Letter Sequence Withholding Request Acceptance |
---|
TAC:ME3589, Clarify Application of Setpoint Methodology for LSSS Functions (Approved, Closed) TAC:ME3590, Clarify Application of Setpoint Methodology for LSSS Functions (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement, Supplement, Supplement
|
MONTHYEARML1008503912010-03-18018 March 2010 GE-Hitachi Nuclear Energy Americas, LLC Affidavit Requesting That GEH Proprietary Report, NEDC-33484P Be Withheld from Public Disclosure Project stage: Request ML1008503922010-03-19019 March 2010 Application for Withholding Proprietary Information from Public Disclosure Project stage: Request RS-10-002, Request for License Amendment Re Measurement Uncertainty Recapture Power Uprate2010-03-25025 March 2010 Request for License Amendment Re Measurement Uncertainty Recapture Power Uprate Project stage: Request ML1008504032010-03-31031 March 2010 NEDO-33484, Rev. 0, Safety Analysis Report for Limerick Generating Station Units 1 & 2 Thermal Power Optimization Project stage: Request ML1010310792010-04-19019 April 2010 Supplemental Information Needed for Acceptance of Requested Licensing Action Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Acceptance Review RS-10-085, Supplement to License Amendment Request for Measurement Uncertainty Recapture Power Uprate2010-04-26026 April 2010 Supplement to License Amendment Request for Measurement Uncertainty Recapture Power Uprate Project stage: Supplement ML1012409982010-05-0606 May 2010 Acceptance of Requested Licensing Action Measurement Uncertainty Recapture Power Uprate Request and Standby Liquid Control System Modification Project stage: Acceptance Review ML1013303752010-05-24024 May 2010 Electronic Transmission, Draft Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Draft RAI ML1014700892010-06-0303 June 2010 Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML1015802912010-06-0707 June 2010 Electronic Transmission, Draft Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Draft RAI ML1015906292010-06-15015 June 2010 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML1016804402010-06-21021 June 2010 Electronic Transmission, Draft Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Draft RAI ML1015803382010-06-25025 June 2010 Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML1016901212010-07-0202 July 2010 Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML1018800202010-07-0808 July 2010 Electronic Transmission, Draft Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Draft RAI ML1019400532010-07-15015 July 2010 Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML1018700242010-07-15015 July 2010 Electronic Transmission, Draft Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Draft RAI ML1018700082010-07-15015 July 2010 Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: RAI RS-10-116, Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate2010-07-22022 July 2010 Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Request RS-10-127, Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate2010-07-28028 July 2010 Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Request RS-10-129, Schedule for Responding to Request for Additional Information2010-07-28028 July 2010 Schedule for Responding to Request for Additional Information Project stage: Request RS-10-126, Additional Information and Supplement Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate2010-08-10010 August 2010 Additional Information and Supplement Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Supplement RS-10-132, Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate2010-08-12012 August 2010 Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Request RS-10-133, Limerick, Units 1 and 2 - Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate2010-08-12012 August 2010 Limerick, Units 1 and 2 - Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Request RS-10-144, Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate2010-08-30030 August 2010 Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Request ML1024402642010-08-31031 August 2010 0000-0114-0580-RO-NP, Rev. 0, Limerick Generating Station, Units 1 & 2, Upper Shelf Energy Evaluation for LPCI Nozzle Forging Material Project stage: Request ML1028005382010-10-19019 October 2010 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance RS-10-212, Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate2010-12-17017 December 2010 Additional Information Supporting Request for License Amendment Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Request RS-11-003, Supplement to License Amendment Request for Measurement Uncertainty Recapture Power Uprate2011-01-0707 January 2011 Supplement to License Amendment Request for Measurement Uncertainty Recapture Power Uprate Project stage: Supplement ML1100606332011-01-18018 January 2011 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML1106910952011-04-0808 April 2011 Issuance of Amendments 201 & 163 Measurement Uncertainty Recapture Power Uprate and Standby Liquid Control System Changes Project stage: Approval ML1110400892011-04-20020 April 2011 Correction Letter for Limerick Generating Station, Units 1 and 2 - Safety Evaluation Regarding Measurement Uncertainty Recapture Power Uprate and Standby Liquid Control System Changes Project stage: Approval 2010-06-03
