ML14164A752

From kanterella
Jump to navigation Jump to search
NRC-032 - Letter from Gregory Bowman, NRC, to Sandra Warren, General Manager, Aerotest Operations, Inc., NRC Non-Routine Inspection Report No. 50-228/2012-204 (Aug. 14, 2012) (ADAMS Accession No. ML12213A001)
ML14164A752
Person / Time
Site: Aerotest
Issue date: 08/14/2012
From:
NRC/OGC
To:
Atomic Safety and Licensing Board Panel
SECY RAS
References
RAS 26039, ASLBP 14-931-01-LT-BD01, 50-228-LT
Download: ML14164A752 (18)


See also: IR 05000228/2012204

Text

15&

6XEPLWWHG -XQH  

August 14, 2012

Ms. Sandra Warren, General Manager

Aerotest Operations, Inc.

3455 Fostoria Way

San Ramon, CA 94583

SUBJECT: AEROTEST OPERATIONS, INC. - NRC NON-ROUTINE INSPECTION

REPORT NO. 50-228/2012-204

Dear Ms. Warren:

On July 16 - 23, 2012, the U.S. Nuclear Regulatory Commission (NRC or the Commission)

completed an inspection at your Aerotest Radiography and Research Reactor facility

(Inspection Report No. 50-228/2012-204). The enclosed report documents the inspection

results which were discussed on July 23, 2012, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records and interviewed personnel. Based on

the results of this inspection, no findings of significance were identified. No response to this

letter is required.

In accordance with Title 10 of the Code of Federal Regulations, Section 2.390, Public

inspections, exemptions, and requests for withholding, a copy of this letter, its enclosure, and

your response (if any) will be available electronically for public inspection in the NRC Public

Document Room or from the NRCs document system (Agencywide Documents Access and

Management System (ADAMS)). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this inspection, please contact Craig Bassett at

(301) 466-4495 or by electronic mail at Craig.Bassett@nrc.gov.

Sincerely,

/JNguyen for RA/

Gregory T. Bowman, Chief

Research and Test Reactors Oversight Branch

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Docket No. 50-228

License No. R-98

Enclosure: NRC Inspection Report No. 50-228/2012-204

cc w/encl: See next page



Aerotest Operations, Inc. Docket No. 50-228

cc w/encl:

Dario Brisighella, President

Aerotest Operations, Inc.

Autoliv

3350 Airport Road

Ogden, UT 84405

Fred Meren, Reactor Supervisor

Aerotest Operations, Inc.

3455 Fostoria Way

San Ramon, CA 94583

California Energy Commission

1516 Ninth Street, MS-34

Sacramento, CA 95814

Radiological Health Branch

P.O. Box 997414, MS 7610

Sacramento, CA 95899-7414

Test, Research, and Training

Reactor Newsletter

University of Florida

202 Nuclear Sciences Center

Gainesville, FL 32611



August 14, 2012

Ms. Sandra Warren, General Manager

Aerotest Operations, Inc.

3455 Fostoria Way

San Ramon, CA 94583

SUBJECT: AEROTEST OPERATIONS, INC. - NRC NON-ROUTINE INSPECTION

REPORT NO. 50-228/2012-204

Dear Ms. Warren:

On July 16 - 23, 2012, the U.S. Nuclear Regulatory Commission (NRC, the Commission)

completed an inspection at your Aerotest Radiography and Research Reactor facility

(Inspection Report No. 50-228/2012-204). The enclosed report documents the inspection

results which were discussed on July 23, 2012, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records and interviewed personnel. Based on

the results of this inspection, no findings of significance were identified. No response to this

letter is required.

In accordance with Title 10 of the Code of Federal Regulations, Section 2.390, Public

inspections, exemptions, and requests for withholding, a copy of this letter, its enclosure, and

your response (if any) will be available electronically for public inspection in the NRC Public

Document Room or from the NRCs document system (Agencywide Documents Access and

Management System (ADAMS)). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this inspection, please contact Craig Bassett at

(301) 466-4495 or by electronic mail at Craig.Bassett@nrc.gov.

