Annual Assessment EOC Letter and Inspection/Activity Plan
ML110620121
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 03/04/2011
From: Jamnes Cameron
NRC/RGN-III/DRP/B6
To: Weber L
Indiana Michigan Power Co
References
Download: ML110620121 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 March 4, 2011 Mr. Larry Weber Senior Vice President and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR D. C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 (REPORT 05000315/2011001; 05000316/2011001)

Dear Mr. Weber:

On February 17, 2011, the NRC completed its end-of-cycle performance review of D. C. Cook Nuclear Plant, Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2010 through December 31, 2010. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRCs assessment of your performance in the Security Cornerstone and its security-related inspection plan.

The NRC determined that overall, D. C. Cook Units 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at D. C. Cook Units 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRC=s Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green).

Therefore, the NRC plans to conduct ROP baseline inspections at your facility. In addition to the ROP baseline, inspections are planned for Temporary Instruction (TI) 2515/179, Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS, TI 2515/177, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, and also Independent Spent Fuel Storage Installation (ISFSI)

Inspections 60854.1, Preoperational Testing of ISFSIs at Operating Plants, 60855.1, Operation of an ISFSI at Operating Plants, and 60856.1, Review of 10 CFR 72.212(b)

Evaluations at Operating Plants.

The enclosed inspection plan lists the inspections scheduled through June 30, 2012. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 9 months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

L. Weber In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 630-829-9833 with any questions you have regarding this letter.

Sincerely,

/RA/

Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74

Enclosure:

D. C. Cook Plant Inspection/Activity Plan cc w/encl: Distribution via ListServ

D.C. Cook Inspection / Activity Plan 03/01/2011 - 06/30/2012 Planned Dates No. of Staff Start End Inspection Activity Title on Site ISFSI - ISFSI DESIGN AND CONSTRUCTION 1 01/20/2011 04/01/2011 IP 60853 On-Site Fabrication Of Components And Construction On An ISFSI ISFSI - ISFSI INSPECT. - SCHEDULE DEPENDENT 4 02/01/2011 05/31/2011 IP 60856 Review of 10 CFR 72.212(b) Evaluations 05/01/2011 12/31/2011 IP 60854.1 Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants BI EP - EP EXERCISE INSPECTION / PI VERIFICATION 3 02/28/2011 03/04/2011 IP 7111401 Exercise Evaluation 02/28/2011 03/04/2011 IP 71151 Performance Indicator Verification BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 02/28/2011 03/04/2011 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 02/28/2011 03/04/2011 IP 71124.04 Occupational Dose Assessment 02/28/2011 03/04/2011 IP 71151 Performance Indicator Verification BI ENG - MODIFICATIONS / 50.59 INSPECTION 3 03/21/2011 04/08/2011 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 04/25/2011 04/29/2011 IP 71124.07 Radiological Environmental Monitoring Program 04/25/2011 04/29/2011 IP 71151-PR01 RETS/ODCM Radiological Effluent BI PI&R - BIENNIAL PI&R INSPECTION 5 05/02/2011 05/20/2011 IP 71152B Identification and Resolution of Problems BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 06/20/2011 06/24/2011 IP 2515/179 Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS 06/20/2011 06/24/2011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 06/20/2011 06/24/2011 IP 71124.02 Occupational ALARA Planning and Controls 06/20/2011 06/24/2011 IP 71151-OR01 Occupational Exposure Control Effectiveness BI ENG - INSERVICE INSPECTION - UNIT 1 2 09/21/2011 10/30/2011 IP 7111108P Inservice Inspection Activities - PWR BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 10/03/2011 10/07/2011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 10/03/2011 10/07/2011 IP 71124.02 Occupational ALARA Planning and Controls ISFSI - ISFSI INSPECTION - SCHEDULE DEPENDENT 2 01/01/2012 05/31/2012 IP 60854.1 Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants 06/01/2012 11/30/2012 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants STRIKE - STRIKE CONTINGENCY - RP/MAINT 2 01/16/2012 02/16/2012 IP 92709 Licensee Strike Contingency Plans

D.C. Cook Inspection / Activity Plan 03/01/2011 - 06/30/2012 Planned Dates No. of Staff Start End Inspection Activity Title on Site BI ENG - TRIENNIAL HEAT SINK INSPECTION 2 01/30/2012 02/03/2012 IP 7111107T Heat Sink Performance BI EP - EP ROUTINE INSPECTION / PI VERIFICATION 2 02/13/2012 02/17/2012 IP 7111402 Alert and Notification System Testing 02/13/2012 02/17/2012 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 02/13/2012 02/17/2012 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 02/13/2012 02/17/2012 IP 71151 Performance Indicator Verification BI OL - BIENNIAL REQUAL PROGRAM INSPECTION 2 02/20/2012 02/24/2012 IP 7111111B Licensed Operator Requalification Program BI ENG - INSERVICE INSPECTION - UNIT 2 1 03/20/2012 04/28/2012 IP 7111108P Inservice Inspection Activities - PWR BI RP - RADIATION PROTECTION BASELINE INSPECTIO 1 03/26/2012 03/30/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 03/26/2012 03/30/2012 IP 71151 Performance Indicator Verification BI RP - RADIATION PROTECTION BASELINE INSPECTIO 1 05/14/2012 05/18/2012 IP 71124.05 Radiation Monitoring Instrumentation

L. Weber In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 630-829-9833 with any questions you have regarding this letter.

Sincerely,

/RA/

Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket Nos. 50-315; 50-316 License Nos. DPR-58; DPR-74

Enclosure:

D. C. Cook Plant Inspection/Activity Plan cc w/encl: Distribution via ListServ DOCUMENT NAME: G:\DRPIII\1-Secy\1-Work In Progress\2010 EOC Letters\DC Cook EOC Letter.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME AGarmoe*JC for JCameron DATE 02/28/11 02/28/11 OFFICIAL RECORD COPY

Letter to L. Weber from J. Cameron dated March 4, 2011.

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR D. C. COOK NUCLEAR POWER PLANT, UNITS 1 AND 2 (REPORT 05000315/2011001; 05000316/2011001)

DISTRIBUTION:

Daniel Merzke RidsNrrDorlLpl3-1 Resource RidsNrrPMDCCook Resource RidsNrrDirsIrib Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPassessment Resource