Category:Inspection Report
MONTHYEARIR 05000445/20230042024-01-29029 January 2024 Integrated Inspection Report 05000445/2023004 and 05000446/2023004 ML24018A1072024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000445/2024012 and 05000446/2024012) and Request for Information IR 05000445/20234022023-11-30030 November 2023 NRC Security Inspection Report 05000445/2023402 and 05000446/2023402 IR 05000445/20230052023-08-23023 August 2023 Updated Inspection Plan for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2023005 and 05000446/2023005)- Mid Cycle Letter 2023 IR 05000445/20233012023-08-21021 August 2023 NRC Examination Report 05000445/2023301 and 05000446/2023301 IR 05000445/20230112023-07-20020 July 2023 Fire Protection Team Inspection Report 05000445/2023011 and 05000446/2023011 IR 05000445/20230022023-07-14014 July 2023 Integrated Inspection Report 05000445/2023002 and 05000446/2023002 IR 05000445/20230012023-04-13013 April 2023 Integrated Inspection Report 05000445/2023001 and 05000446/2023001 IR 05000445/20234012023-03-29029 March 2023 NRC Security Inspection Report 050004452023401 and 050004462023401 (Cover Letter Only) IR 05000445/20230102023-03-24024 March 2023 Biennial Problem Identification and Resolution Inspection Report 05000445/2023010 and 05000446/2023010 IR 05000445/20220062023-03-0101 March 2023 Annual Assessment Letter for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2022006 and 05000446/2022006) IR 05000445/20220042023-01-26026 January 2023 Integrated Inspection Report 05000445/2022004 and 05000446/2022004 IR 05000445/20220102023-01-23023 January 2023 TI-194 Report 05000445/2022010 and 05000446/2022010 IR 05000445/20224012022-12-19019 December 2022 Cyber Security Inspection Report 05000445/2022401 and 05000446/2022401 (Cover Letter Only) IR 05000445/20224202022-12-0707 December 2022 Security Baseline Inspection Report Cover Letter 05000445/2022420 and 05000446/2022420 ML22319A0732022-11-15015 November 2022 Review of the Fall 2021 Steam Generator Tube Inspection Report IR 05000445/20220032022-11-0101 November 2022 Integrated Inspection Report 05000445/2022003 and 05000446/2022003 and Notice of Violation ML22299A0562022-11-0101 November 2022 Integrated Inspection Report 05000445/2022003 and 05000446/2022003 and Notice of Violation IR 05000445/20220052022-08-22022 August 2022 Updated Inspection Plan for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2022005 and 05000446/2022005) IR 05000445/20224032022-08-0909 August 2022 NRC Security Inspection Report 05000445/2022403 and 05000446/2022403 (Full Report) IR 05000445/20220022022-08-0505 August 2022 2nd Quarter 2022 Integrated Inspection Report 05000445/2022002 and 05000446/2022002 ML22174A2792022-06-22022 June 2022 Notification of NRC Evaluations of Changes, Tests and Experiments Inspection (05000445/2022003 and 05000446/2022003) and Request for Information IR 05000445/20220012022-04-26026 April 2022 Integrated Inspection Report 05000445/2022001 and 05000446/2022001 IR 05000445/20224022022-04-25025 April 2022 Security Baseline Inspection Report 05000445/2022402 and 05000446/2022402 IR 05000445/20210062022-03-0202 March 2022 Annual Assessment Letter for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2021006 and 05000446/2021006) IR 05000445/20200112022-02-0707 February 2022 Amended - Comanche Peak Nuclear Power Plant - Triennial Fire Protection Inspection Report 05000445/2020011 and 05000446/2020011 and Notice of Violation IR 05000445/20210042022-01-25025 January 2022 Integrated Inspection Report 05000445/2021004 and 05000446/2021004 IR 05000445/20210122022-01-13013 January 2022 TI-194 Report 05000445/2021012 and 05000446/2021012 IR 05000445/20214052021-12-15015 December 2021 Security Baseline Inspection Report 05000445/2021405 and 05000446/2021405 IR 05000445/20214032021-12-0909 December 2021 Powerplant, Units 1 and 2 - Security Baseline Inspection Report 05000445/2021403 and 05000446/2021403 IR 05000445/20210032021-11-0303 November 2021 Integrated Inspection