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000352/20243012024-02-0202 February 2024 Initial Operator Licensing Examination Report 05000352/2024301 and 05000353/2024301 IR 05000352/20230042024-01-31031 January 2024 Integrated Inspection Report 05000352/2023004 and 05000353/2023004 IR 05000352/20240112024-01-31031 January 2024 Information Request to Support Post-Approval Site Inspection for License Renewal; Inspection Report 05000352/2024011 ML24026A2962024-01-26026 January 2024 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS)- Syrs, . ML24004A0342024-01-17017 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0026 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000352/20230102024-01-11011 January 2024 Age-Related Degradation Report 05000352/2023010 and 05000353/2023010 IR 05000352/20234012023-12-21021 December 2023 Cybersecurity Inspection Report 05000352/2023401 and 05000353/2023401 ML23321A2362023-12-14014 December 2023 Issuance of Amendment Nos. 262 and 224 Adoption of TSTF-477, Revision 3 and Associated Technical Specification Changes ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23333A2182023-11-29029 November 2023 Operator Licensing Examination Approval ML23325A2062023-11-21021 November 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML23313A0432023-11-13013 November 2023 Summary of Regulatory Audit in Support of Amendment Request for Control Room Air Conditioning Technical Specifications ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000352/20230032023-10-27027 October 2023 Integrated Inspection Report 05000352/2023003 and 05000353/2023003 and Independent Spent Fuel Storage Installation Inspection 07200065/2023001 ML23297A1722023-10-24024 October 2023 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000352/2024010 and 05000353/2024010 IR 05000352/20235012023-10-17017 October 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000352/2023501 and 05000353/2023501 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23276A5162023-10-0303 October 2023 Federal Emergency Management Agency Level 1 Finding from 2023 Evaluated Emergency Preparedness Exercise ML23275A1082023-09-29029 September 2023 FEMA Level 1 Findings Limerick NPP- Boyertown/Colebrookdale ML23241A9452023-09-27027 September 2023 Generation Station, Units 1 and 2 Regulatory Audit Plan Supporting Review of the Equipment Qualification Portion of Limerick Digital Instrumentation and Controls License Amendment Request ML23269A0522023-09-26026 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000352/2023010 and 05000353/2023010 ML23255A0952023-09-12012 September 2023 Resubmittal of License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS) to Address ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23249A1002023-09-0606 September 2023 Requalification Program Inspection IR 05000352/20230052023-08-31031 August 2023 Updated Inspection Plan for Limerick Generating Station, Units 1 and 2 (Report 05000352/2023005 and 05000353/2023005) ML23248A2082023-08-31031 August 2023 UFSAR Cover Page ML23242A2172023-08-30030 August 2023 Response to Request for Additional Information for Application to Adopt TSTF-477, Revision 3, Add Action for Two Inoperable Control Room AC Subsystems and Associated Technical Specification Changes NMP2L2851, Relief Request Associated with Successive Inspections for Generic Letter 88-01 / BWRVIP-75-A Augmented Examinations2023-08-25025 August 2023 Relief Request Associated with Successive Inspections for Generic Letter 88-01 / BWRVIP-75-A Augmented Examinations ML23228A0942023-08-16016 August 2023 Response to Request for Additional Information for Supplemental License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the . IR 05000352/20230022023-08-14014 August 2023 Integrated Inspection Report 05000352/2023002 and 05000353/2023002 ML23220A0182023-08-0808 August 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000352/2023401 and 05000353/2023401 RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor ML23212B2362023-07-31031 July 