Southern California Edison Company 23 PARKER STREET IRVINE, CALIFORNIA 92718 F. R. NANDY TELEPHONE MANAGER, NUCLEAR LICENSING July 1 (714) 454-4504 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Gentlemen:
Subject:
Docket No. 50-206 Eleventh Edition of the Integrated Implementation Schedule (IIS)
San Onofre Nuclear Generating Station, Unit 1
Reference:
Letter from F. R. Nandy (SCE) to Document Control Desk (NRC),
dated December 27, 1990;
Subject:
Tenth Edition of the Integrated Implementation Schedule (IIS)
San Onofre Nuclear Generating Station, Unit 1 In accordance with License Condition 3.J to Provisional Operating License DPR-13, this letter provides the eleventh edition of the San Onofre Unit 1 Integrated Implementation Schedule (IIS).
If there are any questions on the enclosure or if you require additional information, please contact me.
Very truly yours, Enclosure cc:
G. Kalman, NRC Senior Project Manager, San Onofre Unit 1 J. 0. Bradfute, NRC Project Manager, San Onofre Unit 1 J. B. Martin, Regional Administrator, NRC Region V C. W. Caldwell, NRC Senior Resident Inspector, San Onofre Units 1, 2&3 r j10711-
)72t~
FDR_
ENCLOSURE INTEGRATED IMPLEMENTATION SCHEDULE SAN ONOFRE NUCLEAR GENERATING STATION, UNIT 1 ELEVENTH EDITION JUNE 1991 Introduction License Condition 3.J, "Integrated Implementation Schedule" (IIS), requires Southern California Edison (SCE) to follow the IIS Program Plan issued in License Amendment No. 98 on April 20, 1987.Section V.A of the Plan states that SCE will update Schedules A, B, and C semi-annually. Schedule A items have implementation dates required by NRC regulations, orders or license conditions. Schedule B items are other items which have implementation dates committed to by SCE which would result in either:
(a)
Plant modifications; (b)
Procedure revisions; (c)
Changes in facility staffing requirements; (d) Items perceived by SCE as prospective NRC requirements; (e) Major tasks resulting from mandates of agencies other than the NRC; or (f) Evaluation of major NRC-initiated issues not required by Regulation, License Conditions, or Orders Schedule C lists SCE initiated plant betterment projects. The Plan also states that SCE will summarize progress in implementing NRC requirements concerning plant modifications; identify changes since the last report; summarize the reasons for schedule changes associated with Schedules A and B; and, indicate the expected percentage allocation of resources on Regulatory and Betterment projects for the next refueling/modification outage.
This report, the eleventh edition of the IIS, provides the required status update for the period December 1990 through May 1991. The tenth edition of the IIS was provided to the NRC by letter, F. R. Nandy to NRC Document Control Desk, dated December 27, 1990.
The current Schedules A, B, and C are enclosed as Attachments 1, 2 and 3, respectively.
Progress In Implementing NRC Requirements Since the last submittal (IIS Tenth Edition) in December 1990, Unit 1 concluded the Cycle 11 refueling outage on March 23, 1991.
All of the modifications reported for Cycle 11 in the Tenth Edition of the IIS have been completed except the Boric Acid Gas System Modifications. We encountered difficulties in the installation of this DCP and provided status on this item in our Full Term Operating License (FTOL) update letter dated February 22, 1991.
This letter stated that we would provide a completion
Document Control Desk
- 2 schedule with this edition of the IIS. Currently, we forecast completion of this DCP for October 31, 1991.
All of the remaining Schedule A and B modification work reported in this edition of the IIS for the Cycle 12 refueling outage will be completed in the Cycle 12 refueling outage.
Changes Since The Last Report And The Reasons For Schedule Changes Associated With Schedules A and B.
A comparison to the tenth edition of the IIS reveals that the following changes have occurred to the Cycle 12 schedule:
Action Cycle Schedule Modification Deleted 12 C
Turbine Plant Cooling Water (TPCW)
Upgrades - Completed Schedule 12 A
Vital Bus Retransfer Modifications Change (NRC Amendment #143, dated February 28, 1991)
- Schedule 12 A
Spent Fuel Pool Cooling Pump Change Modifications (NRC Amendment #132 dated July 16, 1990) **
The Vital Bus Retransfer Modifications have been moved to Schedule A from Schedule B with the issuance of NRC Amednment 143.
Amendment 143, dated February 28, 1991, made these modifications a License Condition.
The Spent Fuel Pool Cooling Pump Modifications have been moved to Schedule A from Schedule B with the issuance of NRC Amednment 132.
Amendment 132, dated July 16, 1990, made these modifications a License Condition.
Based on the above, there was no need to run the Westinghouse Analytical Ranking Program (WARP) to rank the safety significance of each modification.
The rankings are only used to determine the priority of scheduling work that could not be completed in the next refueling outage.
