MONTHYEARML1109602832011-03-30030 March 2011 License Amendment Request Pursuant to 10 CFR 50.90: Request for Adoption of Technical Specification Task Force Traveler TSTF-514, Revision 3, Revise BWR Operability Requirements and Actions for RCS Leakage ... Project stage: Request ML1109704152011-04-0707 April 2011 Acceptance Review Determination LAR to Adopt TSTF-514, Revision 3 Project stage: Acceptance Review ML1133000382011-11-30030 November 2011 Issuance of Amendment Regarding Adoption of Technical Specification Task Force Traveler TSTF-514, Revision 3 Project stage: Approval 2011-03-30
[Table View] |
|
---|
Category:Letter
MONTHYEARML24268A3382024-10-16016 October 2024 Issuance of Amendment No. 253 Regarding the Modification of TS Surveillance Requirement 4.3.6.a Related to Adoption of TSTF-425, Revision 3 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing IR 05000220/20243022024-10-0303 October 2024 Initial Operator Licensing Examination Report 05000220/2024302 NMP1L3608, Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-09-20020 September 2024 Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000220/20240052024-08-29029 August 2024 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2024005 and 05000410/2024005) IR 05000220/20240102024-08-22022 August 2024 Age-Related Degradation Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3603, Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan2024-08-20020 August 2024 Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000220/20240022024-08-0505 August 2024 Integrated Inspection Report 05000220/2024002 and 05000410/2024002 ML24215A3002024-08-0202 August 2024 Operator Licensing Examination Approval ML24213A1412024-07-31031 July 2024 Requalification Program Inspection NMP1L3601, Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-07-31031 July 2024 Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation NMP2L2883, Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations2024-07-24024 July 2024 Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations ML24198A0852024-07-16016 July 2024 Senior Reactor and Reactor Operator Initial License Examinations RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations NMP1L3584, License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2024-06-13013 June 2024 License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000220/20244012024-05-30030 May 2024 Security Baseline Inspection Report 05000220/2024401 and 05000410/2024401(Cover Letter Only) ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 NMP1L3591, Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request2024-05-18018 May 2024 Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request NMP1L3589, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-05-16016 May 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable NMP1L3582, 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 22024-05-15015 May 2024 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 2 ML24158A2052024-05-15015 May 2024 Annual Radioactive Environmental Operating Report IR 05000220/20240012024-05-10010 May 2024 Integrated Inspection Report 05000220/2024001 and 05000410/2024001 RS-24-049, Updated Notice of Intent to Pursue Subsequent License Renewal Applications2024-05-0909 May 2024 Updated Notice of Intent to Pursue Subsequent License Renewal Applications RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds NMP2L2880, Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum2024-05-0101 May 2024 Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum NMP1L3581, Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report2024-04-30030 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests NMP2L2877, 2023 Annual Environmental Operating Report2024-04-19019 April 2024 2023 Annual Environmental Operating Report NMP2L2878, Core Operating Limits Report2024-04-16016 April 2024 Core Operating Limits Report ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24092A3352024-04-0101 April 2024 NRC Office of Investigations Case No. 1-2023-002 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24074A2812024-03-14014 March 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3577, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-03-13013 March 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable IR 05000220/20230062024-02-28028 February 2024 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2, (Reports 05000220/2023006 and 05000410/2023006) NMP1L3570, Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-02-0101 February 2024 Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation IR 05000220/20230042024-02-0101 February 2024 Integrated Inspection Report 05000220/2023004 and 05000410/2023004 05000410/LER-2023-001, Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater2024-01-30030 January 2024 Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater NMP1L3569, CFR 50.46 Annual Report2024-01-26026 January 2024 CFR 50.46 Annual Report ML24004A2122024-01-0808 January 2024 Senior Reactor and Reactor Operator Initial License Examinations ML23354A0012024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0059 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines NMP1L3566, Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station2023-12-14014 December 2023 Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station IR 05000410/20243012023-12-14014 December 2023 Initial Operator Licensing Examination Report 05000410/2024301 ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 2024-09-04
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARNMP1L3584, License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2024-06-13013 June 2024 License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML23151A3472023-08-21021 August 2023 Issuance of Amendments to Adopt TSTF-295-A, Modify Note 2 to Actions of PAM Table to Allow Separate Condition Entry for Each Penetration NMP1L3534, License Amendment Request - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2023-08-18018 August 2023 License Amendment Request - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling NMP1L3484, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Reatment of Structures, Systems and Components for Nuclear Power Reactors2022-12-15015 December 2022 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Reatment of Structures, Systems and Components for Nuclear Power Reactors NMP1L3482, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-12-15015 December 2022 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML22298A0112022-10-25025 October 2022 License Amendment Request to Adopt Technical Specification Task Force TSTF-295-A, Modify Note 2 to Actions of (Post-Accident Monitoring) PAM Table To. RS-22-092, Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration2022-10-0303 October 2022 Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration NMP1L3477, License Amendment Request - Application to Partially Adopt Technical Specification Task Force (TSTF) Traveler TSTF-568, Revision 2, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2, to Revise.2022-08-12012 August 2022 License Amendment Request - Application to Partially Adopt Technical Specification Task Force (TSTF) Traveler TSTF-568, Revision 2, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2, to Revise. NMP1L3467, License Amendment Request - Revision to Alternative Source Term Calculation for Main Steam Isolation Valve (MSIV) Leakage and Non-MSIV Leakage2022-06-29029 June 2022 License Amendment Request - Revision to Alternative Source Term Calculation for Main Steam Isolation Valve (MSIV) Leakage and Non-MSIV Leakage NMP2L2799, License Amendment Request - Revise Surveillance Requirements to Reduce Excessive Fast Starting of Emergency Diesel Generators2022-05-24024 May 2022 License Amendment Request - Revise Surveillance Requirements to Reduce Excessive Fast Starting of Emergency Diesel Generators RS-22-004, Supplement to Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2022-01-0404 January 2022 Supplement to Application to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements ML21277A1932021-11-16016 November 2021 Enclosure 2, Draft Conforming License Amendments NMP2L2780, Application to Revise Technical Specifications to Adopt TSTF-582, Revision 0, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2021-09-30030 September 2021 Application to Revise Technical Specifications to Adopt TSTF-582, Revision 0, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements JAFP-21-0089, Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2021-09-27027 September 2021 Application to Revise Technical Specifications to Adopt TSTF-541 Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position NMP2L2762, License Amendment Request Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control2021-05-26026 May 2021 License Amendment Request Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control