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System - WEC Documents ML23212B1052023-07-31031 July 2023 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the Digital Modernization Project Installation - Revise ML23202A2192023-07-21021 July 2023 Response to Request for Additional Information for Supplemental License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the . ML23193B0122023-07-20020 July 2023 Audit Plan in Support of Review of License Amendment Request and Exemption Request for Digital Instrumentation and Controls Installation Support (Epids L-2023-LLA-0025 and L-2023-LLE-0005) ML23187A0962023-07-19019 July 2023 Generation Station, Unit Nos. 1 and 2 - Revised Estimated Review Completion Date Concerning License Amendment Request to Replace Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML23208A1522023-07-0606 July 2023 PEMA Letter Dated 7-6-23 Re Limerick Exercise 9-26-23 ML23177A2242023-06-26026 June 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection . ML23145A1972023-06-23023 June 2023 Correction to the Renewed Facility Operating License Pages in Amendment Nos. 255, 256, 257, 258, 259, and 260 2024-02-02
[Table view] Category:Proprietary Information Review
MONTHYEARML23114A3472023-05-0202 May 2023 Request for Withholding Information from Public Disclosure for Limerick Generating Station, Units 1 and 2 (EPIDs L-2023-LLA-0025 and L-2023-LLE-0005) ML21279A0062021-10-13013 October 2021 Request for Withholding Information from Public Disclosure ML21201A3852021-07-23023 July 2021 Request for Withholding Information Regarding Proposed Alternative to Use ASME Code Case N-893 (EPIDs L-2020-LLR-0147 and -0148) ML21084A1352021-04-0505 April 2021 Request for Withholding Information from Public Disclosure ML21028A7122021-02-0303 February 2021 Request for Withholding Information Regarding Proposed Alternative to Use ASME Code Case N-893 (Epids L-2020-LLR-0147 and -0148) ML20317A1342020-11-12012 November 2020 Request for Withholding Information from Public Disclosure; Guarantees of Payment of Deferred Premiums ML19336A0192019-12-0303 December 2019 Request for Withholding Information Regarding Guarantees of Payment of Deferred Premiums ML17320A1452017-11-20020 November 2017 Request for Withholding Information Regarding Guarantees of Payment of Deferred Premiums ML17192A4902017-07-19019 July 2017 Request for Withholding Information from Public Disclosure ML16363A3952017-01-0909 January 2017 Request for Withholding Information from Public Disclosure for Limerick Generating Station, Unit 2 ML16337A2762016-12-0909 December 2016 Calvert; Clinton; Dresden; LaSalle; Limerick; Nine Mile Point; Oyster Creek; Peach Bottom; Quad Cities; R.E. Ginna; Three Mile Island - Request for Withholding Information Regarding; Guarantees of Payment of Deferred Premiums ML16132A2802016-05-12012 May 2016 Request for Withholding Information from Public Disclosure ML16098A3222016-04-27027 April 2016 Request to Withhold Emergency Preparedness Documents from Public Disclosure (CAC Nos. MF7504-MF7525) ML15337A3852015-12-16016 December 2015 Request for Withholding Information from Public Disclosure for Limerick Generating Station, Unit 1 ML15260A5722015-10-0202 October 2015 Request for Withholding Information from Public Disclosure for Limerick Generating Station, Unit 1 ML14119A0642014-05-0505 May 2014 Request for Withholding Information from Public Disclosure for Limerick Generating Station, Unit 1 ML13136A1972013-06-10010 June 2013 Request for Withholding Information from Public Disclosure for Limerick Generating Station, Unit 2 ML13080A3412013-04-0303 April 2013 Request for Withholding Information from Public Disclosure for Limerick Generating Station, Unit 1 ML13016A5002013-01-30030 January 2013 Request for Withholding Information from Public Disclosure for Braidwood Station, Units 1 & 2; Byron Station, Units 1 & 2; Clinton Power Station, Unit 1; Dresden Nuclear Power Station, Units 2 & 3; LaSalle County Station, Units 1 & 2 ML1106103602011-03-0404 March 2011 Request for Withholding Information from Public Disclosure ML1100606332011-01-18018 January 2011 Request for Withholding Information from Public Disclosure ML1015906292010-06-15015 June 2010 Request for Withholding Information from Public Disclosure ML0907103302009-04-30030 April 2009 Corp., Request for Withholding Information from Public Disclosure ML0604602532006-02-24024 February 2006 Request for Withholding Information from Public Disclosure (Tac No. MC9231) ML0601101042006-01-24024 January 2006 Withholding from Public Disclosure, Additional Information Regarding the Cycle Specific SLMCPR (Safety Limit for Minimum Critical Power) for Limerick 1 Cycle 