MONTHYEARML24029A2732024-01-29029 January 2024 NRC Consultation with Commonwealth of Pennsylvania Re Proposed NSHC for Susquehanna License Amendment Request ML23352A2542023-12-18018 December 2023 NRC LIC-109 Acceptance Review Results for Susquehanna Steam Electric Station, License Amendment Request to Revise Technical Specifications (TS) to Adopt TSTF-568 ML23345A0542023-12-0808 December 2023 Email - NRC LIC-109 Acceptance Review Results for Susquehanna License Amendment Request to Revise Technical Specifications to Adopt TSTF-563 ML23334A1502023-11-30030 November 2023 NRC Request for Additional Information Re. Susquehanna Relief Request RR-02 ML23334A1682023-11-30030 November 2023 NRC Request for Additional Information Re. Susquehanna Relief Request RR-01 ML23242A2832023-08-30030 August 2023 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Susquehanna Steam Electric Station, Proposed Alternatives RR01 and RR02 (EPIDs L-2023-LLR-0043 and -0044) ML23230A0712023-08-18018 August 2023 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Susquehanna Steam Electric Station, Proposed Alternative for Valve 251130 ML23188A0802023-07-0707 July 2023 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Susquehanna Steam Electric Station, License Amendment Request to Revise Control Rod Technical Specifications ML23171A4312023-06-20020 June 2023 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Susquehanna Steam Electric Station, Proposed Alternative 5RR-02 ML23103A4702023-04-12012 April 2023 NRR E-mail Capture - Susquehanna Unit 2 - Verbal Authorization of Relief Request 4RR-10 ML23094A1242023-03-31031 March 2023 EN 56387 Update - Paragon Energy Solutions Final Notification of Defect of Automatic Transfer Switch ML23075A0492023-03-16016 March 2023 NRR E-mail Capture - Notification to the State of Pennsylvania Re. Susquehanna Steam Electric Station, Units 1 and 2 - Indirect License Transfer and Draft Conforming Amendments ML23073A1202023-03-14014 March 2023 NRR E-mail Capture - Evacuation Time Estimate Review ML23013A2082023-01-13013 January 2023 Request for Additional Information ML23012A0012023-01-11011 January 2023 NRC Notification to the State of Pennsylvania Re. Emergency Amendment Control Rod Technical Specifications ML22293A0882022-10-20020 October 2022 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Susquehanna License Transfer ML22257A1942022-09-14014 September 2022 NRR E-mail Capture - NRC Notification to the State of Pennsylvania Re. Susquehanna Steam Electric Station, Units 1 and 2 Amendment - Relocating Staff Qualification Requirements ML22213A2612022-08-0101 August 2022 NRR E-mail Capture - NRC Notification to the State of Pennsylvania Re. Susquehanna Steam Electric Station, Units 1 and 2 Amendment - Instrumentation and Control Technical Specifications ML22179A2902022-06-28028 June 2022 NRR E-mail Capture - NRC Notification to the State of Pennsylvania Re. Susquehanna Steam Electric Station, Units 1 and 2 Amendment - TSTF-505, Risk Informed Completion Times ML22146A0742022-05-25025 May 2022 NRR E-mail Capture - NRC Request for Additional Information - Susquehanna License Amendment Request ML22123A1112022-05-0303 May 2022 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Susquehanna Steam Electric Station, License Amendment Request to Relocate Staff Qualifications ML22111A3132022-04-21021 April 2022 NRR E-mail Capture - NRC Request for Additional Information - Susquehanna License Amendment Request ML22084A0222022-03-25025 March 2022 NRR E-mail Capture - Susquehanna Atrium-11 LAR Audit Report ML22038A1062022-02-0404 February 2022 NRR E-mail Capture - Susquehanna Steam Electric Station, Units 1 and 2 - Acceptance of Requested Licensing Action Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR ML22005A0712021-12-21021 December 2021 NRR E-mail Capture - NRC LIC-109 Acceptance Review Results for Susquehanna 1 & 2 ECCS TS LAR ML21190A1702021-06-11011 June 2021 NRR E-mail Capture - NRC Notification to the State of Pennsylvania Regarding a Susquehanna Steam Electric Station, Unit 2 Amendment - Unit 1 Transformer Replacement ML21124A2022021-05-0404 May 2021 NRR E-mail Capture - Acceptance Review for Susquehanna TSTF-505 ML20343A3702020-12-0808 December 2020 NRR E-mail Capture - Acceptance Review of Susquehanna RR 4RR-02 ML20343A3712020-12-0808 December 2020 NRR E-mail Capture - Corrected - Acceptance Review of Susquehanna RR 4RR-02 ML20335A5732020-11-30030 November 2020 NRR E-mail Capture - Susquehanna -Acceptance Review Replacement of Unit 1 Transformers ML20283A7722020-10-0909 October 2020 Submittal of Pennsylvania