ML14164A748

From kanterella
Jump to navigation Jump to search
NRC-037 - Letter from Gregory Bowman, NRC, to Sandra Warren, General Manager, Aerotest Operations, Inc., NRC Non-Routine Inspection Report No. 50-228/2012-206 (Jan. 7, 2013) (ADAMS Accession No. ML12361A147)
ML14164A748
Person / Time
Site: Aerotest
Issue date: 01/07/2013
From:
NRC/OGC
To:
Atomic Safety and Licensing Board Panel
SECY RAS
References
RAS 26039, ASLBP 14-931-01-LT-BD01, 50-228-LT
Download: ML14164A748 (20)


See also: IR 05000228/2012206

Text

15&

6XEPLWWHG -XQH  

January 7, 2013

Ms. Sandra Warren, General Manager

Aerotest Operations, Inc.

3455 Fostoria Way

San Ramon, CA 94583

SUBJECT: AEROTEST OPERATIONS, INC. - NRC NON-ROUTINE INSPECTION

REPORT NO. 50-228/2012-206

Dear Ms. Warren:

From December 10 to 13, 2012, the U.S. Nuclear Regulatory Commission (NRC or the

Commission) completed an inspection at your Aerotest Radiography and Research Reactor

facility (Inspection Report No. 50-228/2012-206). The enclosed report documents the

inspection results, which were discussed on December 13, 2012, with you and other members

of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records and interviewed personnel. Based on

the results of this inspection, no findings of significance were identified. No response to this

letter is required.

In accordance with Title 10 of the Code of Federal Regulations Section 2.390, Public

inspections, exemptions, and requests for withholding, a copy of this letter, its enclosure, and

your response (if any) will be available electronically for public inspection in the NRC Public

Document Room or from the NRCs document system (Agencywide Documents Access and

Management System (ADAMS)). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this inspection, please contact Craig Bassett at

(301) 466-4495 or by electronic mail at Craig.Bassett@nrc.gov.

Sincerely,

/RA/

Gregory T. Bowman, Chief

Research and Test Reactors Oversight Branch

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Docket No. 50-228

License No. R-98

Enclosure: NRC Inspection Report No. 50-228/2012-206

cc w/encl: See next page



Aerotest Operations, Inc. Docket No. 50-228

cc w/encl:

Dario Brisighella, President

Aerotest Operations, Inc.

Autoliv

3350 Airport Road

Ogden, UT 84405

Fred Meren, Reactor Supervisor

Aerotest Operations, Inc.

3455 Fostoria Way

San Ramon, CA 94583

California Energy Commission

1516 Ninth Street, MS-34

Sacramento, CA 95814

Radiological Health Branch

P.O. Box 997414, MS 7610

Sacramento, CA 95899-7414

Test, Research, and Training

Reactor Newsletter

University of Florida

202 Nuclear Sciences Center

Gainesville, FL 32611



January 7, 2013

Ms. Sandra Warren, General Manager

Aerotest Operations, Inc.

3455 Fostoria Way

San Ramon, CA 94583

SUBJECT: AEROTEST OPERATIONS, INC. - NRC NON-ROUTINE INSPECTION

REPORT NO. 50-228/2012-206

Dear Ms. Warren:

From December 10 to 13, 2012, the U.S. Nuclear Regulatory Commission (NRC or the

Commission) completed an inspection at your Aerotest Radiography and Research Reactor

facility (Inspection Report No. 50-228/2012-206). The enclosed report documents the

inspection results, which were discussed on December 13, 2012, with you and other members

of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records and interviewed personnel. Based on

the results of this inspection, no findings of significance were identified. No response to this

letter is required.

In accordance with Title 10 of the Code of Federal Regulations Section 2.390, Public

inspections, exemptions, and requests for withholding, a copy of this letter, its enclosure, and

your response (if any) will be available electronically for public inspection in the NRC Public

Document Room or from the NRCs document system (Agencywide Documents Access and

Management System (ADAMS)). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this inspection, please contact Craig Bassett at

(301) 466-4495 or by electronic mail at Craig.Bassett@nrc.gov.