12, MC9231 ML0506805102005-03-18018 March 2005 Request for Withholding Information from Public Disclosure ML0406106772004-04-0606 April 2004 Request for Withholding Information from Public Disclosure ML0404404252004-02-13013 February 2004 (Egc), Withholding Information from Public Disclosure, Jeffrey A. Benjamin 02/05/2004 Letter Addressing an Issue Related to EGC Plants ML0308400022003-03-25025 March 2003 Withholding Proprietary Information Letter, Request for Withholding Information from Public Disclosure, Limerick Generating Station, Unit 2 ML0221700972002-08-22022 August 2002 Request for Withholding Information from Public Disclosure, Document Entitled Limerick Unit 1 Cycle 9 Fuel Channel Bow Assessment. ML0200304012002-02-0404 February 2002 Proprietary Information Review - Request for Withholding Information from Public Disclosure 2023-05-02
[Table view] |
Text
\.~I'R REGUt _ UNITED STATES
~v "'I)
~ 0'1' NUCLEAR REGULATORY COMMISSION
~
~0 WASHINGTON, D.C. 20555-0001
~
~
~
January 18, 2011
't"', ~
1-1] ~O
....***i' Mr. Michael Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
LIMERICK GENERATING STATION, UNIT NOS. 1 AND 2 - REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE (TAC NOS. ME3589 AND ME3590)
Dear Mr. Pacilio:
By letter dated December 17, 2010 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML103560667), Exelon Generation Company, LLC (Exelon) submitted additional information supporting a license amendment request (LAR) proposing to revise the operating license and technical specifications for Limerick Generating Station (LGS), Units 1 and 2. This LAR proposes to implement an increase of approximately 1.65% in rated thermal power from the currently licensed power limit of 3458 megawatts thermal.
Enclosure 3 to the letter dated December 17, 2010, contains an affidavit dated December 16, 2010, executed by Edward D. Schrull, Vice President, Regulatory Affairs, GE Hitachi Nuclear Energy Americas LLC. (GEH), requesting that information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Part 2, Section 2.390:
- Enclosure 1 of GEH letter GEH-LGS-AEP-143, Michael J. Dick (GEH) to Jeffrey L.
Wilson (Exelon Nuclear), entitled Limerick TPO [thermal power optimization] CVIB
[Vessel and Internals Integrity Branch] Follow-up RAI [request for additional information]
GEH Response.
A nonproprietary copy of Enclosure 1 of GEH letter GEH-LGS-AEP-143 has been placed in the Nuclear Regulatory Commission's (NRCs) Public Document Room and added to the ADAMS Public Electronic Reading Room. It may be found at ADAMS Accession No. ML103560667.
The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
(4) a. Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by GEH's competitors without license from GEH constitutes a competitive economic advantage over GEH and/or other companies.
(4) b. Information that, if used by a competitor, would reduce their expenditure of resources or improve their competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product.
M. Pacilio -2 We have reviewed your application and the material in accordance with requirements of 10 CFR 2.390 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the version of the submitted information marked proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
Please contact me at 301-415-2833, if you have any questions.
Sincerely, fZ-:c; ~....,-v' Peter Bamford, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353 cc:
Mr. Edward D. Schull Vice President, Regulatory Affairs GE-Hitachi Nuclear Energy Americas, LLC 3901 Castle Hayne Road Wilmington, NC 28401 Additional distribution via Listserv
M. Pacilio -2 We have reviewed your application and the material in accordance with requirements of 10 CFR 2.390 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
Therefore, the version of the submitted information marked proprietary will be withheld from public disclosure pursuantto 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
Please contact me at 301-415-2833, if you have any questions.
Sincerely,
/raJ Peter Bamford, Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353 cc:
Mr. Edward D. Schull Vice President, Regulatory Affairs GE-Hitachi Nuclear Energy Americas, LLC 3901 Castle Hayne Road Wilmington, NC 28401 Additional distribution via Listserv DISTRIBUTION:
PUBLIC RidsOgcRp Resource LPLI-2 R/F RidsAcrsAcnw MailCTR Resource RidsNrrLAABaxter Resource RidsNrrPMLimerick Resource RidsRgn1MailCenter Resource RidsNrrDorlDpr Resource RidsNrrDorlLpl1-2 Resource ADAMS Accession No' .. ML110060633
- via email OFFICE LPL1-2/PM LPLI-2/PM LPLI-2/LA LPL 1-2/BC NAME JWhited PBamford ABaxter
DATE 1/11/11 1/11/11 1/13/11 1/18/11 OFFICIAL RECORD COpy