Report 05000445/2021003 and 05000446/2021003 IR 05000445/20213012021-10-19019 October 2021 NRC Examination Report 05000445/2021301 and 05000446/2021301 IR 05000445/20210102021-10-0707 October 2021 Biennial Problem Identification and Resolution Inspection Report 05000445/2021010 and 05000446/2021010 IR 05000445/20214012021-09-0909 September 2021 Security Baseline Inspection Report 05000445/2021401 and 05000446/2021401 IR 05000445/20210052021-09-0101 September 2021 Mid-Cycle Inspection Plan Transmittal Letter for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2021005 and 05000446/2021005) IR 05000445/20214022021-08-19019 August 2021 Security Baseline Inspection Report 05000445/2021402 and 05000446/2021402 IR 05000445/20210022021-08-10010 August 2021 Integrated Inspection Report 05000445/2021002 and 05000446/2021002 IR 05000445/20210012021-06-23023 June 2021 Revised Report - Comanche Peak Nuclear Plant, Units 1 and 2 - Integrated Inspection Report 05000445/2021001; 05000446/2021001 and Independent Spent Fuel Storage Inspection 07200074/2021001 IR 05000445/20214042021-06-17017 June 2021 Material Control and Accounting Program (Public) Inspection Report 05000445/2021404 05000446/2021404 ML21131A0952021-05-11011 May 2021 CP2021001-RP-JE, Comanche Peak Nuclear Power Plant, Units 1 and 2 - Integrated Inspection Report 05000445/2021001 and 05000446/2021001 IR 05000445/20210112021-05-0606 May 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000445/2021011 and 05000446/2021011 and Notice of Violation IR 07200074/20214012021-03-17017 March 2021 (CPNPP) Independent Spent Fuel Storage Installation (ISFSI) IR 07200074/2021401 3-3 IR 05000445/20200062021-03-0303 March 2021 Annual Assessment Letter for Comanche Peak, Units 1 and 2, (Inspection Report 05000445/2020006 and 05000446/2020006) IR 05000445/20200042021-02-0909 February 2021 Integrated Inspection Report 05000445/2020004 and 05000446/2020004 IR 05000445/20200012020-12-22022 December 2020 Revised Report - Comanche Peak Nuclear Power Plant, Units 1 and 2 -Integrated Inspection Report 05000445/2020001 and 05000446/2020001 IR 05000445/20200032020-11-10010 November 2020 Integrated Inspection Report 05000445/2020003 and 05000446/2020003 IR 05000445/20200102020-10-0606 October 2020 Design Basis Assurance Inspection (Programs) Inspection Report 05000445/2020010 and 05000446/2020010 ML20265A0422020-09-21021 September 2020 Commanche Peak Nuclear Power Plant - Triennial Fire Protection Inspection Report 05000445/2020011 and 05000446/2020011 and Notice of Violation IR 05000445/20204102020-09-10010 September 2020 Security Baseline Inspection Report 05000445/2020410 and 05000446/2020410 IR 05000445/20200052020-09-0101 September 2020 Updated Inspection Plan for Comanche Peak Nuclear Power Plant, Units 1 and 2 (Report 05000445/2020005 and 05000446/2020005) 2024-01-29
[Table view] Category:Letter
MONTHYEARCP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 IR 05000445/20230042024-01-29029 January 2024 Integrated Inspection Report 05000445/2023004 and 05000446/2023004 CP-202400034, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1)2024-01-29029 January 2024 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1) ML24024A2102024-01-29029 January 2024 Summary of Regulatory Audit Regarding a License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML24025A0052024-01-25025 January 2024 Review of the Spring 2023 Steam Generator Tube Inspection Report ML24023A0242024-01-24024 January 2024 Correction to Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident Methodology ML24018A1072024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000445/2024012 and 05000446/2024012) and Request for Information ML23159A2082023-12-20020 December 2023 Request for Withholding Information from Public Disclosure ML23319A3872023-12-20020 December 2023 Issuance of Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident (Fsloca) Methodology ML23348A2392023-12-19019 December 2023 Nonacceptance of License Amendment Request to