Sincerely,

/RA/

Gregory T. Bowman, Chief

Research and Test Reactors Oversight Branch

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Docket No. 50-228

License No. R-98

Enclosure: NRC Inspection Report No. 50-228/2012-206

cc w/encl: See next page

DISTRIBUTION:

PUBLIC RidsNrrDprPrta Resource RidsNrrDprPrtb Resource PROB r/f

MNorris (MS T3B46M) MCompton (Ltr only O5-A4) GLappert, NRR CBassett, NRR

STraiforos, NRR CMontgomery, NRR

ACCESSION NO.: ML12361A147 *concurrence via e-mail TEMPLATE #: NRC-002

OFFICE PROB:RI * PROB:LA PROB:BC

NAME CBassett GLappert GBowman

DATE 12/16/2012 12/26/2012 1/7/2013

OFFICIAL RECORD COPY



U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

Docket No: 50-228

License No: R-98

Report No: 50-228/2012-206

Licensee: Aerotest Operations, Inc.

Facility: Aerotest Radiography and Research Reactor

Location: 3455 Fostoria Way

San Ramon, CA 94583

Dates: December 10-13, 2012

Inspector: Craig Bassett

Approved by: Gregory T. Bowman, Chief

Research and Test Reactors Oversight Branch

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation



EXECUTIVE SUMMARY

Aerotest Operations, Inc.

Aerotest Radiography and Research Reactor

Report No: 50-228/2012-206

The primary focus of this non-routine, announced inspection was the onsite review and

observation of Aerotest Operations, Inc. (the licensees) fuel handling and containerization

activities. The inspection included review of selected aspects of the licensees safety program,

including: (1) organizational structure and staffing, (2) review and audit functions,

(3) procedures, (4) radiation protection, and (5) conformance to security plan requirements. The

licensees program was acceptably directed toward the protection of public health and safety

and was in compliance with U.S. Nuclear Regulatory Commission requirements.

Fuel Handling and Containerization

  • Adequate preparations were made for damaged fuel to be placed into canisters.
  • A testing station was developed by the licensees contractor, which allowed the

containerization work to be completed underwater, saving a great deal of personnel

dose.

  • All the damaged fuel elements were placed in canisters and then transferred to storage

in a fuel rack in a timely manner without incident.

Organizational Structure and Staffing

  • The licensees organization and staffing met the requirements specified in the Technical

Specifications.

Review and Audit Functions

  • The Reactor Safeguards Committee conducted reviews and audits in compliance with

the requirements specified in the Technical Specifications.

Procedures

  • Facility procedural review, revision, and control satisfied Technical Specifications

requirements.

Radiation Protection

  • Surveys during work evolutions were completed and documented acceptably to permit

evaluation of the radiological conditions present in the facility.

  • Notices and postings at the facility met regulatory requirements.
  • Personnel dosimetry was being worn and doses were within the regulatory limits.



  • Radiation monitoring equipment was maintained and calibrated as required.
  • Training was provided covering the topics outlined in Title 10 of the Code of Federal

Regulations Section 19.12, as required.

Conformance to the Security Plan Requirements

  • Security facilities, equipment, and procedures satisfied security plan requirements.



REPORT DETAILS

Summary of Plant Status

Aerotest Operations, Inc. (AO or the licensee) ceased operation of their TRIGA conversion

research and test reactor on October 15, 2010. Prior to that time, the reactor had been

operated for neutron radiography, to complete surveillance requirements, and for reactor

operator training. During this inspection the reactor remained shut down and all the fuel was in

storage racks which were located along the wall or at the bottom of the reactor pool. Fuel

elements with cracked cladding were placed in canisters.

1. Background Information

In December 2011 the licensee began an inspection of all their fuel elements in an effort

to comply with their commitment to the U.S. Nuclear Regulatory Commission (NRC) to

inspect all the fuel elements every 5 years. After removing all the elements that they

could, the licensee found that there were 27 aluminum clad fuel elements and 11

graphite elements that were stuck in place and could not be removed through core upper

grid plate (none of the stainless steel clad elements were found to be stuck). The

licensee then used their underwater video camera to conduct an inspection of those fuel

elements. The licensee found that, of those elements that remained in the core, four

had signs of cracks in the cladding. Previously, in 2007, a fifth aluminum clad fuel

element had been removed from service and placed in a storage rack due to cracked

cladding.