RS-21-039, Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments2021-03-25025 March 2021 Supplemental Information Regarding Application for Order Approving Transfers and Proposed Conforming License Amendments ML21057A2732021-02-25025 February 2021 Application for Order Approving License Transfers and Proposed Conforming License Amendments NMP1L3369, Application to Revise Technical Specifications to Adopt TSTF-582, Revision 0 Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2020-12-18018 December 2020 Application to Revise Technical Specifications to Adopt TSTF-582, Revision 0 Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements RS-20-031, License Amendment Request - Application to Adopt Technical Specification Task Force (TSTF) Traveler TSTF-568, Revision 2, Revise Applicability of BWR/4 TS 3.6.2 .5 and TS 3.6 .3.2, Using the Consolidated Line Item Improvement Process2020-04-30030 April 2020 License Amendment Request - Application to Adopt Technical Specification Task Force (TSTF) Traveler TSTF-568, Revision 2, Revise Applicability of BWR/4 TS 3.6.2 .5 and TS 3.6 .3.2, Using the Consolidated Line Item Improvement Process NMP2L2716, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2019-12-26026 December 2019 Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors NMP2L2706, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b.2019-10-31031 October 2019 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b. RS-19-044, License Amendment Request - Deletion of Facility Operating License Conditions Related to Decommissioning Trust Provisions2019-08-28028 August 2019 License Amendment Request - Deletion of Facility Operating License Conditions Related to Decommissioning Trust Provisions JAFP-19-0067, Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability2019-06-27027 June 2019 Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability NMP1L3278, License Amendment Request - Administrative Changes to the Technical Specifications2019-06-26026 June 2019 License Amendment Request - Administrative Changes to the Technical Specifications RS-19-040, Application to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2019-06-25025 June 2019 Application to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program NMP2L2699, License Amendment Request to Revise Technical Specifications Main Steam Isolation Valve Leak Rate2019-05-31031 May 2019 License Amendment Request to Revise Technical Specifications Main Steam Isolation Valve Leak Rate RS-19-003, Application to Adopt TSTF-564, Safety Limit Mcpr.2019-02-0101 February 2019 Application to Adopt TSTF-564, Safety Limit Mcpr. NMP2L2694, Emergency License Amendment Request: One Time Extension to the High Pressure Core Spray Completion Time and Associated Surveillances2018-12-0606 December 2018 Emergency License Amendment Request: One Time Extension to the High Pressure Core Spray Completion Time and Associated Surveillances NMP1L3192, License Amendment Request - Revise Technical Specification 3.3.1 for Primary Containment Oxygen Concentration2018-06-26026 June 2018 License Amendment Request - Revise Technical Specification 3.3.1 for Primary Containment Oxygen Concentration RS-18-020, Application to Revise Technical Specifications to Modify the APRM Channel Adjustment Surveillance Requirement2018-06-15015 June 2018 Application to Revise Technical Specifications to Modify the APRM Channel Adjustment Surveillance Requirement RS-17-161, Fleet License Amendment Request to Relocate Technical Specification Unit/Facility/Plant Staff Qualification ANSI N18.1-1971 and ANSl/ANS-3.1-1978 Requirements to the Exelon Quality Assurance Topical Report (QATR)2018-03-0101 March 2018 Fleet License Amendment Request to Relocate Technical Specification Unit/Facility/Plant Staff Qualification ANSI N18.1-1971 and ANSl/ANS-3.1-1978 Requirements to the Exelon Quality Assurance Topical Report (QATR) NMP1L3188, License Amendment Request - Proposed Change to Remove Boraflex Credit from Spent Fuel Racks2018-02-0909 February 2018 License Amendment Request - Proposed Change to Remove Boraflex Credit from Spent Fuel Racks NMP1L3142, License Amendment Request - Revise Technical Specifications to Apply TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 22017-12-15015 December 2017 License Amendment Request - Revise Technical Specifications to Apply TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 2 RS-17-137, Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements2017-11-0808 November 2017 Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements NMP2L2660, License Amendment Request - Safety Limit Minimum Critical Power Ratio Change2017-11-0303 November 2017 License Amendment Request - Safety Limit Minimum Critical Power Ratio Change NMP2L2652, License Amendment Request - Revise Surveillance Requirement 3.5.1.2 to Remove Note2017-08-22022 August 2017 License Amendment Request - Revise Surveillance Requirement 3.5.1.2 to Remove Note ML17164A1542017-05-31031 May 2017 Enclosure 4C - EAL Basis Document for Nine Mile Point Nuclear Station, Unit 1 ML17164A1552017-05-31031 May 2017 Enclosure 4D - EAL Front Matter for Nine Mile Point Nuclear Station, Unit 1 ML17164A1532017-05-31031 May 2017 Enclosure 4B - EAL Red-Line Basis Document for Nine Mile Point Nuclear Station, Unit 1 NMP2L2641, License Amendment Request - Revise Technical Specifications to Adopt TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours Per Month, Revision 02017-05-31031 May 2017 License Amendment Request - Revise Technical Specifications to Adopt TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours Per Month, Revision 0 NMP1L3158, Enclosure 4E - Procedure Matrix for Nine Mile Point Nuclear Station, Unit 12017-05-31031 May 2017 Enclosure 4E - Procedure Matrix for Nine Mile Point Nuclear Station, Unit 1 JAFP-17-0050, Exigent License Amendment Request to Revise Emergency Action Level HU1.52017-05-19019 May 2017 Exigent License Amendment Request to Revise Emergency Action Level HU1.5 ML17037C4192017-05-11011 May 2017 Amendment to Operating License/Change to Appendix a of Technical Specification Concerning Certain Repairs at Facility and Concomitantly to Allow a Continuation of a Slightly Lower Water Level in the Reactor... NMP2L2643, License Amendment Request-Adoption of TSTF-283-A, Revision 3, Modify Section 3.8 Mode Restriction Notes2017-04-0505 April 2017 License Amendment Request-Adoption of TSTF-283-A, Revision 3, Modify Section 3.8 Mode Restriction Notes RS-17-049, Application to Revise Technical Specifications to Adopt TSTF-529 Clarify Use and Application Rules, Revision 4, Using the Consolidated Line Item Improvement Process2017-03-28028 March 2017 Application to Revise Technical Specifications to Adopt TSTF-529 Clarify Use and Application Rules, Revision 4, Using the Consolidated Line Item Improvement Process NMP2L2640, License Amendment Request - Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 22017-02-28028 February 2017 License Amendment Request - Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 2 NMP2L2639, Supplement to License Amendment Request - Proposed Revision to Technical Specification in Response to GE Energy- Nuclear 10 CFR Part 21 Safety Communication SC05-032017-02-17017 February 2017 Supplement to License Amendment Request - Proposed Revision to Technical Specification in Response to GE Energy- Nuclear 10 CFR Part 21 Safety Communication SC05-03 NMP1L3122, License Amendment Request - Proposed Changes Regarding Partial Length Fuel Rod (PLR) Burnup2017-01-0303 January 2017 License Amendment Request - Proposed Changes Regarding Partial Length Fuel Rod (PLR) Burnup 2024-06-13
[Table view] Category:Technical Specification