Sincerely,

/JNguyen for RA/

Gregory T. Bowman, Chief

Research and Test Reactors Oversight Branch

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Docket No. 50-228

License No. R-98

Enclosure: NRC Inspection Report No. 50-228/2012-204

cc w/encl: See next page

DISTRIBUTION:

PUBLIC RidsNrrDprPrta Resource RidsNrrDprPrtb Resource PROB r/f

MNorris (MS T3B46M) MCompton (Ltr only O5-A4) GLappert, NRR CBassett, NRR

CMontgomery, NRR AAdams, NRR

ACCESSION NO.: ML12213A001 *concurrence via e-mail TEMPLATE #: NRC-002

OFFICE PROB:RI * PRPB:LA PROB:BC

NAME CBassett GLappert GBowman

DATE 7/26/2012 7/31/2012 8/14/2012

OFFICIAL RECORD COPY



U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

Docket No: 50-228

License No: R-98

Report No: 50-228/2012-204

Licensee: Aerotest Operations, Inc.

Facility: Aerotest Radiography and Research Reactor

Location: 3455 Fostoria Way

San Ramon, CA 94583

Dates: July 16-23, 2012

Inspector: Craig Bassett

Approved by: Gregory T. Bowman, Chief

Research and Test Reactors Oversight Branch

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation



EXECUTIVE SUMMARY

Aerotest Operations, Inc.

Aerotest Radiography and Research Reactor

Report No: 50-228/2012-204

The primary focus of this non-routine, announced inspection was the onsite review of selected

aspects of the Aerotest Operations, Inc. (the licensees) 250 Kilowatt (kW) Class II research

reactor safety program including: 1) fuel handling and inspection including defueling activities,

2) radiation protection, 3) conformance to the Security Plan, and 4) Design Change Functions.

The licensees program was acceptably directed toward the protection of public health and

safety, and in compliance with the U.S. Nuclear Regulatory Commission (NRC) requirements.

Fuel Handling and Defueling

Once various obstacles were overcome, the fuel and graphite elements were removed

from the core.

Fuel movements and inspections were completed and documented in accordance with

the requirements specified by procedure.

Following inspection of all the fuel elements, 21 aluminum clad elements were noted to

have cracks in them.

One unresolved item was noted regarding the licensees method of fuel element serial

number verification.

Radiation Protection Program

Surveys and associated checks were completed and documented acceptably to permit

evaluation of the radiological conditions present in the facility.

Notices and postings at the facility met the regulatory requirements.

Personnel dosimetry was being worn and doses were within the regulatory limits.

Radiation monitoring equipment was maintained and calibrated as required.

Training was provided as required covering the topics outlined in Title 10 of the Code of

Federal Regulations Section 19.12.

Conformance to the Security Plan Requirements

Security facilities, equipment, and procedures satisfied the Physical Security Plan

requirements.

Design Change Functions

A change is being considered in the method of attaching the upper grid plate to the core

support structure which will need to be reviewed and approved.



REPORT DETAILS

Summary of Plant Status

Aerotest Operations, Inc. (Aerotest or the licensee) had ceased to operate their TRIGA

Conversion research reactor on October 15, 2010. Prior to that time the reactor had been

operated for neutron radiography, to complete surveillance requirements, and for reactor

operator training. During this inspection, the reactor remained shut down and all of the fuel and

graphite elements were removed from the core and placed in storage racks. All the fuel

elements were inspected for damage to the cladding.

1. Background Information

During December 5-12, 2011, the licensee attempted to complete an inspection of all the

fuel to comply with their commitment to the NRC of inspecting all the fuel elements every

five years. As in previous inspections, those elements that could be removed were

placed in storage along the side of the reactor tank, in storage baskets on the floor of the

pool, or in storage holes in the thermal column. After those elements were removed, the

licensee found that there were 27 aluminum (Al) elements and 11 graphite elements that

could not be removed from the core. (One of the stainless steel (SS) elements and one

of the graphite elements were left in the core because they could not be removed due to

their respective locations.)

The licensee then used their underwater video camera to conduct an inspection of those

elements that could not be removed. The licensee found that, of those elements that

remained in the core, there were four that had signs of cracks in the cladding. (The

licensee then had 5 Al fuel elements that had cracks in the cladding, including one found

previously in 2007). Because of the cracking problem noted in some of the stuck

elements, the elements that had been removed from the core were not returned to the

core but left in their respective storage locations. No cause for the cracking could be

determined but the licensee surmised that it may have been caused from age and the

environment in which the elements were maintained (neutron flux, thermal cycling, and

immersed in water for almost 50 years).