On January 9, 2012, the licensee notified the NRC of the cracked fuel elements. The

licensee submitted a letter documenting the problem the same day. From January 17-

18, 2012, the NRC completed an inspection at the Aerotest Radiography and Research

Reactor (ARRR) (see NRC Inspection Report No. 50-228/2012-201).

The licensee subsequently made the decision to remove the stuck fuel elements from

the core and they hired a contractor, Secured Transportation Services (STS), to assist in

the project. STS developed a project plan proposal for removing all the elements and

submitted it to the licensee. The proposal was found to be acceptable and preparations

for the actual removal work began. The contractor developed reactor work instructions

(RWIs) for the project to ensure that all those who worked on the project understood

their respective roles. When all the elements had been removed from the core, it was

the intention of the licensee to place the fuel elements with cracked cladding in specially

designed and fabricated canisters. Before beginning removal of the fuel with damaged

cladding, the licensee anticipated that four to five more elements would be found with

cracks in the cladding, in addition to the ones already noted. Therefore, a total of ten

canisters were ordered and fabricated and a storage rack was designed and fabricated

to hold up to twelve canisters in the reactor pool.

During the period of July 16-26, 2012, licensee and contractor personnel were able to

remove all the stuck fuel elements from the core and conduct an initial examination of

the elements. The licensee then proceeded to examine all the remaining aluminum clad

elements and all of the stainless steel clad elements that were stored in the pool.

Initially, two elements with cracked cladding were placed into the specially designed



-2-

canisters (i.e., canned) and placed in the new storage rack. However, after examining

all the fuel elements, the licensee determined that there were substantially more fuel

elements with cladding problems than had originally been anticipated. The licensee then

contracted to have more canisters and a larger storage rack fabricated. At that point the

fuel element work was stopped and all the elements were placed in appropriate storage.

This was done because the STS personnel had other commitments and could not return

until a later date to assist in the canning of the rest of the fuel elements with damaged

cladding. During the period when the stuck fuel was being removed from the core, the

NRC completed a non-routine inspection at the ARRR (see NRC Inspection Report No.

50-228/2012-204).

On August 10, 2012, the licensee submitted a letter to the NRC documenting the fact

that the inspection of the fuel elements at the facility indicated that there were a total of

22 fuel elements with cracks in the cladding. Also, further review of the video

documentation of the entire inventory of elements was scheduled to be conducted during

the week of September 10, 2012. The NRC conducted another non-routine inspection

during that period to review the actual status of the fuel elements (see NRC Inspection

Report No. 50-228/2012-205). Plans were made to have STS personnel return to the

ARRR facility on December 10, 2012, to complete the containerization process.

During this inspection, the inspector observed as the remaining fuel elements with

cladding degradation were placed in the canisters. A lid was then installed on each

canister and it was sealed, drained, and then backfilled with helium gas. Finally, the

canisters were positioned in a new storage rack at the bottom of the reactor pool.

2. Organizational Structure and Staffing

a. Inspection Scope (Inspection Procedure (IP) 69001)

The inspector reviewed the following regarding the licensees organization and

staffing to ensure that the requirements of Technical Specification (TS) Section

10.0 and TS 12.1 were met:

  • Management and staff responsibilities
  • Staffing for safe maintenance of the reactor facility
  • Aerotest Operations, Inc. organizational structure
  • Annual Summary of Changes, Tests, and Experiments at ARRR for the

period from July 1, 2010, through June 30, 2011, issued July 28, 2011

  • Annual Summary of Changes, Tests, and Experiments at ARRR for the

period from July 1, 2011, through June 30, 2012, issued July 31, 2012

b. Observations and Findings

Through discussions with licensee representatives, the inspector determined that

management responsibilities at the facility had not changed since the previous

routine NRC inspection in June 2012 (NRC Inspection Report No. 50-228/2012-

202). The inspector noted that the General Manager was the local official in

charge of day-to-day operations at the facility. The Reactor Supervisor/Reactor

Operations Manager retained direct control over, and overall responsibility for,



-3-

management of the reactor as specified in the TS. The General Manager and

the Reactor Supervisor reported to the President, Aerotest Operations, Inc.