Relocate Technical Specification 3.9.3, Nuclear Instrumentation, to the Technical Requirements Manual CP-202300575, (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 22023-12-13013 December 2023 (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 2 ML23333A0872023-12-13013 December 2023 Transmittal of Dam Safety Inspection Report - Public CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 ML23313A0732023-12-0606 December 2023 Issuance of Amendment Nos. 184 and 184 Regarding Revision to Technical Specifications to Implement WCAP-17661-P-A, Rev. 1, Improved Roac and CAOC Fq Surveillance Technical Specifications ML23291A4382023-11-30030 November 2023 Notice of Availability of the Draft Plant-Specific Supplement 60, to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Comanche Peak Nuclear Power Plant, Unit Numbers 1 and 2, License Renewal Applica ML23325A0182023-11-30030 November 2023 Schedule Revision for the License Renewal Application Review IR 05000445/20234022023-11-30030 November 2023 NRC Security Inspection Report 05000445/2023402 and 05000446/2023402 CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation ML23308A0032023-11-17017 November 2023 Letter to R. Nelson, Executive Director; Achp; Re., Comanche Peak Draft Environmental Impact Statement ML23308A0022023-11-17017 November 2023 Letter to M. Wolfe, Executive Director; Shpo; Re., Comanche Peak Draft Environmental Impact Statement ML23317A3002023-11-13013 November 2023 Letter to R. Sylestine, Chairman, Alabama-Coushatta Tribe of Texas Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2972023-11-13013 November 2023 Letter to R. Martin, President, Tonkawa Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2872023-11-13013 November 2023 Letter to J. Garza, Chairman, Kickapoo Traditional Tribe of Texas Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2832023-11-13013 November 2023 Letter to D. Dotson, President, Delaware Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2852023-11-13013 November 2023 Letter to E. Martinez, President, Mescalero Apache Tribe Regarding Comanche Peak Draft Environmental Impact Statement ML23306A0302023-11-13013 November 2023 Letter to J. Cernek, Chairman; Coushatta Tribe of Louisiana Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2902023-11-13013 November 2023 Letter to M. Pierite, Chairman, Tunica Biloxi Tribe of Louisiana Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2982023-11-13013 November 2023 Letter to R. Morrow, Town King, Thlopthlocco Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2842023-11-13013 November 2023 Letter to D. Kaskaske, Chairman, Kickapoo Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2822023-11-13013 November 2023 Letter to D. Cooper, Chairman, Apache Tribe of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2962023-11-13013 November 2023 Letter to M. Woommavovah, Chairman, Comanche Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2812023-11-13013 November 2023 Letter to C. Hoskin, Principal Chief, Cherokee Nation; Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2862023-11-13013 November 2023 Letter to J. Bunch, Chief, United Keetoowah Band of Cherokee Indians Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3032023-11-13013 November 2023 Letter to W. Yargee, Chief, Alabama-Quassarte Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2882023-11-13013 November 2023 Letter to L. Johnson, Chief, Seminole Nation of Oklahoma Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3012023-11-13013 November 2023 Letter to S. Yahola, Mekko, Kialegee Tribal Town Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2792023-11-13013 November 2023 Letter to B. Gonzalez, Chairman, Caddo Nation Regarding Comanche Peak Draft Environmental Impact Statement ML23317A3022023-11-13013 November 2023 Letter to T. Parton, President, Wichita and Affiliated Tribes Regarding Comanche Peak Draft Environmental Impact Statement ML23317A2892023-11-13013 November 2023 Letter to L. Spottedbird, Chairman, Kiowa Indian Tribe