On January 9, 2012, the licensee notified the NRC about the cracks that had been noted

in the fuel elements. The licensee submitted a letter documenting the problems that

same day. (The NRC had been notified of the cracked element removed from the core

in 2007 by a phone conversation between the licensee and Project Manager on

September 19, 2011.)

On January 17-18, 2012, the NRC completed an inspection at the Aerotest Radiography

and Research Reactor (see NRC Inspection Report No. 50-228/2012-201). During that

inspection one unresolved item was identified for possibly operating the reactor with

damaged fuel elements.

The licensee subsequently made the decision to remove all the fuel elements from the

core. It was decided to hire a contractor who would develop a plan to remove all the



-2-

stuck elements and submit a proposed project plan and reactor work instructions (RWIs)

to the licensee. A company, Secured Transportation Services (STS), was chosen for the

work.

2. Fuel Handling and Inspection Including Defueling Operations

a. Inspection Scope (IP 69001)

The inspector reviewed selected aspects of the following to verify that fuel

movement and handling was being conducted as required by Technical

Specifications (TS) Section 5.1.1 and Section 11:

Current Core Configuration Map

Current Fuel Element Storage Location Map

Fuel handling equipment and reactor instrumentation

Selected Operational Log Sheets for the past three months

Core Configuration Map for the period prior to December 2011

Fuel Element Storage Location Map prior to December 2012

Various current records and data sheets related to fuel movement

Reactor Safeguards Committee (RSC) meeting minutes for 2011 and to

date in 2012

Fuel movement and examination records including video of fuel

inspection

Listing of the Stuck Fuel Elements and Graphite Elements including a

description of each

Section IV of the ARRR Procedures Manual entitled, Critical Assembly

and Power Calibration, PCN No. 6, RSC approval dated November 2,

2005, with the latest Temporary Change (PCN No. 6A) dated

December 12, 2011

Aerotest Operations (AO) RWI No. AO RWI 101, Aerotest - Canister

Handling, Loading, Drying, and Conditioning, Rev. 0, dated June 25,

2012

RWI No. AO RWI 102, Aerotest - Fuel Handling Procedure, Rev. 0,

dated June 25, 2012

RWI No. AO RWI 103, Aerotest - Fuel Inspection Procedure, Rev. 0,

dated June 25, 2012

RWI No. AO RWI 104, Aerotest - Instrumented Fuel Element Cropping

Procedure, Rev. 0, dated June 26, 2012

RWI No. AO RWI 105, Aerotest - Upper Grid Plate Relocation, Rev. 0,

dated June 26, 2012

Project Plan, Aerotest Operations Fuel Removal, Inspection, and

Canning, Document (Doc.) No. Aero-PP-01, Rev. 0, dated June 25, 2012

In addition, the inspector observed the planning, discussions, and actions of the

licensee and contractor personnel during removal of the stuck fuel and graphite

elements from the core.



-3-

b. Observations and Findings

(1) Plan for Removing the Remaining Elements from the Core

As indicated above, a project plan was developed by the contractor which

provided guidance and instructions on the process to be used for

removing the elements that remained in the core. Procedures had been

developed outlining the various steps that were involved. The inspector

verified that the plan and procedures had been reviewed and approved by

the RSC before the work started.

The project plan included various steps in order to remove the stuck fuel

and graphite elements from the core and accomplish complete defueling

of the core. The plan included the following work evolutions:

a) Assembling of the extension tools necessary for the job of working

in the reactor pool including an articulating grapple arm on the end

of a pole, a tool to rotate the elements in the inspection stand, and

a canister holding tool that could be fastened on the end of a pole.

(It was noted that eight storage canisters with special lids

containing drain and vent ports and a pintal on top, with which to

grapple onto the canister using a fuel handling tool, were also

fabricated, leak tested, and shipped to the facility to be used to

contain the cracked elements.)

b) Placing the newly constructed inspection stand and canister

storage rack in the pool.

c) Raising the upper grid plate to allow removal of the elements from

underneath using the articulating grapple tool.

d) Removing all the fuel and graphite elements that were previously

stuck and could not be removed out through the top of the grid

plate.

e) Cutting the wires and top tube off (or cropping) the two

instrumented fuel elements (IFEs) so that they could be placed in

a storage location and so the one that was damaged could be

placed in a storage canister.

f) Inspecting all the fuel elements including the ones that were not

damaged or stuck.

g) Placing the damaged elements in storage canisters (or canning

the elements).

