ML121930104
Letter Sequence Draft RAI | |
---|---|
TAC:ME7905, Clarify Application of Setpoint Methodology for LSSS Functions (Approved, Closed) | |
Initiation Administration
| |
MONTHYEARML12040A0732011-10-31031 October 2011
[Table View]0000-0101-7647-R3, Columbia Generating Station Plant-Specific Responses Required by Numac Prnm Retrofit Plus Option III Stability Trip Function Topical Report, (NEDC-3241 OP-A) Project stage: Request ML12040A0752011-11-30030 November 2011 NEDO-33690, Revision 0, Columbia Generating Station Power Range Neutron Monitoring System Response Time Analysis Report Project stage: Request ML12040A0762012-01-31031 January 2012 NEDO-33694, Revision 1, Columbia Generating Station Power Range Neutron Monitoring System Diversity and Defense-in-Depth (D3) Analysis Project stage: Request GO2-12-017, License Amendment Request to Change Technical Specification in Support of Prnm/Arts/Mellla Implementation2012-01-31031 January 2012 License Amendment Request to Change Technical Specification in Support of Prnm/Arts/Mellla Implementation Project stage: Request ML12040A0772012-01-31031 January 2012 NEDO-33697, Revision 1, Columbia Generating Station Power Range Neutron Monitoring System Design Analysis Report Project stage: Request ML12040A0792012-01-31031 January 2012 NEDO-33698, Revision 1, Columbia Generating Station Power Range Neutron Monitoring System Design Report on Computer Integrity, Test and Calibration, and Fault Detection. Enclosure 2, Attachment 14 to List of Commitments and Enclosure 3 Are Project stage: Request ML12040A0802012-01-31031 January 2012 NEDO-33507, Revision 1, Columbia Generating Station Aprm/Rbm/Technical Specifications / Maximum Extended Load Line Limit Analysis (Arts/Mellla) Project stage: Request ML12040A0742012-01-31031 January 2012 NEDO-33685, Revision 1, Digital I&C-ISG-06 Compliance for Columbia Generating Station Numac Power Range Neutron Monitoring Retrofit Plus Option III Stability Trip Function Project stage: Request ML1210702222012-04-16016 April 2012 Acceptance Review Email, License Amendment Request, Technical Specification Changes to Support Installation of GE Hitachi Power Range Neutron Monitoring System; Implementation of Arts/Mellla Project stage: Acceptance Review ML1216704012012-06-15015 June 2012 E-mail, Draft Request for Additional Information, Amendment Request, Technical Specification Changes to Support Installation of GE Hitachi Power Range Neutron Monitoring System; Implementation of Arts/Mella Project stage: Draft RAI ML1216704042012-06-15015 June 2012 Draft Request for Additional Information, Amendment Request, Technical Specification Changes to Support Installation of GE Hitachi Power Range Neutron Monitoring System; Implementation of Arts/Mellla Project stage: Draft RAI ML1219301002012-07-10010 July 2012 Email, Draft Request for Additional Information, Round 2, Technical Specification Changes to Support Installation of GE Hitachi Power Range Neutron Monitoring System; Implementation of Arts/Mellla Project stage: Draft RAI ML1219301042012-07-10010 July 2012 Draft Request for Additional Information, Round 2, Technical Specification Changes to Support Installation of GE Hitachi Power Range Neutron Monitoring System; Implementation of Arts/Mellla Project stage: Draft RAI ML12201B0502012-07-23023 July 2012 Request for Additional Information, Rounds 1 and 2, Technical Specification Changes to Support Installation of GE Hitachi Power Range Neutron Monitoring System; Implementation of Arts/Mellla Project stage: RAI ML12192A3252012-07-30030 July 2012 Request for Withholding Information from Public Disclosure, Affidavit Dated 10/31/11 Executed by E. Schrull, GE Hitachi Americas LLC, 0000-0101-7647-R3 Plant-Specific Responses Required by NEDC-32410P-P-A Project stage: Withholding Request Acceptance ML12192A4542012-07-30030 July 2012 Request for Withholding Information from Public Disclosure, Affidavit Dated 1/5/12, Executed