MONTHYEARML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24156A1072024-06-0404 June 2024 NRR E-mail Capture - (External_Sender) Supplement for FitzPatrick TS 3.4.2-2 ML24131A0612024-05-10010 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24122B5072024-05-0101 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-591, Revision 0 ML24024A1372024-01-24024 January 2024 NRR E-mail Capture - Final Snsb RAI Regarding FitzPatrick Amendment to Modify Safety Relief Valves Setpoint Lower Tolerance ML24017A1112024-01-17017 January 2024 NRR E-mail Capture - Acceptance of Requested Licensing Action Amendment Request to Adopt TSTF-529, Clarifyuse and Applicaion Rules, Revision 4 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC Fleet Request License Amendment Request to Adopt TSTF-580, Revision 1 ML23261C3982023-09-0808 September 2023 Acceptance Review of Amendment to Update the Fuel Handling Accident Analysis ML23244A2662023-09-0101 September 2023 Acceptance of Requested Licensing Action Amendment Request to Modify Surveillance Requirement 3.4.3.1, Safety Relief Valves Setpoint Lower Tolerance ML23237B3972023-08-24024 August 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Alternative Request to Use Updated BWRVIP Guidelines ML23194A1822023-08-0303 August 2023 Acceptance Review for LAR Re SRM 3.3.1.2 ML23163A2292023-06-12012 June 2023 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-580, Revision 1 ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI NRC-2100-2022, EN 55999 Valcor Coil Shell Assemblies Final Notification (004)2022-09-12012 September 2022 EN 55999 Valcor Coil Shell Assemblies Final Notification (004) NRC 2110-2022, EN 55999 - Valcor Engineering Corporation (009)2022-07-18018 July 2022 EN 55999 - Valcor Engineering Corporation (009) ML22124A2672022-05-0404 May 2022 Request for Additional Information for James A. FitzPatrick Nuclear Power Plant TSTF-505 ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML22063A4742021-11-29029 November 2021 Acceptance of Requested Licensing Action License Amendment Request to Eliminate Selected Response Time Testing ML21301A0672021-10-28028 October 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-541 ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21252A0482021-09-0707 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21246A2112021-09-0303 September 2021 Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-505 ML21246A2072021-09-0303 September 2021 Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 ML21215A3502021-08-0303 August 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-554 ML21187A0522021-07-0606 July 2021 Fitz RAI Regarding FitzPatrick Amendment Request to Modify SR 3.5.1.6 ML21246A2142021-06-23023 June 2021 Acceptance of Requested Licensing Action Regarding License Amendment Request to Adopt TSTF-264 ML21154A0142021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0132021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0112021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21144A1072021-05-17017 May 2021 Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-582 ML21117A0442021-04-26026 April 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21084A2532021-03-24024 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Transfer Application ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21033A8552021-02-0202 February 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request to Expand the Use ASME Codes Cases N-878 and N-880 ML21014A5112021-01-12012 January 2021 Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-545 Revision 3 ML20352A2752020-12-17017 December 2020 Request for Additional Information Regarding FitzPatrick Primary Containment Isolation Valve Amendment Request ML20350B5582020-12-14014 December 2020 NRR E-mail Capture - Exelon Generation Company, LLC -Alternative Request for Documentation of Replacement of Pressure Retaining Bolting ML20294A0372020-10-19019 October 2020 Request for Additional Information Primary Containment Isolation Valve License Amendment Request ML20266G3032020-09-22022 September 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Request to Use Paragraph IWA-5120 of the 2017 Edition of the ASME B&PV Code, Section XI ML20217L3882020-08-0404 August 2020 Acceptance of Requested Licensing Action License Amendment Request to Modify Primary Containment Isolation Valve TS (EPID L-2020-LLA-0145) (E-Mail) ML20204A9692020-07-22022 July 2020 Acceptance of Requested Licensing Action License Amendment Request to Adopt-TSTF-478 Revision 2 ML20122A2302020-05-0101 May 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of Fleet License Amendment Request to Adopt TSTF-566 ML20066L3682020-03-0505 March 2020 Request for Additional Information: License Amendment Request for Change to the Technical Specifications to Revise the Allowable Value for Reactor Water Cleanup (RWCU) System Primary Containment ML20056E7992020-02-25025 February 2020 Request for Additional Information for LAR on Primary Containment Hydrodynamic Loads ML20035D5762020-02-0303 February 2020 Request for Additional Information: License Amendment Request for Application of the Alternative Source Term for Calculating Loss-of-Coolant Accident Dose Consequence ML20027A0672020-01-24024 January 2020 Accepted for Review - Fitzpatrick License Amendment Request to Adopt TSTF-568, Revision 2, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 ML20027A0112020-01-23023 January 2020 Request for Additional Information: License Amendment Request for Change to the Technical Specifications to Revise the Allowable Value for Reactor Water Cleanup (RWCU) System Primary Containment Isolation 2024-07-12
[Table view] |
Text
NRR-PMDAPEm Resource From: Thadani, Mohan Sent: Tuesday, November 19, 2013 2:38 PM To: Adner, Chris (CAdner@entergy.com)
Cc: Jones, Heather
Subject:
Request for Additional Information-James A. FitzPatrick Nuclear Power Plant-Revise License Condition 2.T Chris:
The Nuclear Regulatory Commission (NRC) staff is reviewing the information provided by Entergy Nuclear Operations, Inc. for James A. FitzPatrick Nuclear Power Plant (JAFNPP) in its license amendment request (LAR) dated May 7, 2013, (Agencywide Documents Access and Management System [ADAMS] Accession No. ML13128A165). The NRC staff has concluded that additional information is necessary to complete its review.
