ML13203A277

From kanterella
Jump to navigation Jump to search
Nextera'S Reply to Answers to Nextera'S Motion for Summary Disposition of Contention 4D
ML13203A277
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 07/22/2013
From: Doris Lewis
NextEra Energy Seabrook, Pillsbury, Winthrop, Shaw, Pittman, LLP
To:
Atomic Safety and Licensing Board Panel
SECY RAS
References
RAS 24838, 50-443-LR, ASLBP 10-906-02-LR-BD01
Download: ML13203A277 (17)


Text

July 22, 2013 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of )

) Docket No. 50-443-LR NextEra Energy Seabrook, LLC )

) ASLBP No. 10-906-02-LR (Seabrook Station, Unit 1) )

NEXTERAS REPLY TO ANSWERS TO NEXTERAS MOTION FOR

SUMMARY

DISPOSITION OF CONTENTION 4D I. INTRODUCTION NextEra Energy Seabrook, LLC (NextEra) hereby replies to the answers of the NRC Staff and of Friends of the Coast/New England Coalition (FOTC/NEC)1 to NextEras motion for summary disposition of Contention 4D.2 In essence, the NRC Staff takes the position that, in order to determine whether any additional severe accident mitigation alternatives (SAMA) are cost beneficial, the sensitivity (Exposure Index (EI)) analysis performed by NextEra to gauge the possible effect of using a more complex atmospheric dispersion model should be added to upper bound estimates of SAMA benefits derived using the 95th percentile core damage frequency (CDF) as an uncertainty analysis. See, e.g., Staff Answer at 1-2, 10-12.

FOTC/NEC essentially copies the NRC Staffs position, making no effort to provide any expert support of its own to defend any of its original claims. See FOTC/NEC Answer at 3. NextEra respectfully submits that this position is incorrect for two fundamental reasons.

1 NRC Staff Answer to NextEras Motion for Summary Disposition of Friends of the Coast/New England Coalition Contention 4D (SAMA Analysis Atmospheric Modeling) (July 15, 2013) (Staff Answer); Friends of the Coast and New England Coalitions Answer to NextEras Motion for Summary Disposition of Contention 4B (SAMA Source Terms) and Contention 4D (SAMA Analysis Atmospheric Modeling) (July 15, 2013) (FOTC/NEC Answer).

2 NextEras Motion for Summary Disposition of Friends of the Coast/New England Coalition Contention 4D (SAMA Analysis Atmospheric Modeling) (May 10, 2013) (Motion).

First, Commission case law and guidance direct use of mean values (best estimates) in determining whether SAMAs are cost beneficial, consistent with the Commissions obligations under NEPA and its practices in performing cost-benefit analysis. Second, adding the EI sensitivity analysis to the upper bound estimates, which already include a substantial uncertainty factor, is inconsistent with NRC practice and essentially amounts to double counting. The more appropriate conclusion is that the possible impact from using a more complex atmospheric dispersion model is much smaller than, and well within the bounds of, the uncertainty factor that was applied to produce upper bound values.

In addition, even if the Licensing Board were to deny NextEras motion (which as discussed below, it should not), it would still be appropriate to narrow the scope of the issues remaining in contention. As provided in 10 C.F.R. § 2.710(a), all material facts that have not been controverted must be deemed admitted. Here, FOTC/NEC has not controverted - indeed, has explicitly admitted - a multitude of factual statements not only establishing the reasonableness of using the ATMOS dispersion model (embedded in MACCS2) for the SAMA analysis, but also refuting all of FOTC/NECs original claims concerning the appropriateness of using MACCS2 for a 50-mile domain; whether it accounts for sea breeze effects, hot spots, terrain effects, and onsite deposition and re-suspension; and whether use of meteorological data from a single anemometer and year is reasonable. Given these admissions by FOTC/NEC (also agreed to by the Staff with additional expert support), all of these issues should be considered resolved.

II. BACKGROUND As reflected in NextEras Supplement 2 to Severe Accident Mitigation Alternatives (Mar.

19, 2012) (SAMA Supplement), included as Attachment 4D-B to the Staff Answer, the cost-2

benefit analysis of SAMAs provided as part of NextEras application presented a baseline estimate of SAMA benefits with a multiplier of 2.1 relating to seismic risk, and an additional estimate reflecting inclusion of uncertainty. See SAMA Supplement, Table 1. NextEra described this approach in its discussion of SAMA Sensitivity Assessments (id. at 33), which also included numerous other sensitivity analyses, and under the heading Sensitivity to Upper Bound Accident Costs, explained:

The nominal cost-benefit assessment considers the mean (best estimate) core damage/accident release frequencies derived from the Seabrook SB2011 PRA.

To account for upper bound uncertainty in the PRA model results, the best estimate accident costs are multiplied by an uncertainty factor of 2.35 to represent the cost-benefit associated with the 95th percentile (upper bound) accident release impacts. The increase factor of 2.35 is based on the ratio of the best estimate CDF mean value of 1.23E-05/yr to the CDF upper bound (95th percentile) value of 2.86E-05/yr. This approach is consistent with the NEI 05-01 industry guidance.

The upper bound cost-benefit of each SAMA candidate is considered when judging the candidate as being potentially cost-beneficial. Although this approach is consistent with NRC expectation for identification of potentially cost-beneficial SAMAs, it is noted that final determination of cost and benefit would include a more realistic assessment of both the cost of a specific modification and its associated value in risk reduction.

Id. at 35. As this discussion makes clear, while NextEra considered whether uncertainty might make additional SAMAs cost beneficial,3 final determinations of cost benefit are based on realistic assessment.

In its motion for summary disposition of Contention 4D, NextEra performed an additional sensitivity analysis to compare the results of wind roses produced using CALMET 3

In the Affidavit accompanying the Staff Answer,3 the NRC Staff states that NextEra identified three SAMAs as being potentially cost-beneficial in its baseline analysis, three additional SAMAs as potentially cost-beneficial from its uncertainty analysis, and one further SAMA as being cost-beneficial based on the seismic multiplier.

Affidavit of John G. Parillo Concerning NextEras Motion for Summary Disposition of Friends of the Coast/New England Coalition Contention 4D (SAMA Analysis Atmospheric Modeling) (July 15, 2013) at ¶¶ 9-11. It is unclear why the NRC Staff parsed the potentially cost-beneficial SAMA in this manner. As NextEras SAMA analysis shows, six SAMAs were identified as potentially cost-beneficial using the baseline analysis with seismic multiplier, and the uncertainty analysis indicated that one additional SAMA might be cost-beneficial. See SAMA Supplement, Table 1.

3

with the annual wind rose for the Seabrook Station used in the MACCS2 analysis. Motion at 65.

This Exposure Index analysis was specifically described as a sensitivity analysis4 providing an indication of the change in risk that could result from using the CALMET based trajectory rose instead of the Seabrook Station wind rose reflected in the SAMA analysis. Motion at 65-66.

The EI sensitivity analysis estimated a potential increase of approximately 32% in total averted costs (id. at 67) and evaluated the potential effect on the SAMA closest to becoming cost-beneficial (SAMA #77), based on the best estimate with seismic multiplier to quantify this total benefit. Id. at 68. As reflected in the Motion, [i]ts best estimate (with seismic risk multiplier) total benefit of $6.41 million would need to increase by more than a factor of two in order to meet or exceed the expected SAMA cost of more than $15 million. Id. See also Joint Declaration of Dr. Steven R. Hanna and Dr. Kevin R. OKula in Support of NextEras Motion for Summary Disposition of Contention 4D (SAMA Analysis Atmospheric Modeling) (May 10, 2013) at ¶ 131 (Joint Declaration). As discussed below, NextEras use of best estimate (i.e.

mean) values is consistent with NRC precedent and guidance.

III. SAMA ANALYSIS IS BASED ON MEAN VALUES (BEST ESTIMATES)

Two basic tenets of NEPA law are germane to whether mean (best estimate) or upper bound estimates should be used to determine whether SAMAs are cost beneficial. First, NEPA does not require analysis of worst-case scenarios. Robertson v. Methow Valley Citizens Counsel, 490 U.S. 332, 333 (1989).

[Council on Environmental Quality] explained that by requiring that an EIS focus on reasonably foreseeable impacts, the new regulation will generate information and discussion on those consequences of greatest concern to the public and of greatest relevance to the agencys decision, rather than distorting the decision-4 The analysis was presented in a report entitled Exposure Index Study Using MACCS2 and CALMET: A Sensitivity Study Supporting the Seabrook Station SAMA Analysis, (EI Report), provided as Attachment 4 to the Motion.

4

making process by overemphasizing highly speculative harms. [The] regulation is entitled to substantial deference.

Id. at 356 (citations omitted).5 Therefore, a NEPA analysis should estimate realistic consequences, not the worst-case scenario.

Second, NEPA requirements are tempered by a practical rule of reason. Entergy Nuclear Generation Co. (Pilgrim Nuclear Power Station), CLI-10-22, 72 N.R.C. 202, 208 (2010), citing Communities, Inc. v. Busey, 956 F.2d 619, 626 (6th Cir. 1992); Hells Canyon Alliance v. United States Forest Serv., 227 F.3d 1170, 1184-85 (9th Cir. 2000). See also Entergy Nuclear Generation Co. (Pilgrim Nuclear Power Station), CLI-10-11, 71 N.R.C. 287, 315-16 (2010). Accordingly, NEPA requires only a reasonable mitigation alternatives analysis, containing reasonable estimates, including, where appropriate, full disclosures of any known shortcomings in available methodology, disclosure of incomplete or unavailable information and significant uncertainties, and a reasoned evaluation of whether and to what extent these or other considerations credibly could or would alter the Pilgrim SAMA analysis conclusions on which SAMAs are cost-beneficial to implement.

Pilgrim, CLI-10-22, 72 N.R.C. at 208-09 (citations omitted).

Consistent with these principles, the Commission has explained that:

NRC SAMA analysis is neither a worst-case nor a best-case impacts analysis. It is NRC practice to utilize the mean values of the consequence distributions for each postulated release scenario or category - the mean estimated value for predicted total population dose and predicted off-site economic costs. These mean consequence values are multiplied by the estimated frequency of occurrence of specific accident scenarios to determine population dose risk and offsite economic cost risk for each type of accident sequence studied. There is in SAMA analysis, therefore, an averaging of potential consequences. As a policy matter, license renewal applicants are not required to base their SAMA analysis upon consequence values at the 95th percentile consequence level (the level used for the GEIS severe accident environmental impacts analysis).

5

[W]orst-case scenarios need not be considered because their consideration involves the arduous and unproductive task of analyzing conceivable, but very speculative, catastrophes and diverts NRCs limited resources from other more productive efforts. Private Fuel Storage, L.L.C. (Independent Spent Fuel Storage Installation), CLI-02-25, 56 N.R.C. 340, 354 (2002).

5

Pilgrim, CLI-10-11, 71 N.R.C. at 316-17 (emphasis in original) (footnote omitted). Further, the Commission has agreed that use of 95th percentile values are essentially a worst case analysis not required by NEPA.

As the Board in LBP-11-18 states, the 95[th] percentile is akin to a worst-case scenario analysis. And the Supreme Court expressly has held that NEPA does not require a worst case inquiry. We ourselves have stated that to require worst case analyses can easily lead to limitless NEPA analyses because it is always possible to introduce yet another additional variable to a hypothetical scenario to conjure up a worse worst case.

Entergy Nuclear Generation Co. (Pilgrim Nuclear Power Station), CLI-12-1, 75 N.R.C. 39, 56-57 (2012) (footnotes omitted).6 The Commissions admonition to use mean values is consistent not only with NEPA, but also consistent with Commission policy on probabilistic risk assessment (PRA) and cost-benefit analysis. In its Safety Goals Policy Statement (51 Fed. Reg. 30,028, 30,031 (Aug. 21, 1986)), the Commission adopted the use of mean estimates for implementing the quantitative objectives of the safety goal policy. In its policy statement on the use of PRA in nuclear regulatory activities, the Commission affirmed that PRA evaluations in support of regulatory decisions should be as realistic as practicable. 60 Fed. Reg. 42,622, 42,629 (Aug. 16, 1995)

(emphasis added). Thus, the cost-benefit portion of a SAMA analysis looks at the average case, not the worst case, in determining whether a SAMA would be potentially cost beneficial.

Otherwise, the cost benefit analysis would be skewed.

In the same vein, the NRCs Regulatory Analysis Guidelines state:

Value and impact estimates are to be incremental best estimates relative to the baseline case. . . .

6 While these holdings relate to the consequence portion of risk assessment, there is no reason why probability estimates would be treated any differently.

6

When possible, best estimates should be made in terms of the mean or expected value. However, depending upon the level of detail available from the data sources employed in the regulatory analysis, acceptable estimates could include other point estimates such as the median. However, the rationale for use of estimates other than mean values should be provided.

NUREG/BR-0058, Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory Commission (Rev. 4, Sept. 2004) (Guidelines) at 23 (emphasis added).7 The NRC Handbook implementing these guidelines states:

Section 4.3 of the [Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory Commission] requires the use of best estimates. Often these are evaluated in terms of the mean or "expected value," the product of the probability of some event occurring and the consequences which would occur assuming the event actually happens. Sometimes, measures other than the expected value may be appropriate, such as the median or even a point estimate. However, the expected value is generally preferred.

NUREG/BR-0184, Regulatory Analysis Technical Evaluation Handbook (Jan. 1997)

(Handbook) at 4.7, 5.20 (emphasis added).

Both the NRC Regulatory Analysis Guidelines and Handbook also call for uncertainty analysis, which may include presentation of upper and lower bounds or best and worst-case values. See, e.g., Guidelines at 23; Handbook at 5.7 to 5.8. But uncertainty analysis is presented to provide perspective; neither the Guidelines nor the Handbook contemplate using upper-bound estimates to determine if an action is cost-beneficial (which would obviously be inconsistent with the clear direction to use mean values).

7 The NRCs Regulatory Analysis Guidelines consider OMB guidelines issued pursuant to various executive orders.

For example, OMB Circular A-4, Regulatory Analysis (Sept, 17, 2003) states:

Where there is a distribution of outcomes, you will often find it useful to emphasize summary statistics or figures that can be readily understood and compared to achieve the broadest public understanding of your findings. It is a common practice to compare the best estimates of both benefits and costs with those of competing alternatives. These best estimates are usually the average or the expected value of benefits and costs. Emphasis on these expected values is appropriate as long as society is risk neutral with respect to the regulatory alternatives. While this may not always be the case, you should in general assume risk neutrality in your analysis. If you adopt a different assumption on risk preference, you should explain your reasons for doing so.

OMB Circular A-4 at 42.

7

Consistent with Commission direction, NRC-endorsed guidance on preparation of SAMA analysis indicate that cost-benefit analysis of SAMAs should use baseline risk measures using mean values (NEI 05-01 at 15-17, 22, 27-28).8 Sensitivity analysis, including a discussion of uncertainty, is then performed to evaluate how changes in assumptions would affect the cost benefit analysis. Id. at 30. As explained in that guidance:

A discussion of CDF uncertainty, and conservatisms in the SAMA analysis that off-set uncertainty, should be included. For example, use of conservative risk modeling to represent a particular plant change may be used to offset uncertainty in risk modeling; use of conservative implementation cost estimates may be used to offset uncertainty in cost estimates; and use of an uncertainty factor derived from the ratio of the 95th percentile to the mean point estimate for internal events CDF may be used to account for CDF uncertainties. Estimate an uncertainty factor based on this discussion and perform a sensitivity analysis using the uncertainty factor on the results. [Based on analysis to date the ratio of the 95th percentile to the mean point estimate for typical internal events CDF values is 2 to 5 (Reference 1).]

Provide pertinent results and discuss how they affect the conclusions of the SAMA analysis. If SAMAs appear cost-beneficial in the sensitivity results, discussion of conservatisms in the analysis, (e.g., conservatisms in cost estimates discussed in Section 7.2), and their impact on the results may be appropriate.

Id. at 30. Thus, the results of uncertainty analysis may prompt further discussion of the conservatisms in the analysis,9 but they are not used to determine whether a SAMA is cost-beneficial.

8 See Notice of Availability of the Final License Renewal Interim Staff Guidance LR-ISG-2006-03: Staff Guidance for Preparing Severe Accident Mitigation Alternatives Analyses, 72 Fed. Reg. 45,466 (Aug. 14, 2007)

(The NRC staff recommends that applicants for license renewal follow the guidance provided in Nuclear Energy Institute (NEI) 05-01, Severe Accident Mitigation Alternatives (SAMA) Analysis Guidance Document, Revision A, when preparing their SAMA analyses.). See also Regulatory Guide 4.2, Supp. 1, Preparation of Environmental Reports for Nuclear Power Plant License Renewal Applications (June 2013) at 44 (In structuring the analysis, the applicant should consider the methodology presented in NUREG/BR-0184, Regulatory Analysis Technical Evaluation Handbook, issued January 1997, and the guidance provided in NEI 05-01, Revision A, Severe Accident Mitigation Alternatives (SAMA) Analysis, Guidance Document, issued November 2005.).

9 The discussion of the Seabrook SAMA analysis includes considerable discussion of such conservatism. As the draft SEIS states, The majority of the SAMA evaluations were performed in a bounding fashion in that the SAMA was assumed to eliminate the risk associated with the proposed enhancement. On balance, such calculations overestimate the benefit and are conservative. The NRC staff reviewed NextEras bases for calculating the 8

The position taken by the NRC Staff and echoed by FOTC/NEC that upper bound estimates should be used appears based solely on dicta in one of the Commission decisions in the Pilgrim license renewal proceeding. Staff Answer at 11-12, citing Pilgrim, CLI-12-1, 75 N.R.C.

at 58. In that case, the Licensing Board had ruled that an intervenors claim that the 95th percentile of consequence values should be used rather than the mean had not been raised as part of the admitted SAMA contention in the proceeding. See Pilgrim, CLI-12-1, 75 N.R.C. at 55.

After affirming this ruling, the Commission added:

We further note that in a highly predictive analysis such as a SAMA analysis, there are bound to be significant uncertainties, and therefore an uncertainty analysis is performed. Baseline analysis results therefore are multiplied by an uncertainty factor. The final cost-benefit comparisons are based not on the baseline analysis results, but on revised results that take into account an uncertainty factor. Pilgrim Watch does not address the additional uncertainty analysis.

risk reduction for the various plant improvements and concludes that the rationale and assumptions are reasonable and generally conservative (i.e., the estimated risk reduction is higher than what would actually be realized).

NUREG-1437, Supp. 46, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 46 Regarding Seabrook Station, Second Draft Report for Comment (April 2013) (DSEIS) at 5-13.

See also id. at F-33. Further, in estimating the cost of SAMAs, [t]he cost estimates, conservatively, did not specifically account for inflation, contingencies, implementation obstacles, or replacement power costs (RPC).

DSEIS at 5-13, F-45. Moreover, the bases for calculating the risk reduction for the various plant improvements are generally conservative (i.e., the estimated risk reduction is higher than what would actually be realized). Id.

at F-34. As also discussed in the draft SEIS, NextEra examined five years of meteorological data and chose the most conservative for its baseline estimates. Id. at F-22. Use of the meteorological data from the other years examined would have decreased the population dose risk in the range of 5 to 13 percent and decreased the offsite economic risk by 3 to 12 percent. Id. The baseline analysis also included perpetual rainfall in the 40-50 mile spatial segment. Id. If measured rainfall had been used, the population dose risk would have decreased by 14 percent and the offsite economic risk would have decreased by 15 percent. Id. Increased plume mixing and dispersion associated with the formation of a mixing front was conservatively ignored. Id. at F-24. The evacuation time used in the baseline analysis was based on estimates under adverse weather conditions and assumed a lower percentage of the population evacuating than was assumed in NRC risk assessment. Id. at F-23.

And NextEra applied a multiplier of 2.1 to its baseline risk estimates (separate from the uncertainty analysis) to account for the potential impact of revised seismic hazard curves. Id. at F-18. Moreover, as reflected in the Declaration of Randy Gaunnt Concerning NextEras Motion for Summary Disposition of Friends of the Coast/New England Coalition Contention 4B (July 15, 2013) at ¶¶ 30-31, 33-35, the release fractions used in NextEras SAMA analysis are also conservative.

9

Id. at 58 (citing Pilgrim SEIS,10 Vol. 2, at G-41, where revised baseline benefits were increased by a factor of 1.62, the ratio of the 95th percentile core damage frequency (CDF) to the mean CDF). This statement is dicta because it was unrelated to holding that a challenge to use of mean values had not been timely raised. Further, the Commissions statement that final cost benefit comparisons are based on revised results that take into account an uncertainty factor was not based on any Licensing Board ruling or on the briefs before the Commission,11 but rather appears to have been based simply on the Commissions own reading of the Pilgrim SEIS. Moreover, the Pilgrim SEIS cited by the Commission does not refer to any general practice. To the contrary, the page of the Pilgrim SEIS cited by the Commission states that the NRC staff requested that the baseline evaluation be revised to include only the impact of internal and external events (without uncertainties), and that the impact of the analysis of uncertainties on the SAMA evaluation be considered separately. . . . Pilgrim SEIS, supra note 10, Vol. 2 at G-41.

It goes on to discuss the results of uncertainty analysis, and observes:

Entergy reexamined the Phase II SAMAs to determine if any would be potentially cost beneficial if the revised baseline benefits were increased by an additional factor of 1.6. No additional SAMAs were identified.

Id. That Entergy chose to consider whether the results of the uncertainty analysis might affect its cost-benefit conclusions in no way implies that final cost benefit comparisons are based on revised results that take into account an uncertainty factor. Thus, the dicta in CLI-12-1 should 10 NUREG-1437, Supp. 29, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 29 Regarding Pilgrim Nuclear Power Station (July 2007) (Pilgrim SEIS).

11 See Pilgrim: Memorandum and Order (Ruling on Timeliness of Mean Consequence Values Issue) (Mar. 3, 2011)

(ADAMS Accession No. ML110620363); NRC Staffs Answer to Pilgrim Watchs Request for Review of the Licensing Boards July 19, 2011 Partial Initial Decision (LBP-11-18) (Aug. 15, 2011) at 17-20 (ADAMS Accession No. ML11227A290); Entergys Answer Opposing Pilgrim Watchs Request for Review (Aug. 15, 2011) at 17-20 (ADAMS Accession No. ML11227A296). See also NRC Staff Brief Regarding Timeliness of Pilgrim Watchs Raising of Means Consequences Concern (Oct. 1, 2010) (ADAMS Accession No. ML102770491); NRC Staffs Reply to Pilgrim Watchs Brief (Oct. 8, 2010) (ADAMS Accession No. ML102810699).

10

not overrule the numerous Commission pronouncements that cost-benefit analysis should be based on best estimates (mean values).

The position taken by the Staff also appears inconsistent with its position and the disposition of a similar contention in the Pilgrim proceeding. In assessing whether a more complex dispersion model might change SAMA results in the Pilgrim proceeding, the Staff testified that next most cost-beneficial SAMA was more than a factor of two greater than its benefit.12 Review of the results of the Pilgrim SAMA analysis, which are contained in Table G-4 of the Pilgrim SEIS, indicates that this next most cost-beneficial SAMA was SAMA #8, with a implementation cost (>$5,000,000) more than twice the benefit ($2,410,000).13 The $2,410,000 benefit for SAMA #8 in Table G-4 of the Pilgrim SEIS is taken from Pilgrims Revised Summary of Phase II SAMA Analysis and is the baseline benefit without uncertainty.14 It is therefore very surprising that the Staff is taking a different position in the Seabrook proceeding.

Finally, it should be recognized that a contention advocating use of 95th percentile consequence levels was rejected in this proceeding. Seabrook, LBP-11-2, 73 N.R.C. 28, 77 (2011). It is therefore inappropriate to now deny summary disposition of Contention 4D based 12 Pilgrim, Exhibit NRC-14, NRC Staff Testimony of Nathan E. Bixler and S. Tina Ghosh Concerning the Impact of Alternative Meteorological Models on the Severe Accident Mitigation Alternatives Analysis at ¶ A42 (ADAMS Accession No. ML110330544); Pilgrim, Exhibit NRC-15, NRC Staff Testimony of James V. Ramsdell, Jr.

Concerning the Impact of Specific Meteorological Conditions On the Severe Accident Mitigation Analysis at ¶ A36 (ADAMS Accession No. ML110600934) (Using the values in the [Pilgrim] FSEIS, an increase in the value of the offsite consequences by a factor of about 2.5 would be needed to make the next lowest cost SAMA appear cost-beneficial). (Note that an increase in offsite consequences of about 2.5 translated into an increase of closer to 2 in benefit, because offsite consequences only constituted a percentage of total risk.) See also Entergy Nuclear Generation Co. (Pilgrim Nuclear Power Station), LBP-11-18, 74 N.R.C 29, 40-41, 48-50 (2011).

13 Pilgrim SEIS, supra note 10, Vol. 2 at G-28 (Table G-4); Pilgrim, Exhibit ENT-1, Testimony of Dr. Kevin R.

OKula and Dr. Steven R. Hanna on Meteorological Matters Pertaining to Pilgrim Watch Contention 3 at ¶¶ A46-A47 (ADAMS Accession No. ML110030985) (identifying this next most cost-beneficial SAMA as SAMA #8, with a implementation cost (>$5,000,000) of more than twice the benefit ($2,410,000), based on the results in Table G-4 of the Pilgrim SEIS).

14 See Pilgrim, Exhibit ENT-7, License Renewal Application Amendment 4, at 35 (Table RAI.3-2 Revised Summary of Phase II SAMA Analysis) (ADAMS Accession No. ML110600873).

11

on an argument that 95th percentile values should be used to determine whether SAMAs are cost-beneficial.

IV. ADDING THE EI SENSITIVITY ANALYSIS TO UPPER BOUND ESTIMATES IS DOUBLE COUNTING The Staffs position that the EI sensitivity analysis should be added to upper bound estimates is also inconsistent with the manner in which the NRC performed sensitivity and uncertainty analysis. As reflected in the DSEIS, a multiplier of 2.35 was derived from the ratio of the CDF mean value to the 95th percentile to account for uncertainty. Thus, in effect, the upper bound CDF was used as a surrogate for general analytic uncertainty. Multiple other sensitivity analyses were also performed.15 Other than the sensitivity analysis of the impact of updated seismic hazard curves (which resulted in a seismic multiplier of 2.1 that NextEra factored into its cost-benefit analysis16), the results of these sensitivity analyses were small compared to the 2.35 uncertainty multiplier. Aside from the seismic multiplier, none of the other sensitivity-analysis results were added to the uncertainty analysis.

15 See generally SAMA Supplement at 33-35(describing sensitivity analyses relating to Annual Met Data Set, Meteorology Specification in last Spatial Segment, Sea-breeze Sensitivity, Release Category LE4 Sensitivity to No Evacuation, Sensitivity to Variation in Other Level 3 Parameters, Sensitivity to Variation in Discount Rate, Sensitivity to Extended Period, Sensitivity to Upper Bound Accident Costs, and Sensitivity to Increased Seismic Risk); DSEIS at 5-11 to 5-12. As described in the DSEIS, four sensitivity analyses were performed varying the release height of a plume. DSEIS at F-21. Two sensitivity analyses were performed varying the thermal content of each release. Id. Two sensitivity analyses were performed varying building wake effects. Id. at F-21 to F-22.

Sensitivity analyses were performed using meteorological data from four other years. Id. at F-22. Several sensitivity analyses were performed using refined population projections. Multiple sensitivity analyses were performed varying evacuation speed and delays, including analysis assuming no evacuation. Id. Sensitivity analyses were performed increasing the frequency of thermal internal boundary (TIBL) and TIBL lid height. Id.

at F-24. A sensitivity analysis was performed to consider the impact of updated seismic hazard curves. Id. at F-2, F-13, F-18, F-25-26, F-46. Two sensitivity analyses were performed varying the discount rate. Id. at F-51, F-57.

And, a sensitivity analysis was performed increasing the analysis period to encompass not only the period of extended operation but also the remaining term on the current license. Id. at F-51.

16 In determining whether SAMAs may be cost-beneficial, NextEra applied its baseline estimates with seismic multiplier included, both in its LRA (see SAMA Supplement, Table 1), and in its summary disposition motion (Joint Declaration at ¶ 131).

12

For example, NextEras sensitivity analysis of extending the analyzed period of extended operation from 20 to 41 years determined that the cost-benefit worth during the extended period would be greater by a factor of 1.3. SAMA Supplement at 35. This increase was not added to the upper bound estimates. Instead, NextEra concluded that the increased benefit was significantly less than the upper bound (95th percentile) [cost-benefit worth] (id.) and that The cost-benefit worth of all SAMA candidates assuming the 41 year extended period is shown to be less than the SAMA cost-benefit worth when considering the uncertainty (upper bound) benefit.

Id. Thus, the effect of a sensitivity analysis of magnitude very close to that estimated by the EI analysis was considered by comparison to the uncertainty value, not by addition to it.

There is no basis to treat the EI sensitivity analysis results any differently. The potential increase of approximately 30 percent indicated by the EI analysis is well within (less than a fourth of) the uncertainty multiplier and therefore already adequately accounted for in the uncertainty analysis.17 Further, there are many sensitivity analysis results that could be added to the uncertainty factor, which would make the upper bound estimates increasingly unrealistic. Indeed, adding the results of every sensitivity analysis to the upper bound estimates, and using those upper bound estimates for cost-benefit determinations, would in the end produce the sort of worst case analyses that the Commission has cautioned could easily become limitless. See Pilgrim, CLI-12-1, 75 N.R.C. at 56-57.

In sum, NextEras summary disposition motion presented a sensitivity analysis to show that a more complex dispersion model would not be expected to produce results significantly 17 The potential 30-percent increase suggested by the EI analysis is also similar in magnitude to the conservatisms recognized in the DSEIS. See supra note 9.

13

different than the ATMOS model embedded in MACCS2, and therefore that use of MACCS2 meets the standard of reasonableness. The sensitivity analysis demonstrated this. Further, both the NRC Staff and FOTC/NEC have admitted that:

The ATMOS model is reasonable for a SAMA analysis because that analysis is focused on calculating integrated (summed) mean annual consequences over a broad region (50-mile radius). Short-term fluctuations in wind direction and terrain effects have little effect on the summed consequences over the entire geographic domain.

An extensive study (Molenkamp et al. (2004), NUREG/CR-6853) demonstrates that the MACCS2 ATMOS Gaussian plume segment model results are within the same range as more complex dispersion models that account for variable meteorological and terrain effects.

More accurate modeling of the sea breeze phenomenon would not significantly alter the overall impacts estimated by MACCS2/ATMOS.

The CALMET trajectory analysis confirms that consideration of time and spatially variable wind fields, such as sea breezes, would have no significant impact on the SAMA analysis results.18 Nothing more is required to address the basic claim in Contention 4D that NextEra used an inappropriate air dispersion model and meteorological data inputs. See Pilgrim, CLI-12-1, 75 N.R.C. at 57 (To be litigable in an NRC hearing, a SAMA contention must identify a deficiency that could credibly render the SAMA analysis altogether unreasonable under NEPA standards).