Through review of records and discussions with licensee personnel, the inspector

determined that staffing at the facility had been reduced because the reactor was

no longer in operation. During the fuel containerization work, staffing was

sufficient for the tasks performed and was augmented by two contractor

personnel to facilitate timely completion of the project.

c. Conclusion

The licensees organization and staffing met the requirements specified in the

TS. During the containerization project, licensee staff was augmented by two

contractor personnel and staffing was sufficient for the tasks performed.

2. Review and Audit Functions

a. Inspection Scope (IP 69001)

The inspector reviewed the following to ensure that the audits and reviews

stipulated in the requirements of TS 12.1.3 were being completed:

  • Reactor Safeguards Committee (RSC) meeting minutes for the most

recent meetings held on November 22, 2011, July 11, 2012, and

November 6, 2012

  • TS-defined duties of the RSC, including the review and audit functions
  • Section I of the ARRR Procedures Manual, Administrative Procedures,

Procedure Change Notice (PCN) No. 2, RSC approval dated June 28,

1990, and last reviewed May 16, 2011

b. Observations and Findings

Review and Audit Functions

The inspector reviewed the RSC meeting minutes from November 2011 through

the present. The minutes showed that the RSC met annually as required and

considered the types of topics outlined by the TS. An additional meeting had

been held in July to discuss the fuel containerization project. The inspector

determined that the review functions required by the TS were being completed by

the RSC. Through records review the inspector noted that the RSC membership

satisfied the TS requirements and RSC charter stipulations.

The inspector noted that the chairman of the RSC had completed an annual

unannounced audit of various aspects of the reactor facility operations and

programs as stipulated in the TS. The most recent audit was completed on

August 20, 2012. The audits, as well as the resulting findings, were appropriate

and the licensees response and corrective actions, if needed, were acceptable.



-4-

c. Conclusion

Audits and reviews were being conducted acceptably by the RSC in accordance

with the requirements specified in the TS.

3. Procedures

a. Inspection Scope (IP 69001)

The inspector reviewed the following to ensure that the requirements of TS

Section 12 were met concerning written procedures:

  • Procedure approval sheets
  • Section I of the ARRR Procedures Manual, Administrative Procedures,

PCN No. 2, RSC approval dated June 28, 1990, and last reviewed

May 16, 2011, which detailed the process used to review, revise, and

approve all facility procedures

  • Section IV of the ARRR Procedures Manual, Critical Assembly and

Power Calibration Procedures, PCN No. 9, RSC approval dated

November 6, 2012

  • AO RWI No. 101, Aerotest - Canister Handling, Loading, Drying, and

Conditioning, Rev. 1, dated November 28, 2012

b. Observations and Findings

The inspector verified that procedures had been developed and were available

for fuel handling operations and were being implemented at the facility as

required. Procedures were being reviewed biennially and revised as needed.

The last review had been completed on May 16, 2011. Procedure approval

sheets were maintained and PCN forms were completed as required when

changes were made. The inspector also noted that, when procedures were

revised, the revisions were presented to the RSC for review and approval. The

last procedure revision was reviewed and approved by the RSC during the most

recent meeting of the committee on November 6, 2012.

During a previous inspection, it was noted that the contractor who had been hired

to help with the damaged fuel containerization had also written various RWIs for

the project. These instructions were not considered facility procedures, and thus

were not required to be reviewed and approved by the RSC. Nevertheless, the

inspector verified that the instructions had been reviewed by the RSC chairman

and that he did not have any concerns about their use at the facility. The

inspector reviewed AO RWI No. 101, Aerotest - Canister Handling, Loading,

Drying, and Conditioning. It was noted that this instruction had been revised

and changed by the contractor because they had developed a different method

for canning the fuel. The newly revised instruction had been reviewed and

approved by the facility General Manager.