(2) Plan of the Day and Problem Resolution

Prior to starting work each day, the licensee and contractor personnel met



-4-

and discussed in detail what would be attempted during that days

activities. Safety precautions and the applicable procedure(s) were

reviewed. Everyone was allowed the opportunity to voice any concerns

they might have and the course of action for the day was agreed upon.

Although various setbacks and problems arose during the project,

everyones input was considered before proceeding. After a consensus

was reached, the project work began again.

At one point, following the problem with an upper grid plate bolt shearing,

a conference call was held with the licensee staff, the contractor

personnel, and the Chair of the RSC. After the problem and possible

course of action was explained, the RSC Chair requested that certain

measures be taken and the next course of action was discussed and

agreed upon.

(3) Removal of the Remaining Fuel Elements

As noted above, various problems occurred during the project. In an

effort to raise the upper grid plate, three of the four bolts holding the plate

in place sheared off as they were being removed (the fourth bolt was

loosened without incident). When licensee and contractor personnel tried

to raise upper grid plate, it became bound. It was thought that the Control

Rod Guide Tubes (CRGTs) were potentially causing the grid plate to bind

so the licensee attempted to remove the three CRTGs. That effort proved

unsuccessful and the focus of attention turned again on other methods to

move the upper grid plate. Eventually, after mechanical agitation, it was

raised about one inch. The IFE cropping operation required extra effort

but the top tube and wires were successfully removed.

Once the various obstacles to removal of the elements were overcome,

the fuel removal proceeded with the elements being lifted slightly with the

articulating grapple tool, tipped slightly and worked out from under the

grid plate through an opening in the core support structure. All the fuel

and graphite elements were eventually removed and the core was

completely defueled without further problems. The elements were

removed as stipulated by RWIs.

(4) Fuel Inspection

As noted previously, the inspection stand was placed in the pool to

facilitate element inspection. Fuel element inspection was accomplished

by placing each element in the inspection stand and, using an underwater

camera, observing the length of the element. The element was then

rotated one quarter turn and the length was again observed. Those that

were noted to be cracked were designated to be placed in a canister for

canning. All the observations of the fuel elements were documented

and videotaped so that a closer examination could be conducted at a later

time if necessary. The inspections were completed in accordance with

the appropriate RWI.



-5-

After the element inspection was complete, the licensee found that there

were 21 Al clad fuel elements which exhibited some type of cracks - most

had longitudinal crack but at least two had circumferential cracks toward

the upper portion of the elements. One other fuel element appeared to

have the beginning of a crack. No cracks were noted in any of the SS

clad elements. The licensee made the decision to place all the cracked

elements in canisters for storage.

Because the licensee originally knew of four cracked elements and it was

anticipated that there would only be a few others found, the licensee

directed the contractor to manufacture eight canisters (one other was

manufactured as a test canister). A storage rack with 12 positions was

also designed and fabricated to hold the canisters. In light of the fact that

21 cracked elements were found, the licensee ordered more canisters

and a larger storage rack. These will not be ready for at least five weeks.

Also, the licensee made the decision to have the contractor personnel

assist in placing all the cracked elements in canisters. However, due to

other commitments, the contractor personnel will not be able to return to

Aerotest until October 2012. It was agreed that leaving the cracked fuel

elements in storage racks until October would not pose any greater risk

than having them in the core (as they had been in the past). The licensee

was informed that the issue of ensuring that all the cracked fuel elements

were placed in canisters would be followed by the NRC as an Inspector

Follow-up Item (IFI) and will be reviewed during a future inspection (IFI

50-228/2012-204-01).

(5) Placing Cracked Element in Canisters

One portion of the inspection stand contained a position where a canister

could be placed. The method that the licensee planned to use for placing

an element in a canister consisted of the following steps. After the

inspection of a damaged element was completed, it would be placed in

the canister (which had been positioned in the rack) so that the

configuration control of the element would be maintained (i.e., all of the

element would be contained inside the canister even if the element were

to fall apart). The canister would then be brought to the surface of the

pool and the lid attached. The canister would then be drained/dewatered

using compressed helium gas and a vacuum drawn on the canister.

