Discusses Evaluation of Lift Rigs for Reactor Coolant Pump Motors & Equipment Hatches Per NUREG-0612.Evaluation Complete.Rigs Will Be Constructed by Westinghouse
ML13310A818
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 07/06/1983
From: Baskin K
Southern California Edison Co
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
REF-GTECI-A-36, REF-GTECI-SF, RTR-NUREG-0612, RTR-NUREG-612, TAC-08082, TAC-8082, TASK-A-36, TASK-OR NUDOCS 8307130248
Download: ML13310A818 (1)


Text

Southern California Edison Company P. 0.

BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD, CALIFORNIA 91770 K. P. BASKIN TELEPHONE MANAGER OF NUCLEAR ENGINEERING, (213) 572-1401 SAFETY, AND LICENSING July 6, 1983 Director, Office of Nuclear Reactor Regulation Attention: D. M. Crutchfield, Chief Operating Reactors Branch No. 5 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C.

20555 Gentlemen:

Subject:

Docket No. 50-206 NUREG-0612, Control of Heavy Loads at.Nuclear Power Plants San Onofre Nuclear Generating Station Unit I

References:

1. Letter, K. P. Baskin, SCE, to D. M. Crutchfield, NRC, NUREG-0612, Control of Heavy Loads at Nuclear Power Plants, January 19, 1983
2. Letter, R. Dietch, SCE, to H. R. Denton, NRC, San Onofre Nuclear Generating Station, Unit 1, June 10, 1983 The referenced letter indicated to you that we will complete our bid evaluation of lift rigs for Lhe reactor coolant pump motors and equipment hatches by September 1, 1983. This evaluation is complete and the lift rigs

-- will -be -constructed -by Westinghouse Electric Corporatibhn.

The completion schedule for these lift rigs andthe modification to the north turbine deck extension are to be established in the resolution of the proposed plan in Reference 2.

If you have any questions, please let me know.

Very truly yours,