Other: L-13-376, Addendum to the Beaver Valley Power Station, Unit No. 1, Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, ML13135A229, ML13135A230, ML13135A231, ML13135A233, ML13135A234, ML13135A235, ML13135A236, ML13135A237, ML13135A238, ML13135A240, ML13135A241, ML13135A242, ML13135A243, ML13135A244, ML13135A245, ML13135A246, ML13135A247, ML13135A248, ML13135A249, ML13135A251, ML13151A052, ML13295A695, ML14009A089
|
MONTHYEARL-12-242, FENOC Response to NRC Request for Information Pursuant 10 CFR 50.54(f) Seismic Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident2012-07-10010 July 2012 FENOC Response to NRC Request for Information Pursuant 10 CFR 50.54(f) Seismic Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident Project stage: Response to RAI ML13135A2422012-08-10010 August 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Cover Through Page 176 Project stage: Other ML13135A2432012-08-10010 August 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix a - Resumes and Qualifications Project stage: Other ML13135A2442012-08-10010 August 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B - Seismic Walkdown Checklists (Swcs), Sheet 1 of 379 Through Sheet 201 of 379 Project stage: Other ML13135A2452012-08-10010 August 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B - Seismic Walkdown Checklists (Swcs), Sheet 202 of 379 Through Sheet 379 of 379 Project stage: Other ML13135A2462012-08-10010 August 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix C - Area Walk-by Checklists (Awcs) Through End Project stage: Other ML13135A2292012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendices C Through End Project stage: Other ML13135A2472012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Cover Through Page 153 Project stage: Other ML13135A2482012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix a - Resumes and Qualifications Project stage: Other ML13135A2492012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B - Seismic Walk-Down Checklists (Swcs), Sheet 1 of 461 Through Sheet 203 of 461 Project stage: Other ML13135A2512012-09-28028 September 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B - Seismic Walk-Down Checklists (Swcs), Sheet 204 of 461 Through Sheet 461 of 461 Project stage: Other ML13135A2302012-10-23023 October 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Project stage: Other ML13135A2312012-10-23023 October 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix a - Resumes and Qualifications Project stage: Other ML13135A2332012-10-23023 October 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B - Seismic Walkdown Checklists (Swcs), Sheet 1 of 439 Through Sheet 200 of 439 Project stage: Other ML13135A2342012-10-23023 October 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B - Seismic Walkdown Checklists (Swcs), Sheet 201 of 439 Through Sheet 439 of 439 Project stage: Other ML13135A2352012-10-23023 October 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendices C Through E Project stage: Other ML13135A2362012-10-31031 October 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Project stage: Other ML13135A2372012-10-31031 October 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix a - Resumes and Qualifications Project stage: Other ML13135A2412012-10-31031 October 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix C - Area Walk-by Checklists (Awcs) and Appendix D - Component List for Anchorage Configuration Check Project stage: Other ML13135A2402012-10-31031 October 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B - Seismic Walkdown Checklists (Swcs), Sheet 302 of 513 Through Sheet 513 of 513 Project stage: Other ML13135A2382012-10-31031 October 2012 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B - Seismic Walkdown Checklists (Swcs), Sheet 1 of 513 Through Sheet 301 of 513 Project stage: Other ML13008A0292012-11-27027 November 2012 FENOC Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident Project stage: Response to RAI L-12-347, FENOC Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Flooding Aspects of Recommendation 2.3 of Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident2012-11-27027 November 2012 FENOC Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Flooding Aspects of Recommendation 2.3 of Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident Project stage: Response to RAI L-13-118, Resubmittal of FENOC Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Seismic Aspects of Recommendation 2.3 of Near-Term Task Force Review of Insights from Fukushima2013-04-29029 April 2013 Resubmittal of FENOC Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Seismic Aspects of Recommendation 2.3 of Near-Term Task Force Review of Insights from Fukushima Project stage: Response to RAI L-13-113, FENOC Response to NRC Request for Information Pursuant to 10CFR50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insight from the Fukushima2013-04-29029 April 2013 FENOC Response to NRC Request for Information Pursuant to 10CFR50.54(f) Regarding the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force (NTTF) Review of Insight from the Fukushima Project stage: Response to RAI ML13151A0522013-06-17017 June 2013 Plan for the Regulatory Audit Regarding Seismic Walkdowns at Beaver Valley, to Support Implementation of Near-Term Task Force Recommendation 2.3, Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident Project stage: Other L-13-312, Updated Submittal of FENOC Response to NRC Request for Information Pursuant to 10CFR50.54(f) Re the Seismic Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident2013-09-24024 September 2013 Updated Submittal of FENOC Response to NRC Request for Information Pursuant to 10CFR50.54(f) Re the Seismic Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident Project stage: Response to RAI ML13295A6952013-11-21021 November 2013 Audit Report Regarding Seismic Walkdowns to Support Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Dai-Ichi Nuclear Power Plant Accident - Beaver Valley Power Station Units 1 and 2 Project stage: Other L-13-376, Addendum to the Beaver Valley Power Station, Unit No. 1, Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report2014-01-27027 January 2014 Addendum to the Beaver Valley Power Station, Unit No. 1, Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Project stage: Other ML14009A0892014-02-10010 February 2014 Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima Daiichi Nuclear Power Plant Accident Project stage: Other 2012-09-28
[Table View] |
Text
FENOC I76 South Main Street FirstEnergy Nuclear Operating Company Akron, Ohio 44308 Peter P. Sena III President and Chief Operating Officer November 27, 2012 L-12-283 10 CFR 50.54(f)
ATTN: Document Control Desk U.S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, MD 20852
SUBJECT:
Beaver Valley Power Station, Unit Nos. 1 and 2 Docket No. 50-334, License No. DPR-66 Docket No. 50-412, License No. NPF-73 Davis-Besse Nuclear Power Station Docket No. 50-346, License No. NPF-3 Perry Nuclear Power Plant Docket No. 50-440, License No. NPF-58 FENOC Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Reqarding the Seismic Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insigqhts from the Fukushima Dai-ichi Accident On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued a letter titled, "Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f)
Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident," to all power reactor licensees and holders of construction permits in active or deferred status. Enclosure 3 of the 10 CFR 50.54(f) letter contains specific Requested Actions, Requested Information, and Required Responses associated with Recommendation 2.3 for Seismic Walkdowns.