Finally, the canister would be backfilled with helium gas to complete the

operation. During the inspection two cracked elements were successfully

placed in canisters using the above steps.

(6) Maintaining Control of the Elements and Records

The inspector reviewed the records being maintained for the defueling

operation and fuel transfers. The appropriate records were being filled

out by one person designed as the recorder as required. It was noted

that positive control was maintained over the fuel and graphite element



-6-

transfers. During this inspection, the inspector verified that the fuel

movements were conducted in compliance with procedure and pre-

planned fuel moves. It was noted that the licensee was documenting the

various movements that had been completed and maintaining the

required records.

During the inspection it was also noted that the serial numbers on many

of the older AL clad elements could not be read. It appeared that some of

the numbers may have been obliterated over the years by the use of the

fuel handling tool. The licensee indicated that they did not necessarily

track or visually identify the fuel elements by serial number but typically

by the position in the core or storage rack. This location tracking

method had been used for years to identify and verify the elements.

Because this method of fuel and serial number verification appeared to be

somewhat less rigorous than usual, the licensee was informed that the

issue of fuel verification would be considered by the NRC as an

Unresolved Item (URI) and would be reviewed during a future inspection

(URI 50-228/2012-204-02).

(7) TS Section 11 - Fuel Storage and Transfer

TS Section 11 required that the licensee store fuel in specific locations

and transfer fuel only under certain conditions.

Through direct observation the inspector verified that the licensee was not

storing fuel in the floor of the Reactor Room although such storage was

allowed. All fuel was stored in a locked vault or in the reactor pool/tank.

Not more than one fuel element was allowed in the facility which was not

in storage or in the core lattice.

c. Conclusion

Fuel movements and inspections and defueling operations were completed and

documented in accordance with the requirements specified by standard

procedure and by the Reactor Work Instructions that had been developed for the

defueling project. Twenty-one Al clad elements were found with cracked

cladding. One URI was noted concerning fuel element serial number verification.

3. Radiation Protection Program

a. Inspection Scope (IP 69001)

The inspector reviewed the following to verify compliance with Title 10 of the

Code of Federal Regulations (10 CFR) Part 20 and the requirements in TS Sections 6.2, 7.0, and 12.1.2:

  • Special Work Permits (SWPs) - Numbers 2012-01 through

2012-03



-7-

  • Radiological signs and posting at the entrances to controlled or restricted

areas

  • Calibration records for portable monitoring instruments provided by the

contractor

  • Training provided to the contractor personnel and NRC inspector
  • Radiation protection surveillance and survey data for the defueling project

recorded on:

- Instrument Calibration forms

- Air Filter Paper Counting Sheet forms

- Aerotest Operations, Inc. Monthly Radiation Survey forms

- Aerotest Operations, Inc. Quarterly Maintenance Check List forms

  • Section VI of the ARRR Procedures Manual entitled, Radiological Safety

Procedures, PCN No. 3, RSC approval dated April 29, 1996

  • Section VIII of the ARRR Procedures Manual entitled, Maintenance

Procedures, PCN No. 2, RSC approval dated January 14, 1993

  • ALARA and Radiation Protection Program for Aerotest Operations, Inc.,

updated August 14, 2004

The inspector also observed the use of dosimetry and radiation monitoring

equipment during the inspection and conducted radiation surveys of various

items and during various work evolutions using an NRC survey meter.

b. Observations and Findings

(1) Surveys

Radiation and contamination survey results indicated that defueling

project activities were being conducted in accordance with applicable

procedures. The results of the surveys were documented on the

applicable forms and were evaluated as required. No surveys showed

any contamination above established limits.

During the inspection the inspector conducted radiation surveys during

work evolutions. The radiation levels noted by the inspector, using an

NRC survey meter, were similar to those detected by the licensee. No

anomalies were noted.

The inspector noted that licensee and contractor personnel were using

the appropriate monitoring equipment during and following the various

work evolutions. Everyone monitored after handling any equipment or

items that might have been contaminated.