MONTHYEARNMP1L3601, Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-07-31031 July 2024 Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling NMP1L3482, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-12-15015 December 2022 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML22298A0112022-10-25025 October 2022 License Amendment Request to Adopt Technical Specification Task Force TSTF-295-A, Modify Note 2 to Actions of (Post-Accident Monitoring) PAM Table To. ML22292A1312022-10-0505 October 2022 5 to Updated Final Safety Analysis Report, Technical Specification Bases, Rev. 69 RS-22-092, Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration2022-10-0303 October 2022 Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration NMP1L3477, License Amendment Request - Application to Partially Adopt Technical Specification Task Force (TSTF) Traveler TSTF-568, Revision 2, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2, to Revise.2022-08-12012 August 2022 License Amendment Request - Application to Partially Adopt Technical Specification Task Force (TSTF) Traveler TSTF-568, Revision 2, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2, to Revise. NMP2L2780, Application to Revise Technical Specifications to Adopt TSTF-582, Revision 0, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2021-09-30030 September 2021 Application to Revise Technical Specifications to Adopt TSTF-582, Revision 0, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements NMP2L2762, License Amendment Request Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control2021-05-26026 May 2021 License Amendment Request Adoption of Technical Specification Task Force (TSTF) Traveler TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control JAFP-20-0049, Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability2020-06-22022 June 2020 Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability NMP2L2718, Supplemental Information No.1 for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 22019-12-12012 December 2019 Supplemental Information No.1 for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 JAFP-19-0067, Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability2019-06-27027 June 2019 Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability RS-19-039, Fleet License Amendment Request - Common Language for Technical Specification High Radiation Area Administrative Controls2019-06-26026 June 2019 Fleet License Amendment Request - Common Language for Technical Specification High Radiation Area Administrative Controls NMP2L2693, Technical Specification Bases, Rev. 572018-10-24024 October 2018 Technical Specification Bases, Rev. 57 NMP2L2664, Supplemental Information No. 2 for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 22018-01-12012 January 2018 Supplemental Information No. 2 for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 2 NMP2L2652, License Amendment Request - Revise Surveillance Requirement 3.5.1.2 to Remove Note2017-08-22022 August 2017 License Amendment Request - Revise Surveillance Requirement 3.5.1.2 to Remove Note NMP2L2640, License Amendment Request - Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 22017-02-28028 February 2017 License Amendment Request - Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 2 ML16309A4002016-10-24024 October 2016 Revision 47 to Technical Specification Bases, List of Effective Pages ML16309A4022016-10-24024 October 2016 Revision 47 to Technical Specification Bases, Section B2.0, Safety Limits (Sls) ML16309A4032016-10-24024 October 2016 Revision 47 to Technical Specification Bases, Section B3.0, Limiting Condition for Operation (LCO) Applicability ML16309A4012016-10-24024 October 2016 Revision 47 to Technical Specification Bases, Table of Contents ML16309A4052016-10-24024 October 2016 Revision 47 to Technical Specification Bases, Section B3.2, Power Distribution Limits ML16309A4082016-10-24024 October 2016 Revision 47 to Technical Specification Bases, Section B3.5, Emergency Core Cooling Systems (ECCS) and Reactor Core Isolation Cooling (RCIC) System ML16309A4132016-10-24024 October 2016 Revision 47 to Technical Specification Bases, Section B3.9, Refueling Operations ML16209A2182016-07-26026 July 2016 Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3, TS Lnservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing. NMP1L3070, License Amendment Request - Reactivity Anomalies Surveillance2016-03-18018 March 2016 License Amendment Request - Reactivity Anomalies Surveillance NMP2L2592, Supplemental Information Regarding TSTF-425 License Amendment Request2015-09-24024 September 2015 Supplemental Information Regarding TSTF-425 License Amendment Request NMP1L3027, Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3)2015-05-12012 May 2015 Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3) ML15089A2312015-03-26026 March 2015 Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3) NMP1L3010, Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3)2015-03-26026 March 2015 Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3) NMP2L2576, License Amendment Request - Relocation of Secondary Containment Bypass Leakage Paths Table from Technical Specifications to the Technical Requirements Manual2015-03-23023 March 2015 License Amendment Request - Relocation of Secondary Containment Bypass Leakage Paths Table from Technical Specifications to the Technical Requirements Manual NMP2L2563, License Amendment Request - Primary Containment Isolation Instrumentation Technical Specification Allowable Value Change2014-11-17017 November 2014 License Amendment Request - Primary Containment Isolation Instrumentation Technical Specification Allowable Value Change ML14191A2552014-07-10010 July 2014 Nine Mile Point and Ginna, Unit 1 - Application to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process ML12156A3632012-06-0101 June 2012 Emergency License Amendment Request Pursuant to 10 CFR 50.90: Revision of the Main Steam Isolation Valve Allowable Leakage Rate Limit ML11306A2982011-10-27027 October 2011 Submittal of Revision 22 to the Final Safety Analysis Report (Updated), 10 CFR 50.59 Evaluation Summary Report, Technical Specifications Bases Changes, and Report Consistent with 10 CFR 54.37(b) ML11214A2142011-07-25025 July 2011 License Amendment Request, Extension of the Completion Time for Inoperable Diesel Generator - Response to NRC Request for Additional Information ML1109602832011-03-30030 March 2011 License Amendment Request Pursuant to 10 CFR 50.90: Request for Adoption of Technical Specification Task Force Traveler TSTF-514, Revision 3, Revise BWR Operability Requirements and Actions for RCS Leakage ... ML0935000902009-12-0909 December 2009 License Amendment Request to Remove Operating Mode Restrictions for Performing Surveillance Testing of the Division 3 Battery - Technical Specification 3.8.4, DC Sources - Operating ML0931602572009-10-26026 October 2009 Submittal of Revision 21 to the Final Safety Analysis Report (Updated), 10 CFR 50.59 Evaluation Summary Report, Technical Specifications Bases Changes, and Report Consistent with 10 CFR 54.37(b) ML0907802502009-03-0909 March 2009 Submittal of Amendment Request for Technical Specification Improvement to Revise Control Rod Scram Time Testing Frequency ML0906403012009-03-0303 March 2009 License Amendment Request Pursuant to 10 CFR 50.90: Relocation of Pressure and Temperature Limit Curves to the Pressure and Temperature Limits Report ML0827502992008-09-29029 September 2008 Technical Specifications ML0802501622008-01-24024 January 2008 Response to NRC Request for Additional Information Regarding Nine Mile Point Nuclear Station, Unit No. 1, Revision of Rod Worth Minimizer Limiting Condition for Operation During Startup ML0726401032007-09-19019 September 2007 License Amendment Request for Adoption of TSTF-484, Revision 0, Use of TS 3.10.1 for Scram Time Testing Activities. ML0721906052007-07-30030 July 2007 Application for Technical Specification Change TSTF-477, Rev. 3, Add Action for Two Inoperable Control Room AC Subsystems to the Technical Specifications Using Consolidated Line Item Improvement Process ML0721205922007-07-23023 July 2007 Application for Technical Specification Improvement to Adopt TSTF-476, Revison 1, Improved BPWS Control Rod Insertion Process (NEDO-33091), Using the Consolidated Line Item Improvement ML0721205872007-07-23023 July 2007 License Amendment Request Pursuant to 10 CFR 50.90: Revision of Rod Worth Minimizer Limiting Condition for Operation During Startup - Technical Specification Section 3.1.1.b ML0720504232007-07-12012 July 2007 Application to Revise Technical Specifications Regarding Control Room Envelope Habitability in Accordance with TSTF-448, Revision 3, Using the Consolidated Line Item Improvement Process ML0720504742007-07-12012 July 2007 Application to Revise Technical Specifications Regarding Control Room Envelope Habitability in Accordance with TSTF-448, Revision 3, Using the Consolidated Line Item Improvement Process 2024-07-31
[Table view] Category:Amendment
