MONTHYEARW3F1-2011-0061, Commitment to Provide 10 CFR 50.48(c) License Amendment Request and Request for Continued Enforcement Discretion2011-07-26026 July 2011 Commitment to Provide 10 CFR 50.48(c) License Amendment Request and Request for Continued Enforcement Discretion Project stage: Request ML1120916372011-07-28028 July 2011 Biweekly Notice - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations Project stage: Other W3F1-2011-0074, License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)2011-11-17017 November 2011 License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) Project stage: Request ML1200304302012-01-0303 January 2012 Email PRA Peer Review Report Project stage: Other ML1200304372012-01-0303 January 2012 Fpra Pr Position Paper Final Project stage: Other ML1201205332012-01-12012 January 2012 Email, Supplemental Information Needed for Acceptance of Requested Licensing Action, License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light-Water Reactor Generating Plants Project stage: Acceptance Review W3F1-2012-0005, Supplemental Information in Support of the NRC Acceptance Review of Waterford 3 License Amendment Request to Adopt NFPA 8052012-01-26026 January 2012 Supplemental Information in Support of the NRC Acceptance Review of Waterford 3 License Amendment Request to Adopt NFPA 805 Project stage: Supplement ML1203401282012-02-0303 February 2012 Acceptance Review Email, License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Acceptance Review ML1203802572012-03-0909 March 2012 Request to Reinstate Enforcement Discretion License Amendment Request to Adopt NFPA Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Other ML1208704852012-04-0303 April 2012 Regulatory Audit Scheduled to Begin 5/7/2012 in Support of the License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Other ML12185A2122012-07-18018 July 2012 Request for Additional Information, License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: RAI ML12275A0132012-09-27027 September 2012 Application for Order Approving Transfers of Licenses and Conforming License and ESP Amendments Project stage: Request W3F1-2012-0064, Response to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request2012-09-27027 September 2012 Response to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request Project stage: Response to RAI W3F1-2012-0083, 90-Day Response to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 8052012-10-16016 October 2012 90-Day Response to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 Project stage: Response to RAI ML13072A0632013-03-22022 March 2013 Request for Additional Information, Round 2, License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: RAI ML13129A1502013-05-10010 May 2013 Request for Supplement of Review Schedule and Interim Milestones, License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Other ML13157A0622013-06-26026 June 2013 Request for Additional Information, Round 3, License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: RAI W3F1-2013-0048, Supplement to NFPA 805 License Amendment Request (LAR)2013-12-18018 December 2013 Supplement to NFPA 805 License Amendment Request (LAR) Project stage: Supplement ML14023A2792014-01-23023 January 2014 Notice of Meeting with Entergy Operations, Inc., to Discuss Waterford Unit 3 License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Meeting PMNS20140175, Notice of Meeting with Entergy Operations, Inc., to Discuss Its National Fire Protection Association (NFPA) 805 License Amendment Request Supplement Changes for the Waterford Steam Electric Station, Unit 32014-01-24024 January 2014 Notice of Meeting with Entergy Operations, Inc., to Discuss Its National Fire Protection Association (NFPA) 805 License Amendment Request Supplement Changes for the Waterford Steam Electric Station, Unit 3 Project stage: Meeting W3F1-2014-0025, Updated Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR)2014-06-11011 June 2014 Updated Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR) Project stage: Response to RAI ML14232A0262014-09-15015 September 2014 Continuation of Enforcement Discretion, License Amendment Request to Adopt NFPA Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Other ML14350A2122014-12-22022 December 2014 Regulatory Audit Plan; January 12-14, 2015 Audit in Support of the Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Other ML15022A2392015-02-0606 February 2015 Request for Additional Information- National Fire Protection Association Standard NFPA 805 Project stage: RAI W3F1-2015-0015, Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request2015-03-12012 March 2015 Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request Project stage: Response to RAI W3F1-2015-0024, Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR)2015-04-10010 April 2015 Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR) Project stage: Response to RAI W3F1-2015-0025, Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR) Waterford Steam Electric Station, Unit 3 (Waterford 3)2015-05-14014 May 2015 Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR) Waterford Steam Electric Station, Unit 3 (Waterford 3) Project stage: Response to RAI ML15182A3462015-07-13013 July 2015 Request for Additional Information - National Fire Protection Association Standard NFPA 805 Project stage: RAI ML15197A2292015-07-21021 July 2015 Request for Additional Information Regarding National Fire Protection Association Standard 805 Project stage: RAI ML15239A7392015-08-31031 August 2015 Summary of Public Meeting with Entergy Operations, Inc. to Discuss Main Control Room Abandonment Regarding NFPA-805 License Amendment Request Project stage: Meeting W3F1-2015-0078, Revised Implementation Item Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR)2015-09-24024 September 2015 Revised Implementation Item Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR) Project stage: Request W3F1-2015-0081, Request for Additional Information (RAI) Clarification Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR)2015-10-13013 October 2015 Request for Additional Information (RAI) Clarification Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR) Project stage: Request W3F1-2015-0085, Transfer of License and Conforming Amendment2015-10-29029 October 2015 Transfer of License and Conforming Amendment Project stage: Other W3F1-2016-0003, Revised Licensing Actions and Implementation Items Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR)2016-01-18018 January 2016 Revised Licensing Actions and Implementation Items Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR) Project stage: Request 2013-06-26
[Table View] |
Text
W3F1-2011-0061 July 26, 2011 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
SUBJECT:
Commitment to Provide 10 CFR 50.48(c) License Amendment Request and Request for Continued Enforcement Discretion Waterford Steam Electric Station, Unit 3 Docket No. 50-382 License No. NPF-38
REFERENCES:
- 1. NRC Policy Statement, Interim Enforcement Policy for Certain Fire Protection Issues, Federal Register Vol. 76, No. 133, Tuesday July 12, 2011, pages 40777 through 40779.