by E. Schrull, GE Hitachi Americas LLC, NEDC-33694P, Revision 1 Project stage: Withholding Request Acceptance ML12192A5352012-07-30030 July 2012 Request for Withholding Information from Public Disclosure, Affidavit Dated 1/5/12, Executed by E. Schrull, GE Hitachi Americas LLC, NEDC-33697P, Revision 1 Project stage: Withholding Request Acceptance ML12192A4332012-07-30030 July 2012 Request for Withholding Information from Public Disclosure, Affidavit Dated 11/1/11, Executed by E. Schrull, GE Hitachi Americas LLC, NEDC-33690P, Revision 0 Project stage: Withholding Request Acceptance ML12192A5892012-07-30030 July 2012 Request for Withholding Information from Public Disclosure, Affidavit Dated 1/5/12, Executed by E. Schrull, GE Hitachi Americas LLC, NEDC-33698P, Revision 1 Project stage: Withholding Request Acceptance ML12192A3612012-07-30030 July 2012 Request for Withholding Information from Public Disclosure, Affidavit Dated 1/5/12 Executed by E. Schrull, GE Hitachi Americas LLC, NEDC-33685P, Revision 1 Project stage: Withholding Request Acceptance ML12193A1092012-07-30030 July 2012 Request for Withholding Information from Public Disclosure, Affidavit Dated 1/27/12, Executed by E. Schrull, GE Hitachi Americas LLC, NEDC-33507P, Revision 1 Project stage: Withholding Request Acceptance GO2-12-105, Submittal of Phase 2 Information in Support of License Amendment Request to Change Technical Specifications in Support of Prnm /Arts/Mellla Implementation; NEDO-33750, NEDO-33753; NEDO-33754: NEDO-33755; & NEDO-337582012-07-31031 July 2012 Submittal of Phase 2 Information in Support of License Amendment Request to Change Technical Specifications in Support of Prnm /Arts/Mellla Implementation; NEDO-33750, NEDO-33753; NEDO-33754: NEDO-33755; & NEDO-33758 Project stage: Request GO2-12-116, Response to Request for Additional Information Regarding License Amendment Request to Implement Prnm/Arts/Mellla2012-08-22022 August 2012 Response to Request for Additional Information Regarding License Amendment Request to Implement Prnm/Arts/Mellla Project stage: Response to RAI ML12249A0112012-09-0505 September 2012 Redacted, Request for Additional Information, Amendment Request for Technical Specification Changes to Support Installation of GE Hitachi Power Range Neutron Monitoring System; Implementation of Arts/Mellla Project stage: RAI ML12261A1972012-09-17017 September 2012 Email, Draft Request for Additional Information, Round 4, Technical Specification Changes to Support Installation of GE Hitachi Power Range Neutron Monitoring System; Implementation of Arts/Mellla Project stage: Draft RAI GO2-12-135, Response to Request for Additional Information Regarding License Amendment Request to Implement Prnmiarts/Mellla2012-10-0505 October 2012 Response to Request for Additional Information Regarding License Amendment Request to Implement Prnmiarts/Mellla Project stage: Response to RAI ML12283A2692012-10-15015 October 2012 Request for Additional Information, Round 4, Technical Specification Changes to Support Installation of GE Hitachi Power Range Neutron Monitoring System; Implementation of Prnm/Arts/Mellla Project stage: RAI ML12328A0782012-10-31031 October 2012 NEDO-33751, Revision 3, Columbia Generating Station Power Range Neutron Monitoring System Reliability Analysis, Attachment 3 Project stage: Request GO2-12-162, Response to Request for Additional Information Regarding License Amendment Request to Implement Prnm/Arts/Mellla2012-11-12012 November 2012 Response to Request for Additional Information Regarding License Amendment Request to Implement Prnm/Arts/Mellla Project stage: Response to RAI ML12192A4812012-11-13013 November 2012 Request for Withholding Information from Public Disclosure, Affidavits Dated 11/16/11 and 7/26/12, Executed by E. Schrull, GE Hitachi Americas LLC, NEDC-33696P, Revisions 0 and 1 Project stage: Withholding Request Acceptance ML12229A4682012-11-13013 November 2012 Request for Withholding Information from Public Disclosure, 6/4/12 Affidavit Executed by E. Schrull, GEH-Hitachi, NEDC-33750P, Revision 0 Project stage: Withholding Request Acceptance ML12229A4762012-11-13013 November 2012 Request for Withholding Information from Public Disclosure, 6/7/12 Affidavit Executed by E. Schrull, GEH-Hitachi, NEDC-33753P, Revision 0 Project stage: Withholding Request Acceptance ML12229A4802012-11-13013 November 2012 Request for Withholding Information from Public Disclosure, 6/7/12 Affidavit Executed by E. Schrull, GEH-Hitachi, NEDC-33754P, Revision 0 Project stage: Withholding Request Acceptance ML12229A4822012-11-13013 November 2012 Request for Withholding Information from Public Disclosure, 6/27/12 Affidavit Executed by E. Schrull, GEH-Hitachi, NEDC-33756P, Revision 0 Project stage: Withholding Request Acceptance ML12229A4832012-11-13013 November 2012 Request for Withholding Information from Public Disclosure, 6/7/12 Affidavit Executed by E. Schrull, GEH-Hitachi, NEDC-33758P, Revision 0 Project stage: Withholding Request Acceptance ML12229A4902012-11-13013 November 2012 Request for Withholding Information from Public Disclosure, 6/12/12 Affidavit Executed by E. Schrull, GEH-Hitachi, Letter GE-MS-CT-106244-JC14 Project stage: Withholding Request Acceptance ML12328A0792012-11-30030 November 2012 NEDO-33789, Revision 0, Numac Power Range Neutron Monitoring Components 268X1331TCG001, 268X1332TCG001, G002 268X1333TCG001, Qualification Summary for Energy Northwest (Enw) Columbia Generating Station (Cgs), Attachment 5 Project stage: Request ML12229A4712012-12-18018 December 2012 Request for Withholding Information from Public Disclosure, 6/29/12 and 10/22/12 Affidavits Executed by E. Schrull, GEH-Hitachi, NEDC-33751P, Revisions 2 and 3 Project stage: Withholding Request Acceptance ML12345A3662012-12-18018 December 2012 Request for Withholding Information from Public Disclosure, Affidavit Dated 11/1/12 Executed by E. Schrull, GEH-Hitachi, NEDC-33789P, Revision 0 Project stage: Withholding Request Acceptance ML12345A3582012-12-18018 December 2012 Request for Withholding Information from Public Disclosure, 9/26/12 Affidavit Executed by E.Schrull, GEH-Hitachi, GEH 10/5/12 Responses to Nrc/De/Eicb 9/5/12 Request for Additional Information Project stage: RAI ML13015A2722012-12-31031 December 2012 NEDO-33685, Rev 2, Digital I&C-ISG-06 Compliance for Columbia Generating Station Numac Power Range Neutron Monitoring Retrofit Plus Option III Stability Trip Function. Project stage: Request ML13015A2732012-12-31031 December 2012 NEDO-33698, Rev 2, Columbia Generating Station Power Range Neutron Monitoring System Design Report on Computer Integrity, Test and Calibration, and Fault Detection Project stage: Request ML13025A3512013-02-21021 February 2013 Request for Withholding Information from Public Disclosure, Affidavit Dated 12/12/12, Executed by L. Dolan, GE Hitachi Americas LLC, NEDC-33685P, Revision 2 Project stage: Withholding Request Acceptance ML13025A3612013-02-21021 February 2013 Request for Withholding Information from Public Disclosure, Affidavit Dated 12/12/12, Executed by L. Dolan, GE Hitachi Americas LLC, NEDC-33698P, Revision 2 Project stage: Withholding Request Acceptance ML13067A1062013-03-12012 March 2013 Redacted, Request for Additional Information, Round 5, Technical Specification Changes to Support Installation of GE Hitachi Power Range Neutron Monitoring System; Implementation of Arts/Mellla Project stage: RAI ML13098A7782013-04-0808 April 2013 Request for Additional Information Following 4/3/13 Calculation Audit, Technical Specification Changes to Support Installation of GE Hitachi Power Range Neutron Monitoring System; Implementation of Arts/Mellla Project stage: RAI ML13099A0432013-04-10010 April 2013 Request for Additional Information Following 4/3/13 Calculation Audit, Technical Specification Changes to Support Installation of GE Hitachi Power Range Neutron Monitoring System; Implementation of Arts/Mellla Project stage: RAI GO2-13-059, Response to Request for Additional Information Regarding License Amendment Request to Implement Prnm/Arts/Mellla2013-04-11011 April 2013 Response to Request for Additional Information Regarding License Amendment Request to Implement Prnm/Arts/Mellla Project stage: Response to RAI PNP 2013-038, 2012 Annual Radioactive Effluent Release and Waste Disposal Report2013-04-23023 April 2013 2012 Annual Radioactive Effluent Release and Waste Disposal Report Project stage: Request ML13109A1632013-04-26026 April 2013 Request for Withholding Information from Public Disclosure - 4/2/13 and 4/10/13 Affidavits Executed by L. Dolan, GEH; Enclosures 1 and 3 of Geh'S Request for Additional Information Responses Project stage: RAI 2012-07-10 |
ML121930104 | |
Person / Time | |
---|---|
Site: | Columbia |
Issue date: | 07/10/2012 |
From: | Lauren Gibson Plant Licensing Branch IV |
To: | Dunham Z Energy Northwest |
Gibson, Lauren, NRR/DORL/LPL4, 415-1056 | |
References | |
TAC ME7905 | |
Download: ML121930104 (2) | |
Similar Documents at Columbia | |
---|---|
Category:Request for Additional Information (RAI)
MONTHYEARML24011A1522024-01-10010 January 2024
[Table view]March 2024 Emergency Preparedness Exercise Inspection-Request for Information ML23110A2642023-04-20020 April 2023 Request for Information License Renewal Phase 2 Inspection ML22343A1802022-12-0808 December 2022 February 2023 Emergency Preparedness Program Inspection - Request for Information ML22301A1432022-10-28028 October 2022 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - License Amendment Request to Adopt TSTF-505 - EPID L-2022-LLA-0023 ML22242A1082022-08-30030 August 2022 Information Request, Information Request, Security IR 2022404 ML22235A1052022-08-22022 August 2022 August 2022 Emergency Preparedness Exercise Inspection Request for Information ML22145A4462022-06-0606 June 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000397/2022401 ML22144A0342022-05-18018 May 2022 NRR E-mail Capture - Draft - Request for Additional Information - Columbia Generating Station - LAR to Change TS 3.4.11 - Reactor Coolant System Pressure and Temperature Limits - EPID L-2021-LLA-0191 ML22041A4572022-02-10010 February 2022 Notification of NRC Design Bases Assurance Inspection (Team) (05000397/2022010) and Request for Information ML21277A3572021-10-12012 October 2021 CGS Brq RFI Letter, Columbia Generating Station - Notification of Inspection (NRC Inspection Report 05000397/2021004) and Request for Information ML21216A0502021-08-0303 August 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia - License Amendment Request to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO EPID L-2021-LLA-0259 ML21209A9792021-07-28028 July 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - License Amendment Request to Remove License Condition 2.C.(34) and Revise License Condition 2.C.(35) - EPID L-2021-LLA-0074 ML21120A1182021-04-30030 April 2021 NRR E-mail Capture - Final - Request for Additional Information - Columbia Generating Station - On-Site Cooling System Sediment Disposal Approval Request - EPID L-2020-LLL-0031 ML21068A2842021-03-0404 March 2021 2021002 Inservice Inspection (ISI) Request for Information (RFI) ML20336A1852020-11-30030 November 2020 NRR E-mail Capture - Final - RAI - Columbia - One -Time Exemption from 10 CFR 73, App B, Sect VI, Subsection C.3.