Regarding Comanche Peak Draft Environmental Impact Statement ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23360A6312023-10-26026 October 2023 FEMA, Submittal of Radiological Emergency Preparedness Final Report for the Comanche Peak Nuclear Power Plant Medical Services Drill Evaluated on August 23, 2023 CP-202300416, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-10-12012 October 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300432, Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 42023-10-0404 October 2023 Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 4 ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23263A0242023-09-21021 September 2023 Revision of Schedule for the Environmental Review of the Comanche Peak Nuclear Power Plant Units 1 and 2 License Renewal Application 2024-01-31
[Table view] |
See also: IR 05000445/2011004
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION IV
612 EAST LAMAR BLVD, SUITE 400
ARLINGTON, TEXAS 76011-4125
June 30, 2011
Rafael Flores, Senior Vice President
and Chief Nuclear Officer
Luminant Generation Company LLC
Comanche Peak Nuclear Power Plant
P.O. Box 1002
Glen Rose, TX 76043
SUBJECT: COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 -
NOTIFICATION OF INSPECTION (NRC INSPECTION REPORT
05000445/2011004; 05000446/2011004) AND REQUEST FOR INFORMATION
Dear Mr. Flores:
On August 15, 2011, the U.S. Nuclear Regulatory Commission (NRC) will begin the onsite
portion of the Gas Accumulation Management in Emergency Core Cooling, Decay Heat
Removal, and Containment Spray Systems Temporary Instruction at your Comanche Peak
Nuclear Power Plant, Units 1 and 2. This inspection will be performed in accordance with NRC
Temporary Instruction (TI) 2515/177.
Experience has shown that this inspection is resource intensive both for the NRC inspectors
and your staff. In order to minimize the impact to your onsite resources and to ensure a
productive inspection, we have enclosed a request for documents needed for this inspection.
The documents have been divided into two groups.
- The first group lists information necessary for our initial inspection scoping and in-office
preparation activities. This information should be separated by information request number,
especially if provided electronically (e.g., folder with the information request number). This
information should be available to the inspector no later than August 1, 2011. Upon review of
these documents, the inspectors will select additional documentation for review upon arrival.
By August 10, 2011, the inspector will communicate the initial selected samples.
- The second group of documents requested is needed to support our onsite inspection
activities. This set of documents should be available to the inspector on August 15, 2011. It
is also requested that corrective action documents and responses to questions developed
during the inspection be provided to the inspector as the documents are generated.
We have discussed the schedule for these inspection activities with your staff and understand
that our regulatory contact for this inspection will be Gary Merka of your licensing organization.
If there are any questions about this inspection or the materia! requested, please contact the
inspector, Matt Young, at 817-276-6545 or by email at '-'-==:.J:-==~=~='
-2-
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, control number
3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to,
a request for information or an information collection requirement unless the requesting
document displays a currently valid Office of Management and Budget control number.
In accordance with Code of Federal Regulations, Title 10, Part 2.390 of the NRC's Rules of
Practice, a copy of this letter and its enclosure will be available electronically for public
inspection in the NRC Public Document Room or from the Publicly Available Records (PARS)
component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web
site at (the Public Electronic Reading Room).