Expected Percentages Allocation Of Resources On Regulatory And Betterment Projects For The Next Refueling/Modification Outage Approximately 99% of the resource allocation of the next (Cycle 12) refueling outage is on regulatory projects.
Document Control Desk
-3 ATTACHMENT 1 INTEGRATED IMPLEMENTATION SCHEDULE A MODIFICATIONS ASSOCIATED WITH RULE, REGULATION OR ORDER' Cycle 12 Reactor Vessel Level Indicating System (RVLIS) (NRC Order, January 2, 1990)
Simulator (Non-Outage Related) - (Letter to NRC, November 2, 1990)
Safety Injection Recirculation System Modifications (Letter to NRC, October 26, 1988)
Safety Injection System Improvements (Letter to NRC, October 26, 1988)
Turbine Deck Steel Plating (NRC Order, January 2, 1990)
Safety Parameter Display System (NRC Order, January 2, 1990)
Control Room Design Review Modifications (Al Groups) (NRC Order, January 2, 1990)
Upgrade Core Exit Thermocouples (To be implemented with Schedule A RVLIS) (NRC Order, January 2, 1990)
Control Room Habitability (NRC Order, January 2, 1990)
Addition of Synchrocheck Relays to Emergency Diesel Generators (NRC Order, January 2, 1990)
Undervoltage Relays for Protection from Degraded Grid Voltage (SEP VIII-1.A) (NRC Order, January 2, 1990)
Inservice Testing Modifications Vibration Instrumentation for Diesel Oil Transfer Pumps (Letter from NRC, July 30, 1990, and NRC Order, January 2, 1990)
Flow Instrumentation for SI Pumps (Letter to NRC, October 29, 1990, and NRC Order, January 2, 1990)
Steam Generator Overfill Protection (NRC Order, January 2, 1990)
Single Failure Analysis, Separation & RG 1.97 (NRC Order, January 2, 1990)
Reg. Guide 1.97, Non-Single Failure (NRC Order, January 2, 1990)
Vital Bus Retransfer Modification (LER 90-011, NRC Amendment #143 dated February 28, 1991)
Spent Fuel Pool Cooling Pump Modifications (Letter to NRC, May 16, 1990, and NRC Amendment #132 dated July 16, 1990)
Including Amendment Applications
Document Control Desk
- 4 ATTACHMENT 1 -
(CONTINUED)
INTEGRATED IMPLEMENTATION SCHEDULE A MODIFICATIONS ASSOCIATED WITH RULE, REGULATION OR ORDER ONGOING MAJOR EVALUATIONS REQUIRING SCE SUBMITTAL ITEM TYPE DESCRIPTION SUBMITTAL DATE TMI III.D.3.4 Control Room Habitability November 1991 (Letter to NRC, April 10, 1991)
SEP III-5.A Effects of Pipe Breaks on July 31, 1991 III-5.B Structures, Systems, and (Complete 111-7.B Components Inside Analysis)
V-5 Containment, Pipe Break Outside Containment (Letter to NRC, July 30, 1990)
SEP VI-7.C.2 Provide an Integrated September 30, 1991 IX-3 Resolution of Open Items (Interim Submittal)
RG 1.97 (Letter to NRC, July 1, 1990)
December 30, 1991 (Final Evaluation)
USI A-46 Seismic Adequacy of Cycle 12 Outage Equipment (Plant Walkdowns) (Letter to NRC, October 7, 1988)
Document Control Desk 5
ATTACHMENT 2 INTEGRATED IMPLEMENTATION SCHEDULE B MODIFICATIONS ASSOCIATED WITH NRC COMMITMENTS AND OTHER REQUIREMENTS Cycle 11 Boric Acid Gas System Modifications (Letters to NRC, March 5, 1990 and February 22, 1991)
Cycle 12 Emergency Response Data System (GL 89-15)
Containment Spray Penetration Upgrade (Letter to NRC, February 27, 1991)
Document Control Desk
-6 ATTACHMENT 2 -
(CONTINUED)
INTEGRATED IMPLEMENTATION SCHEDULE B MODIFICATIONS ASSOCIATED WITH NRC COMMITMENTS AND OTHER REQUIREMENTS ONGOING MAJOR EVALUATIONS REQUIRING SCE SUBMITTAL ITEM TYPE DESCRIPTION SUBMITTAL DATE IPE Integrated Plant November 1992 Evaluation (GL 88-20)
ATWS Anticipated Transient Without December 1992 Scram - Diverse Scram System (Letter to NRC, July 23, 1990)
.Document Control Desk
- 7 ATTACHMENT 3 INTEGRATED IMPLEMENTATION SCHEDULE C MODIFICATIONS ASSOCIATED WITH BETTERMENT PROJECTS Cycle 12 HP Turbine Upgrade Battery #2 Replacement