Please provide a response to the following request for additional information (RAI) within 30 days from the date of this email.
Best regards, Mohan C Thadani Senior Project Manager FitzPatrick, Ginna, and Constellation Fleet Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1476 Mohan.Thadani@nrc.gov REQUEST FOR ADDITIONAL INFORMATION REGARDING LICENSE AMENDMENT REQUEST TO REVISE LICENSE CONDITION 2.T ENTERGY NUCLEAR OPERATIONS, INC.
JAMES A. FITZPATRICK NUCLEAR POWER PLANT DOCKET NO. 50-333 1
The Nuclear Regulatory Commission (NRC) staff is reviewing the information provided by Entergy Nuclear Operations, Inc. (ENO) (the licensee) for James A. FitzPatrick Nuclear Power Plant (JAFNPP) in its license amendment request (LAR) dated May 7, 2013, (Agencywide Documents Access and Management System
[ADAMS] Accession No. ML13128A165), and has concluded that additional information is necessary to complete its review. Please provide a response which addresses the following request for additional information (RAI):
Background
The renewed facility operating license condition (LC) 2.T currently states:
License Renewal Commitments/Conditions - The UFSAR supplement, as revised, describes certain future activities to be completed prior to and during the period of extended operation. ENF and ENO shall complete these activities in accordance with Appendix A of NUREG-1905, Safety Evaluation Report Related to the License Renewal of James A. FitzPatrick Nuclear Power Plant, issued April 2008. ENF and ENO shall notify the NRC in writing within 10 days of completion of those activities required prior to the period of extended operation and those activities required during the period of extended operation.
Consistent with Revisions 1 and 2 of NUREG-1800, Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants [SRP-LR], (ADAMS Accession Nos. ML052110007 and ML103490036),
the primary purpose of LC 2.T is to ensure that certain license renewal programs and activities are implemented and/or completed prior to the period of extended operation consistent with Appendix A commitments, and that the NRC receive notification of completion to enable verification by NRC inspection.
Issue The licensee proposes to remove activities in accordance with Appendix A of NUREG-1905, Safety Evaluation Report Related to the License Renewal of James A. FitzPatrick Nuclear Power Plant, issued April 2008 from LC 2.T to be replaced with regulatory commitments codified into the UFSAR no later than October 17, 2014.
The licensee also proposes to add language to LC 2.T clarifying that changes to the UFSAR, which includes the Appendix A list of commitments, be governed by 10 CFR 50.59 criteria. The licensee proposes for LC 2.T to state:
License Renewal Commitments - The UFSAR supplement, as revised, describes certain future programs and activities to be completed prior to the period of extended operation. ENF and ENO shall complete these regulatory commitments codified into the UFSAR no later than October 17, 2014. ENF and ENO shall notify the NRC in writing within 10 days of completion of these activities so that they can be verified by NRC Inspection. Following incorporation into the UFSAR, the need for prior Commission approval of any changes will be governed by 10 CFR 50.59.
However, since the issuance of the renewed license for Fitzpatrick, the NRC has reviewed and accepted other versions of LCs that can be summarized as follows:
The licensees UFSAR supplement submitted pursuant to 10 CFR 54.21(d), as revised during the license renewal application review process, and as supplemented by Appendix A of NUREG-XXXX, Safety Evaluation Report Related to the License Renewal of [Plant] dated [Month Year], describes certain programs to be implemented and activities to be completed prior to the period of extended operation.
- a. The licensee shall implement those new programs and enhancements to existing programs no later than the PEO date.
- b. The licensee shall complete those inspection and testing activities by the PEO date.
2
The licensee shall notify the NRC in writing within 30 days after having accomplished item (a) above and include the status of those activities that have been or remain to be completed in item (b) above.
These later versions of LCs, in effect, explicitly attach commitments made by the licensees to their corresponding UFSAR supplements so that licensees can manage the implementation of those activities described in the UFSAR in accordance with 10 CFR 50.59 rather than 10 CFR 50.90.
RAI Provide an explanation or rewording of the proposed LC language to further clarify how the commitments for FitzPatrick are related to the programs and activities as described in the UFSAR.
3
Hearing Identifier: NRR_PMDA Email Number: 1005 Mail Envelope Properties (Mohan.Thadani@nrc.gov20131119143700)
Subject:
Request for Additional Information-James A. FitzPatrick Nuclear Power Plant-Revise License Condition 2.T Sent Date: 11/19/2013 2:37:39 PM Received Date: 11/19/2013 2:37:00 PM From: Thadani, Mohan Created By: Mohan.Thadani@nrc.gov Recipients:
"Jones, Heather" <Heather.Jones@nrc.gov>
Tracking Status: None "Adner, Chris (CAdner@entergy.com)" <CAdner@entergy.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 5649 11/19/2013 2:37:00 PM image003.jpg 4263 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received: