Acceptance Review Results Regarding Ultimate Heat Sink License Amendment Requests
ML13192A240
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 07/30/2013
From: James Kim
Plant Licensing Branch 1
To: Heacock D
Dominion Nuclear Connecticut
Kim J
References
TAC MF1779, TAC MF1780
Download: ML13192A240 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 30, 2013 Mr. David A Heacock President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT NOS. 2 AND 3 - ACCEPTANCE REVIEW RESULTS REGARDING ULTIMATE HEAT SINK LICENSE AMENDMENT REQUESTS (TAC NOS. MF1779 AND MF1780)

Dear Mr. Heacock:

By letter dated May 3,2013, Dominion Nuclear Connecticut, Inc., the licensee, submitted license amendment requests (LAR) to increase the current ultimate heat sink water temperature limit from 75 degrees Fahrenheit to 80 degrees Fahrenheit for Millstone Power Station, Unit Nos. 2 and 3 (Millstone 2 and 3). The purpose of this letter is to provide the results of the Nuclear Regulatory Commission (NRC) staffs acceptance review of this LAR. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required.

This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your applications dated May 3, 2013, and supplemental information dated June 27, 2013 for Millstone 2 and July 2, 2013 for Millstone 3, and concluded that they do provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendments in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical reView, there may be instances in which issues that impact the NRC staff's ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.

D. Heacock -2 If you have any questions, please contact me at (301) 415-4125.

Sincerely, James Kim, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No(s). 50-336 and 50-423 cc: Distribution via Listserv

D. Heacock -2 If you have any questions, please contact me at (301) 415-4125.

Sincerely, Ira!

James Kim, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No(s). 50-336 and 50-423 cc; Distribution via Listserv DISTRIBUTION; PUBLIC RidsN rrDorlLpl1-1 RidsNrrPM Millstone LPL1-1 RlF RidsNrrLAKGoldstein RidsAcrsAcnw_MaiICTR RidsNrrDorlDpr RidsRgn1 MailCenter GPurciarello, NRR RidsOGCMailCenter RidsNrrDssSbpb RWolfgang, NRR RisNrrDeEpnb PSahay. NRR RidsNrrDeEeeb GCooper, NRR RidsNrrDraAfpb BTitus. NRR MHamm, NRR RidsNrrDssStsb KBucholtz. NRR ADAMS Accession No. ML13192A240 OFFICE NRRlDORULPL1-1/PM NRRlDORULPL1-1/LA NRRlDORULPL1-1/BC (A) NRR/DORULPL1-1/PM NAME JKim KGoldstein RBeall JKim DATE 7/30/2013 7/12/2013 7/30/2013 7/3012013 OFFICIAL RECORD COpy