MONTHYEARML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling NMP1L3482, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2022-12-15015 December 2022 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML22298A0112022-10-25025 October 2022 License Amendment Request to Adopt Technical Specification Task Force TSTF-295-A, Modify Note 2 to Actions of (Post-Accident Monitoring) PAM Table To. RS-22-092, Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration2022-10-0303 October 2022 Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration NMP2L2780, Application to Revise Technical Specifications to Adopt TSTF-582, Revision 0, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements2021-09-30030 September 2021 Application to Revise Technical Specifications to Adopt TSTF-582, Revision 0, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements JAFP-20-0049, Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability2020-06-22022 June 2020 Application to Adopt TSTF-427, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System Operability NMP2L2718, Supplemental Information No.1 for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 22019-12-12012 December 2019 Supplemental Information No.1 for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 RS-19-039, Fleet License Amendment Request - Common Language for Technical Specification High Radiation Area Administrative Controls2019-06-26026 June 2019 Fleet License Amendment Request - Common Language for Technical Specification High Radiation Area Administrative Controls NMP2L2664, Supplemental Information No. 2 for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 22018-01-12012 January 2018 Supplemental Information No. 2 for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 2 NMP2L2652, License Amendment Request - Revise Surveillance Requirement 3.5.1.2 to Remove Note2017-08-22022 August 2017 License Amendment Request - Revise Surveillance Requirement 3.5.1.2 to Remove Note NMP2L2640, License Amendment Request - Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 22017-02-28028 February 2017 License Amendment Request - Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 2 NMP1L3027, Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3)2015-05-12012 May 2015 Application for Technical Specifications Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program (Adoption of TSTF-425, Revision 3) NMP2L2576, License Amendment Request - Relocation of Secondary Containment Bypass Leakage Paths Table from Technical Specifications to the Technical Requirements Manual2015-03-23023 March 2015 License Amendment Request - Relocation of Secondary Containment Bypass Leakage Paths Table from Technical Specifications to the Technical Requirements Manual NMP2L2563, License Amendment Request - Primary Containment Isolation Instrumentation Technical Specification Allowable Value Change2014-11-17017 November 2014 License Amendment Request - Primary Containment Isolation Instrumentation Technical Specification Allowable Value Change ML14191A2552014-07-10010 July 2014 Nine Mile Point and Ginna, Unit 1 - Application to Revise Technical Specifications to Adopt TSTF-523, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process ML1109602832011-03-30030 March 2011 License Amendment Request Pursuant to 10 CFR 50.90: Request for Adoption of Technical Specification Task Force Traveler TSTF-514, Revision 3, Revise BWR Operability Requirements and Actions for RCS Leakage ... ML0935000902009-12-0909 December 2009 License Amendment Request to Remove Operating Mode Restrictions for Performing Surveillance Testing of the Division 3 Battery - Technical Specification 3.8.4, DC Sources - Operating ML0907802502009-03-0909 March 2009 Submittal of Amendment Request for Technical Specification Improvement to Revise Control Rod Scram Time Testing Frequency ML0906403012009-03-0303 March 2009 License Amendment Request Pursuant to 10 CFR 50.90: Relocation of Pressure and Temperature Limit Curves to the Pressure and Temperature Limits Report ML0827502992008-09-29029 September 2008 Technical Specifications ML0720504742007-07-12012 July 2007 Application to Revise Technical Specifications Regarding Control Room Envelope Habitability in Accordance with TSTF-448, Revision 3, Using the Consolidated Line Item Improvement Process ML0707800592007-03-15015 March 2007 Technical Specification 4.1.1 Regarding Control Rod System Surveillance Requirements ML0536202882005-12-16016 December 2005 License Amendment Request: Proposed Changes to Technical Specification 4.1.4 Regarding Core Spray Instrumentation ML0511100732005-04-19019 April 2005 Tech Spec Pages for Amendment 115 and 188 Reporting Requirements for Annual Radiological Environmental Operating Report ML0510204002005-04-0101 April 2005 License Amendment Request Pursuant to 1O CFR 50.90: Request for Amendment to Extend Completion Time for Emergency Uninterruptible Power Supply Inverters ML0503304712005-01-24024 January 2005 Application for Technical Specification Improvement to Eliminate Requirements to Provide Monthly Operating Reports and Occupational Radiation Exposure Reports ML0424003162004-08-17017 August 2004 Unit I, License Amendment Request Pursuant to 10 CFR 50.90: Addition of 24 Hours for Restoration of Primary Containment Oxygen Concentration ML0421103812004-07-16016 July 2004 License Amendment Request Pursuant to 10 CFR 50.90: Revision of Intermediate Range Monitor Surveillance Frequency and Relocation of Selected Instrumentation Requirements to a License-Controlled Document ML0403302112004-01-27027 January 2004 TS Amendment Pages for License No. NPF-069 ML0330305992003-10-27027 October 2003 TS Pages Amendment 183 ML0324608472003-08-15015 August 2003 License Amendment Request Pursuant to 10 CFR 50.90: Revision of Reactor Pressure Vessel Pressure-Temperature Limits ML0233807302002-11-22022 November 2002 Facility Operating License DPR-63, License Amendment Request: Technical Specifications Section 6.0, Administrative Controls - Response to RA Information TAC No. MB2441 ML0229603382002-10-0707 October 2002 Application for Technical Specification Change Regarding Missed Surveillances Using the Consolidated Line Item Improvement Process ML0217101682002-06-0707 June 2002 Application for Technical Specification Improvement to Eliminate the Requirements for the Post Accident Sampling System Using the Consolidated Line Item Improvement Process ML0207305992002-03-13013 March 2002 Technical Specifications, Issuance of Amendment Safety Limit Minimum Critical Power Ratio (Tac No. MB3327) ML0206302682002-03-0101 March 2002 Technical Specifications for Amendment No. 103 ML0204301512002-02-11011 February 2002 Issuance of Amendment Ventilation Requirements During Irradiated Fuel Handling ML18018B0461978-03-22022 March 1978 Letter Transmitting an Application for Amendment to Appendix a of the Operating License ML17037C4331977-08-0808 August 1977 Letter Regarding Surveillance Requirements and Limiting Conditions for Operations and Requesting an Application for Amendment to the Operating License That Will Change the Technical Specifications ML17037C4131977-07-22022 July 1977 Letter Enclosing Application for Amendment to Operating License and Proposed Changes to Technical Specifications Concerning Changes in Management and Organization ML17037C4141977-07-18018 July 1977 Letter Enclosing an Application for Amendment to Operating License and Proposed Changes to the Technical Specifications to Provide for More Flexible Operation and Concerning Load Line Limit Analysis ML17037C4161977-07-14014 July 1977 Application for Amendment to Operating License and Proposed Change to Technical Specification Concerning the Emergency Cooling System ML17037C4181977-05-19019 May 1977 Letter Enclosing an Application to Amend Operating License and a Requested Change in the Technical Specifications Relating to Instrumentation Used to Monitor Drywell Suppression Chamber Differential Pressure and Suppression .. ML17037C4341977-03-0404 March 1977 Letter Regarding a Preliminary Review of the December 7, 1976 Request for Technical Specification Changes to Reactor Operating Limits After Reload for Cycle 5 Operation and Requesting Additional Information to Complete Review ML17037C4391976-09-30030 September 1976 Letter Requesting Submittal of an Application for License Amendment to Incorporate the Requirements of the Model Technical Specifications ML17037C4531976-01-19019 January 1976 Letter Transmitting an Application for Amendment to Operating License and a Proposed Change to Technical Specifications (Appendix a) to Clarify Cloride and Oxygen Levels ML17037C1771975-12-19019 December 1975 Letter Enclosing a Corrected Attachment to License Amendment No. 11 Change No. 27 to the Technical Specifications Provisional Operating License No. DPR-16 ML17037C1831975-11-0303 November 1975 Letter Regarding Application for Amendment to Technical Specifications and an Inadvertent Error Not Made on the Persons Listed in the Certificate of Service ML17037C4681975-09-23023 September 1975 Letter Regarding a Stress Assisted Corrosion Problem and an Enclosed Safety Evaluation by the Office of NRR - Supporting Amendment to License No. DPR-63 and Changes to the Technical Specifications Inoperable Control Rod .. 2024-04-12
[Table view] |
Text
Sam Belcher P.O. Box 63 Vice President-Nine Mile Point Lycoming, New York 13093 315.349.5200 315.349.1321 Fax CENGO.
a joint venture of Constellation e NINE MILE POINT NUCLEAR STATION March 30, 2011 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTENTION: Document Control Desk
SUBJECT:
Nine Mile Point Nuclear Station Unit No. 2, Docket No. 50-410 License Amendment Request Pursuant to 10 CFR 50.90: Request for Adoption of Technical Specification Task Force Traveler TSTF-514, Revision 3, "Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation" Pursuant to 10 CFR 50.90, Nine Mile Point Nuclear Station, LLC (NMPNS) hereby requests an amendment to the Nine Mile Point Unit 2 (NMP2) Renewed Facility Operating License NPF-69.
The proposed amendment would revise Technical Specification (TS) Section 3.4.7, "RCS Leakage Detection Instrumentation," to define a new time limit for restoring inoperable Reactor Coolant System (RCS) leakage detection instrumentation to operable status and establish alternate methods of monitoring RCS leakage when required monitors are inoperable. TS Bases changes which reflect the proposed changes and more accurately reflect the contents of the facility design basis related to operability of the RCS leakage detection instrumentation are provided for information only. These changes are consistent with NRC-approved Revision 3 to Technical Specification Task Force (TSTF) Improved Standard Technical Specification (STS) Change Traveler TSTF-514, "Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation." The availability of this TS improvement was announced in the Federal Register on December 17, 2010 (75 FR 79048) as part of the consolidated line item improvement process (CLIIP).
The Enclosure provides an evaluation of the proposed changes and a marked-up copy of the existing TS and TS Bases pages to show the proposed changes. NMPNS has concluded that the activities associated Aoo0
Document Control Desk March 30, 2011 Page 2 with the proposed amendment represent no significant hazards consideration under the standards set forth in 10 CFR 50.92. There are no regulatory commitments identified in this submittal.
Approval of the proposed license amendment is requested by March 29, 2012, with implementation within 90 days of receipt of the approved amendment.
Pursuant to 10 CFR 50.91(b)(1), NMPNS has provided a copy of this license amendment request, with Enclosure, to the appropriate state representative.
Should you have any questions regarding the information in this submittal, please contact John J. Dosa, Director Licensing, at (315) 349-5219.
Very truly yours, STATE OF NEW YORK TO WIT:
COUNTY OF OSWEGO I, Sam Belcher, being duly sworn, state that I am Vice President-Nine Mile Point, and that I am duly authorized to execute and file this license amendment request on behalf of Nine Mile Point Nuclear Station, LLC. To the best of my knowledge and belief, the statements contained in this document are true and correct. To the extent that these statements are not based on my personal knowledge, they are based upon information provided by other Nine Mile Point employees and/or consultants. Such information has been reviewed in accordance with company practice and I believe it to be reliable.
Subscribed and sworn before me, a Notary Public in and for the State of New York and County of
_____ ,this -ZD dayof W.*ck) ,2011.
WITNESS my Hand and Notarial Seal: AlD4(. *'
Notary Public My Commission Expires:
Date O o w R N. 01 My CombdoIto 1pW12/201
Document Control Desk March 30, 2011 Page 3 SB/JMT
Enclosure:
Evaluation of the Proposed Change cc: Regional Administrator, Region I, NRC Project Manager, NRC Resident Inspector, NRC A. L. Peterson, NYSERDA
ENCLOSURE EVALUATION OF THE PROPOSED CHANGE TABLE OF CONTENTS
1.0 DESCRIPTION
2.0 PROPOSED CHANGE
S
3.0 BACKGROUND
4.0 TECHNICAL ANALYSIS
5.0 REGULATORY SAFETY ANALYSIS 5.1 No Significant Hazards Consideration Determination 5.2 Applicable Regulatory Requirements/Criteria
6.0 ENVIRONMENTAL CONSIDERATION
7.0 REFERENCES
ATTACHMENTS
- 1. Proposed Technical Specification Changes (Mark-up)
- 2. Proposed Technical Specification Bases Changes (Mark-up)
Nine Mile Point Nuclear Station, LLC March 30, 2011
ENCLOSURE EVALUATION OF THE PROPOSED CHANGE
1.0 DESCRIPTION
The proposed amendment would revise Nine Mile Point Unit 2 (NMP2) Technical Specification (TS)
Section 3.4.7, "RCS Leakage Detection Instrumentation," to define a new time limit for restoring inoperable Reactor Coolant System (RCS) leakage detection instrumentation to operable status and establish alternate methods of monitoring RCS leakage when required monitors are inoperable. TS Bases changes which reflect the proposed TS changes are also provided. These changes are consistent with NRC-approved Revision 3 to Technical Specification Task Force (TSTF) Improved Standard Technical Specification (STS) Change Traveler TSTF-514, "Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation." The availability of this TS improvement was announced in the Federal Register on December 17, 2010 (75 FR 79048) as part of the consolidated line item improvement process (CLIIP).
2.0 PROPOSED CHANGE
S The proposed changes revise and add a new Condition C to TS 3.4.7, "RCS Leakage Detection Instrumentation." New Condition C is applicable when the drywell atmospheric gaseous radioactivity monitor is the only operable TS-required instrument monitoring RCS leakage; i.e., TS-required drywell atmospheric particulate and drywell floor drain tank fill rate monitors are inoperable. New Condition C Required Actions require monitoring RCS leakage by obtaining and analyzing grab samples of the drywell atmosphere every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />; monitoring RCS leakage using administrative means every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />; and taking action to restore monitoring capability using the drywell floor drain tank fill rate monitoring system within 7 days.
Additionally, the Bases for TS 3.4.7, which summarize the reasons for the specifications, are revised to clarify the specified safety function for each required instrument in the Limiting Condition for Operation (LCO), delete discussion from the TS Bases that could be construed to alter the meaning of TS operability requirements, and reflect the changes made to TS 3.4.7. The TS Bases changes are provided for information only (Attachment 2) and will be processed in accordance with the NMP2 Bases Control Program, TS 5.5.10, Technical Specification (TS) Bases Control Program.
Nine Mile Point Nuclear Station, LLC (NMPNS) is not proposing variations or deviations from the TS changes described in TSTF-514, Revision 3, or the NRC staff's model safety evaluation (SE) published in the FederalRegister on December 17, 2010 (75 FR 79048) as part of the CLIIP Notice of Availability.
Minor changes are proposed to be made to Bases pages B 3.4.7-1 and B 3.4.7-3, that were not identified as a change in TSTF-514, Revision 3, upon implementation of the amendment. On page B 3.4.7-1, the word "three" will be substituted for the word "two" in the sentence "LEAKAGE from the RCPB inside the drywell is detected by at least one of three independently monitored variables, such as drywell floor drain tank fill rate changes and drywell gaseous and particulate radioactivity levels." This change simply reflects the fact that three independent variables exist at NMP2. Words were added to page B 3.4.7-3 (Insert A to the marked-up Bases pages) to clarify that surveillance tests are used to determine monitoring system operability. Also, note that the NMP2 Bases description of the drywell floor drain tank fill rate monitoring system varies slightly from the Bases description provided in the TSTF-514, Revision 3 mark-up. These variations have no impact on the conclusions delineated in the Staff's model safety evaluation.
1 of 5
ENCLOSURE EVALUATION OF THE PROPOSED CHANGE
3.0 BACKGROUND
NRC Information Notice (IN) 2005-24, "Nonconservatism in Leakage Detection Sensitivity," dated August 3, 2005, informed addressees that the reactor coolant activity assumptions for primary containment atmosphere gaseous radioactivity monitors may be non-conservative. This means the monitors may not be able to detect a one gallon per minute leak within one hour. Some licensees, in response to IN 2005-24, have taken action to remove the gaseous radioactivity monitor from the TS list of required monitors. However, industry experience has shown that the primary containment atmosphere gaseous radiation monitor is often the first monitor to indicate an increase in RCS leak rate. As a result, the TSTF and the NRC staff met on April 29, 2008, and April 14, 2009, to develop an alternative approach to address the issue identified in IN 2005-24. The agreed solution is to retain the primary containment atmosphere gaseous radiation monitor in the LCO list of required equipment, revise the specified safety function of the gaseous monitor to specify the required instrument sensitivity level, revise the Actions requiring additional monitoring, and provide less time before a plant shutdown is required when the primary containment atmosphere gaseous radiation monitor is the only operable monitor.
4.0 TECHNICAL ANALYSIS
NMPNS has reviewed TSTF-514, Revision 3, and the model SE published on December 17, 2010 (75 FR 79048) as part of the CLIIP Notice of Availability. NMPNS has concluded that the technical bases presented in TSTF 514, Revision 3, and the model SE prepared by the NRC staff are applicable to NMP2.
The NMP2 primary methods for detecting a small unidentified leak within the primary containment include continuous monitoring of drywell floor drain tank fill rate and airborne gaseous and particulate radioactivity increases (Updated Safety Analysis Report (USAR) Section 5.2.5.1.1). The drywell leakage collected in the floor drain tank includes unidentified leakage from the control rod drives (CRD), valve flanges, component cooling water, service water, air cooler drains, and any leakage not connected to the equipment drain sump. The fission product monitoring system continuously monitors the primary containment atmosphere for airborne radioactivity (iodine, noble gases, and particulates) (USAR Section 5.2.5.2.1). Instrumentation that monitors these parameters is located in TS 3.4.7, "RCS Leakage Detection Instrumentation."
USAR Section 3.1.2.30, "Quality of Reactor Coolant Pressure Boundary (Criterion 30)," provides a discussion of the criterion and NMP2's design conformance to GDC 30 of 10 CFR 50, Appendix A. The criterion, in part, states that a means shall be provided for detecting and, to the extent practical, identifying the location of the source of the reactor coolant leakage. NMP2's position regarding design conformance indicates that the leak detection system provides a means for detecting reactor coolant leakage and consists of sensors and instruments to detect, annunciate, and in some cases isolate the Reactor Coolant Pressure Boundary (RCPB) from potentially hazardous leaks before predetermined limits are exceeded. The leak detection system is designed to meet the requirements of GDC 30 of 10 CFR 50, Appendix A.
NMP2 conforms with the Regulatory Position (paragraph C) of Regulatory Guide (RG) 1.45 (May 1973),
as described in USAR Section 5.2.5.9, with an alternate approach to Position C.5. Section 5.2.5.9 states that leakage is separated into identified and unidentified categories and each is independently monitored, thus meeting position C. 1 of RG 1.45. Leakage from unidentified sources inside the primary containment is collected into the floor drain sump and monitored with an accuracy better than 1 gpm, thus meeting position C.2. By monitoring (1) floor and equipment drain sump fillup and pump out rates, (2) airborne 2 of 5
ENCLOSURE EVALUATION OF THE PROPOSED CHANGE particulates, and (3) airborne gaseous radiation rate, position C.3 is satisfied. Radiation monitoring of cooling water from identified system heat exchangers satisfies position C.4. The sensitivity and response time of each leakage detection system is consistent with equipment capabilities available in the industry (Position C.5), as noted in USAR Table 1.8-1, "Conformance with Division 1 NRC Regulatory Guides."
The floor drain sump monitoring, air particulates monitoring, and gaseous radiation monitoring are designed to detect the leakage rates given in USAR Table 5.2-8. Regarding position C.6, all leakage detection systems are designed to be capable of performing their safety functions following seismic events that do not require plant shutdown. Thus, position C.6 is met. Leak detection indicators, alarms, procedures and graphs are provided to satisfy position C.7. The leakage detection systems are equipped with provisions to permit testing for operability and calibration during plant operation thus satisfying position C.8. The NMP2 TSs comply with position C.9.
The proposed TS changes will include the addition of Required Action C. 1 to analyze grab samples of the drywell atmosphere and Required Action C.2 to monitor RCS leakage by administrative means. The administrative means of monitoring will include diverse alternative methods from which appropriate indicators may be selected based on plant conditions. NMPNS will utilize the following method or methods considering the plant conditions and historical or expected sources of unidentified leakage:
drywell pressure, drywell temperature, drywell unit coolers inlet and outlet air temperatures, and drywell unit cooler outlet cooling water temperature (Reactor Building Closed Loop Cooling System).
Actions to verify that these indications have not increased since the required TS monitors became inoperable and the Required Action to analyze drywell atmospheric grab samples are sufficient to alert the operating staff to an unexpected increase in RCS leakage.
5.0 REGULATORY SAFETY ANALYSIS 5.1 No Significant Hazards Consideration Determination Nine Mile Point Nuclear Station, LLC (NMPNS) has evaluated the proposed changes to the Technical Specifications (TS) using the criteria in 10 CFR 50.92 and has determined that the proposed changes do not involve a significant hazards consideration. An analysis of the issue of no significant hazards consideration is presented below:
Description of Amendment Request: The proposed amendment would revise TS 3.4.7, "RCS Leakage Detection Instrumentation," Conditions and Required Actions.
Basis for proposed no significant hazards consideration determination: As required by 10 CFR 50.91(a),
the NMPNS analysis of the issue of no significant hazards consideration using the standards in 10 CFR 50.92 is presented below:
- 1. Does the proposed change involve a significant increase in the probability or consequences of an accident previously evaluated?
Response: No.
The proposed change clarifies the operability requirements for the RCS leakage detection instrumentation and reduces the time allowed for the plant to operate when the only TS-required operable Reactor Coolant System (RCS) leakage detection instrumentation monitor is the drywell atmospheric gaseous radioactivity monitor. The monitoring of RCS leakage is not a precursor to 3 of 5
ENCLOSURE EVALUATION OF THE PROPOSED CHANGE any accident previously evaluated. The monitoring of RCS leakage is not used to mitigate the consequences of any accident previously evaluated. Therefore, it is concluded that this change does not involve a significant increase in the probability or consequences of an accident previously evaluated.
- 2. Does the proposed change create the possibility of a new or different kind of accident from any accident previously evaluated?
Response: No.
The proposed change clarifies the operability requirements for the RCS leakage detection instrumentation and reduces the time allowed for the plant to operate when the only TS-required operable RCS leakage detection instrumentation monitor is the drywell atmospheric gaseous radioactivity monitor. The proposed change does not involve a physical alteration of the plant (no new or different type of equipment will be installed) or a change in the methods governing normal plant operation. Therefore, it is concluded that the proposed change does not create the possibility of a new or different kind of accident from any previously evaluated.
- 3. Does the proposed change involve a significant reduction in a margin of safety?
Response: No.
The proposed change clarifies the operability requirements for the RCS leakage detection instrumentation and reduces the time allowed for the plant to operate when the only TS-required operable RCS leakage detection instrumentation monitor is the drywell atmospheric gaseous radioactivity monitor. Reducing the amount of time the plant is allowed to operate with only the drywell atmospheric gaseous radioactivity monitor operable increases the margin of safety by increasing the likelihood that an increase in RCS leakage will be detected before it potentially results in gross failure. Therefore, it is concluded that the proposed change does not. involve a significant reduction in a margin of safety.
Based upon the above analysis, NMPNS concludes that the requested change does not involve a significant hazards consideration, as set forth in 10 CFR 50.92(c).
5.2 Applicable Regulatory Requirements/Criteria A description of the proposed TS change and its relationship to applicable regulatory requirements were published in the FederalRegister Notice of Availability on December 17, 2010 (75 FR 79048). NMPNS has reviewed the NRC staff's model SE referenced in the CLIIP Notice of Availability and concluded that the regulatory evaluation section is applicable to NMP2. Note that NMP2 is not committed to RG 1.45, Revision 1, "Guidance on Monitoring and Responding to Reactor Coolant System Leakage," issued on May 2008.
6.0 ENVIRONMENTAL CONSIDERATION
The proposed change would change a requirement with respect to installation or use of a facility component located within the restricted area, as defined in 10 CFR Part 20, or would change an inspection or surveillance requirement. However, the proposed change does not involve (i) a significant hazards consideration, (ii) a significant change in the types or significant increase in the amounts of any 4 of 5
ENCLOSURE EVALUATION OF THE PROPOSED CHANGE effluents that may be released offsite, or (iii) a significant increase in individual or cumulative occupational radiation exposure. Accordingly, the proposed change meets the eligibility criterion for categorical exclusion set forth in 10 CFR 51.22(c)(9). Therefore, pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the proposed change.