-5-

c. Conclusion

Facility procedural review, revision, and control satisfied TS requirements.

4. Fuel Handling and Containerization Operations

a. Inspection Scope (IP 69001)

The inspector reviewed selected aspects of the following to verify that fuel

handling was being conducted as required by TS 5.1.1, TS Section 11, and by

procedure:

  • Current fuel element storage location map
  • Various current records and data sheets related to fuel movement
  • Listing of the cracked fuel elements, including the location of each
  • Schematics of the canister draining, drying, and inert gas fill rig/setup
  • Fuel inspection and examination records, including video of fuel

inspections

  • Detailed drawings of the base ring and testing station to be used during

the fuel element canning/containerization process

  • AO RWI No. 101, Aerotest - Canister Handling, Loading, Drying, and

Conditioning, Rev. 1, dated November 28, 2012

  • AO RWI No. 102, Aerotest - Fuel Handling Procedure, Rev. 0, dated

June 25, 2012

  • Project Plan Aero-PP-01, Aerotest Operations Fuel Removal, Inspection,

and Canning, Rev. 0, dated June 25, 2012

In addition, as noted above, the inspector observed the planning, discussions,

and actions of licensee and contractor personnel as the remaining fuel elements

with damaged cladding were sealed in canisters and the canisters positioned in

the new storage rack in the reactor pool.

b. Observations and Findings

(1) Preparations for Fuel Containerization

As discussed above, after the licensee found that numerous fuel

elements had cracks or other problems with their cladding, the licensee

decided to place them all in canisters to provide for safe storage. STS

originally designed and fabricated enough specialized canisters for eight

regular and two instrumented fuel elements. Two regular elements had

been placed in the canisters in July (see NRC Inspection Report No. 50-

228/2012-204). Because of the number of damaged fuel elements found,

STS was asked to fabricate more canisters and return to help with the

containerization process. More canisters were subsequently fabricated, a

new storage rack was completed, and the containerization or canning

operation for the remainder of the elements with cracked cladding



-6-

occurred during the week of December 10, 2012. As noted above, STS

contractor personnel were on site to assist the licensee.

In order to provide the maximum shielding possible for those performing

the canning work, the licensee and contractor personnel developed a

testing station to be used in the containerization process. The testing

station allowed work to be performed on a canister loaded with fuel (i.e.,

attaching the lid to the canister with bolts and then sealing, backfilling,

and testing the sealed container) under four feet of water. During the

previous canning operation in July, once a canister was loaded with an

element, it had to be brought to the surface of the pool so the lid could be

installed. One person would then have to hold the canister and lid while

another person tightened the bolts in the lid with a torque wrench. This

resulted in a moderate dose to both individuals involved. The new design

for a canister and lid working area using water as shielding resulted in

significant dose reduction.

(2) Use of the Testing Station/Canister Loading and Testing Apparatus

With the testing station securely installed, the licensee then fastened an

underwater camera in place to record the operations that would take

place below the surface. After loading an element in a submerged

canister, the container was then raised to within approximately three and

one half feet of the pool surface and lowered into place in the testing

station. The lid, with extension fill and drain tubes attached to the vent

and drain valves, was then lowered onto the canister and the lid bolts

were tightened with a torque wrench to the appropriate predetermined

value by using an extension with a hex head attached. With the lid

installed, the extension fill and drain tubes were attached to the vacuum

and pressurization system. It was then possible to drain/dewater the

canister using pressurized gas, draw a vacuum on the canister with a

vacuum pump, and then backfill it with helium gas. Once this was

completed and verified, the canister and enclosed fuel element were

removed from the testing station, weighed, and placed in a designated

storage location in the new storage rack.

The inspector observed as each of the elements with damaged cladding

was placed into a canister and the canister was closed, dried, tested, and

backfilled with the cover gas. The canisters were then placed into pre-

designated locations in the new storage rack on the reactor pool floor.

c. Conclusion

Adequate preparations were made for the damaged fuel to be placed into

canisters. A testing station was developed by the contractor, which allowed the

containerization work to be completed underwater, resulting in a reduction in

dose to workers. All the damaged fuel elements were placed in canisters and

then transferred to storage in a fuel rack without incident.



