Southern California Edison Company 23 PARKER STREET IRVINE, CALIFORNIA 92718 R. M. ROSENBLUM TELEPHONE MANAGER OF December 27, 1990 (714) 454-4505 NUCLEAR REGULATORY AFFAIRS U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C.
20555 Gentlemen:
Subject:
Docket No. 50-206 Tenth Edition of the Integrated Implementation Schedule (IIS)
San Onofre Nuclear Generating Station, Unit 1
Reference:
Letter from F. R. Nandy (SCE) to Document Control Desk (NRC),
dated June 22, 1990;
Subject:
Ninth Edition of the Integrated Implementation Schedule (IIS)
San Onofre Nuclear Generating Station, Unit 1 In accordance with License Condition 3.J to Provisional Operating License DPR 13, this letter provides the tenth edition of the San Onofre Unit 1 Integrated Implementation Schedule (IIS).
If there are any questions on the enclosure or if you require additional information, please contact me.
Very truly yours,
Enclosure:
As stated cc: J. B. Martin, Regional Administrator, NRC Region V C. W. Caldwell, NRC Senior Resident Inspector C. D. Townsend, NRC Resident Inspector G. Kalman, NRR SONGS 1 Project Manager 9101070002 901227 8
PDR ADOCK 05000206 4o P.
ENCLOSURE INTEGRATED IMPLEMENTATION SCHEDULE SAN ONOFRE NUCLEAR GENERATING STATION, UNIT 1 TENTH EDITION DECEMBER 1990 Introduction License Condition 3.J, "Integrated Implementation Schedule" (IIS),
requires Southern California Edison (SCE) to follow the IIS Program Plan issued in License Amendment No. 98 on April 20, 1987.
Section V.A of the Plan states that SCE will update Schedules A, B, and C semi-annually. Schedule A items have implementation dates required by NRC regulations, orders or license conditions.
Schedule B items are other items which have implementation dates committed to by SCE which would result in either:
(a) Plant modifications; (b) Procedure revisions; (c) Changes in facility staffing requirements; (d) Items perceived by SCE as prospective NRC requirements; (e) Major tasks resulting from mandates of agencies other than the NRC; or (f) Evaluation of major NRC-initiated issues not required by Regulation, license conditions, or orders Schedule C lists SCE initiated plant betterment projects.
The Plan also states that SCE will summarize progress in implementing NRC requirements concerning plant modifications; identify changes since the last report; summarize the reasons for schedule changes associated with Schedules A and B; and, indicate the expected percentage allocation of resources on Regulatory and Betterment projects for the next refueling/modification outage.
This report, the tenth edition of the IIS, provides the required status update for the period June 1990 through November 1990.
The ninth edition of the IIS was provided to the NRC by letter, F. R. Nandy to NRC Document Control Desk, dated June 22, 1990.
The current Schedules A, B, and C are enclosed as Attachments 1, 2 and 3, respectively.
Progress In Implementing NRC Requirements Since the last submittal (IIS Ninth Edition) in June 1990, Unit 1 entered the Cycle 11 refueling outage on June 30, 1990.
The following modifications, reported in the Ninth Edition of the IIS, have been completed:
Design Basis Precipitation Modifications (Rooftop Drainage Modifications - Scuppers)
Utility Bus Panel Replacement Spent Fuel Pool Cooling Pump Addition (short term)
All of the remaining Schedule A and B modification work reported in the Ninth Edition of the IIS for the Cycle 11 refueling outage, is currently in progress and will be completed in the Cycle 11 refueling outage.
Changes Since The Last Report And The Reasons For Schedule Changes Associated With Schedules A and B.
A comparison to the ninth edition of the IIS reveals that the following changes have occurred to the Cycle 11 and 12 schedules:
Action Cycle Schedule Modification Schedule 11 A
CVCS Valves MOV-LCV-1100 B, Change C, and D Added 11 B
ECCS Single Failure Analysis Modifications Added 11 B
Environmental Qualification Modifications Added 11 C
PASS Upgrades Deleted 12 A
Waste Gas Decay Tank Monitoring Instrumentation Modifications
- Added 12 B
Vital Bus Retransfer Modification Added 12 C
HP Turbine Upgrade Added 12 C
Battery #2 Replacement Added 12 C
Turbine Plant Cooling Water Upgrades
- SCE reported in the Ninth Edition of the IIS, that the Waste Gas Decay Tank Monitoring Instrumentation modifications, required by NRC Order dated January 2, 1990, would be completed by the Cycle 12 refueling outage.
This modification was completed in June of 1986.
All of the modifications which were added to Schedule B will be completed in the respective Cycle 11 or Cycle 12 Refueling Outages. It is not possible to move any of the Cycle 12 projects to Cycle 11, since the outage is already in progress.
Based on the above, there was no need to run the Westinghouse Analytical Ranking Program (WARP) to rank the safety significance of each modification.
The rankings are only used to determine the priority of scheduling work that could not be completed in the next refueling outage.
Expected Percentages Allocation Of Resources On Regulatory And Betterment Projects For The Next Refueling/Modification Outage All (100%) of the resource allocation of the current (Cycle 11) refueling outage is on regulatory projects; there will be no resource allocation on betterment projects.
Approximately 80% of resources for the next (Cycle 12) refueling outage will be-allocated to regulatory projects.