(2) Postings and Notices

During tours of the facility, the inspector observed that caution signs,

postings, and controls in the restricted or controlled areas were

acceptable for the hazards involving radiation, high radiation, and

contamination and were posted as required by 10 CFR Part 20,



-8-

Subpart J. Radiological signs were typically posted at the entrances to

controlled areas.

Copies of current notices to workers were posted in various areas in the

facility including the hallway in the Reactor Bay just outside the Control

Room. Other postings also characterized the industrial hygiene hazards

that were present in the areas as well. The inspector noted that the

copies of NRC Form-3, Notice to Employees, posted at the facility as

required by 10 CFR Part 19.11, were the current version.

(3) Dosimetry

The inspector determined that the licensee used thermoluminescent

dosimeters (TLDs) for whole body monitoring of beta and gamma

radiation exposure (with an additional component to measure neutron

radiation). The licensee also used TLD finger rings for extremity

monitoring. The dosimetry was supplied and processed by Radiation

Detection Company, a company that was a National Voluntary Laboratory

Accreditation Program accredited vendor. The licensee issued also

contractor personnel dosimeters and finger rings to be used for the job

and issued pocket ion chambers each day to track daily exposure.

(4) Radiation Monitoring Equipment

During a previous inspection in June 2012, the inspector determined that

licensee survey meters had the acceptable up-to-date calibration sticker

attached. The inspector noted that the calibration of portable instruments

was being verified quarterly as required by procedure. Calibration of

survey meters and equipment supplied by the contractor was also

reviewed. Those instruments were found to be properly calibrated as

required.

(5) Training

The inspector observed the training given to the contractor personnel.

Those individuals were acceptably trained in radiation protection

practices. The inspector also received training concerning the Special

Work Permit issued for the defueling project.

(7) Radiation Work Permit Program

SWPs were required to be prepared for special operations typically

performed by non-Aerotest maintenance and other support personnel

who were required to work in radiation areas. The inspector noted that

SWPs had been written and issued for the contractor personnel as well

as for the inspector. The SWPs had been prepared and implemented in

accordance with the requirements specified in the licensees Radiological

Safety Procedures. The controls and safety precautions specified were

appropriate for the work conducted under the SWP.



-9-

(8) Facility Tours

The inspector toured the facility on various occasions and observed

activities in offices, support areas, the Reactor Bay, and the mezzanine

area. Through observations of, and interviews with, licensee staff, the

inspector confirmed that personnel complied with the signs, postings, and

controls. The facilitys radioactive material storage areas were noted to

be properly posted. No unmarked radioactive material was detected in

the facility.

c. Conclusion

The inspector determined that the Radiation Protection and ALARA Programs, as

implemented by the licensee, satisfied regulatory requirements because:

1) surveys and associated checks were completed and documented acceptably

to permit evaluation of the radiation hazards present; 2) postings met regulatory

requirements; 3) personnel dosimetry was being worn as required; 4) radiation

survey and monitoring equipment was being maintained and calibrated as

required; and, 5) radiation protection training was being conducted for contractor

personnel as required.

4. Conformance to Security Plan Requirements

a. Inspection Scope (IPs 81401, 81402, 81431, 81810)

The inspector reviewed the following to verify compliance with Section 3.2 of the

TS and with the licensees NRC-approved Physical Security Plan (PSP) entitled,

Aerotest Radiography and Research Reactor Security Plan, last revised

January 7, 2005:

  • Access controls currently in effect
  • Monthly Alarm Check List forms for 2012
  • Emergency detection devices and physical barriers

last revised January 14, 2005, and last reviewed May 16, 2011

  • Section III of the ARRR Procedures Manual entitled, General Emergency

Procedures, Permanent Change Notice (PCN) Number (No.) 4, RSC

approval dated January 28, 2005

  • Section V of the ARRR Procedures Manual entitled, Security

Procedures, PCN No. 3, RSC approval dated February 11, 2005

b. Observations and Findings

The inspector conducted an inspection of the Security Plan and response in June

2012 (refer to NRC Inspection Report No. 50-228/2012-203). During that

inspection the inspector verified that the licensee was maintaining adequate

security and control over the facility. As noted during the June 2012 inspection,



- 10 -

the PSP in use by the licensee was the same as the version approved by the

NRC. That version was dated January 7, 2005, and had last been reviewed on

May 16, 2011. The PSP was being reviewed biennially as required and annual

security training was completed as stipulated by the PSP. Implementing

procedures were consistent with the PSP.