-7-

3. Radiation Protection Program

a. Inspection Scope (IP 69001)

The inspector reviewed the following to verify compliance with Title 10 of the

Code of Federal Regulations (10 CFR) Part 20 and the requirements in TS 6.2,

TS Section 7.0, and TS 12.1.2:

  • Special Work Permits (SWPs) 2012-01 through 2012-03
  • Radiological signs and posting at the entrances to controlled or restricted

areas

  • Calibration records for the electronic dosimeters provided by the

contractor

  • Radiation protection surveillance and survey data for the defueling project
  • Section VI of the ARRR Procedures Manual, Radiological Safety

Procedures, PCN No. 3, RSC approval dated April 29, 1996

  • Section VIII of the ARRR Procedures Manual, Maintenance Procedures,

PCN No. 2, RSC approval dated January 14, 1993

  • ALARA [As Low as Reasonably Achievable] and Radiation Protection

Program for Aerotest Operations, Inc., updated August 14, 2004

The inspector also observed the use of dosimetry and radiation monitoring

equipment during the inspection.

b. Observations and Findings

(1) Surveys

Appropriate radiation surveys were conducted during all phases of the

containerization project. The survey results indicated that fuel canning

activities were being conducted in accordance with applicable

procedures. The results of the surveys were documented on the

applicable forms and continually evaluated as required. Surveys in the

area where people were working directly on the canning activities (i.e.,

at pool side) indicated a general area radiation level of less than one

millirem per hour during all aspects of the operation (i.e., lifting the loaded

canisters into position on the testing station and working on the draining

and conditioning of the canisters).

The inspector noted that licensee and contractor personnel were using

the appropriate monitoring equipment during the various work evolutions.

Those directly involved in the canning monitored themselves after

handling the canning equipment or items that might have been

contaminated.



-8-

(2) Postings and Notices

During tours of the facility, the inspector observed that caution signs,

postings, and controls in the restricted or controlled areas were

acceptable for hazards involving radiation, high radiation, and

contamination, and were posted as required by 10 CFR Part 20,

Subpart J. Radiological signs were typically posted at the entrances to

controlled areas.

Copies of current notices to workers were posted in various areas in the

facility including the hallway in the reactor bay outside the control room.

Other postings also characterized the industrial hygiene hazards that

were present in the areas. The inspector noted that the copies of

NRC Form 3, Notice to Employees, posted at the facility as required by

10 CFR 19.11, were the current version.

(3) Dosimetry

The inspector determined that the licensee used thermoluminescent

dosimeters (TLDs) for whole body monitoring of beta and gamma

radiation exposure (with an additional component to measure neutron

radiation). The licensee also used TLD finger rings for extremity

monitoring. The dosimetry was supplied and processed by Radiation

Detection Company, a company that was a National Voluntary Laboratory

Accreditation Program accredited vendor. The licensee also issued

dosimeters and finger rings to contractor personnel to be used for the job

and issued pocket ion chambers each day to track daily exposure.

STS also provided electronic dosimeters for everyone to use during the

project. Similar to the pocket ion chambers issued by the licensee, the

electronic dosimeters were also used to track daily exposure. During the

entire project, the highest dose received by any one individual was

approximately 5 millirem.

(4) Radiation Monitoring Equipment

During the inspection the inspector determined that licensee survey

meters were appropriately calibrated. The inspector noted that the

calibration of portable instruments was being verified quarterly as

required by procedure.

