E-mail from J Whited to P Lashley: Second Draft RAI on Capsule Withdrawal Schedule Review
ML14055A307
Person / Time
Site: Beaver Valley
Issue date: 02/24/2014
From: Jeffrey Whited
Plant Licensing Branch 1
To: Lashley P
FirstEnergy Nuclear Operating Co
Whited J
Shared Package
ml14055a387 List:
References
Download: ML14055A307 (1)


Text

Whited, Jeffrey From: Whited, Jeffrey Sent: Monday, February 24, 2014 1:13 PM To: phlashley@firstenergycorp.com Cc: talentz@firstenergycorp.com

Subject:

SECOND DRAFT-RAI to FENOC PROPOSED REVISION TO REACTOR VESSEL SURVEILLANCE CAPSULE WITHDRAWAL SCHEDULES Attachments: DRAFT Capsule Second RAIs.docx Mr. Lashley, By letter dated May 28, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13151A058), as supplemented by letter dated December 13, 2013 (ADAMS Accession No. ML13350A581), First Energy Nuclear Operating Company submitted a request to revise the reactor vessel surveillance capsule withdrawal schedules for the Beaver Valley Power Station, Units 1 and 2.

The NRC staff has reviewed the information submitted by the licensee, and based on this review, determined additional information is required to complete the assessment of the submitted information. Please find attached a Draft Request For Additional Information. It is being sent to you to ensure that the question is understandable, the regulatory basis for the question is clear, and to determine if the information was previously docketed. Please respond to me by Friday, February 28, 2013, and notify me if you desire to hold a teleconference to discuss the question. The NRC staff will request a response to the RAIs within 30 days of the formal NRC RAI transmittal letter.

Thank you, Jeffrey Whited Project ManagerBeaver Valley and Susquehanna Plant Licensing Branch I2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission (301)4154090 jeffrey.whited@nrc.gov 1