Letter Requesting Exemption from Biennial Exercise Requirements for Pennsylvania Nuclear Power Plants in Calendar Year 2020 ML20261H4272020-09-17017 September 2020 NRR E-mail Capture - Corrected Acceptance Review for Susquehanna - Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements ML20261H4212020-09-16016 September 2020 NRR E-mail Capture - Corrected Acceptance Review for Susquehanna - Revise Technical Specifications to Adopt TSTF-582, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements ML20195B1282020-07-13013 July 2020 NRR E-mail Capture - Acceptance Review for Susquehanna- Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules (EPID L-2020-Lla-0139) ML20178A6502020-06-26026 June 2020 Acceptance Review for Susquehanna - Revise Technical Specification 3.8.1 to Create a New Condition for an Inoperable Manual Synchronization Circuit ML20028F6352020-01-28028 January 2020 NRR E-mail Capture - Acceptance Review of LAR to Revise the Dose Consequence Analysis for a Loss of Coolant Accident ML19319A0092019-11-14014 November 2019 NRR E-mail Capture - Draft RAI for SSES Units 1 and 2 LAR to Replace ESW Piping ML19319B1922019-11-14014 November 2019 NRR E-mail Capture - RAI for Susquehanna, 1 and 2 License Amendment Request - Replace the Emergency Service Water System and Residual Heat Removal Service Water System ML19234A0342019-08-19019 August 2019 Acceptance Review: Susquehanna Units 1 and 2 License Amendment Request for Advanced Framatome Methodologies for Atrium 11 ML19234A1222019-08-19019 August 2019 Acceptance Review: Susquehanna Units 1 and 2 License Amendment Request for TSTF-535 ML19128A0232019-05-0707 May 2019 Request for Additional Information: Susquehanna Steam Electric Station, Units 1 and 2 License Amendment Request for ESW Piping Replacement ML19107A0092019-04-16016 April 2019 License Amendment Request for TSTF-439 ML19039A0892019-02-0808 February 2019 Acceptance of Requested Licensing Action License Amendment Request to Revise Emergency Service Water Piping Technical Specifications During Replacement ML19003A4752019-01-0303 January 2019 Acceptance Review Susquehanna Units 1 and 2 License Amendment Request for TSTF-501 ML18347A3282018-12-12012 December 2018 E-Mail from M. Krick/Sses SSES ISFSI (Conversation Held on December 12, 2018) ML18122A2412018-05-0202 May 2018 NRR E-mail Capture - Accepted for Review - Sequoyah 1 and 2, Request to Modify Essential Raw Cooling Water Motor Control Center Breakers and to Revise the Updated Final Safety Analysis Report (SQN-TS-17-04) ML18108A3022018-04-18018 April 2018 NRR E-mail Capture - Accepted for Review - Sequoyah License Amendment Request to Adopt 10CFR50.69 Risk-informed SSC Categorization ML17290A0242017-10-16016 October 2017 NRR E-mail Capture - Acceptance Review: Susquehanna Units 1 and 2 License Amendment Request for TSTF-542 ML17081A3802017-03-21021 March 2017 E-mail - Multi-Licensee License Amendment Request Example ML16211A3562016-07-29029 July 2016 Acceptance of Requested Licensing Action Request for Order Approving Indirect Transfer of Control 2024-01-29
[Table view] |
Text
From: Vaidya, Bhalchandra Sent: Wednesday, November 09, 2011 7:34 AM To: 'Coddington, Cornelius T'; 'Rochester, Margaret'; 'Petrilla III, John J' Cc: Salgado, Nancy; Lingam, Siva; Gonzalez, Hipolito; Purtscher, Patrick; Boyle, Patrick; Burkhardt, Janet
Subject:
ACCEPTANCE OF REQUESTED LICENSING ACTION RE: Susquehanna Unit 2 Relief Request 3RR-18 TAC No. ME7381
SUBJECT:
PPL Susquehanna, Unit 2- ACCEPTANCE OF REQUESTED LICENSING ACTION RE: PROPOSED RELIEF REQUEST NO. 3RR-18 TO THE THIRD 10-YEARINSERVICE INSPECTION PROGRAM FOR SUSQUEHANNA SES UNIT 2 PLA-6753 (TAC NO. ME7381)
By letter dated October 3, 2011, you submitted PROPOSED RELIEF REQUEST NO. 3RR-18 TO THE THIRD 10-YEARINSERVICE INSPECTION PROGRAM FOR SUSQUEHANNA SES UNIT 2 (ADAMS Accession No. ML112780095). The purpose of this communication is to provide the results of the NRC staff=s acceptance review of the relief request.
The acceptance review of the relief request was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff in Vessels and Internals Integrity Branch (EVIB) of Division of Engineering (DE) has reviewed your applications and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief request in terms of regulatory requirements and the protection of public health and safety and the environment.
If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.
If you have any questions, please contact me.
Bhalchandra K. Vaidya Licensing Project Manager NRC/NRR/DORL/LPL1-1 (301)-415-3308 (O) bhalchandra.vaidya@nrc.gov