(5) Training

During a previous inspection, the inspector verified that the training given

to contractor personnel, including training on radiation protection

practices, satisfied NRC requirements. Contractor personnel did not

require any further training for the work performed during this period. The

inspector had also received training concerning the SWP issued for the

fuel element inspection and canning project. The training provided



-9-

satisfied the requirements and covered the topics outlined in

10 CFR 19.12.

(7) Radiation Work Permit Program

SWPs were required to be prepared for special operations typically

performed by non-Aerotest maintenance and other support personnel

who were required to work in radiation areas. The inspector noted that

SWPs had been written and issued for the contractor personnel, as well

as for the inspector. The SWPs had been prepared and implemented in

accordance with the requirements specified in the licensees radiological

safety procedures. The controls and safety precautions specified were

appropriate for the work conducted under the SWP.

c. Conclusion

The inspector determined that the radiation protection and ALARA programs, as

implemented by the licensee, satisfied regulatory requirements because:

(1) surveys and associated checks were completed and documented acceptably

to permit evaluation of the radiation hazards present, (2) postings met regulatory

requirements, (3) personnel dosimetry was being worn as required, (4) radiation

survey and monitoring equipment were being maintained and calibrated as

required, and (5) radiation protection training had been conducted relative to the

fuel element containerization work that was done.

4. Conformance to Security Plan Requirements

a. Inspection Scope (IPs 81401, 81402, 81431, 81810)

The inspector reviewed the following to verify that fuel containerization activities

were conducted in compliance with TS 3.2 and the licensees NRC-approved

physical security plan (PSP), Aerotest Radiography and Research Reactor

Security Plan, last revised January 7, 2005:

  • Access controls currently in effect
  • Alarm checklist forms for 2012
  • Emergency detection devices and physical barriers

last revised January 14, 2005, and last reviewed May 16, 2011

  • Section III of the ARRR Procedures Manual, General Emergency

Procedures, PCN No. 4, RSC approval dated January 28, 2005

  • Section V of the ARRR Procedures Manual, Security Procedures, PCN

No. 3, RSC approval dated February 11, 2005

b. Observations and Findings

The inspector previously conducted an inspection of the PSP in June 2012 (see

NRC transmittal letter for Inspection Report No. 50-228/2012-203). During that



- 10 -

inspection the inspector verified that the licensee was maintaining adequate

security and control over the facility.

During this inspection the inspector verified that the physical protection system

remained in place and was as stipulated in the PSP. The system was being

maintained and tested as required by procedure. The inspector verified that the

required control continued to be maintained over access to the facility, the

reactor pool, and over fuel handling equipment.

c. Conclusion

Security facilities, equipment, and procedures satisfied PSP requirements.

5. Follow-up on Previously Identified Issues

a. Inspection Scope

The inspector reviewed the licensees actions taken in response to previously

identified items in various NRC inspection reports, including four previously

opened inspector follow-up items (IFIs).

b. Observation and Findings

(1) IFI 50-228/2012-201-02 - Follow-up on the issue of cracks in the fuel

elements.

During a previous inspection, various factors that may have led to the fuel

elements developing cracks in the cladding were reviewed. These

included reviews of operations, maintenance, and surveillance records,

and fuel element history records. At that time the licensee was unable to

conclusively determine a probable cause for the cracks in the fuel. The

NRC indicated that this issue would continue to be reviewed, to include a

review of the videos produced by the licensee of the cracks and the

condition of the stuck fuel elements.

The inspector continued to evaluate IFI 50-228/2012-201-02 during this

inspection. Previous inspections had been conducted to review this

issue, including inspections in July and September 2012 which involved

observing the removal of the stuck fuel elements from the core and

reviewing the videos of those elements. It was noted that the licensee

had committed to conduct a root cause analysis of the problem and IFI

50-228/2012-205-01 was opened to follow the completion of that analysis.

Because of the prior inspections that had been completed and the

commitment by the licensee to conduct a thorough analysis, IFI 50-

228/2012-201-02 is closed. Review of the licensees causal analysis will

be tracked under IFI 50-228/2012-205-01.

(2) IFI 50-228/2012-204-01 - Review the licensees actions to ensure that all

the cracked fuel elements are placed in canisters.



- 11 -

As noted above, during this inspection all the elements with cracked or

damaged cladding were successfully placed in canisters and no issues of

significance were identified. As such, IFI 50-228/2012-204-01 is closed.

(3) IFI 50-228/2012-204-03 - Review the licensees 10 CFR 50.59 evaluation

and review of the proposed new mechanism for attaching the upper grid

plate to support structure.

