OL - TVA Letter to NRC_10-04-12_Revision of Commit for U2 Implementation of Maint Rule
ML12309A007
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 10/04/2012
From:
- No Known Affiliation
To:
Division of Operating Reactor Licensing
References
Download: ML12309A007 (5)


Text

WBN2Public Resource From: Boyd, Desiree L [dlboyd@tva.gov]

Sent: Thursday, October 04, 2012 1:40 PM To: Epperson, Dan; Wilson, George; Poole, Justin Cc: Arent, Gordon; Hamill, Carol L; Boyd, Desiree L

Subject:

TVA letter to NRC_10-04-12_Revision of Commit for U2 Implementation of Maint Rule Attachments: 10-04-12_Revision of Commit for U2 Implementation of Maint Rule_Final.pdf Please see attached TVA letter that was sent to the NRC today.

Thank You,

~*~*~*~*~*~*~*~*~*~*~

Désireé L. Boyd WBN Unit 2 Licensing dlboyd@tva.gov 423-365-8764 1

Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 746 Mail Envelope Properties (7AB41F650F76BD44B5BCAB7C0CCABFAF33D04CC6)

Subject:

TVA letter to NRC_10-04-12_Revision of Commit for U2 Implementation of Maint Rule Sent Date: 10/4/2012 1:39:32 PM Received Date: 10/4/2012 1:39:36 PM From: Boyd, Desiree L Created By: dlboyd@tva.gov Recipients:

"Arent, Gordon" <garent@tva.gov>

Tracking Status: None "Hamill, Carol L" <clhamill@tva.gov>

Tracking Status: None "Boyd, Desiree L" <dlboyd@tva.gov>

Tracking Status: None "Epperson, Dan" <Dan.Epperson@nrc.gov>

Tracking Status: None "Wilson, George" <George.Wilson@nrc.gov>

Tracking Status: None "Poole, Justin" <Justin.Poole@nrc.gov>

Tracking Status: None Post Office: TVANUCXVS2.main.tva.gov Files Size Date & Time MESSAGE 274 10/4/2012 1:39:36 PM 10-04-12_Revision of Commit for U2 Implementation of Maint Rule_Final.pdf 72897 Options Priority: Standard Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date:

Recipients Received:

Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 October 4, 2012 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391

Subject:

Watts Bar Nuclear Plant (WBN) Unit 2 - Revision of Commitment for Unit 2s Implementation of the Maintenance Rule

References:

1. TVA to NRC letter dated October 17, 2011, Watts Bar Nuclear Plant (WBN)

Unit 2 - Revision of Commitment for Unit 2s Implementation of the Maintenance Rule (ADAMS Accession No. ML11292A199)

2. TVA to NRC letter dated November 17, 2010, Watts Bar Nuclear Plant (WBN) Unit 2 - Revision of Commitment for Unit 2s Implementation of the Maintenance Rule (ADAMS Accession No. ML103210644)
3. TVA to NRC letter dated January 29, 2008, Watts Bar Nuclear Plant (WBN) -

Unit 2 - Regulatory Framework for the Completion of Construction and Licensing Activities for Unit 2 (ADAMS Accession No. ML080320443)

The purpose of this letter is to revise the due date for the Maintenance Rule implementation for Unit 2 systems from October 31, 2012 (Reference 1) to June 20, 2014. This change is the result of Unit 2 schedule changes. Reference 2 had also previously changed this date as a result of schedule changes.

U.S. Nuclear Regulatory Commission Page 3 October 4, 2012 bcc: Jessie Quichocho U.S. Nuclear Regulatory Commission MS 8 B1A One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 Fred Brown, Deputy Regional Administrator for Construction U.S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., N.E., Suite 1200 Atlanta, GA 30303-1257