(l)(1) Regarding Annual Force-On-Force Exercises Due to COVID-19 Pandemic - EPID L-2020-LLE-0172 ML20325A0402020-11-19019 November 2020 NRR E-mail Capture - Draft - RAI - Columbia - One -Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force -On-Force Exercises Due to COVID-19 Pandemic - EPID L-2020-LLE-0172 ML20267A5162020-09-23023 September 2020 NRR E-mail Capture - Columbia Generating Station - Final - Request for Additional Information - Fourth Ten-Year Interval Inservice Inspection (ISI) Program Relief Request 4ISI-09 - EPID L-2020-LLR-0068 ML20245E2822020-08-31031 August 2020 NRR E-mail Capture - Columbia Additional Request for Additional Information: Exigent License Amendment Request to Extend Technical Specification 3.8.7, Distribution Systems - Operating, Completion Time ML20239A9702020-08-26026 August 2020 NRR E-mail Capture - Columbia Additional Request for Additional Information: Exigent License Amendment Request to Extend Technical Specification 3.8.7, Distribution Systems - Operating, Completion Time ML20149K4362020-05-26026 May 2020 NRR E-mail Capture - Formal RAIs for Columbia (COVID-19) QA Plan Change Surveillance, Request Response by Tuesday June 2, 2020 ML20112F4572020-04-21021 April 2020 NRR E-mail Capture - Official Release of NRC RAIs for Columbia Covid Exigent Due Friday April 24, 2020 ML20034E6082020-02-0303 February 2020 NRR E-mail Capture - RAI Formal Release Columbia TSTF 563 LAR, 30 Day Response Period Due March 3, 2020 ML20028E1512020-01-27027 January 2020 Notification of Evaluations of Changes, Tests, and Experiments Inspection (Inspection Report 05000397/2020002) and Request for Information ML19267A1842019-09-24024 September 2019 Request for Information for Upcoming Open Phase Condition Inspection at Columbia Generating Station ML19232A2282019-08-20020 August 2019 NRR E-mail Capture - Formal Release of RAIs Ref: Columbia Exigent Amendment - One Electrical RAI, ML19183A4752019-07-0202 July 2019 NRR E-mail Capture - Formal Release of RAIs Ref: Columbia HVAC LAR L-2019-LLA-0034 ML18088A0152018-03-29029 March 2018 Notification of NRC Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/ Staffing/Multi-Unit Dose Assessment Plans (05000397/2018010) and Request for ML17341B0272017-12-0707 December 2017 NRR E-mail Capture - RAI Associated with Columbia Amendment Request Revise Tech Spec 5.5.12 for Permanent Extension of Type a and Type C Containment Testing Frequencies for MF9469, EPID: L-2017-LLA-0197, ILRT, LLRT LAR - New RAI Response Da ML17292A0572017-10-18018 October 2017 NRR E-mail Capture - New RWCU RAI Due Date Now November 24, 2017 ML17249A6882017-09-0606 September 2017 NRR E-mail Capture - RAIs for Columbia Relief Request RAI (MF8925), 3ISI-19 ML17205A3152017-07-20020 July 2017 Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000397/2017004) and Request for Information ML17193A2192017-07-12012 July 2017 NRR E-mail Capture - Columbia RWCU LAR MF8318, Formal Release of RAIs ML17144A1702017-05-24024 May 2017 NRR E-mail Capture - NRC RAIs for Columbia Relief Request MF8922, 3ISI-16 ML17047A7492017-02-16016 February 2017 Response to Request for Additional Information, Columbia Mur LAR Evib Rais ML17006A0922017-01-0404 January 2017 NRR E-mail Capture - Eicb RAIs for Columbia Mur ML17006A0902017-01-0404 January 2017 NRR E-mail Capture - Non Proprietary Request for Additional Information Regarding Columbia Mur Power Uprate ML16356A1382016-12-21021 December 2016 NRR E-mail Capture - Columbia Mur LAR Evib RAIs Non - Proprietary Version - Revise Operating License and Technical Specifications for Measurement Uncertainty Recapture Power Uprate ML16342C4322016-12-0707 December 2016 NRR E-mail Capture - Columbia Measurement Uncertainty Recapture Power Uprate LAR Rais: Human Performance: MF8060, Formal Release for Response on Monday January 9, 2017 ML16327A1842016-11-22022 November 2016 NRR E-mail Capture - Non Proprietary Request for Additional Information Regarding Columbia Mur Power Uprate ML16323A1192016-11-16016 November 2016 NRR E-mail Capture - Eicb RAIs for Columbia Mur ML16218A3902016-08-0808 August 2016 Supplemental Information Needed for Acceptance of Requested Licensing Action, Request for Measurement Uncertainty Recapture (Mur) Power Uprate (from 3486 Mwt to 3544 Mwt) ML16194A3702016-07-11011 July 2016 Notification of NRC Triennial Heat Sink Performance Inspection 05000397/2016003 and Request for Information