By letter dated July 10, 2012 (Accession No. ML12192A615), FirstEnergy Nuclear Operating Company (FENOC) confirmed its intent to use EPRI Report 1025286, Seismic Walkdown Guidance: For Resolution of Fukushima Near-Term Task Force Recommendation 2.3: Seismic, as the basis for the seismic walkdowns.
This letter submits FENOC's 180 day response to the 10 CFR 50.54(f) letter. The required seismic walkdown reports are provided as Enclosures A, B, C, and D for Beaver Valley Power Station, Unit No. 1 (BVPS-1); Beaver Valley Power Station, Unit No. 2 (BVPS-2);
Davis-Besse Nuclear Power Station (DBNPS); and Perry Nuclear Power Plant (PNPP),
respectively.
During the seismic walkdowns, certain plant areas were inaccessible due to conditions expected during normal power operation. Therefore, within 120 days of their next refueling
Beaver Valley Power Station, Unit Nos. 1 and 2 Davis-Besse Nuclear Power Station Perry Nuclear Power Plant L-12-283 Page 2 outages, BVPS-1, DBNPS, and PNPP will each submit to the NRC a supplemental report documenting the results of their additional seismic walkdowns.
Regulatory Commitments for this submittal are provided on the Attachment. If there are any questions or if additional information is required, please contact Mr. Thomas A. Lentz, Manager-Fleet Licensing, at 330-315-6810.
I declare under penalty of perjury that the foregoing is true and correct. Executed on November.1)
, 2012.
Sincr Peter P. Sena, III
Attachment:
Regulatory Commitment List
Enclosures:
A.
Beaver Valley Power Station Unit 1 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report B.
Beaver Valley Power Station Unit 2 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report C.
Davis-Besse Nuclear Power Station Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report D.
Perry Nuclear Power Plant Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report cc:
Director, Office of Nuclear Reactor Regulation (NRR) (w/o Enclosures)
NRC Region I Administrator (w/o Enclosures)
NRC Region III Administrator (w/o Enclosures)
NRC Resident Inspector (BVPS) (w/o Enclosures)
NRC Resident Inspector (DBNPS) (w/o Enclosures)
NRC Resident Inspector (PNPP) (w/o Enclosures)
NRR Project Manager (BVPS) (w/o Enclosures)
NRR Project Manager (DBNPS) (w/o Enclosures)
NRR Project Manager (PNPP) (w/o Enclosures)
Director BRP/DEP (w/o Enclosures)
Site BRP/DEP Representative (w/o Enclosures)
Utility Radiological Safety Board (w/o Enclosures)
Attachment L-1 2-283 Regulatory Commitment List Page 1 of 1 The following list identifies those actions committed to by FirstEnergy Nuclear Operating Company (FENOC) for the Beaver Valley Power Station, Unit No. 1; the Davis-Besse Nuclear Power Station; and the Perry Nuclear Power Plant. Any other actions discussed in the submittal represent intended or planned actions by FENOC. They are described only as information and are not regulatory commitments. Please notify Mr. Thomas A. Lentz, Manager - Fleet Licensing, at (330) 315-6810 of any questions regarding this document or associated regulatory commitments.
Reaulatorv Commitments Due Date
- 1. [Applicable to Beaver Valley Power Station, Unit No. 1]
Submit to the Nuclear Regulatory Commission (NRC) a supplemental report documenting the seismic walkdowns of equipment listed within "Beaver Valley Power Station Unit 1 Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report," Table 6-3.
- 2. [Applicable to Davis-Besse Nuclear Power Station]
Submit to the Nuclear Regulatory Commission (NRC) a supplemental report documenting the seismic walkdowns of equipment listed within "Davis-Besse Nuclear Power Station Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report," Table 6-3 and Table 6-3a.
- 3. [Applicable to Perry Nuclear Power Plant]
Submit to the Nuclear Regulatory Commission (NRC) a supplemental report documenting the seismic walkdowns of equipment listed within "Perry Nuclear Power Plant Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report,"
Table 6-3.
Within 120 days following completion of the fall 2013 refueling outage.
Within 120 days following completion of the spring 2014 refueling outage.
Within 120 days following completion of the spring 2013 refueling outage.