7.0 REFERENCES
(1) Technical Specification Task Force (TSTF) Improved Standard Technical Specification (STS)
Change Traveler TSTF-514, "Revise BWR Operability Requirements and Actions for RCS Leakage Instrumentation," Revision 3 5 of 5
ATTACHMENT 1 PROPOSED TECHNICAL SPECIFICATION CHANGES (MARK-UP)
The current versions of the following NMP2 Technical Specification pages have been marked-up by hand to reflect the proposed changes:
3.4.7-1 3.4.7-2 Nine Mile Point Nuclear Station, LLC March 30, 2011
RCS Leakage Detection Instrumentation 3.4.7 3.4 REACTOR COOLANT SYSTEM (RCS) 3.4.7 RCS Leakage Detection Instrumentation LCO 3.4.7 The following RCS leakage detection instrumentation shall be OPERABLE:
- a. Drywell floor drain tank fill rate monitoring system; and
- b. One channel of either drywell atmospheric particulate or atmospheric gaseous monitoring system.
APPLICABILITY: MODES 1, 2, and 3.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. Drywell floor drain A.1 Restore drywell floor 30 days tank fill rate drain tank fill rate monitoring system monitoring system to inoperable. OPERABLE status.
I + f B. Required drywell atmospheric monitoring system inoperable.
B.1 Analyze grab samples of drywell atmosphere.
Once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> C
AND B.2 Restore required 30 days drywell atmospheric monitoring system to OPERABLE status.
(continued)
NMP2 3.4.7-1 Amendment 94, 49--,0
RCS Leakage Detection Instrumentation 3.4.7 ACTIONS (continued)
CONDITION REQUIRED ACTION COMPLETION TIME
, Required Action and 40Be in MODE 3. 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> associated Completion Time of Condition A,0 AND B not met. 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> 02 B in MODE 4.
1- *'. i 1*
All required leakage 1 Enter LCO 3.0.3. Immediately detection systems inoperable.
SURVEILLANCE REQUIREMENTS
NOTE--------------------------------
When a channel is placed in an inoperable status solely for performance of required Surveillances, entry into associated Conditions and Required Actions may be delayed for up to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> provided the other required leakage detection instrumentation is OPERABLE.
SURVEILLANCE FREQUENCY SR 3.4.7.1 Perform CHANNEL CHECK of required drywell 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> atmospheric monitoring system.
SR 3.4.7.2 Perform CHANNEL FUNCTIONAL TEST of the 31 days drywell floor drain tank fill rate monitoring system.
SR 3.4.7.3 Perform source check of required drywell 31 days atmospheric monitoring system.
(continued)
NMP2 3.4.7-2 Amendment 94I
INSERT 1 (for TS paqe 3.4.7-1) of C.1 Analyze grab samples NOTE-------- C. 1 Analyze grab samples of Once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Only applicable when the the drywell atmosphere.
drywell atmospheric gaseous monitoring system AND is the only OPERABLE monitor. C.2 Monitor RCS LEAKAGE by Once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> administrative means.
C. Drywell floor drain tank AND fill rate monitoring system inoperable. C.3 Restore drywell floor drain 7 days tank fill rate monitoring system to OPERABLE status.
ATTACHMENT 2 PROPOSED TECHNICAL SPECIFICATION BASES CHANGES (MARK-UP)
The current versions of the following NMP2 Technical Specification Bases pages have been marked-up by hand to reflect the proposed changes. These changes are provided for information only:
B 3.4.7-1 B 3.4.7-2 B 3.4.7-3 B 3.4.7-4 B 3.4.7-6 Nine Mile Point Nuclear Station, LLC March 30, 2011
RCS Leakage Detection Instrumentation B 3.4.7 B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.7 RCS Leakage Detection Instrumentation BASES* ] 'i BACKGROUND GDC 30 of 10 CFR , Appendix Ai(Ref. 1), requires means for detecting and, o the extent practical, identifying the location of e source of RCS LEAKAGE. Regulatory Guide 1.45 Ref. 2) describes acceptable methods for selecting leakage detection systems.
Limits on LEAKAGE from the reactor coolant pressure boundary (RCPB) are required so that appropriate action can be taken before the integrity of the RCPB is impaired (Ref. 2).
SLeakage detection systems for the RCS are provided to alert the operators when leakage rates above normal background
" 'A levels are detected and also to supply quantitative measurement of rates. The Bases for LCO 3.4.5, "RCS A /* 0-,, Operational rates. LEAKAGE," discuss the limits on RCS LEAKAGE Systems for separating the.LEAKAGE of an identified source from an unidentified source are necessary to provide prompt S ,'and quantitative information to the operators to permit them tc take immediate cor ctiv tion.
LEAKAGE from the PB inside the drywell is detected by at
- >p least one of o independently monitored variables, such as drywell floor drain tank fill rate changes and drywell
- gaseous kA and particulate radioactivity levels. The primary
-o means of quantifying LEAKAGE in the drywell is the drywell floor drain tank fill rate monitoring system.
2* The drywell floor drain tank fill rate monitoring system IV) .This monitors the LEAKAGE collected in the floor drain tank.
unidentified LEAKAGE consists of LEAKAGE from control rod drives, valve flanges or packings, floor drains, component cooling water, and drywell air cooling unit condensate drains, and any LEAKAGE not collected in the drywell equipment drain tank. Leakage into the drywell C X 'j ' __ floor drain system flows through a piping header that V 'J penetrates the containment, wall and is then directed to the drywell floor drain tank located in the reactor building.
The drywell floor drain tank is monitored by one level transmitter that supplies level indication in the main control room.
(continued)
NMP2 B 3.4.7-1 Revision- )
RCS Leakage Detection Instrumentation B 3.4.7 BASES BACKGROUND Two drywell floor drain pumps take suction from the drywell (continued) floor drain tank and discharge to the Liquid Radioactive Waste System via the reactor building floor drain system header. The pumps alternate :as lead and backup on each successive start. When a high level is reached in the floor drain tank, a level switch actuates to start the lead floor drain pump. In the event the level continues to rise, a second level switch actuates to start the backup floor drain pump. When the level decreases to a low level, both floor drain pumps are stopped. A flow indicator in the discharge line of the drywell floor drain pumps provides flow indication in the control room. In addition, a leak rate recorder is provided capable of identifying a 1 gpm change over an hour period.
The drywell atmospheric monitoring systems (particulate and gaseous) continuously monitor the drywell atmosphere for airborne particulate and gaseous radioactivity. A sudden increase of radioactivity, which may be attributed to RCPB steam or reactor water LEAKAGE, is annunciated in-control room.shedryet atmos -ere partimulate gas rad' tivi~e monitori g system re not ~pable f ntifyi* leak* ates, t are se itive e fugh tol indc inr dLEK ae p wi in I *r
\(Re ) -grchn nLA rates e det -ed in
,,rio APPLICABLE A threat of significant compromise to the RCPB exists if the SAFETY ANALYSES barrier contains a crack that is large enough to propagate rapidly. LEAKAGE rate limits are set low enough to detect the LEAKAGE emitted from a single crack in the RCPB (Refs.
andTM).V1Eacha of t~e leakaoe delectionsvster~s ins ' e tha-iate, /arm 9f exces'ý L A control room alarm allows the operators to evaluate the significance of the indicated LEAKAGE and, if necessary, shut down the reactor for further investigation and corrective action. The allowed LEAKAGE rates are well belo the rates predicted for critical crack sizes (Ref.