ML16069A3592016-03-0909 March 2016 NRR E-mail Capture - Second Round Rais: Columbia MF6042 LAR TSTF-425 ML16061A5542016-03-0101 March 2016 Notification of NRC Design Bases Inspection (05000397/2016007) and Initial Request for Information ML16061A5662016-03-0101 March 2016 Notification of Design Bases Inspection (Programs)(Inspection Report 05000397/2016008) and Initial Request for Information ML15254A2572015-09-16016 September 2015 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1 Seismic Reevaluations ML15215A0432015-08-18018 August 2015 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Reevaluations ML14262A3412014-09-24024 September 2014 Request for Additional Information, Round 2, License Amendment Request to Revise TS Table 3.3.1.1-1 Function 7, Scram Discharge Volume Water Level - High ML14192B0312014-08-13013 August 2014 Redacted, Request for Additional Information, Nrr/Dss/Scvb, Request to Modify Emergency Core Cooling Systems Surveillance Requirements for Low Pressure Core Spray and Low Pressure Coolant Injection Pump Flows ML14206A0112014-07-31031 July 2014 Request for Additional Information, License Amendment Request to Revise TS Table 3.3.1.1-1 Function 7, Scram Discharge Volume Water Level - High 2024-01-10 |
Text
REQUEST FOR ADDITIONAL INFORMATION (RAI)
LICENSE AMENDMENT REQUEST TO IMPLEMENT PRNM/ARTS/MELLLA ENERGY NORTHWEST COLUMBIA GENERATING STATION DOCKET NO. 50.397 REACTOR SYSTEMS BRANCH (SRXB)
SRXB RAI - 1 In page 1-2 of NEDC-33507P (Rev. 1), plants with either full or partial Average Power Range Monitor/Rod Block Monitor/Technical Specifications/Maximum Extended Load Line Limit Analysis (ARTS/MELLLA) were listed. The staff requests the licensee to clarify the following:
a) Does CGS plan to implement full or partial ARTS/MELLLA?
b) Provide the basis for your decision in part (a) and the main differences between the two options with respect to CGS plant operation.
SRXB RAI - 2 Provide the CGS core design for which the MELLLA analysis was performed and the following results of fuel-dependent portion of the analysis:
a) Describe core design for the current Cycle 20 for which the MELLLA analysis was performed, including number of GE14 and ATRIUM-10 fuels assumed to comprise the core, and their burnup history (i.e., number of cycles exposed in the core) for each fuel types.
b) For a given core condition of a mixed core, the Specified Acceptable Fuel Design Limits (SAFDLs), such as MCPR, LHGR, PCT, etc., depend on the type of fuel design and their respective burnup history. Which fuel design (GE14 or ATRIUM-10) produces the limiting SAFDLs for the transient and accident analyses performed at the MELLLA conditions? Explain why.
SRXB RAI - 3 The fourth bullet from the bottom of page 7-2 of NEDC-33507P (Rev. 1) stated, A full core of GE14 fuel is assumed to comprise the core.
a) Clarify which of the transient and accident analyses (i.e., AOOs, LOCA, ASME Overpressure and ATWS) assumed a full core of GE14 fuel.
b) Explain why GE14 fuel was assumed to comprise the entire core when the core included ATRIUM-10 fuel, as well.
c) If a full core of GE14 fuel was assumed to comprise the core, then explain how the analysis captures a situation when ATRIUM-10 fuel is more limiting in the transient and accident analyses, and provide reasonable assurance as to how the analysis of record is most conservative.
SRXB RAI - 4 In Table 7-1 of NEDC-33507P, ECCS-LOCA Rated Thermal Power was assumed to be equal to 3629 MWt, which is 4.1% (143 MWt) higher than the Current Licensed Thermal Power (CLTP) of 3486 MWt. The staff understands that Appendix K to 10 CFR Part 50 requires analyses to be performed at 2% higher than the CLTP to allow for instrumentation error. Explain why LOCA analysis was performed at a thermal power which is 4.1% higher than the CLTP.
SRXB RAI - 5 Describe your training program for the operators in preparation for implementing the ARTS/MELLLA operation at CGS.