- 2. Summary of May 18,2011, Meeting with the Nuclear Energy Institute, Industry Representatives, and Licensees on Transitioning to National Fire Protection Association Standard 805, May 31, 2011.
Dear Sir or Madam:
In accordance with the NRC Interim Enforcement Policy for Certain Fire Protection Issues (Reference 1), Entergy Operations, Inc. (Entergy) commits to submit the license amendment request (LAR) implementing 10 CFR 50.48(c) for Waterford Steam Electric Station, Unit 3 (Waterford 3) by November 30, 2011. This LAR will seek NRC approval to apply the methodology under National Fire Protection Association (NFPA) 805, Performance Based Standard for Fire Protection for Light Water Reactor Electric Generation Plants.
During a meeting conducted between members of Nuclear Energy Institute (NEI), industry representatives, and the NRC on May 18, 2011 (Reference 2), it was noted that Waterford 3 proposed to submit the LAR by the end of September 2011. It was also discussed in Reference 2, that these dates did not represent licensee commitments. Actual submittal dates would be based on licensee letters formally submitted to the NRC following additional assessment by the licensees.
The Waterford 3 Fire Protection Probabilistic Risk Assessment (PRA) is applying alternate PRA methods to those provided in NUREG/CR-6850 which are currently undergoing review by an EPRI Peer Review Group. Consistent with the NRC desire for these alternate methods to be resolved prior to submittal, Entergy is working toward timely resolution of Joseph A. Kowalewski Vice President, Operations Waterford 3 Entergy Operations, Inc.
17265 River Road Killona, LA 70057-3093 Tel 504-739-6715 Fax 504-739-6698 jkowale@entergy.com
W3F1-201 1-0061 Page 2 these changes in methods with the EPRI Peer Review Group. The proposed submittal by November 30, 2011 is based upon Entergys evaluation of the resources necessary to ensure the quality and completeness of the license amendment request and to allow for generic approval or plant specific application of these alternative methods.
Entergy believes that the proposed submittal date for the Waterlord 3 NFPA 805 LAR is responsive to the revised Policy Statement. Entergy requests that the enforcement discretion be extended to the LAR submittal commitment date.
This letter contains one new commitment.
If you have any questions or require additional information, please contact William J.
Steelman at 504-739-6685.
Sincerely,
,JS
Attachment:
List of Regulatory Commitments
W3F1-2011-0061 Page 3 cc:
Mr. Elmo E. Collins, Jr.
Regional Administrator U. S. Nuclear Regulatory Commission Region IV 612 E. Lamar Blvd., Suite 400 Arlington, TX 76011-4125 RidsRgn4MailCenter@nrc.gov NRC Senior Resident Inspector Waterford Steam Electric Station Unit 3 P.O. Box 822 Killona, LA 70066-0751 marlone.davis@nrc.gov Dean.Overland@nrc.gov U. S. Nuclear Regulatory Commission Attn: Mr. N. Kalyanam Mail Stop O-07D1 Washington, DC 20555-0001 Kaly.Kalyanam@nrc.gov
Attachment to W3F1-2011-0061 List of Regulatory Commitments
Attachment to W3F1-2011-0061 Page 1 of 1 List of Regulatory Commitments The following table identifies those actions committed to by Entergy in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.
TYPE (Check One)
COMMITMENT ONE-TIME ACTION CONTINUING COMPLIANCE SCHEDULED COMPLETION DATE (If Required)
Entergy Operations, Inc. (Entergy) commits to submit the License Amendment Request (LAR) implementing 10 CFR 50.48(c) for Waterford Steam Electric Station, Unit 3 (Waterford 3)
X November 30, 2011