Pressure Switch

ERFIS

Emergency Response Facilities Information System

FI

Flow Indicator

FR

Flow Recorder

FT

Flow Transmitter

HVH

Heating Ventilation Handling

LI

Level Indicator

LR

Level Recorder

LT

Level Transmitter

PAM

Post Accident Monitoring

PCV

Pressure Control Valve

PI

Pressure Indicator

PR

Pressure Recorder

12

PT

Pressure Transmitter

RC

Reactor Coolant (Accoustical Flow Switches)

RG

Regulatory Guide

RE

Reactivity Element (Neutron)

RI

Reactivity Indicator

RR

Reactivity Recorder

TE

Temperature Element

TI

Temperature Indicator

TM

Temperature Monitor

TR

Temperature Recorder