Therefore, these actions provide adequate response before a significant break in the RCPB can occur.
RCS leakage detection instrumentation satisfies Criterion 1 of Reference6.
NMP2 B 3.4.7-2 Revision p
RCS Leakage Detection Instrumentation B 3.4.7 BASES (continued)
APPLICABILITY In MODES 1, 2, and 3, leakage detection systems are required to be OPERABLE to support LCO 3.4.5. This Applicability is consistent with that for LCO 3.4.5.
ACTIONS A.1 With the drywell floor drain tank fill rate monitoring system inoperable, no other form of sampling can provide the equivalent information to quantify leakage. However, the drywell atmospheric activity monitor will provide indications of changes in leakage.
With the drywell floor drain tank fill rate monitoring system inoperable, but with RCS unidentified and total LEAKAGE being determined every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> (SR 3.4.5.1),
operation may continue for 30 days. The 30 day Completion Time of Required Action A.1 is acceptable, based on operating experience, considering the multiple forms of leakage detection that are still available.
B.1 and B.2 6I With both gaseous and particulate drywell atmospheric monitoring channels inoperable (i.e., the required drywell atmospheric monitoring system), grab samples of the drywell atmosphere shall be taken and analyzed to provide periodic leakage information. Provided a sample is obtained and (continued)
NMP2 B 3.4.7-3 Revision 0, 9-0"V44d9
RCS Leakage Detection Instrumentation B 3.4.7 BASES ACTIONS B.1 and B.2 (continued) analyzed every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, the plant may be operated for up to 30 days to allow restoration of at least one of the required monitors.
The 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> interval provides periodic information that is adequate to detect LEAKAGE. The 30 day Completion Time for restoration recognizes that at least one other form of 6
1"- leakage detection is available.
I If any Req- Aion ann 'ass~ociated Completion Time of Condition B cannot be met, the plant must be brought to a MODE ih- wich the LCO does not apply. To achieve this status, the plant must be brought to at least MODE 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and to MODE 4 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. The allowed Completion Times are reasonable, based on operating experience, to reach the required plant conditions in an orderly manner and without challenging plant systems.
With all required monitors inoperable, no required automatic means of monitoring LEAKAGE are available, and immediate plant shutdown in accordance with LCO 3.0.3 is required.
SURVEILLANCE The Surveillances are modified by a Note to indicate that REQUIREMENTS when a channel is placed in an inoperable status solely for performance of required Surveillances, entry into associated Conditions and Required Actions may be delayed for up to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, provided the other required instrumentation (either the drywell floor drain tank fill rate monitoring system or the drywell atmospheric monitoring channel, as applicable) is OPERABLE. Upon completion of the Surveillance, or (continued)
NMP2 B 3.4.7-4 Revision 0, 64!39 ))
RCS Leakage Detection Instrumentation B 3.4.7 BASES SURVEILLANCE SR 3.4.7.5 REQUIREMENTS (continued) This SR requires the performance of a CHANNEL CALIBRATION of the required RCS leakage detection instrumentation channels.
The calibration verifies the accuracy of the instrument string, including the instruments located inside the drywell. The Frequency of 24 months is a typical refueling cycle and considers channel reliability. Operating experience has proven this Frequency is acceptable.
~-I-N/
REFERENCES 1. 10 CFR 50, Appendix A, GDC 30. A "Z,-r
- 2. Regulatory Guide 1.45, ay 1973. _
(
ior in ASTM A1O6B Pipes
. GEAP-5620, "Failure Containing Axial Behav Wall Flaws," April 1968.
Through-NUREG-75/067, "Investigat i on and Evaluation of fr~rninn in Aiictpnitir qt; Si n1 Pc Steel Piping of IRnilinr Wn+/-or Qantnrz "1 flr-nhov. 1975.
USAR, Section 5.2.5.5.3.
. 10 CFR 50.36(c)(2)(ii).
NMP2 B 3. 4. 7-6 Revision
INSERT A (for TS Bases page B 3.4.7-3)
This LCO requires instruments of diverse monitoring principles to be OPERABLE to provide confidence that small amounts of unidentified LEAKAGE are detected in time to allow actions to place the plant in a safe condition, when RCS LEAKAGE indicates possible RCPB degradation.
The LCO requires two instruments to be OPERABLE.
The drywell floor drain tank fill rate monitoring system is required to quantify the unidentified LEAKAGE rate from the RCS. Thus, for the system to be considered OPERABLE it must be capable of determining the leakage rate. The identification of an increase in unidentified LEAKAGE will be delayed by the time required for the unidentified LEAKAGE to travel to the drywell floor drain tank and it may take longer than one hour to detect a 1 gpm increase in unidentified LEAKAGE, depending on the origin and magnitude of the LEAKAGE. This sensitivity is acceptable for drywell floor drain tank fill rate monitoring system OPERABILITY.
The reactor coolant contains radioactivity that, when released to the drywell, can be detected by the gaseous or particulate drywell atmospheric radioactivity monitor. Only one of the two detectors is required to be OPERABLE. Radioactivity detection systems are included for monitoring both particulate and gaseous activities because of their sensitivities and rapid responses to RCS LEAKAGE, but have recognized limitations. Reactor coolant radioactivity levels will be low during initial reactor startup and for a few weeks thereafter, until activated corrosion products have been formed and fission products appear from fuel element cladding contamination or cladding defects. If there are few fuel element cladding defects and low levels of activation products, it may not be possible for the gaseous or particulate drywell atmospheric radioactivity monitors to detect a 1 gpm increase within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> during normal operation. The gaseous or particulate drywell atmospheric radioactivity monitor is OPERABLE when it is capable of detecting a 1 gpm increase in unidentified LEAKAGE within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> given an RCS activity equivalent to that assumed in the design calculations for the monitors (Reference 7). This is shown by performance of the required surveillance tests.
The LCO is satisfied when monitors of diverse measurement means are available. Thus, the drywell floor drain tank fill rate monitoring system, in combination with a gaseous or particulate drywell atmospheric radioactivity monitor, provides an acceptable minimum.
INSERT B (for TS Bases page B 3.4.7-4)
C.1, C.2, and C.3 With the drywell floor drain tank fill rate monitoring system inoperable, the only means of detecting LEAKAGE is the drywell atmospheric gaseous radioactivity monitor. A Note clarifies this applicability of the Condition. The drywell atmospheric gaseous radioactivity monitor typically cannot detect a 1 gpm leak within one hour when RCS activity is low. In addition, this configuration does not provide the required diverse means of leakage detection. Indirect methods of monitoring RCS leakage must be implemented. Grab samples of the drywell atmosphere must be taken and analyzed and monitoring of RCS leakage by administrative means must be performed every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> to provide alternate periodic information.
Administrative means of monitoring RCS leakage include monitoring and trending parameters that may indicate an increase in RCS leakage. There are diverse alternative mechanisms from which appropriate indicators may be selected based on plant conditions. It is not necessary to utilize all of these methods, but a method or methods should be selected considering the current plant conditions and historical or expected sources of unidentified leakage. NMPNS will utilize the following method or methods considering the plant conditions and historical or expected sources of unidentified leakage: drywell pressure, drywell temperature, drywell unit coolers inlet and outlet air temperatures, and drywell unit cooler outlet cooling water temperature (Reactor Building Closed Loop Cooling System).
These indications, coupled with the atmospheric grab samples, are sufficient to alert the operating staff to an unexpected increase in unidentified LEAKAGE.
The 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> interval is sufficient to detect increasing RCS leakage. The Required Action provides 7 days to restore another RCS leakage monitor to OPERABLE status to regain the intended leakage detection diversity. The 7 day Completion Time ensures that the plant will not be operated in a degraded configuration for a lengthy time period.