ATTACHMENT 1 INTEGRATED IMPLEMENTATION SCHEDULE A MODIFICATIONS ASSOCIATED WITH RULE, REGULATION OR ORDER Cycle 11 Anticipated Transient Without Scram -
Diverse Turbine Trip (NRC Order, January 2, 1990)
CCW Permanent Fix (Letter to NRC, March 17, 1989)
Charging Pump Motor Rewind (Letter to NRC, March 17, 1989) 480V Overload Modifications (Letter to NRC, March 17, 1989)
EQ of Hot Leg Recirculation System (Letter to NRC, September 5, 1989)
Mid-loop Water Level Indication (RWLI) (GL 88-17)
CVCS Valves MOV-LCV-1100 B, C, and D (NRC Order, January 2, 1990)
Cycle 12 Reactor Vessel Level Indicating System (RVLIS)
(NUREG-0737 and NRC Order, January 2, 1990)
Simulator (Non-Outage Related) - (Letter to NRC, November 2, 1990)
Safety Injection Recirculation System Modifications (Letter to NRC, October 26, 1988)
Safety Injection System Improvements (Letter to NRC, October 26, 1988)
Turbine Deck Steel Plating (NUREG-0612 and NRC Order, January 2, 1990)
Safety Parameter Display System (NRC Order, January 2, 1990)
Control Room Design Review Modifications (All Groups) (NUREG-0737 Supplement 1 and NRC Order, January 2, 1990)
Upgrade Core Exit Thermocouples (To be implemented with Schedule A RVLIS) (NRC Order, January 2, 1990)
Control Room Habitability (Letter to NRC, July 6, 1990)
Addition of Synchrocheck Relays to Emergency Diesel Generators (NRC Order, January 2, 1990)
Undervoltage Relays for Protection from Degraded Grid Voltage (SEP VIII-1.A) (Letter to NRC, August 3, 1990)
Inservice Testing Modifications Vibration Instrumentation for Diesel Oil Transfer Pumps (Letter from NRC, July 30, 1990)
Flow Instrumentation for SI Pumps (Letter to NRC, October 29, 1990)
Steam Generator Overfill Protection (GL 89-19)
Single Failure Analysis, Separation & RG 1.97 (Letter to NRC, May 2, 1990)
Reg. Guide 1.97, Non-Single Failure (Letter to NRC, May 2, 1990)
ATTACHMENT 1 -
(CONTINUED)
INTEGRATED IMPLEMENTATION SCHEDULE A MODIFICATIONS ASSOCIATED WITH RULE, REGULATION OR ORDER ONGOING MAJOR EVALUATIONS REQUIRING SCE SUBMITTAL ITEM TYPE DESCRIPTION SUBMITTAL DATE TMI III.D.3.4 Control Room Habitability May 1991 (Letter to NRC, July 6, 1990)
SEP V-11.B Residual Heat Removal Return To Service (RTS)
System Interlock Cycle 11 Outage Requirements SEP III-5.A Effects of Pipe Breaks on July 31, 1991 III-5.B Structures, Systems, and (Complete 111-7.B Components Inside Analysis)
V-5 Containment, Pipe Break Outside Containment (Letter to NRC, July 30, 1990)
SEP VI-7.C.2 Provide an Integrated June 30, 1991 IX-3 Resolution of Open Items RG 1.97 (Letter to NRC, May 2, 1990)
USI A-46 Seismic Adequacy of Cycle 12 Outage Equipment (Plant Walkdowns) (Letter to NRC, October 7, 1988)
SEP VIII-1.A Adequacy of Station Voltages (Letter to NRC, August 3, 1990)
Submittal of Re-analysis March 31, 1991 Results
S0 ATTACHMENT 2 INTEGRATED IMPLEMENTATION SCHEDULE B MODIFICATIONS ASSOCIATED WITH NRC COMMITMENTS AND OTHER REQUIREMENTS Cycle 11 CV517/518 Actuator Upgrades (LER 89-024,90-005, 90-013)
HV851A/B Backup Nitrogen Upgrade (LER 89-028)
Auxiliary Feedwater Venturi Modification (Letter to NRC, July 3, 1990)
SV2900/SV3900 Valve Upgrade (Letter to NRC, July 25, 1988 and LER 88-004-02)
Boric Acid Gas System Modifications (Letter to NRC, March 5, 1990)
ECCS Single Failure Analysis Modifications (Letter to NRC, July 31, 1990 and LER 90-016)
Environmental Qualification Modifications (LER 90-017)
Cycle 12 Spent Fuel Pool Cooling Pump Modifications (long term exact modifications are to be determined) (Letter to NRC, May 16, 1990)
Emergency Response Data System (GL 89-15)
Vital Bus Retransfer Modification (LER 90-011, Amendment Application #189 submitted September 28, 1990, NRC approval pending)
ATTACHMENT 2 -
(CONTINUED)
INTEGRATED IMPLEMENTATION SCHEDULE B MODIFICATIONS ASSOCIATED WITH NRC COMMITMENTS AND OTHER REQUIREMENTS ONGOING MAJOR EVALUATIONS REQUIRING SCE SUBMITTAL ITEM TYPE DESCRIPTION SUBMITTAL DATE IPE Integrated Plant November 1992 Evaluation (GL 88-20)
ATWS Anticipated Transient Without December 1992 Scram - Diverse Scram System (Letter to NRC, July 23, 1990)
ATTACHMENT 3 INTEGRATED IMPLEMENTATION SCHEDULE C MODIFICATIONS ASSOCIATED WITH BETTERMENT PROJECTS Cycle 11 PASS Upgrade (Ongoing Program)
Cycle 12 HP Turbine Upgrade Battery #2 Replacement Turbine Plant Cooling Water Upgrades