Thomas R. Farnholtz, Chief
Engineering Branch 1
Division of Reactor Safety
Dockets: 50-445; 50-446
Licenses: NPF-87; NPF-89
Enclosure: Management of Gas Accumulation in Emergency Core Cooling, Decay Heat
Removal, and Containment Spray Systems Temporary Instruction Document Request
cc w/encl:
Distribution via ListServ for Comanche Peak
MANAGEMENT OF GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY
HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS TEMPORARY INSTRUCTION
DOCUMENT REQUEST
inspection Report: 05000445/2011004; 05000446/2011004
On-site Inspection Dates: August 15-19, 2011
Inspection Procedure: TI 2515/177, "Management of Gas Accumulation in
Emergency Core Cooling, Decay Heat Removal, and
Containment Spray Systems"
Lead InspectorlTeam Leader: Matt Young
817 -276-6545
Matt.young@nrc.gov
The following information should be sent to the Region IV office in hard copy or electronic
format (ims.certrec.com or compact disc, preferred), in care of Matt Young, to facilitate the
selection of specific items that will be reviewed during the onsite inspection week. The
inspector will select specific items from the information requested below and then request from
your staff additional documents needed during the onsite inspection weeks. Also, we request
that you categorize the documents in your response with the numbered list below. Please
provide requested documentation electronically if possible. If requested documents are large
and only hard copy formats are available, please inform the inspector(s), and provide subject
documentation during the first day of the onsite inspection. If you have any questions regarding
this information request, please call the inspector as soon as possible.
I. Information Requested By August 1, 2011
1. List of corrective action program documents (with a short description) associated with
Generic Letter (GL) 2008-01, voids in piping, and pressure transients for the previous
three years.
2. List of changes (with a short description and tracking number) to the final safety analysis
report (FSAR), technical specifications, technical specification bases, and technical
requirements manual associated with the resolution of GL 2008-01.
3. List of calculations associated with GL 2008-01, including calculations that have been
changed or created in response to GL 2008-01 (with a short description of the
calculation and the change).
4. List (with a short description) of gas intrusion mechanisms that apply to the plant and the
affected system locations (e.g. identify the source, conditions, and expected void
locations).
5. List of the suction piping sections identified as susceptible to gas accumulation (the list
should identify the corresponding system).
- 1- Enclosure
6. List of the discharge piping sections identified as susceptible to gas accumulation (the
list should identify the corresponding system).
7. Copies of isometric drawings of the emergency core cooling, residual heat removal, and
containment spray systems (hard-copies are preferred).
8. Copies of piping and instrumentation diagrams (P&IDs) of the emergency core cooling,
residual heat removal, and containment spray systems (hard-copies are preferred).
9. Copies of program documents and procedures developed to implement the resolution of
GL 2008-01.
10. List of actions that were completed in response to GL 2008-01.
11. Copies of the modification packages for hardware modifications as part of the resolution
of GL 2008-01.
12. Design basis documents of the emergency core cooling, residual heat removal, and
containment spray systems.
13. Design basis documents of keep-full systems of the emergency core cooling, residual
heat removal, and containment spray systems.
14. System walkdown reports associated with the resolution of GL 2008-01.
15. If applicable, provide a list of inaccessible locations where plant walkdowns of the
emergency core cooling, residual heat removal, and containment spray systems have
not been completed. Include an explanation of why each area is considered
inaccessible.
16. Copies of surveillance procedures associated with the resolution of GL 2008-01 and the
results of the last two surveillances for the emergency core cooling, residual heat
removal, and containment spray systems.
17. Copies of procedures used for detecting and determining void volumes.
18. Copies of procedures used for filling and venting.
19. Copies of trends of periodic venting results.
20. Copies of the engineering evaluations performed for all identified voids in the past three
years.
21. Basis for the void acceptance criteria (e.g. calculation). If applicable, provide the
justification for any deviation from the void acceptance criteria established by the Office
of Nuclear Reactor Regulation (NRR).
22. Copy of any void transport analyses.
-2- Enclosure
23. Copy of vortexing calculations associated with systems under the scope of GL 2008-01.
24. Copies of self-assessments associated with the implementation of the GL 2008-01
program.
II. Information Requested By August 15,2011
25. Copies of the selected corrective action program documents.
26. Copies of the selected licensing and design basis document changes.
27. Copies of the selected calculations.
28. Copies of training documents that ensure that personnel are aware of gas-related
concerns.
29. Copies of corrective action program implementing procedures.
30. Electronic copies of the current technical specifications, technical specification bases,
final safety analysis report, and technical requirements manual.
-3- Enclosure