During this inspection the inspector verified that the physical protection system,

consisting of barriers, alarms, equipment, and instrumentation, remained in place

and was as stipulated in the PSP. The system was being maintained and tested

periodically as required by procedure. Access controls were implemented as

required and keys to the various facility doors were controlled and held only by

designated personnel. It was noted that the licensee had verified that the

background investigations and clearances of the contractor personnel were

current.

c. Conclusion

Security facilities, equipment, training, and procedures satisfied PSP

requirements.

5. Design Change Functions

a. Inspection Scope (IP 69001)

The inspector reviewed the following to ensure that the design change functions

outlined in TS Section 12.1.3 were completed:

  • RSC meeting minutes for July 11, 2012
  • Section I of the ARRR Procedures Manual entitled, Administrative

Procedures, PCN No. 2, RSC approval dated June 28, 1990

b. Observations and Findings

The inspector verified that the licensee was aware that changes or modifications

to the facility were required to be analyzed by the staff and the results of the

analyses presented to the RSC. Following a review, the RSC would then

approve them if the changes or modifications were determined to be acceptable.

If necessary the change would be submitted to the NRC for review and approval.

As noted in Paragraph 2 above, one off the obstacles encountered by the

licensee was raising the upper grid plate to allow the elements to be removed

from underneath. When the licensee tried to loosen the four bolts holding the

upper grid plate to the core support structure, three bolts would not turn.

Eventually the three bolts snapped off in place while the fourth bolt was loosened

and unscrewed about two inches. In order to reattach the upper grid plate to the

core support structure in the future, several methods were discussed. The

contractor personnel indicated that they might be able to develop a clamping

mechanism that could be used instead of the bolts. This would eliminate the

necessity of redrilling the upper grid plate and drilling and tapping the core



- 11 -

support structure. Because this would be a change to the current structure, the

licensee would need to perform a 10 CFR 50.59 evaluation and review of the

proposed new attachment mechanism. The licensee was informed that the issue

of reviewing any changes made will be considered an IFI and will be reviewed

during a future inspection (IFI 50-228/2012-204-03).

c. Conclusion

Audits and reviews were being conducted acceptably by the RSC in accordance

with the requirements specified in the TS. No changes had been made at the

facility since the last inspection but the process remained in place such that

changes or modifications would be reviewed and approved by the RSC as

required.

6. Exit Interview

The inspection scope and results were summarized on July 23, 2012, with members of

licensee management. The inspector described the areas inspected and discussed the

inspection findings. No dissenting comments were received from the licensee. Although

proprietary information was reviewed during the inspection, no such material is included

in this report.

-

PARTIAL LIST OF PERSONS CONTACTED

Licensee Personnel

C. Bauman Research and Development Manager

A. Meren Reactor Supervisor and Reactor Operations Manager

T. Richey Neutron Radiography Manager

S. Warren General Manager and Radiological Safety Officer

M. Wilkinson Quality Assurance Manager

Other Personnel

R. Boyd Vice President, Secured Transportation Services (STS)

B. Williams President, Secured Transportation Services (STS)

INSPECTION PROCEDURES USED

IP 69001 Class II Non-Power Reactors

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

50-228/2012-204-01 IFI Review the licensees actions to ensure that all the cracked fuel

elements are placed in canisters.

50-228/2012-204-02 URI Review the issue of fuel verification at the Aerotest facility.

50-228/2012-204-03 IFI Review the licensees 10 CFR 50.59 evaluation and review of

the proposed new mechanism for attaching the upper grid plate

to support structure.

Closed

None



-2-

PARTIAL LIST OF ACRONYMS USED

10 CFR Title 10 of the Code of Federal Regulations

ADAMS Agencywide Documents Access and Management System

Al Aluminum

ARRR Aerotest Radiography and Research Reactor

CRGT Control Rod Guide Tube

IFI Inspector Follow-up Item

IP Inspection Procedure

kW kilowatt

No. Number

NRC U.S. Nuclear Regulatory Commission

PCN Procedure Change Notice

PSP Physical Security Plan

RSC Reactor Safeguards Committee

RWI Reactor Work Instruction

SS Stainless steel

SWP Special Work Permit

TS Technical Specification

URI Unresolved Item