During a previous inspection, the process of removing the stuck fuel

elements from the core was reviewed. One of the obstacles encountered

by the licensee was raising the upper grid plate to allow the elements to

be removed from underneath. When the licensee tried to loosen the four

bolts holding the upper grid plate to the core support structure, three bolts

would not turn. Eventually the three bolts snapped off in place, while the

fourth bolt was loosened and unscrewed about two inches. In order to

reattach the upper grid plate to the core support structure in the future,

several methods were discussed. STS contractor personnel indicated

that they could develop a clamping mechanism that could be used

instead of the bolts. This would eliminate the necessity of redrilling the

upper grid plate and drilling and tapping the core support structure.

Because this would be a change to the current structure, the licensee was

aware that they would need to perform a 10 CFR 50.59 evaluation and

review of the proposed new attachment mechanism.

During this inspection the inspector reviewed this issue. It was noted that

STS had developed a clamping device for the upper grid plate and that

they were in the process of conducting and documenting a 10 CFR 50.59

evaluation to determine if NRC approval would be required prior to

installation. Therefore, this issue remains open.

(4) IFI 50-228/2012-205-01 - Review the licensees actions to complete a

root cause or fault tree analysis concerning the fuel element cracked

cladding problem.

During a previous inspection, the licensee indicated that they were

planning to conduct a root cause or fault tree analysis concerning what

might have caused the cladding of the various fuel elements to crack.

During this inspection the inspector reviewed this issue. It was noted that

the licensee had made the decision to postpone completion of a root

cause analysis of the cladding degradation until after all the elements with

damaged cladding were placed in canisters and stored properly. Since

this activity was only just completed during this inspection, this issue

remains open.

c. Conclusion

Four inspector follow-up items were reviewed and two were closed.



- 12 -

6. Exit Interview

The inspection scope and results were summarized on December 13, 2012, with

members of licensee management. The inspector described the areas inspected and

discussed the inspection findings. Proprietary information was reviewed during the

inspection; however, no material is included in this report.



PARTIAL LIST OF PERSONS CONTACTED

Licensee Personnel

C. Bauman Research and Development Manager

A. Meren Reactor Supervisor and Reactor Operations Manager

T. Richey Neutron Radiography Manager

S. Warren General Manager and Radiological Safety Officer

M. Wilkinson Quality Assurance Manager

Other Personnel

R. Boyd Vice President, Secured Transportation Services

B. Williams President, Secured Transportation Services

INSPECTION PROCEDURES USED

IP 69001 Class II Non-Power Reactors

IP 81401 Plans, Procedures, and Reviews

IP 81402 Reports of Safeguards Events

IP 81431 Fixed Site Physical Protection of Special Nuclear Material of Low Strategic

Significance

IP 81810 Protection of Safeguards Information

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

None

Closed

50-228/2012-201-02 IFI Follow-up on the issue of cracks in the fuel elements.

50-228/2012-204-01 IFI Review the licensees actions to ensure that all the cracked fuel

elements are placed in canisters.

Discussed

50-228/2012-201-01 URI Operating the reactor with possible defective fuel was identified

as a potential TS violation.

50-228/2012-204-02 URI Review the issue of fuel verification at the Aerotest facility.

50-228/2012-204-03 IFI Review the licensees 10 CFR 50.59 evaluation and review of

the proposed new mechanism for attaching the upper grid plate

to support structure.

50-228/2012-205-01 IFI Review the licensees actions to complete a Root Cause or fault

tree analysis concerning the fuel element cracked cladding

problem.



PARTIAL LIST OF ACRONYMS USED

10 CFR Title 10 of the Code of Federal Regulations

ADAMS Agencywide Documents Access and Management System

ALARA As Low as Reasonably Achievable

AO Aerotest Operations

ARRR Aerotest Radiography and Research Reactor

IFI Inspector Follow-up Item

IP Inspection Procedure

NRC U.S. Nuclear Regulatory Commission

PCN Procedure Change Notice

PSP Physical Security Plan

RSC Reactor Safeguards Committee

RWI Reactor Work Instruction

STS Secured Transportation Services

SWP Special Work Permit

TLD Thermoluminescent Dosimeter

TS Technical Specification