In light of all parties agreement that the MACCS2 modeling was reasonable, further proceedings to point out that the EI sensitivity results were well within the bounds of the uncertainty multiplier (already apparent from the record), or to discuss the conservatisms in the modeling offsetting uncertainty (already discussed in the DSEIS19) would contribute little to the decision making in this proceeding.

18 NRC Staff Response to NextEras Statement of Material Facts for Contention 4D (SAMA Analysis Atmospheric Modeling) (July 15, 2013) at ¶¶ 6-7, 13-14; Friends/NEC Response NextEras Statement of Material Facts for Contention 4D (SAMA Analysis Atmospheric Modeling) (July 15, 2013) at ¶¶ 6-7, 13-14.

19 See supra note 9.

14

V. ALL UNCONTROVERTED STATEMENTS OF MATERIAL FACT SHOULD BE DEEMED ADMITTED Even if the Licensing Board denies NextEras motion, it should nevertheless narrow the scope of the issues remaining in controversy by treating as admitted all uncontroverted statements of material fact set forth in NextEras Statement of Material Facts (May 10, 2013),

provided in support of the motion for summary disposition of Contention 4D. Pursuant to 10 C.F.R. § 2.710(a), [a]ll material facts set forth in the statement required to be served by the moving party will be considered admitted unless controverted by the statement required to be served by the opposing party. Thus, the Board may grant summary disposition with respect to uncontroverted matters. See, e.g., Texas Utilities Co. (Comanche Peak Steam Electric Station, Units 1 and 2), LBP-84-44, 20 N.R.C. 1340, 1353-55 (1984); Pennsylvania Power & Light Co.

(Susquehanna Steam Electric Station, Units 1 and 2), LBP-81-8, 13 N.R.C. 335, 341-43 (1981).20 Here, both the NRC Staff and FOTC/NEC have admitted NextEras statements 1-9 and 12-23 of NextEras Statement of Facts,21 not only agreeing to the reasonableness of the MACCS2 modeling but also resolving the underlying claims concerning the appropriateness of using MACCS2 for a 50-mile domain; consideration of sea breeze effects, hot spots, terrain effects, and onsite deposition and re-suspension; and use meteorological data from a single anemometer and year. Indeed, FOTC/NEC copies the NRC Staffs admission of these facts verbatim and makes no effort to provide any expert support of its own in defense of any of its 20 Granting summary disposition with respect to the uncontroverted statements of fact would further the purpose of summary disposition to provide an efficacious means of avoiding unnecessary and possibly time-consuming hearings on demonstrably insubstantial issues. . . . See Houston Lighting & Power Co. (Allens Creek Nuclear Generating Station, Unit 1), ALAB-590, 11 N.R.C. 542, 550 (1980). See also Statement of Policy on Conduct of Licensing Proceedings, CLI-81-8, 13 N.R.C. 452, 457 (1981) (encouraging Boards to use the summary disposition process where the proponent of a contention has failed to establish that a genuine issue exists, so that evidentiary hearing time is not unnecessarily devoted to such issues.)

21 NRC Staff Response to NextEras Statement of Material Facts for Contention 4D (SAMA Analysis Atmospheric Modeling) (July 15, 2013); Friends/NEC Response NextEras Statement of Material Facts for Contention 4D (SAMA Analysis Atmospheric Modeling) (July 15, 2013).

15

original claims. Given the parties admission of these facts and FOTC/NECs failure to make any effort on its own to defend its contention, all of the uncontroverted statements of fact should be deemed admitted and resolved in this proceeding.

VI. CONCLUSION For all the reasons discussed above, the Board should grant NextEras motion for summary disposition of Contention 4D.

Respectfully Submitted,

/Signed electronically by David R. Lewis /

Steven C. Hamrick David R. Lewis NextEra Energy Seabrook, LLC Pillsbury Winthrop Shaw Pittman LLP 801 Pennsylvania Avenue, NW Suite 220 2300 N St. NW Washington, DC 20004 Washington, DC 20037 Telephone: 202-349-3496 Telephone: 202-663-8474 Dated: July 22, 2013 Counsel for NextEra Energy Seabrook, LLC 16

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of )

) Docket No. 50-443-LR NextEra Energy Seabrook, LLC )

) ASLBP No. 10-906-02-LR (Seabrook Station, Unit 1) )

CERTIFICATE OF SERVICE I hereby certify that the foregoing NextEras Reply to Answers to NextEras Motion for Summary Disposition of Contention 4D has been served through the E-Filing system on the participants in the above-captioned proceeding, this 22nd day of July 2013.

/Signed electronically by David R. Lewis/

David R. Lewis